Professional Documents
Culture Documents
Definition
Question and Answer Sessions
Intro and Supporting Diagrams
Bulk Electric System
Definition
Question and Answer Sessions
Intro and Supporting Diagrams
What is the Bulk Electric System?
Exclusions
The Bulk Electric System and
(established by the Definition)
Inclusions Rules of
(established Procedure
through
procedures)
3 RELIABILITY | ACCOUNTABILITY
Many Resources to Assist You
• Bulk Electric System Definition Reference Document
Describes the application of the BES Definition
• BES Notification Review Guidelines
Describes how ERO Enterprise staff will review Self‐Determined Notifications
submitted through BESnet
• BES Exception Request Evaluation Guidelines
Describes how ERO Enterprise staff will review Exception Requests submitted
through BESnet
• BES Implementation Guidance Document (pending)
Outlines standards applicability and registration expectations
4 RELIABILITY | ACCOUNTABILITY
Many Resources to Assist You
• BESnet Application Users Guide
Manual for the online BESnet application
• Frequently Asked Questions (FAQ)
Explains application, submittal, and process for BES Definition implementation
• FERC Orders 773 and 773‐A
Regulations approving modified BES definition
• NERC Rules of Procedure
Section 500 and Appendix 5C
• Various White Papers
Providing Technical Justification
5 RELIABILITY | ACCOUNTABILITY
For Additional Information
http://www.nerc.com/pa/RAPA/Pages/BES.aspx
6 RELIABILITY | ACCOUNTABILITY
BES Project Web Site
7 RELIABILITY | ACCOUNTABILITY
Training Webinars and Activities
http://www.nerc.com/pa/RAPA/Pages/BES.aspx
BES Business Process Q&A Webinars
June 5 June 11 (with PC/OC meetings in Orlando)
June 16 June 23
June 30
NERC BESnet Training Webinars
June 17 June 18 June 19 June 20
June 24 June 25 June 27
Refer to Implementation Schedule on Website
for schedule details
8 RELIABILITY | ACCOUNTABILITY
9 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I1
10 RELIABILITY | ACCOUNTABILITY
Inclusion I1 - Transformers
Figure I1‐1: Typical Two Winding Transformer (BES)
Figure I1‐3: Typical Two Winding Transformer (non‐BES)
11 RELIABILITY | ACCOUNTABILITY
Inclusion I1 - Transformers
Figure I1‐2: Typical Three Winding Transformer (BES)
Figure I1‐4: Typical Three Winding Transformer (non‐BES)
12 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I2
13 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
14 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
19 MVA 19 MVA
> 100kV
19 MVA 19 MVA
Generator Site Boundary
Figure I2-3: Multiple Generators at a Single Site (BES)
15 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
15 MVA 15 MVA
> 100kV
15 MVA 25 MVA
Generator Site Boundary
16 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
The generation site has generation with a gross aggregate nameplate
rating greater than 75 MVA (actual 79 MVA) connected through the
high-side of the step-up transformers at a voltage of 100 kV or above.
By the application of Inclusion I2, the generation site is included in
the BES.
> 100kV
> 100kV
< 100kV
The generator step-up transformers,
associated with the 10 MVA generator,
including the interconnecting bus work are
> 100kV > 100kV < 100kV considered a BES Element. The generator
contributes to the gross aggregate
< 100kV < 100kV nameplate rating of the site.
< 100kV
< 100kV
50 MVA 19 MVA
17 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
18 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I4
19 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Figure I4-1 Dispersed Generation Site (Single Voltage Transformation) – Wind Farm
20 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Typical dispersed generation site and substation
design (single transformation of voltage level) with a
gross aggregate nameplate rating of 80 MVA
(Individual Generator Unit Rating: 2 MVA). By
application of Inclusion I4 the dispersed power
producing resources and the Elements from the point
of aggregation to the common point connection are
BES Elements.
Green indicates the portions of the Collector
System that are not included in the BES.
Blue identifies the dispersed power producing
resources and BES Elements between the point
where those resources aggregate to greater than 75
MVA to a common point of connection at a voltage
of 100 kV or above.
Configuration
The common point of connection is where the
not relevant to < 100kV / > 100kV individual transmission Element(s) of the
collector system is connected to the 100 kV or
determination. higher Transmission system. (Note: This point is
typically specified in the respective
Transmission Owner and Generator Operator
Interconnection Agreements.)
> 100kV
Figure I4-2 Dispersed Generation Site (Unknown Collector System Configuration) – Wind Farm
21 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Dispersed generation site and substation design (single transformation of voltage level) with a gross
aggregate nameplate rating of 80 MVA (Individual Photovoltaic Bank Rating: 20 MVA). By application of
Inclusion I4 the Photovoltaic Cells & Inverters (generators) are included in the BES.
Green indicates the portions of the Collector System that are not included in the BES.
Blue identifies BES dispersed power producing resources (Photovoltaic Cells & Inverters) and the
BES Elements between the point of aggregation and the common point of connection.
The point of aggregation is where the individual generator name plate ratings of the
dispersed generation total > 75 MVA (actual 80 MVA) and a failure would result in
loss of 75 MVA capacity or greater to the BES.
Figure I4-3 Dispersed Generation Site (Single Voltage Transformation) – Solar Array
22 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Figure I4-4 Dispersed Generation Site (Multiple Voltage Transformations) – Solar Array
23 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I5
24 RELIABILITY | ACCOUNTABILITY
Inclusion I5 – Reactive Power
Devices
Reactive Resource ‘1’ is connected
through the tertiary winding of a
transformer that meets the inclusion criteria
established by Inclusion I5 (i.e., through a
transformer that is designated in Inclusion
I1) and is therefore considered to be a BES
Element.
Reactive Resource ‘2’ is connected
directly to the station bus ( > 100 kV)
and is therefore considered to be a 1
BES Element.
> 100kV
> 100kV
Figure I5‐1: Reactive Resources (BES & non‐BES)
25 RELIABILITY | ACCOUNTABILITY
EXCLUSIONS
E1
26 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only
27 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only
A B C
> 100 kV
D E F
Substation
Boundary
Sub-100 kV Loop
< 50 kV
To Load To Load
Figure E1-2: Multiple Radial Systems (Underlying Loop Facilities < 50 kV)
28 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only
A B C
> 100 kV
D E F
Substation
Boundary
Sub-100 kV Loop
To Load To Load
29 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV
30 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV
31 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV
> 100kV
< 100kV / < 100kV < 100kV
15 MVA
Blackstart Resource
Generator Site Boundary
The generator has been
identified as a Blackstart To Load
Resource by application of
Inclusion I3.
Figure E1-6: Radial System: Blackstart Resource
32 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
Figure E1-7: Radial System: Multiple (BES & non-BES) Generation Resources (Non-Retail)
33 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV
Blue identifies the BES (included) The single point of connection is where the radial
radial system. The depicted radial system (group of contiguous transmission
system does not meet the exclusion Elements) emanates at a voltage of 100 kV or
criteria established in Exclusion E1b higher from the Transmission system.
due to the presence of > 75 MVA
gross aggregate nameplate rating of
connected non-retail generation
(actual 85 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV
12 MVA
> 100kV
< 100kV
< 100kV
> 100kV
14 MVA
34 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV
Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 69 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV
12 MVA
> 100kV
< 100kV < 100kV
> 100kV
14 MVA
35 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
Figure E1-11: Radial System: Generation Resource (Non-Retail) & Serving Load
36 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
Figure E1-12: Radial System: Generation Resource (Non-Retail) & Serving Load
37 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
Figure E1-13: Radial System: Generation Resource (Non-Retail) & Serving Load
38 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
> 100 kV
Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 69 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV
Figure E1-14: Radial System: Generation Resource (Non-Retail) & Serving Load
39 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
> 100 kV
Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 57 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV
Generator Site
< 100kV / > 100kV
Boundary
To Load
< 100kV / > 100kV 10 MVA The substation
transformers are not
part of the BES since
both (primary and
Customer owned secondary) terminals
generation (retail) and are not operated at >
> 100kV associated customer 100 kV as per
< 100kV owned equipment Inclusion I1.
excluded from the BES
by application of To Load
14 MVA Exclusion E2
Figure E1-15: Radial System: Generation Resource (Retail & Non-Retail) & Serving Load
40 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Normally OPEN Switching Device
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.
Substation
> 100kV Boundary
> 100kV < 100kV
Substation < 100kV
Boundary
< 100 kV
< 100 kV
To Load
The normally open (N.O.) device Normally Open To Load
between the radial sub-100 kV systems (N.O.)
does not affect this exclusion.
Figure E1-16: Radial System: Normally Open Switching Device between Load Serving Radial Systems
41 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.
Substation
> 100kV Boundary
> 100kV < 50kV
Substation < 50kV
Boundary
< 50 kV
< 50 kV
To Load
The normally closed (N.C.) Normally Closed To Load
device between the radial
systems operating < 50 kV
(N.C.)
does not affect this exclusion.
Substation
> 100kV Boundary
> 100kV < 100kV / > 50kV
Substation
< 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
To Load
The normally closed (N.C.) device Normally Closed To Load
between the radial systems operating at
voltages < 100kV and > 50 kV affects this
(N.C.)
exclusion.
> 100 kV
Substation
> 100kV Boundary
> 100kV < 50kV
Substation < 50kV
Boundary
< 50 kV
< 50 kV
To Load
The normally closed (N.C.) Normally Closed To Load
device between the radial
systems operating < 50 kV
(N.C.)
does not affect this exclusion.
Figure E1-19: Radial System: Normally Closed Switching Device (> 100 kV)
between Load Serving Radial Systems with a < 50 kV Loop
44 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.
Substation
> 100kV Boundary
> 100kV < 100kV / > 50kV
Substation
< 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
To Load
The normally closed (N.C.) device Normally Closed To Load
between the radial systems operating at
voltages < 100kV and > 50 kV requires
(N.C.)
evaluation based on Exclusion E3.
46 RELIABILITY | ACCOUNTABILITY
Exclusion E2 Behind-the-Meter
Industrial Generation
Figure E2-1: Behind-the-Meter Generation: Net Capacity to the BES Less Than 75 MVA
47 RELIABILITY | ACCOUNTABILITY
Exclusion E2 Behind-the-Meter
Industrial Generation
Cogeneration Operation: Net capacity to the BES is > 75 MVA (Actual 100 MVA)
> 100kV
M 50 MVA to Industrial
Process
Figure E2-2: Behind-the-Meter Generation: Net Capacity to the BES Greater Than 75 MVA
48 RELIABILITY | ACCOUNTABILITY
EXCLUSIONS
E3
49 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
10 MVA 15 MVA
Blue identifies BES 30 MVA
(included) local The generators (non-retail) have a gross
network. The included individual nameplate rating < 20 MVA
local network does not (actual 10 MVA & 15 MVA) and the
meet the exclusion To Load generation site has generation with a
criteria established in gross aggregate nameplate rating < 75
25 MVA
MVA (actual 25 MVA). By application
Exclusion E3a. due to the < 100kV of Inclusion I2 the generators are not
M
presence of the BES
138kV considered BES Elements.
generator identified by
Inclusion I2. (See textbox
To Load Customer owned generation <300kV
associated with the 30
behind the customer’s meter
MVA Generator). is excluded from the BES by 230kV
< 100kV application of Exclusion E2.
138kV
The substation transformers are
not part of the BES since both
(primary and secondary) terminals
are not operated at > 100 kV as per
Inclusion I1.
The multiple points of connection are where Transformer voltages are utilized for
230kV the local network (group of contiguous illustrative purposes only. Actual voltages
Power 138kV
transmission Elements) emanates at a voltage of associated with local networks will vary
100 kV or higher from the Transmission system.
Flow 230kV depending on the system configuration.
10 MVA 15 MVA
15 MVA
The local network does not The generators (non-retail) have a gross
meet the exclusion criteria individual nameplate rating < 20 MVA
established in Exclusion E3 due (actual 10 MVA & 15 MVA) and the
to the following: To Load generation site has generation with a
gross aggregate nameplate rating < 75
25 MVA
MVA (actual 25 MVA). By application
Power flows out of the
network system into the
< 100kV of Inclusion I2 the generators are not
M
interconnected 138kV considered BES Elements.
Transmission system
(E3b.) Customer owned generation
To Load <300kV
behind the customer’s meter
is excluded from the BES by 230kV
< 100kV application of Exclusion E2.
138kV
The substation transformers are
not part of the BES since both
(primary and secondary) terminals
are not operated at > 100 kV as per
Inclusion I1.
The multiple points of connection are where Transformer voltages are utilized for
230kV the local network (group of contiguous Power illustrative purposes only. Actual voltages
138kV
transmission Elements) emanates at a voltage of Flow associated with local networks will vary
100 kV or higher from the Transmission system. 230kV depending on the system configuration.
53 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
54 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV
< 300 kV
Operated at voltages
< 300 kV
Power only flows into the
networked system (E3b.) The normally open (N.O.)
Assumed that the
device between the radial
networked system is not
part of a Flowgate or
systems does not affect this
transfer path and is not exclusion.
monitored in an IROL
(E3c.)
Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
55 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV
< 300 kV
Power
Flow
The network does not meet the The normally open (N.O.)
exclusion criteria established in
device between the radial
Exclusion E3 due to power
flowing out of the networked
systems does not affect this
system (E3b.). exclusion.
Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
56 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV
Power
Flow
< 300 kV
Power
Flow
The presence of the sub-
The local network meets the 100 kV loop establishes
exclusion criteria established in multiple points of
Exclusion E3 by the following: connection at a voltage
level of 100 kV or higher to
Operated at voltages the Transmission System.
< 300 kV
Power only flows into the
networked system (E3b.)
Assumed that the
networked system is not
part of a Flowgate or Normally Closed
transfer path and is not
monitored in an IROL (N.C.)
(E3c.)
Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
Normally Closed
(N.C.)
To Load
< 100 kV / > 50 kV To Load
The normally closed (N.C.) device between The substation transformers are not part of the
the sub-100 kV systems establishes a loop BES since both (primary and secondary)
configuration which requires evaluation based terminals are not operated at > 100 kV as per
on Exclusion E3. Inclusion I1.
Figure E3-8: Local Network (non-BES) with Sub-100 kV Looped Facilities (Switching Devices Identified: N.C. > 100 kV &
N.C. < 100 kV/> 50 kV)
57 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV
Power
Flow
< 300 kV
Normally Closed
(N.C.)
Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV
Normally Closed
(N.C.)
To Load
< 100 kV / > 50 kV To Load
The normally closed (N.C.) device between
The substation transformers are not part of the
the sub-100 kV systems establishes a loop
BES since both (primary and secondary)
configuration which requires evaluation based
terminals are not operated at > 100 kV as per
on Exclusion E3.
Inclusion I1.
Figure E3-9: Local Network (BES) with Sub-100 kV Looped Facilities
58 (Switching Devices Identified: N.C. > 100 kV & N.C. < 100 kV/> 50 kV) RELIABILITY | ACCOUNTABILITY