MSPL Limited
Ref 9
Rev
Standard Operating Procedure (SOP) 0.0
No.
Topic: SOP FOR INCOMING Date 01.02.2019
MATERIAL INSPECTION Page 1 of 11
3. RESPONSIBILITY:
3.1 Quality Cell – is responsible for preparing, approving and maintaining this
document.
3.2 Material Department - is responsible for ensuring the receiving inspection
function is complied with in accordance with this document
3.3 Inspection Engineers - are responsible for performing the receiving inspection
activities defined in this document.
3.4 Material Review Board – are responsible in final decision for acceptance/rejection
of special category items in case of discrepancy. MRB will be consisting of Plant
Head, Purchase Head and user HOD as decision taker.
4.2. IS Standards
7. ACTIVITY CHARACTERISTICS
Purchase Order,
Inspection Correct receipt
Drawing, Zero Rejection and
report, Test of materials as 1 Year by MRB
Vendor/TPIATes deviation in quality
Certificates per specification
t Reports
8. DEFINITION:
TC – Test Certificate
DR – Defect Report
9. AMENDMENT HISTORY:
Page
Current Current
Sl no. Amendment Description Number Issue Date
Ver. No. Rev. No
(s)
JOB
IDENTIFICATION
√ √ √ √ √ √ X X
11. INSTRUCTIONS:
An incoming inspection, also known as a receiving inspection or material inspection,
validates the quality of purchased materials based on set acceptance criteria. It is performed
by designated Inspection Engineer personnel in the Plant.
When notified that material that requires inspection has been received, gather relevant
documentation for the material, which may include Inspection Criteria, Component
Specification, Purchase Order, Vendor History, and Certificate of Compliance or Test.
Documentation may be paper or electronic format.
11.1. DOCUMENTATION VERIFICATION
Begin an Inspection Report (Part History Record) for the material. Record Item Number,
Item Description, Revision (if applicable), Date Received, Quantity received, Lot Number,
Purchase Order (PO) Number, Supplier ID, and Inspection Document(s) and revision. Record
the following documentation verification results on the Inspection Report.
11.1.1. Verify Engineer Drawings and Specifications
Verify that the engineering drawings and specifications used for inspection are at the
appropriate revision level.
15 INSPECT MATERIAL
11.1.11. Accept
A shipment of material is accepted if Document Verification is satisfactory, and the material
meets or exceeds all of the acceptance criteria in the Inspection Criteria. For sample
inspection, acceptance criteria is met if the number or percentage of nonconformities found in
the sample is less than or equal to the acceptance number for the sampling plan. Disposition
as nonconforming material any sample material found with nonconformities.
11.1.12. Reject
A shipment of material is rejected if Document Verification is not satisfactory, or if the
material does not meet one or more of the acceptance criteria in the Inspection Criteria. For
sample inspection, acceptance criteria is not met if the number or percentage of
nonconformities found in the sample is greater than or equal to the rejection number for the
sampling plan.
16 Disposition
11.1.13. Accepted Material
Complete the Inspection Report and Receipt Record, including quantity accepted, quantity
rejected, page numbering. Date, initial, and stamp the report. Attach material certifications to
the report if applicable.
Status the material "Accepted" by attaching the appropriate material label and making entries
in Data works.
Retain (file) the Inspection Report and the Supplier History Form. Move material to
inventory as required.
11.1.14. Rejected Material
The rejected item(s) is segregated from the acceptable material, and a Rejected (red tag) tag is
prepared and placed with the material/product to indicate that it is nonconforming. A Defect
Report (DR) in the inspection report format is prepared prior to the disposition and re-
processing of the nonconforming material/product.
The rejected material along with the DR and/or Reject tag will be placed in the
Nonconforming Material Hold area for discrepant material until dispositioned is approved by
Material Review Board (MRB) in case of special items like Grate plates, side plates,
imported spares, gearboxes, conveyor belts, fabricated items, etc.
12. EMS CONSIDERATION : Not Applicable
(*2) The width, length, weight and height tolerances that shall be used on materials/products
is +/- 5% unless otherwise specified by the Purchase Order or drawing/specification.
lot.
a) Part Number,
b) Lot or Batch, Date Code or Serial No.
Traceability,
c) Quantity,
d) Statement stating full compliance of
requirements,
e) Supplier Name,
f) Measurement Attribute Data (as required) and
g) Supplier written Approval
Annexure - 1
Department Inspection By
PO No. Supplier
Inspection Details :
Remarks:
Images: