Professional Documents
Culture Documents
a. Short write-up on Jetty along with Basic design and construction details.
Answer: The proposed development for the Crude oil Import terminal and related facilities is located at South Port,
Mundra, Gujarat. The location of offshore jetty has been proposed at 25 m CD natural contour to facilitate the 3,30,000
cbm Crude oil tanker having draft of about 22.0 m so that manoeuvring of the tanker will happen in the deep waters
having depths between 25 to 30 m CD. The sub-sea pipeline from off shore jetty will be laid at requisite depths under the
sea bed up to land fall point and then overland up to COT to facilitate transfer of crude from the vessel to Crude Oil
Tanks ashore.
b. Suitability of proposed Jetty for berthing of VLCC’s carrying 330000 cbm of Crude OIL.
Answer: As already mentioned under point (a), the jetty is being designed to handle VLCC upto 330,000 cbm.
c. Details of similar VLCC Jetty available/ operational in India or Abroad along with proven track records
Buckeye Bahamas Hub located at Freeport, Grand Bahamas Island has approximately 35 Lakh MT of storage capacity
and 8 berths, including 2 VLCC offshore berths. The google image and photographs of the Bahamas jetty is attached
below:
Fujairah VLCC Berth Dingjiakou, China VLCC Berth
d. Reasons for choosing Jetty over SBM along with providing pros & cons of Jetty.
Answer: In terms of overall project economics, Adani recommends to have a VLCC jetty as compared to SBM owing to
the below factors:
The Capex and Opex for SBM is relatively higher compared to jetty option; additional dry dock requirement for
SBMs makes it more cost intensive
VLCC Jetty is expected to have a lower project lifecycle cost than compared to SBM
Capex & Opex can be shared with HRRL once detailed engineering studies are carried out post
signing of definitive agreement
e. Draft available at Jetty at all times without dredging? Quantum of dredging and frequency, if dredging is
required?
Answer: The proposed offshore jetty has been located at natural contour of -25 m CD at approximately 2.8 km offshore
from western arm of south port breakwater. The seaward side of the jetty will be the berthing face of the Jetty. Typically,
the VLCC having a draft of 22 m will be handled with sufficient UKC (>15 % of deepest draft) at all times. The contours
from the shore to the offshore jetty location are gradually sloping from -2.7 m CD to -25 m CD. The slope of the sea bed
APSEZL confirms that draft to handle VLCC (carrying 330000 cbm of crude oil) will be maintained and if dredging is
At this location SBM is not possible as depth requirement for SBM is 30 mtrs while at proposed jetty location depth is
25 mtr.
The slope of the sea bed along with the contour of 5 m interval is shown below:
f. Reliability of jetty from operations point of view throughout the year and in all weather conditions?
Answer: Marine modelling study has been conducted for the proposed offshore jetty location and Wave rose diagram
along with downtime analysis has been carried out. (Refer Attached PFR)
As per wave rose diagram and directional distribution of significant wave height at the location of offshore jetty, wave
more than 1 to 1.5 m is almost Nil and hence, calm weather at jetty location is available throughout the year.
design.
On shore Pipeline 9 KM
Off shore pipeline 3 KM
j. Suitability of laying pipeline over the sea bed considering various marine features
Answer: The pipeline would be laid within a trench which would be created on the sea-bed and the top will be filled
with sand. This would give a protection to the crude pipeline from marine features and the practice is followed globally
for all such submarine pipelines.
Answer: The jetty would be provided with Marine Loading Arms (MLA) which would be capable of unloading crude at
the rate of 10,000- 12,000 cbm per hour thereby emptying a VLCC within 36 hours subject to suitable pumping rate by
the vessel.
l. Details of facilities/ resources available with APSEZL for OIL spill response, Firefighting, two way-Intelligent
Pigging, lighting & power at jetty.
Answer:
Oil spill plan and is equipped with latest oil spill equipment as per the Coast Guard requirement.
They have risk mitigation measures in place for handling any leakage/ spillage of crude oil from Jetty to COT.
APSEZL will be responsible for any impact to environment, marine life and Oil spill clearance subject to Vessel
The terminal will be self-sufficient in terms of firefighting facility and same will be built as per international
standards.
The ship also has its fire-fighting system. However, additionally the tugs have the firefighting capability details
Bi-directional pigging of pipeline from VLCC Jetty to COT and from COT to VLCC Jetty shall be provided.
Therefore, both at the jetty & COT end, there will be pig receiver cum launcher facility by APSEZL and HRRL
respectively. Pig launching pumps at COT end will be provided by HRRL with connection from crude header
and from service water as well. During pigging of pipeline from COT to VLCC Jetty, the ship’s tanks shall be
used at Jetty to receive pipeline inventory. Pigging from Jetty end shall be done using crude itself by using the
ship’s pumping system and pipeline inventory shall be received at any suitable tank in the COT.
Surge relief system will be part of COT scope of HRRL. Emergency shutdown and monitoring facilities
including OFC connectivity between Jetty & COT will be part of APSEZL scope.
Answer:
Following are the further scope of studies which is required once the project kicks in to execution stage:
Navigational simulation and mooring analysis for VLCC vessel
Offshore Geo-tech investigation at offshore island Jetty location as well as at regular interval of Sub-
Bathymetry for the proposed development area i.e along the subsea pipeline route and offshore jetty
location
Risk analysis
n. Identified Risks?
Answer:
Risks shall be identified during detailed Risk Analysis and suitable mitigation measures as per the Report will be put in
place.
o. Statutory rules, standards and Guidelines to which the entire facility will comply with?
Answer:
All permanent works expecting the crack width limitation criteria has been designed to the latest Indian codes of
practice, design standards, regulations and/or guidelines appropriate to the element of the jetty. When Indian standards
are not available for any particular application, other reputed international codes or widely accepted references have been
considered. The following is the list of main codes of practices used in the design.
Indian standards
IS 4651 (Part 1–5): Codes of Practice for Planning and Design of Ports and Harbors
IS 9527 (Part 3): Code of Practice for Design and Construction of Port and Harbor Structures
IS 875 (Part 3): Code of Practice for Design Loads for Building and Structures–Wind Load
British standards
API–RP–2A (WSD) 2000–12 (Twenty First edition) by American Petroleum Institute – Recommended practice
for planning, designing and constructing fixed offshore platforms – working stress design
API–Spec–2B 2001–07–01 (Sixth edition) by American Petroleum Institute – Specification for the fabrication
Answer:
The schedule shall be cover the proposed development of Offshore jetty at -25 m CD contour along with sub-sea
pipeline, Landfall point and land pipeline up to COT. The construction of the offshore jetty at -25 m CD will be at
critical path. However, the same will constructed, installed and commissioned as per schedule mentioned in Term Sheet.
q. In case of non-availability of Jetty for extended period, what is the recourse available to unload crude oil and
deliver to the COT/Refinery?
Answer: We don’t such situations except for Force Majeure conditions, in which case FM clauses shall apply and the
same shall be captured in the definitive agreement. However, in case Landing & Shipping declaration is not granted to
APSEZL, then alternate arrangement for decanting of crude oil will be made as per terms and conditions mentioned in
term sheet.
a. source of water for firefighting and routing of line from source and its ROU.
b. source of water for potable use and routing of line from source and its ROU.
c. Details of CRZ Mapping- Refer Finalized COT plot map
d. Coordinates of the plot- Refer Finalized COT plot map
e. Marking of roads around the plot- Refer Finalized COT plot map
u. Who is a Co-developer? Is any approval required to get the Co-developer status? If yes, what is the time
required to get the approval and who gives the approval?
Answer: A Co-developer is one who intends to provide any infrastructure facilities in the identified area in the SEZ.
The proposal under sub-section (11) of section 3 of SEZ Rules for providing infrastructural facilities in the Special
Economic Zone as a Co-developer shall be made in Form A1 to the concerned Development Commissioner who, within
a period of fifteen days, shall forward it to the Board (under Ministry of Commerce) with his recommendations. As per
eligibility, Board has the right to approve the proposal.
In case co-developer status is not received, the land will get converted to DTA (Domestic Tariff Area) by de- notification
of SEZ status.
v. At what stage, APSEZL will hand over the land to HRRL (before or after getting the co-developer status)?
Answer: After co-developer status is granted, APSEZL can handover the land and construction activities can be started.
u. Berthing Policy and tariff Structure as charged to IOCL (Mentioned on the page below)
The above charges are for Tug hire for inward and outward custom clearance.
On demand charges not applicable for every vessel call-As per published Berthing Policy and Tariff
Structure (BPTS) as published on www.adaniports.com
(Mentioned as additional services in term sheet as and when required and requested)
Pilot attendance charge-When a pilot is required to stay on board the vessel from berthing to sailing
on request of the master.
Lay-up berth hire/idling charge-In case vessel incapable of commence cargo discharge within three
hours of all fast or unable to vacate berth within 3 hrs of completion of discharge
Pilotage cancellation & pilotage detention charge
Warping/turnaround charge per GT of vessel
Tug/ Boat hire charges beyond the stipulated 5 hrs slab
Cold move charges (Planned & Unplanned)
Immobilization and additional charge as per requirement
Additional tug hire/country craft charges on specific request of master/vessel agent
Tariff for bollard pull test
Tariff for diving operation
Misc. service charges
o Fresh water supply
o Garbage collection
o Ambulance. etc. (BPTS may be referred for all such charges)
Fire-fighting charges in case of fire onboard
Discharge of ship generated waste
STS operation charges on specific request
Crane hire charges
Charges pertaining to services provided in unforeseen circumstances
As per mutual discussion