You are on page 1of 10

Pressure Drop Improvements

in a Fixed Bed Reactor


Significant reduction of pressure drop was achieved with the installation of two different catalyst
support systems. The modifications were very minor, inexpensive, resulting in energy savings and
increased production rates.

Venkat Pattabathula and David Craig


Agrium Inc.

Introduction reduce front-end pressure drop as most of the equipment

W
was operating close to its maximum allowable working
ith the natural gas prices continuing an pressure (mawp). One of the options was to reduce the
upward trend, there has been a push to ∆P across the shift converters.
reduce the front-end pressure drop in A project was implemented to reduce the ∆P in the
ammonia plants both to improve energy efficiency and to high temperature shift (HTS) converter with an axial-
increase production rates. In the past, the front-end pres- radial flow converter and a paper was presented on this
sure drop has been reduced by short loading catalyst vol- modification in the year 2000 AIChE Ammonia Safety
umes in the secondary reformer and in the high and low Symposium held in Seattle. Another opportunity for
temperature shift converters. This paper discusses how pressure drop reduction existed in the low temperature
significant pressure drop reductions were achieved with shift (LTS) guard and main bed reactors. The LTS guard
the installation of a catalyst support grid, and low differ- bed was added to the original plant design a few years
ential pressure (∆P) support balls in the shift converters. after initial start-up to extend and protect the LTS main
Analysis of modifications to the catalyst support system bed catalyst life. In early 2001, the upcoming LTS guard
and the resulting benefits are also addressed. These modi- catalyst change out was seen as a potential opportunity
fications were made in the Agrium plants located in Bor- to reduce front-end pressure drop. Any LTS guard ves-
ger, Texas and Redwater, Alberta. sel modifications would have to be cost effective, in that
it would take a minimum outage and entail no major
changes to the vessel.
PART A: The Borger plant LTS guard has a typical ‘elephant
stool’ gas collection and catalyst support system as
Background – Borger, Texas Plant shown in Figure 1. The ‘elephant stool’ carries the load
of the inert support and catalyst directly above the outlet
M.W. Kellogg originally designed Agrium Borger pipe. There is a solid plate on the top of the stool, which
Nitrogen Operations ammonia plant for 1000 stpd and is supported by vertical flat bars equally spaced around
over the last 30 years, the plant production rates were its circumference and resting on the bottom head. A
increased in steps to the current capacity of 1500 stpd. screen covers the cylindrical part of the ‘elephant stool’,
This was achieved through many debottlenecking pro- ensuring that the inert material will not escape into the
jects in the process equipment. It became necessary to

2002 31 AMMONIA TECHNICAL MANUAL


CATALYST BED

SCREEN

SUPPORT MATERIAL
ELEPHANT STOOL
WITH SCREEN

Figure 1: LTS Guard Vessel ‘Elephant Stool’ Gas Collection


And Catalyst Support System

outlet pipe. The ‘elephant stool’ design has a proven re- 95% of what can theoretically be achieved with an
liability in the industry; however, the dynamic gas col- empty vessel.
lection characteristics associated with the ‘elephant
stool’ and inert support media can lead to flow maldis-
tributions and additional pressure drop. Borger Ammonia Plant Modifications
Haldor Topsoe, Inc. (HTI) used Computational
Based upon the Haldor Topsoe, Inc. CFD studies, it
Fluid Dynamics (CFD) modelling to analyse different
was estimated that the pressure drop across the LTS guard
flow phenomena in both high and low temperature shift
bed could be reduced by 50%, from 12 psi to 6 psi, with
reactors. A CFD study was performed based upon a
the installation of a flat catalyst support grid and replace-
model that incorporated the reactor design, the existing
ment of the bulk of 3/4” balls with 2” support balls.
catalyst and inert support material, and the process con-
With the projected pressure drop savings, it was de-
ditions. The CFD model comprised a reactor section be-
cided to install the first catalyst support grid in the am-
ginning midway through the catalyst bed and extending
monia plant during LTS guard catalyst change out in
into the outlet pipe.
March 2001. Haldor Topsoe, Inc. supplied the new sup-
The CFD study clearly showed that there was a sig-
port grid in parts that could easily fit through the exist-
nificant pressure drop due to unrecoverable exit losses
ing manway. The parts include a support ring with its
from the reactor. The study also confirmed that there
support structure, and 24 pie-shaped sections of the
was a significant pressure drop in the inert support me-
support grid. The support grid was pre-assembled for
dia surrounding the ‘elephant stool’. Some of this pres-
testing in the maintenance workshop by the Borger Ni-
sure loss can be recovered by simply installing larger
trogen Operations (BNO) maintenance team. A picture
support material, but in order to get the maximum bene-
of the pre-assembled grid is shown below in Figure 2.
fit the void fraction and cross sectional entrance area
The catalyst was removed and the reactor inspected
would have to be increased.
before the support plate installation began. The existing
The CFD study also confirmed that the installation
screen on the ‘elephant stool’ was removed since it was
of a flat catalyst support grid around the top of the ‘ele-
no longer needed and would only cause flow resistance.
phant stool’ extending to the wall of the reactor would
A picture of the ‘elephant stool’ prior to screen removal
reduce the pressure drop through the support material by
is shown in Figure 3.

AMMONIA TECHNICAL MANUAL 32 2002


Figure 2: Pre-assembled Catalyst Support Grid

Figure 3: Old Screen Around ‘Elephant Stool’

The installation of the support grid took less than 3/4” balls was loaded on the 2” balls. The bulk of the
24 hours and was easily done by the BNO maintenance 3/4” support balls that were previously in the reactor
team under the supervision of the HTI mechanical spe- were essentially replaced by 2” support balls and the
cialist. The picture of the support ring taken during the in- void space below the support grid around the ‘elephant
stallation is shown in Figure 4. stool’. One-inch Raschig rings were reloaded on top of
The picture of the installed support grid taken during the catalyst bed, which had replaced the support balls in
the support ball loading process is shown in Figure 5. the earlier catalyst change out.
A larger layer of 2” alumina support balls was
loaded on the new support grid. Then a small layer of

2002 33 AMMONIA TECHNICAL MANUAL


Figure 4: Catalyst Grid Support Ring

Figure 5: Installed Support Grid During Support Ball Loading

The sketch on the following page shows the new It is estimated that the ∆P across the LTS guard at a
catalyst support system. 1500 stpd rate will be 4 psi, which is 6-8 psi lower than
The LTS guard bed was put in service on March 7, the previous ‘start of run’ reactor pressure drop. Because
2001, and the differential pressure across the vessel was of the significant ∆P improvements across LTS guard
measured to be 2 psi. Even for the low plant rate of bed; Agrium has decided to install the similar grid in the
1200 stpd, this low ∆P was a significant improvement as LTS main bed during the catalyst change out in 2002.
a result of using the Haldor Topsoe catalyst support grid
technology.

AMMONIA TECHNICAL MANUAL 34 2002


CATALYST BED

3/4" SUPPORT BALLS


2" SUPPORT MATERIAL
CATALYST SUPPORT GRID

VOID SPACE VOID SPACE

ELEPHANT STOOL

Figure 6: LTS Guard Vessel Catalyst Support Grid System (After Modifications)

The installation of the catalyst support grid has re- Conclusions


sulted in an increase of pressure at the suction of the
syngas compressor that has contributed to a lower en- 1. An analysis of the BNO LTS guard catalyst support
ergy consumption in the syngas compressor train at the systemmodifications shows that the pressure drop
same production rates. The modifications to the inter- from the catalyst/inert interface, through the outlet
nals of both the shift converters have allowed us to in- pipe, was reduced with the installation of a flat cata-
crease the plant production rates due to significant re- lyst support grid around the top of ‘elephant stool’
duction of front-end pressure drop. The following chart extending to the wall of the reactor.
shows the effect of the catalyst support grid on the LTS 2. The accuracy of CFD model was confirmed with the
guard bed pressure drop. actual pressure drop on the BNO LTS guard bed.
3. The larger size of the inert support material (2”) sur-
rounding the ‘elephant stool’ has a significant im-
Benefits pact on the reactor pressure drop.
4. The flat support grid design is relatively simple, the
From the achieved pressure drop reduction, the in- fabrication is inexpensive and the installation can eas-
stallation of catalyst support grid had a 4-month payout ily be done in an existing vessel in less than a day.
(based on $2.30 US/MMBtu gas cost). This was better 5. The pressure drop reduction was achieved due to
than the projected payout of 5 months as the actual pres- the increased void fraction, increased ‘elephant
sure drop improvement was higher than estimated. stool’ entrance area (no support media around the
‘elephant stool’), and the increased support media
particle size.

2002 35 AMMONIA TECHNICAL MANUAL


History of LTSG Reactor Pressure Drop
2001
100
14

Pressure Drop (kPa)


Pressure Drop (psi) 12 80

ut
10

O
60

e
ng
8

se
ha

ea
tC
6 40

cr
In
ys
al

e
4

at
at
20

R
C

!
2
0 ! 0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Figure 7: ∆P Across LTS Guard Bed

PART B: change. Details of the present loading and outlet col-


lector were sent to Synetix to determine the modeled
pressure drop on the existing vessel and internals.
Background – Redwater, Alberta Plant Synetix at this point reviewed the HTS, LTS guard and
The Agrium Redwater site has two ammonia plants main bed. The results of these studies showed that the
both designed by Bechtel / Exxon. Original nameplate greatest benefit would be to the HTS bed. Initial projec-
capacity for the plants was 540 and 1600 mtpd. Present tions showed a 4 - 5 psi pressure drop gain over the ex-
production rates are 800 mtpd and 1900 mtpd. The isting bed arrangement at start of run. The cost of the
plants were built in 1969 and 1983 respectively. The changes was relatively small and the modifications to
design of the larger ammonia plant is essentially a con- the internals were relatively simple and involved no
ventional ammonia plant design with a gas turbine ex- welding or modification to the pressure vessel itself.
haust, being used as source of combustion air for the
Primary Reformer. The modifications described in this Synetix Proposed Catalyst
paper were done on the larger ammonia plant. Bed Support System
The system proposed by Synetix was to replace the
Catalyst Support System
outlet collector and support material. CFD modeling had
The present design of the 1900-mtpd plant results in identified the support material and the zone around the
the Primary reformer/ Secondary Reformer operating outlet collector as the major source of pressure drop
close to its design pressure. The pressure limitation lim- within the vessel. The void fraction of traditional ceramic
its the front-end pressure, and therefore the throughput balls is relatively low resulting in a significant pressure
achievable in this plant. Therefore, any reduction in drop as the gas approaches the outlet collector. The CFD
pressure drop downstream of the Secondary Reformer modeling with the existing support system identified a
would benefit either the horsepower requirements on the 10.3-psi pressure drop across the bottom support and out-
synthesis gas compressor or increased throughput. let collector (Figure 10). This represented over 80% of
A turnaround was scheduled for June 2000, during our measured start of run pressure drop
this turnaround it was planned to change out the High The proposed system resulted in a larger diameter
Temperature shift bed. During the catalyst bid process, outlet collector and modified support material that re-
Synetix offered, with their catalyst, an option for install- sulted in a greater void fraction than traditional support.
ing a low-pressure drop system. As part of the offer, The pressure drop reduction by addition of the modified
Synetix offered computational fluid dynamics (CFD) support and outlet collector was estimated by CFD model-
modeling of the reactor to determine the benefits of the ing to be a 4.6-psi pressure drop reduction at start of run.

AMMONIA TECHNICAL MANUAL 36 2002


Installation sor or increased throughput. We believed the conserva-
tive approach was to measure the benefit on reduced
The installation of the outlet collector took ap- horsepower of the synthesis gas compressor. Due to
proximately 3–10 hour shifts to install due to the collec- other modeling projects, we already had a model of the
tor having to be assembled and welded inside the vessel. synthesis gas compressor. By changing the inlet pres-
All the parts of the outlet collector had been previously sure to the synthesis gas compressor model, we were
cut and sized to fit through the top nozzle. No welding able to determine the change in horsepower based on an
to the shell was required for this modification. increase in suction pressure. The horsepower change
meant a change in steam consumption for the turbine.
Since the ammonia plant exports steam into a common
Benefits plant system, the ability to export more high-pressure
The lower pressure drop could benefit the plant in steam meant a reduction in utility boiler load and gas
either reduced horsepower at the synthesis gas compres- savings.

Catalyst

Ceramic Support Balls of


decreasing size (1” -> ¼”)

Outlet Collector (Elephant


Stool) Diameter same as outlet
line

Figure 8: HTS Vessel Original Catalyst Support

Figure 9: Original Outlet Collector On HTS Vessel

2002 37 AMMONIA TECHNICAL MANUAL


HIGH TEMPERATURE SHIFT COMPUTATIONAL FLUID DYNAMICS with
spherical supports

500.54 psi
(34.52 bar)

P.d = 10.3 PSI (0.71 bar)


490.25 psi
(33.81 bar)

Figure 10: Estimated Pressure Drop with Ceramic Support Balls

AMMONIA TECHNICAL MANUAL 38 2002


HIGH TEMPERATURE SHIFT COMPUTATIONAL FLUID DYNAMICS with
STREAMLINE™ Low Pressure Drop System

499.24 psi
(34.43 bar)

P.d = 5.7 PSI (0.39 bar)


493.58 psi
(34.04 bar)

Figure 11: Estimated Pressure with Modified Support and Collector

Figure 12: Modified Outlet Collector

2002 39 AMMONIA TECHNICAL MANUAL


Performance Guarantee
As part of the contract with Synetix, a performance
guarantee for the pressure drop gain was supplied. The
guaranteed performance drop based on a fixed plant rate
was 4 psi, which was lower than the CFD modeling pre-
diction.

Actual Benefits
After the plant was restarted, the actual measured
pressure drop was between 4 – 4.5 psi; lower than the
previous start of run pressure drop. This was very close
to what the modeling had predicted and within the guar-
anteed pressure drop. Based upon the 4-psi pressure
drop reduction, the extra costs incurred to install this
support system had approximately a 6-month payout
(based on $2.30 US/ MMBtu gas cost).

Authors’ Acknowledgement
We would like to acknowledge both Haldor Topsoe
Inc. and Synetix for providing the new technology on
Figure 13: Shaped Ceramic Support Material catalyst bed support systems. We would also like to
thank the operations and maintenance teams of Agrium
The following sketch shows the new catalyst sup- Borger and Redwater Nitrogen Plants in implementing
port system. the pressure drop improvement projects.

CAT

16x1
36x36x10mm SUPPORT

MODIFIED OUTLET COLLECTOR 3" SUPPORT MATERIA

Figure 14: HTS Modified Catalyst Support System

AMMONIA TECHNICAL MANUAL 40 2002

You might also like