5.1.1.

17 All items and equipment though not specifically mentioned in the specification, but
needed to complete the system to meet the intent of the specification shall be deemed
to be included in the scope of the bidder.
5.1.1.18 It is not the intent to completely specify all details of design and construction, but
only to lay down broad sizing and quality criteria for the major equipment and
systems and it is expected that the equipments shall conform in all respects to high
standards of engineering, design and workmanship and shall be capable of
performing in continuous commercial operation up to the contractor’s guarantee in a
specified manner acceptable to the purchaser.

5.2 SCOPE OF SUPPLY AND SERVICES


5.2.1 Induced draft fan assemblies for each cell. The fan blades shall be of adjustable pitch type
and axial flow.
5.2.2 Fan drive motor along with base frame and Hood (Cover) for each cell, Motor shall be IE2
Energy efficient class.
5.2.3 Drive shaft assembly with flexible couplings & bearings for each cell if fan is gear box
driven.
5.2.4 Extended gear reducer, oil lines of SS material with dipstick assembly oil filter & drain for
each cell if fan is gear box driven.
5.2.5 Independent vibration switch and low oil level switch for each cell with 1 NO and 1 NC
contacts if fan is gear box driven.
5.2.6 Removable types Fills and spray nozzles with supporting arrangement.
5.2.7 Main distribution header and lateral pipes.
5.2.8 Drift Eliminators.
5.2.9 Hot water distribution header with lateral distribution pipes.
5.2.10 Cage Ladder for cooling tower from ground level to top of tower.
5.2.11 SS 304 bolts & nuts
5.2.12 Counter flanges with fastener at hot water inlet.
5.2.13 First fill of lubricants, oil, grease, etc,.
5.2.14 Domestic road-worthy packing.
5.2.15 Manual Door as required for maintenance.
5.2.16 Bird cage for fan at the top of Aux. cooling tower.