You are on page 1of 58

Bulk Electric System

Definition
Question and Answer Sessions
Intro and Supporting Diagrams
Bulk Electric System
Definition
Question and Answer Sessions
Intro and Supporting Diagrams
What is the Bulk Electric System?

The Bulk Power System


(established by Section 215 of the FPA)

Exclusions
The Bulk Electric System and
(established by the Definition)
Inclusions Rules of
(established Procedure
through
procedures)

3 RELIABILITY | ACCOUNTABILITY
Many Resources to Assist You

• Bulk Electric System Definition Reference Document 
Describes the application of the BES Definition

• BES Notification Review Guidelines 
Describes how ERO Enterprise staff will review Self‐Determined Notifications 
submitted through BESnet

• BES Exception Request Evaluation Guidelines
Describes how ERO Enterprise staff will review Exception Requests submitted 
through BESnet

• BES Implementation Guidance Document (pending)
Outlines standards applicability and registration expectations

4 RELIABILITY | ACCOUNTABILITY
Many Resources to Assist You

• BESnet Application Users Guide
Manual for the online BESnet application  

• Frequently Asked Questions (FAQ) 
Explains application, submittal, and process for BES Definition implementation

• FERC Orders 773 and 773‐A
Regulations approving modified BES definition 

• NERC Rules of Procedure 
Section 500 and Appendix 5C

• Various White Papers 
Providing Technical Justification

5 RELIABILITY | ACCOUNTABILITY
For Additional Information

http://www.nerc.com/pa/RAPA/Pages/BES.aspx
6 RELIABILITY | ACCOUNTABILITY
BES Project Web Site

7 RELIABILITY | ACCOUNTABILITY
Training Webinars and Activities

http://www.nerc.com/pa/RAPA/Pages/BES.aspx
BES Business Process Q&A Webinars
June 5 June 11 (with PC/OC meetings in Orlando)
June 16 June 23
June 30

NERC BESnet Training Webinars 
June 17 June 18 June 19 June 20
June 24 June 25 June 27

Refer to Implementation Schedule on Website
for schedule details 
8 RELIABILITY | ACCOUNTABILITY
9 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I1

10 RELIABILITY | ACCOUNTABILITY
Inclusion I1 - Transformers

The transformer’s primary and


secondary terminals are
operated at 100 kV or above, > 100kV
and therefore the transformer is > 100kV
included in the BES by
application of Inclusion I1.

Figure I1‐1: Typical Two Winding Transformer (BES)

Figure I1‐3: Typical Two Winding Transformer (non‐BES)

11 RELIABILITY | ACCOUNTABILITY
Inclusion I1 - Transformers

Figure I1‐2: Typical Three Winding Transformer (BES)

Figure I1‐4: Typical Three Winding Transformer (non‐BES)

12 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I2

13 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources

The generator has a gross individual nameplate > 100kV


rating > 20 MVA and is connected through the < 100kV
high-side of the step-up transformer at a voltage
of 100 kV or above. By application of Inclusion
I2 the generator including the generator
terminals through the high-side of the step-up
transformer is included in the BES. > 20 MVA

Figure I2-1: Single Generator (BES)

Figure I2-2: Single Generator (non-BES)

14 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
19 MVA 19 MVA

< 100kV < 100kV


> 100kV > 100kV

> 100kV

> 100kV > 100kV


< 100kV < 100kV

19 MVA 19 MVA
Generator Site Boundary
Figure I2-3: Multiple Generators at a Single Site (BES)

15 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
15 MVA 15 MVA

< 100kV < 100kV


> 100kV > 100kV

> 100kV

> 100kV > 100kV


< 100kV < 100kV

15 MVA 25 MVA
Generator Site Boundary

Figure I2-4: Multiple Generators at a Single Site (BES & non-BES)

16 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources
The generation site has generation with a gross aggregate nameplate
rating greater than 75 MVA (actual 79 MVA) connected through the
high-side of the step-up transformers at a voltage of 100 kV or above.
By the application of Inclusion I2, the generation site is included in
the BES.

> 100kV

> 100kV
< 100kV
The generator step-up transformers,
associated with the 10 MVA generator,
including the interconnecting bus work are
> 100kV > 100kV < 100kV considered a BES Element. The generator
contributes to the gross aggregate
< 100kV < 100kV nameplate rating of the site.

< 100kV
< 100kV

50 MVA 19 MVA

Generator Site Boundary 10 MVA

Figure I2-5: Multiple Generators at a Single Site (BES)

17 RELIABILITY | ACCOUNTABILITY
Inclusion I2 – Generating
Resources

Figure I2-6: Multiple Generators at a Single Site (BES & non-BES)

18 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I4

19 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources

Figure I4-1 Dispersed Generation Site (Single Voltage Transformation) – Wind Farm

20 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Typical dispersed generation site and substation
design (single transformation of voltage level) with a
gross aggregate nameplate rating of 80 MVA
(Individual Generator Unit Rating: 2 MVA). By
application of Inclusion I4 the dispersed power
producing resources and the Elements from the point
of aggregation to the common point connection are
BES Elements.
Green indicates the portions of the Collector
System that are not included in the BES.
Blue identifies the dispersed power producing
resources and BES Elements between the point
where those resources aggregate to greater than 75
MVA to a common point of connection at a voltage
of 100 kV or above.

Configuration
The common point of connection is where the
not relevant to < 100kV / > 100kV individual transmission Element(s) of the
collector system is connected to the 100 kV or
determination. higher Transmission system. (Note: This point is
typically specified in the respective
Transmission Owner and Generator Operator
Interconnection Agreements.)
> 100kV

The point of aggregation is where the


individual generator name plate ratings of the
dispersed generation total > 75 MVA (actual
80 MVA) and a failure would result in loss of
75 MVA capacity or greater to the BES.

Figure I4-2 Dispersed Generation Site (Unknown Collector System Configuration) – Wind Farm

21 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources
Dispersed generation site and substation design (single transformation of voltage level) with a gross
aggregate nameplate rating of 80 MVA (Individual Photovoltaic Bank Rating: 20 MVA). By application of
Inclusion I4 the Photovoltaic Cells & Inverters (generators) are included in the BES.
Green indicates the portions of the Collector System that are not included in the BES.
Blue identifies BES dispersed power producing resources (Photovoltaic Cells & Inverters) and the
BES Elements between the point of aggregation and the common point of connection.

The common point of


connection is where the
individual transmission
Element(s) of the collector
system is connected to the 100
kV or higher Transmission
< 100kV / > 100kV system. (Note: This point is
> 100kV typically specified in the
respective Transmission Owner
and Generator Operator
Interconnection Agreements.)

Photovoltaic Cells &


Inverters (Banks)

The point of aggregation is where the individual generator name plate ratings of the
dispersed generation total > 75 MVA (actual 80 MVA) and a failure would result in
loss of 75 MVA capacity or greater to the BES.
Figure I4-3 Dispersed Generation Site (Single Voltage Transformation) – Solar Array

22 RELIABILITY | ACCOUNTABILITY
Inclusion I4 – Dispersed Power
Producing Resources

Figure I4-4 Dispersed Generation Site (Multiple Voltage Transformations) – Solar Array

23 RELIABILITY | ACCOUNTABILITY
INCLUSIONS
I5

24 RELIABILITY | ACCOUNTABILITY
Inclusion I5 – Reactive Power
Devices
Reactive Resource ‘1’ is connected
through the tertiary winding of a
transformer that meets the inclusion criteria
established by Inclusion I5 (i.e., through a
transformer that is designated in Inclusion
I1) and is therefore considered to be a BES
Element.
Reactive Resource ‘2’ is connected
directly to the station bus ( > 100 kV)
and is therefore considered to be a 1
BES Element.

2 > 100kV/< 100kV

> 100kV

> 100kV

> 100kV > 100kV


< 100kV < 100kV

Reactive Resource ‘3’ is connected through a


dedicated transformer with a high-side voltage of > 4
100 kV and is therefore considered to be a BES LOAD
Element. The dedicated transformer does not meet the
inclusion criteria established by Inclusion I1 and is Reactive Resource ‘4’ is connected directly
therefore not considered to be a BES Element. to the station bus (< 100 kV), and is not
connected through a dedicated transformer
with a high-side voltage of 100 kV or higher
or through a transformer that is designated in
Inclusion I1, and is therefore not considered
to be a BES Element.

Figure I5‐1: Reactive Resources (BES & non‐BES)

25 RELIABILITY | ACCOUNTABILITY
EXCLUSIONS
E1

26 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only

Figure E1-1: Radial System: Serving Only Load

27 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only
A B C

> 100 kV

D E F

Green identifies non-


The single points of
BES (excluded) radial
connection are where
systems.
the radial systems
(group of contiguous
transmission
Elements) emanate at
> 100 kV a voltage of 100 kV or
higher from the
Transmission system.

Substation
Boundary

> 100kV > 100kV


< 50kV < 50kV

Sub-100 kV Loop

< 50 kV

To Load To Load

Figure E1-2: Multiple Radial Systems (Underlying Loop Facilities < 50 kV)

28 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.a Serves Load Only
A B C

> 100 kV

D E F

The presence of the sub-100 kV loop (see text box


below) establishes multiple points of connection at a
> 100 kV
voltage level of 100 kV or higher to the
Transmission System. Therefore, this scenario
cannot be analyzed under Exclusion E1, however,
the configuration shown may be eligible for
exclusion as a ‘local network’.

Substation
Boundary

> 100kV > 100kV


< 100kV / > 50kV < 100kV / > 50kV

Sub-100 kV Loop

< 100kV / > 50kV

To Load To Load

Figure E1-3: Impact of Sub-100 kV Looped Facilities

29 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV

Blue identifies the BES (included)


radial system. The included radial
system from the high-side connection
The single point of connection is
on the generator step-up transformer
where the radial system (group
to the single point of connection of > 100 kV of contiguous transmission
100 kV or above does not meet the
Elements) emanates at a voltage
exclusion criteria established in
of 100 kV or higher from the
Exclusion E1b due to the presence of
Transmission system.
a BES generator (See textbox below).

The generator has a gross


individual nameplate rating > 20
MVA (actual 25 MVA) and is
connected through the high-side > 100kV
of the step-up transformer at a < 100kV
voltage of 100 kV or above. By
application of Inclusion I2 this
unit is a BES Element. 25 MVA

Figure E1-4: Radial System: Single BES Generation Resource

30 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV

Green identifies non-BES


(excluded) radial system. The The single point of connection is
excluded radial system has < 75 where the radial system (group
MVA gross aggregate nameplate > 100 kV of contiguous transmission
rating of connected generation (actual Elements) emanates at a voltage
15 MVA) and therefore meets the of 100 kV or higher from the
criteria of Exclusion E1b. Transmission system.

The generator has a gross


individual nameplate rating < 20
MVA (actual 15 MVA) and is
connected through the high-side > 100kV
of the step-up transformer at a < 100kV
voltage of 100 kV or above. By
application of Inclusion I2 this
unit is not a BES Element. 15 MVA

Figure E1-5: Radial System: Single non-BES Generation Resource

31 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV

Blue identifies the BES (included)


radial system. The included radial
system from the high-side connection
The single point of connection is
on the transformer to the single
where the radial system (group
point of connection of 100 kV or > 100 kV of contiguous transmission
above does not meet the exclusion
Elements) emanates at a voltage
criteria established in Exclusion E1b
of 100 kV or higher from the
due to the presence of a Blackstart
Transmission system.
Resource (See textbox below).

> 100kV
< 100kV / < 100kV < 100kV

15 MVA
Blackstart Resource
Generator Site Boundary
The generator has been
identified as a Blackstart To Load
Resource by application of
Inclusion I3.
Figure E1-6: Radial System: Blackstart Resource

32 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only

Figure E1-7: Radial System: Multiple (BES & non-BES) Generation Resources (Non-Retail)

33 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV

Blue identifies the BES (included) The single point of connection is where the radial
radial system. The depicted radial system (group of contiguous transmission
system does not meet the exclusion Elements) emanates at a voltage of 100 kV or
criteria established in Exclusion E1b higher from the Transmission system.
due to the presence of > 75 MVA
gross aggregate nameplate rating of
connected non-retail generation
(actual 85 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV

> 100kV The non-retail generators have gross


Generator Site individual nameplate ratings < 20 MVA
< 100kV
Boundary (actual 18 MVA, 16 MVA, 15 MVA, 14
MVA, 12 MVA, & 10 MVA). By
18 MVA application of Inclusion I2 these units are
not considered a BES Element.

< 100kV / > 100kV < 100kV / > 100kV


Generator Site Generator Site
Boundary Boundary
16 MVA 10 MVA

Generator Site Boundary

12 MVA
> 100kV
< 100kV
< 100kV
> 100kV
14 MVA

Generator Site Boundary

Figure E1-8: Radial System: Multiple (non-BES) Generation Resources (Non-Retail)

34 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.b Generation Only
> 100 kV

Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 69 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV

> 100kV The non-retail generators have gross


Generator Site individual nameplate ratings < 20 MVA
< 100kV
Boundary (actual 18 MVA, 15 MVA, 14 MVA, 12
MVA, & 10 MVA). By application of
18 MVA Inclusion I2 these units are not considered a
BES Element.

< 100kV / > 100kV


Generator Site
Boundary
10 MVA

Generator Site Boundary

12 MVA
> 100kV
< 100kV < 100kV
> 100kV
14 MVA

Generator Site Boundary

Figure E1-9: Radial System: Multiple (non-BES) Generation Resources (Non-Retail)

35 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load

Figure E1-11: Radial System: Generation Resource (Non-Retail) & Serving Load

36 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load

Figure E1-12: Radial System: Generation Resource (Non-Retail) & Serving Load

37 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load

Figure E1-13: Radial System: Generation Resource (Non-Retail) & Serving Load

38 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
> 100 kV

Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 69 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV

> 100kV The non-retail generators have gross


Generator Site individual nameplate ratings < 20 MVA
< 100kV
Boundary (actual 18 MVA, 15 MVA, 14 MVA, 12
MVA, & 10 MVA). By application of
18 MVA Inclusion I2 these units are not considered a
BES Element.

< 100kV / > 100kV


Generator Site
To Load Boundary
< 100kV / > 100kV 10 MVA

The substation transformers


Generator Site Boundary are not part of the BES
since both (primary and
secondary) terminals are
not operated at > 100 kV as
12 MVA per Inclusion I1.
> 100kV
< 100kV < 100kV To Load
> 100kV
14 MVA
< 100kV
> 100kV
Generator Site Boundary

Figure E1-14: Radial System: Generation Resource (Non-Retail) & Serving Load

39 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
E1.c Generation and Serves Load
> 100 kV

Green identifies the BES The single point of connection is where the radial
(excluded) radial system. The system (group of contiguous transmission
depicted radial system meets the Elements) emanates at a voltage of 100 kV or
exclusion criteria established in higher from the Transmission system.
Exclusion E1b due to the presence of
< 75 MVA gross aggregate
nameplate rating of connected non-
retail generation (actual 57 MVA). 15 MVA
Generator Site
< 100kV Boundary
> 100kV
> 100 kV

> 100kV The non-retail generators have gross


Generator Site individual nameplate ratings < 20 MVA
< 100kV
Boundary (actual 18 MVA, 15 MVA, 14 MVA, & 10
MVA). By application of Inclusion I2 these
18 MVA units are not considered a BES Element.

Generator Site
< 100kV / > 100kV
Boundary
To Load
< 100kV / > 100kV 10 MVA The substation
transformers are not
part of the BES since
both (primary and
Customer owned secondary) terminals
generation (retail) and are not operated at >
> 100kV associated customer 100 kV as per
< 100kV owned equipment Inclusion I1.
excluded from the BES
by application of To Load
14 MVA Exclusion E2

Generator Site Boundary 100 MVA < 100kV


M
> 100kV

Figure E1-15: Radial System: Generation Resource (Retail & Non-Retail) & Serving Load

40 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Normally OPEN Switching Device
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.

Green identifies non-BES


(excluded) radial systems.

The normally open (N.O.)


device between the radial
systems does not affect this
exclusion.

The substation transformers are not part of


the BES since both (primary and Normally Open
secondary) terminals are not operated at > (N.O.)
100 kV as per Inclusion I1.

Substation
> 100kV Boundary
> 100kV < 100kV
Substation < 100kV
Boundary
< 100 kV

< 100 kV

To Load
The normally open (N.O.) device Normally Open To Load
between the radial sub-100 kV systems (N.O.)
does not affect this exclusion.

Figure E1-16: Radial System: Normally Open Switching Device between Load Serving Radial Systems

41 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.

Green identifies non-BES


(excluded) radial systems.

The normally open (N.O.)


device between the radial
systems does not affect this
exclusion.

The substation transformers are not part of


the BES since both (primary and Normally Open
secondary) terminals are not operated at > (N.O.)
100 kV as per Inclusion I1.

Substation
> 100kV Boundary
> 100kV < 50kV
Substation < 50kV
Boundary
< 50 kV

< 50 kV

To Load
The normally closed (N.C.) Normally Closed To Load
device between the radial
systems operating < 50 kV
(N.C.)
does not affect this exclusion.

Figure E1-17: Radial System: Normally Open Switching Device


between Load Serving Radial Systems with a < 50 kV Loop
42 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.

The normally open (N.O.)


device between the radial
systems does not affect this
exclusion.

The substation transformers are not part of


the BES since both (primary and Normally Open
secondary) terminals are not operated at > (N.O.)
100 kV as per Inclusion I1.

Substation
> 100kV Boundary
> 100kV < 100kV / > 50kV
Substation
< 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

To Load
The normally closed (N.C.) device Normally Closed To Load
between the radial systems operating at
voltages < 100kV and > 50 kV affects this
(N.C.)
exclusion.

Figure E1-18: Impact of Sub-100 kV Looped Facilities (Switching


Devices Identified N.O. > 100 kV & N.C. < 100 kV & > 50 kV)
43 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV

> 100 kV

The single point of connection is


The single point of connection is where The normally closed (N.C.) where the radial system (group of
the radial system (group of contiguous device between the radial contiguous transmission
transmission Elements) emanates at a systems operating at voltages Elements) emanates at a voltage
voltage of 100 kV or higher from the > 100kV requires evaluation of 100 kV or higher from the
Transmission system. based on Exclusion E3. Transmission system.

The substation transformers are not


part of the BES since both (primary Green identifies
and secondary) terminals are not Normally Closed non-BES
operated at > 100 kV as per Inclusion (excluded) radial
(N.C.)
I1. systems.

Substation
> 100kV Boundary
> 100kV < 50kV
Substation < 50kV
Boundary
< 50 kV

< 50 kV

To Load
The normally closed (N.C.) Normally Closed To Load
device between the radial
systems operating < 50 kV
(N.C.)
does not affect this exclusion.

Figure E1-19: Radial System: Normally Closed Switching Device (> 100 kV)
between Load Serving Radial Systems with a < 50 kV Loop
44 RELIABILITY | ACCOUNTABILITY
Exclusion E1 Radial Systems
Underlying Loops
> 100 kV
The single point of connection is where
the radial system (group of contiguous
transmission Elements) emanates at a
voltage of 100 kV or higher from the
Transmission system. The single point of connection is
where the radial system (group of
contiguous transmission
> 100 kV Elements) emanates at a voltage
of 100 kV or higher from the
Transmission system.

The normally closed (N.C.)


device between the radial
systems operating at voltages
> 100kV requires evaluation
based on Exclusion E3.

The substation transformers are not part of


the BES since both (primary and Normally Closed
secondary) terminals are not operated at > (N.C.)
100 kV as per Inclusion I1.

Substation
> 100kV Boundary
> 100kV < 100kV / > 50kV
Substation
< 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

To Load
The normally closed (N.C.) device Normally Closed To Load
between the radial systems operating at
voltages < 100kV and > 50 kV requires
(N.C.)
evaluation based on Exclusion E3.

Figure E1-20: Impact of Sub-100 kV Looped Facilities (Switching


Devices Identified N.C. > 100 kV & N.C. < 100 kV & > 50 kV)
45 RELIABILITY | ACCOUNTABILITY
EXCLUSIONS
E2

46 RELIABILITY | ACCOUNTABILITY
Exclusion E2 Behind-the-Meter
Industrial Generation

Figure E2-1: Behind-the-Meter Generation: Net Capacity to the BES Less Than 75 MVA

47 RELIABILITY | ACCOUNTABILITY
Exclusion E2 Behind-the-Meter
Industrial Generation
Cogeneration Operation: Net capacity to the BES is > 75 MVA (Actual 100 MVA)

> 100kV

The point of connection is where


the customer owned equipment is
100 MVA to BES
connected to the 100 kV or higher
Transmission system. (Note: This
point is specified in the respective
Interconnection Agreements.)

M 50 MVA to Industrial
Process

> 100kV/< 100kV

Customer owned generation


resource behind the customer’s
meter is included in the BES:
Boiler > 100kV
By application of Inclusion
< 100kV I2, because the generator’s
gross individual nameplate
rating is > 20 MVA (Actual
150 MVA), and
150 MVA The net capacity to the BES
is > 75 MVA (Actual 100
MVA), therefore Exclusion
E2 does not apply.

Figure E2-2: Behind-the-Meter Generation: Net Capacity to the BES Greater Than 75 MVA

48 RELIABILITY | ACCOUNTABILITY
EXCLUSIONS
E3

49 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks

Figure E3-1: Local Network (non-BES) with Retail & Non-


Retail Generation Resources & Serving Load
50 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
Transformer voltages are utilized for
Power <300kV illustrative purposes only. Actual voltages Power
Blue identifies BES Flow 138kV associated with local networks will vary Flow
(included) local network. depending on the system configuration.
<300kV

The generator (non-retail) has a gross To Load


individual nameplate rating > 20 MVA
(actual 30 MVA) and is connected
through the high-side of the step-up Generation 138kV / <300kV
Site < 100kV
transformer at a voltage of 100 kV or
Boundary 138kV
above (actual 138 kV). By application of
Inclusion I2 the generator is a BES
Element.

10 MVA 15 MVA
Blue identifies BES 30 MVA
(included) local The generators (non-retail) have a gross
network. The included individual nameplate rating < 20 MVA
local network does not (actual 10 MVA & 15 MVA) and the
meet the exclusion To Load generation site has generation with a
criteria established in gross aggregate nameplate rating < 75
25 MVA
MVA (actual 25 MVA). By application
Exclusion E3a. due to the < 100kV of Inclusion I2 the generators are not
M
presence of the BES
138kV considered BES Elements.
generator identified by
Inclusion I2. (See textbox
To Load Customer owned generation <300kV
associated with the 30
behind the customer’s meter
MVA Generator). is excluded from the BES by 230kV
< 100kV application of Exclusion E2.
138kV
The substation transformers are
not part of the BES since both
(primary and secondary) terminals
are not operated at > 100 kV as per
Inclusion I1.

The multiple points of connection are where Transformer voltages are utilized for
230kV the local network (group of contiguous illustrative purposes only. Actual voltages
Power 138kV
transmission Elements) emanates at a voltage of associated with local networks will vary
100 kV or higher from the Transmission system.
Flow 230kV depending on the system configuration.

E3-2: Local Network (BES) with Retail & Non-Retail Generation


Resources & Serving Load
51 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
Transformer voltages are utilized for
Power <300kV illustrative purposes only. Actual voltages Power
Blue identifies BES Flow Flow
138kV associated with local networks will vary
(included) local network.
depending on the system configuration.
<300kV
The generator (non-retail) has a gross To Load
individual nameplate rating < 20 MVA
(actual 15 MVA) and is connected
through the high-side of the step-up Generation 138kV / <300kV
Site < 100kV
transformer at a voltage of 100 kV or
Boundary 138kV
above (actual 138 kV). By application of
Inclusion I2 this generator is a not a BES
Element.

10 MVA 15 MVA
15 MVA
The local network does not The generators (non-retail) have a gross
meet the exclusion criteria individual nameplate rating < 20 MVA
established in Exclusion E3 due (actual 10 MVA & 15 MVA) and the
to the following: To Load generation site has generation with a
gross aggregate nameplate rating < 75
25 MVA
MVA (actual 25 MVA). By application
Power flows out of the
network system into the
< 100kV of Inclusion I2 the generators are not
M
interconnected 138kV considered BES Elements.
Transmission system
(E3b.) Customer owned generation
To Load <300kV
behind the customer’s meter
is excluded from the BES by 230kV
< 100kV application of Exclusion E2.
138kV
The substation transformers are
not part of the BES since both
(primary and secondary) terminals
are not operated at > 100 kV as per
Inclusion I1.

The multiple points of connection are where Transformer voltages are utilized for
230kV the local network (group of contiguous Power illustrative purposes only. Actual voltages
138kV
transmission Elements) emanates at a voltage of Flow associated with local networks will vary
100 kV or higher from the Transmission system. 230kV depending on the system configuration.

Figure E3-3: Local Network (BES) with Retail & Non-Retail


Generation Resources & Serving Load
52 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks

Figure E3-4: Local Network (non-BES) with Sub-100 kV Loop

53 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks

Figure E3-5: Local Network (BES) with Sub-100 kV Loop

54 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV

The presence of the sub-100 kV loop establishes


multiple points of connection at a voltage level
of 100 kV or higher to the Transmission
Power
System. Flow

< 300 kV

The local network meets the


exclusion criteria established in Power
Exclusion E3 by the following: Flow

Operated at voltages
< 300 kV
Power only flows into the
networked system (E3b.) The normally open (N.O.)
Assumed that the
device between the radial
networked system is not
part of a Flowgate or
systems does not affect this
transfer path and is not exclusion.
monitored in an IROL
(E3c.)

The substation transformers are not part of


the BES since both (primary and Normally Open
secondary) terminals are not operated at > (N.O.)
100 kV as per Inclusion I1.

Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

< 100 kV / > 50 kV


To Load
The normally closed (N.C.) device between the Normally Closed To Load
sub-100 kV systems establishes a loop
configuration which requires evaluation based on
(N.C.)
Exclusion E3.

Figure E3-6: Local Network (non-BES) with Sub-100 kV Looped Facilities


(Switching Devices Identified: N.O. > 100 kV & N.C. < 100 kV/> 50 kV)

55 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV

The presence of the sub-100 kV loop establishes


multiple points of connection at a voltage level
of 100 kV or higher to the Transmission
System. Power
Flow

< 300 kV

Power
Flow

The network does not meet the The normally open (N.O.)
exclusion criteria established in
device between the radial
Exclusion E3 due to power
flowing out of the networked
systems does not affect this
system (E3b.). exclusion.

The substation transformers are not part of


the BES since both (primary and Normally Open
secondary) terminals are not operated at > (N.O.)
100 kV as per Inclusion I1.

Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

< 100 kV / > 50 kV


To Load
The normally closed (N.C.) device Normally Closed To Load
between the sub-100 kV systems
establishes a loop configuration which
(N.C.)
requires evaluation based on Exclusion E3.

Figure E3-7: Local Network (BES) with Sub-100 kV Looped Facilities


(Switching Devices Identified: N.O. > 100 kV & N.C. < 100 kV/< 50 kV)

56 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV

Power
Flow

< 300 kV

Power
Flow
The presence of the sub-
The local network meets the 100 kV loop establishes
exclusion criteria established in multiple points of
Exclusion E3 by the following: connection at a voltage
level of 100 kV or higher to
Operated at voltages the Transmission System.
< 300 kV
Power only flows into the
networked system (E3b.)
Assumed that the
networked system is not
part of a Flowgate or Normally Closed
transfer path and is not
monitored in an IROL (N.C.)
(E3c.)

Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

Normally Closed
(N.C.)
To Load
< 100 kV / > 50 kV To Load
The normally closed (N.C.) device between The substation transformers are not part of the
the sub-100 kV systems establishes a loop BES since both (primary and secondary)
configuration which requires evaluation based terminals are not operated at > 100 kV as per
on Exclusion E3. Inclusion I1.

Figure E3-8: Local Network (non-BES) with Sub-100 kV Looped Facilities (Switching Devices Identified: N.C. > 100 kV &
N.C. < 100 kV/> 50 kV)

57 RELIABILITY | ACCOUNTABILITY
Exclusion E3 Local Networks
< 300 kV

Power
Flow

< 300 kV

Power The network does not meet the


Flow exclusion criteria established in
The presence of the sub-100 Exclusion E3 due to power
kV loop establishes multiple flowing out of the networked
points of connection at a system (E3b.).
voltage level of 100 kV or
higher to the Transmission
System.

Normally Closed
(N.C.)

Substation
< 300kV Boundary
< 300kV < 100kV / > 50kV
Substation < 100kV / > 50kV
Boundary
< 100 kV / > 50 kV
< 100 kV / > 50 kV

Normally Closed
(N.C.)
To Load
< 100 kV / > 50 kV To Load
The normally closed (N.C.) device between
The substation transformers are not part of the
the sub-100 kV systems establishes a loop
BES since both (primary and secondary)
configuration which requires evaluation based
terminals are not operated at > 100 kV as per
on Exclusion E3.
Inclusion I1.
Figure E3-9: Local Network (BES) with Sub-100 kV Looped Facilities
58 (Switching Devices Identified: N.C. > 100 kV & N.C. < 100 kV/> 50 kV) RELIABILITY | ACCOUNTABILITY

You might also like