DATE : SEPTEMBER 10, 2019

TO : CAV

PROJECT : PROSENIUM PHASE 2A

ATTENTION : ENGR. DON MENDONES

Project Manager

THRU : Engr. Rodolfo Elmido

Project In Charge

SUBJECT : CEILING ENCLOSURE

We are calling your attention for the ceiling enclosure as per our monitoring you handed over
49th floor. As per schedule you have to start September 6, 2019 for 53 rd floor. You have to catch
up 50th to 51st floor should be handed over September 6, 2019. Our target schedule for this
week 53rd floor end of September 2019.

For your action, .

Thank you,

L.G.BAYANIN JR.

PGCDC-MEPF COORDINATOR