Professional Documents
Culture Documents
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 1
1. GENERAL
4. SHUTDOWN
5. EMERGENCY SHUTDOWN
5.1 Depressurising
5.2 Liquid Levels
5.3 Shutdown Causes
a. Cooling Water Failure
b. Instrument Air Failure
c. Power Failure
d. Hot Oil Failure
e. Fire
f. Tube Burst in F-1301.
5.4 Shutdown Activities
6. EQUIPMENT/INSTRUMENT SUMMARY
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 3
Reference Drawings.
F11W-0180-01
F11W-0180-02
F11W-0181-01
F11W-0181-02
F11W-0181-03
F11W-0181-04
F11W-0181-05
F11W-0181-06
NG-1069/0
NG-1070/0
NG-076
1. GENERAL
The propane molecular sieve adsorbers C-1307A/B and the butane molecular
sieve adsorbers C-1308A/B are fixed bed units filled with molecular sieves.
The molecular sieves adsorb the water and possibly some mercaptan molecules
from the liquid streams.
The bed of sieves are held on a fixed grid, a 20 mesh wire screen. Layers of 1/4”
and 1½” ceramic balls are placed on the wire mesh.
The propane and butane adsorbers are similar except that the fixed grid on the
butane absorber is lighter.
The propane adsorber is filled with 17m 3 of type RK-29- Union Carbide - Molecular
sieves 1/16” pellets.
The butane adsorber is filled with 13m3 of type 9453- Union Carbide - Molecular
sieves.
Above the beds of sieves is a floating grid and screen. It allows movement in the
bed but also contains it.
The ceramic balls form a trap for any dust and dirt particles.
Both inlet and outlet lines have special devices which prevent any sieves or balls
passing into piping and equipment.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 4
Normally, while one bed is in adsorption service the other bed is being
regenerated.
The propane and butane leaving their respective adsorbers contain less than 1
ppm wt of water and less than 5 ppm wt of sulphur.
The frequency of change over of the adsorbers will be dependant upon the
efficiency of the treating units, ADIP and Merox.
Since molecular sieve material is very expensive, particular care should be taken
to ensure that they remain in good condition.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 5
The molecular sieve treating sections contains two units, propane and butane.
They each consist of two adsorbers with identical equipment and functions.
Configuration and operation of the two units is identical. They differ only in actual
size. The present operating conditions are shown in brackets.
In addition to all the other common features the adsorbers also share a
common regeneration gas heater F-1301.
Gas from the HP fuel gas system passes through the Adip gas treating unit at
21.0 barg and at approximately 11,000 kg/hr and 30°C.
The temperature increases over C-1305, in the ADIP gas treating unit, to 43°C.
The gas passes through the Gas Drying Unit S-1305 to remove moisture.
The gas is then heated in the regeneration gas furnace F-1301 to 316°C
(310°C).
The gas is then supplied as required to the regeneration cycles of either the
propane molecular sieve C-1307A/B or the butane molecular sieve C-1308A/B.
b. Operating pressures
The operating pressure of the molecular sieves during the adsorption cycle is
determined by the back pressure controllers in the product rundown lines to
storage and the differential pressure controllers on the product lines
immediately downstream of the sieve beds.
The back pressure controllers are 13-PIC-53 for propane and 13-PIC-54 for
butane.
The PDRC’s will not open until the pressure in the bed is 1.7 barg above the
pressure in the product rundown line.
c. Adsorbing/Regeneration Cycles
Information applies to both systems based on 8 hour cycle.
However with current operation after installation of Merox Unit, space capacity is
available in the beds and cycle length of 4-5 days is achieved.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 6
The gas is vented through product recovery system while filling the absorbers
vessel.
To avoid overlap of the heating periods for butane and propane sieves, the two
cycles are displaced by a 4 hour period.
In addition, a half hour interval between the required operation of the heater allows
for some variation in the relative times between the two cycles.
1) At the end of the adsorbing period of 8 hours the valves for the units are
repositioned to place the regenerated adsorber on line.
2) To start the displacement of product from the spent adsorber, sweetened and
dehydrated gas is admitted to the top of the bed.
Product is displaced from the free void volume in the bed into the main product
outlet line.
3) There is a differential pressure cell at the base of the adsorber that detects the
level of liquid within the bed.
When the level has reached the bottom tangent line of the adsorption column
the cell will be set to reposition the valve to displace the liquid product
remaining in the bottom to the flare system through product recovery system
and starts the interval timer controlling displacement to flare.
When the timer (7 minutes) runs out, the adsorber is shut in until the sequence
control repositions the valves to the heating position.
4) Regeneration gas is taken from the regeneration gas heater at 316°C (310°C)
and passed into the base of the absorber. It exchanges heat with the
adsorbent, vaporizing adsorbed product and contaminants from the bed.
The gas plus de-adsorbed material from the bed is routed through an air cooler
to the fuel system through a back pressure regulator.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 8
5) At the end of the 5 hour period the sequence control will reposition the valves
for the purge step and start the purge interval timer.
During purge, clean product is admitted to the base of the adsorber with the
flow limited through a hand valve. It is vaporized by the hot molsieve bed and
the vapours displace regeneration gas out of the absorber through the air-in
cooler to the LP flare through product recovery system. 77 minutes have been
set for this step to keep the flow requirements low enough to prevent lifting of
the bed.
Product vapours generated by the purge liquid are about twice the total void
volume in the absorber.
When the purge interval time runs out, the valves are positioned for the cooling
and filling step.
6) Clean product passing through a larger hand valve enters the bed. As the
liquid rises, heat is transferred from the bed vaporizing the product.
Vaporized product leaves the adsorber and passes to the air cooler where it is
condensed.
After condensation it is returned to the main product line going to the product
cooling units.
Rates are specified that will cool the bed and refill it with liquid product in about
11 minutes.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 9
7) At the end of this time the sequence control will reposition the valves to
block in the bed to stand idle for 54 minutes before starting the adsorption
cycle.
This 54 minutes idle time is available for remedial action in the event of a
malfunction.
8) Flow rates for the various streams for each regeneration step are given in
the stream property tables.
These rates should be used as a guide for the initial settings on the various
hand valves and flow controls in the units.
d) Regeneration
1) Fuel gas is dried to a dew point of -18°C (80 ppm vol) in the gas dryer
S-1305, before passing to the regeneration gas heater.
S-1305 is a two tower fixed bed dryer, one tower drying and the other
regenerating or on standby, employing a high capacity alumina desiccant
(A 2-5).
The dryer is a fully automated unit, (see the Delair book for detailed
instructions).
2) The operating pressure of the propane and butane molecular sieves during
the regeneration step is determined by the back pressure controllers
13-PICA-23 (set at 18.0 barg) and 13-PICA-29 (set at 5.5 barg)
respectively.
e) Product Separators
Similarly during filling stage also the excess liquid product which may come
from absorbers was also going to flare/burnpit.
Propane Separator
Propane stream from molsieves after cooling in regeneration fin fan cooler
E-1314 A/B is diverted to propane separator V-1351, where liquid is retained
and gas is sent to flare system.
Butane Separator
Butane stream from molsieves after cooling in regeneration fin fan cooler
E-1315 diverted to the butane separator V-1352, where liquid is retained and
vapours are routed to flare system.
Operation of the molecular sieve units consist of the step wise programme as
detailed in drawings NG-1070/0 for propane and NG-1069/0 for butane.
This is initiated by the master cycling timer which keeps the proper order of
sequences and required time spacing between the two cycles.
1. Regeneration
During transition from one step to the next, both status lights of the
relevant steps are illuminated.
b) The valves used are tight shut off. Valve actuators are
of the double acting piston type. On air failure they maintain the existing
position ‘STAY PUT’.
f) The system has semi automatic panel operation and manual local
operation.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 13
They are primarily - with a common fault alarm for each unit - as follows
c) Filling and cooling time elapsed level has not actuated valves.
13-PICAL-23-1 in conjunction with 13-XV-16 during heating cycle allows ‘regen.’ gas
to flow to LP fuel gas.
13-XFV-53 Variable orifice flow valve to control rate of product during cooling and
filling in conjunction with opening of 13-XV-10.
13-XFV-55 Variable orifice flow valve to control purge rate in conjunction with
13-XV-12.
13-PDRC-25 Controls the differential pressure over the bed. It will control the
pressure of the bed at 1.5 barg higher than the pressure of the
product rundown line.
The valve will only open on a signal from dryer logic via solenoid
13-X-54 and will close on completion of regeneration.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 16
TAG NO FUNCTION
13-PDRC-31 Controls the differential pressure over the bed. It will control the
pressure of the bed at 1.7 barg higher than the pressure of the
product rundown line.
17-FRC-011/013 indicates butane flow to Merox Unit at 24933 kg/hr (39580 kg/hr).
The valve will only open on a signal from the dryer logic via
solenoid 13-X-55 and will close on completion of regeneration.
Design temperature is based on 40°C inlet and 329°C outlet. The normal operating
outlet temperature is 316C (310C).
Design pressure is based on 21.0 barg. The normal operating pressure is 19.0
barg.
Number of coils 1
Number of tubes 22
Supplemented by a single tube pilot burner. Facility for inserting a mobile ignition
unit.
High temperature and burner on, signal to 10-PR-1 and 10-PR-2 to continue.
to 13-PIC-126
e) Product Separators
During displacement of product from the spent molecular Sieve absorbers using
sweet dry gas, this stream is first routed to liquid product through regeneration
cooler. Subsequently on detection of low low level in adsorber the displacement
stream from regeneration cooler was originally designed to go to flare/burn pit.
This resulted in product loss.
Similarly during filling stage also the excess liquid product which may come from
absorbers was also going to flare/burn pit.
Propane Separator
Propane stream from absorbers after cooling in regeneration cooler E-1314 A/B is
diverted to propane separator V-1351 where liquid is retained and gas is sent to
flare system. Recovered liquid is recycled back to depropaniser C-1302 under flow
control cascaded with separator level control. Flow is by pressure difference
available between separator and depropaniser. Offspec propane produced during
start-up is manually diverted to depropaniser for recovery.
13-LEA-700 will alarm on low low level in separator and close separator outlet
SDV 13-XV-701. This will avoid gas passing to depropaniser.
13-LEA-701 will alarm on high high level and stop flow to separator by closing
13-XV-701 and open bypass valve 13-XV-702 diverting flow directly to flare
system.
Butane separator
Butane stream from molsieve bed after cooling in regeneration cooler E-1315 is
diverted to butane separator V-1352, where liquid is retained and gas is sent to
flare system. Recovered liquid is recycled back to debutaniser C-1303. Offspec
butane produced during start-up is manually diverted to debutaniser for recovery.
13-LEA-702 will alarm on low low level in separator and close separator outlet
valve 13-XV-703 as well as trip the butane transfer pump P-1352 A/B.
13-LEA-703 will alarm on high high level and stop flow to separator by closing
13-XV-704 and open bypass valve 13-XV-705 diverting flow directly to flare
system.
13-LG-703 locally indicates level in the separator and 13-TG-701 locally indicates
temperature.
The regeneration cycle has been modified since it’s original installation, to recover
product which is displaced from the molecular sieve immediately prior to
regeneration of that adsorber.
This modification has not been integrated into the existing sequence and therefore
the regeneration/recovery cycle requires operator intervention to successfully
operate.
The existing sequence is based on a mechanical cam type sequencer. The valves
included with the product recovery upgrade are not included in the overall logic,
(eg. Valves 13-XV-702, 13-XV-701 for propane and 13-XV-704, 13-XV-705 for
butane).
This section outlines the relevant points of attention for the molecular sieve
adsorber section
This must be checked and checked again. a list of faults, no matter how
small or insignificant the, may seem, must be made. The faults must be
corrected, then removed from the list. This is sometimes referred to as a
‘Punch’ list i.e. “This section is checked ‘PUNCHED OUT’ !”.
Spare sets of P&IDs may be used for this purpose. As each section is
completed it can be marked off on the P&ID. Sections should not be
missed out if done in this manner.
During water flushing a constant check must be made for dirt, scale and oil.
Ensure that all drains and vents are capped.
d) Ensure that the vessels containing molecular sieves have been filled to the
proper levels etc. This should be an operational duty to supervise the
filling, etc. and check levels prior to ‘boxing up’.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 30
2. Ensure that all fire fighting and safety equipments are available and in
there proper locations.
4. Check relief valve installation, ensuring that all block valves on duty
relief valves are CAR SEAL OPEN.
5. The internals, grids, trays, wire mesh, level tapping etc. should be
checked for correct installation.
6. Entry permits should be obtained and all safety rules strictly adhered to.
15. After filling, pressurizing with air and depressurising, purge all lines and
systems with nitrogen.
16. Ensure that line up is correct for normal use except that system should
be isolated from product rundowns and Merox Unit.
17. Commission fuel gas from fuel gas system and commence tightness
test in steps .
23. It should be realized that this will have to be carried out well in advance
of anticipated feed from the Merox Unit as each step will take time.
25. Thoroughly check system to ensure that all valves are in their
correct positions.
27. If any of the sequential valves have to be placed in the hand wheel
position, care must be taken to ensure that it is done correctly.
28. Variable orifice flow valves should be returned to a position for normal
operation.
33. Finally ensure that there are no unwanted items like drums etc.
remaining on site.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 33
When the ADIP treating section has been commissioned and the
charcoal filters are taken into operation the propane molecular sieves
should be started up in the following sequence
XV-1, XV-7, XV-3, XV-4, XV-5, XV-6, XV-2, XV-8 , XV-13 , XV-17,
XV-10, XV-12.
h) Line up to burnpit and slowly fill vessels with a small flow to burn pit.
i) When the vessels are filled with propane, (observe local indicators of
13-LIE-30, 31, 34, 35).
j) Open slowly the block valve in the inlet line until fully open.
1) Line up 13-PDRC-25.
r) Bring the sequence of steps in line with the butane molecular sieve
programme and have master timer set to appropriate time relative to
total cycle and remove master timer override.
NOTE:
h) Line up to burnpit and slowly fill vessels with a small flow to burn pit.
i) When the vessels are filled with propane, (observe local indicators of
13-XV-32, 33, 36, 37).
j) Open slowly the block valve in the inlet line until fully open.
1) Line up 13-PDRC-31.
o) Bring the sequence of steps in line with the propane molecular sieve
programme and have master timer set to appropriate time relative to
total cycle, remove master timer override.
NOTE:
a) Pre-Start-up Inspection
3. Check that air registers, the air damper, and flaps of observation
windows are clean, lubricated, and able to move freely.
5. Check that minimum stops have been set correctly on the air
damper and fuel gas control valves.
6. Check that all associated fire fighting facilities are present and in
useable condition.
1. Check that start-up bleed line for pilots and that burner cocks for
pilots and main burners are closed.
2. Remove fuel gas blind at battery limit and open battery limit cock
valve.
1. When all burner cocks are closed on pilot and main burner, the
lamp ‘ready for purge’ light will be on, lights will also be on local
panel until the furnace purge is completed.
4. The purge timer starts when burner cocks for all pilot and vain
burners are closed and stack damper is fully open.
d) Gas Testing
Note that the term ‘gas free’ denotes that the concentration of
hydrocarbons in air is not more than 4% of the lower explosion limit
as measured by an approved and accurately calibrated explosive
meter.
a. The level in the fuel gas KO Drum is below the trip value.
2. Press the “start ignition torch” button on the local panel. This
will :
After 10 seconds the flame rod holds the propane trip valve open
if a flame is detected, otherwise it will be closed. Flame detection
by the flame rod is indicated by the local panel lamp ignition on.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 40
1. Check that fuel gas pressure on the pilot header is correct for
burner start-up i.e. 0.3 barg. Ensure that stack damper and air
registers are in correct positions for start-up.
c. the fuel gas pressure on the pilot header is not above the
high trip limit of 1.2 burg.
3. Open the burner cock; and press the ‘start burner’ button on the
local panel. This will:
After 8 seconds the flame eye holds the burner trip valve open if
a flame is detected, otherwise it will be closed and the furnace
must be repurged (starting from step 3).
With the pilot in operation, and when the furnace is warmed up, the
furnace can be placed in readiness to start the main burner.
1. Set air register in position for main burner operation and throttle
damper to about 60% open position.
The main burner trip valve will open, admitting fuel gas to the
burners when
c. the flow through the furnace tube is above the low trip limit.
6. When the main burner is in operation check if flames are all right
and adjust air register if necessary.
7. When the main burner has been lit, and the regeneration gas
temperature at the furnace outlet is above the low temperature
alarm, a signal is given to the molecular sieve programmer to
start the heating timer.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 42
If the molecular sieves are to be stopped for a period longer than one week, the
vessels should be regenerated before the fractionation plant is stopped.
Displace the liquid in the adsorbing bed to flare by adjusting the relevant local
valves.
Then block in the vessels and depressurize via the depressurising valves
13-H-13, 14, 15, 16.
Depending on what has to be done the vessels should be purged with inert gas
and spaded off.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 43
5. EMERGENCY SHUTDOWN
General guide lines exist within the Emergency Shutdown Procedures (ESD) for
all the possible causes and types of shutdown.
The types of shutdown can be categorized into three different types i.e.
5.1 Depressurizing
Fuel gas to F-1301 pilot has a 1” vent line to atmosphere. This line is
used when commissioning the pilot burner.
The liquid level valves in the molecular sieve beds are net recognized as
actual shutdown valves but if their functions are not correct and carried
out properly then they can cause some inconvenience by delaying or
stopping the logic timer and programmer.
If the level in V-1320, LP fuel gas drum, rises above 50% it will trip
13-X-195, the fuel gas main supply valve to F-1301.
Other functions will stop the furnace or the programmer. They are
explained in the operational description.
Indirectly the procedure for cooling water failure within the Merox
Units and Adip Unit will affect the molecular sieves.
The ORBIT valve action on air failure is to ‘STAY PUT’ i.e. they will
stay in the position they were in when the air failure occurred.
Regeneration gas flow 13-FIC-30 and 13-FIC-32 will close but have
a bypass facility.
c) Power Failure
e) Fire
In the event of a serious fire the unit will have to be shutdown and
depressurized.
9. When all gas has burned off, ensure that no gas is passing to
F-1301
13. Purge furnace with air prior to any entry for repair etc.
QATAR PETROLEUM VOL : 1
SEC. : 5
NGL-1 OPERATING MANUAL PAGE : 48
The main faults that can affect the molecular sieve dryers have been
covered.
The seriousness of the failure, other than that which affects the rest of
NGL-1, should be considered.
c) In the case of air failure and power failure, the nature of the failure
and the position of the rest of the system would have to be taken into
account when making decisions.
VOLUME 1 SECTION 5