ANNEX NO.

1
PRELIMINARY MATRIX OF PROJECT RISKS ALLOCATION

Risk category Description Consequences Elimination

Risk location

Existing structure The existing structures are Increase in costs and increase The Concessionaire shall transfer the risk
(modernization) inadequate in order to adapt in time necessary to complete to the constructor, who can rely on
the development the project technical expertise reports in the project
phase

Location conditions Unforeseeably difficult soil Increase in costs and time The Concessionaire transfers the risk to the
conditions necessary to complete the constructor, who can rely on technical
project expertise reports in the project phase

Approvals All the necessary approvals Delays in the project Before the project commencement, the
cannot be obtained or they commencement or Grantor shall perform a detailed
can be obtained subject to completion and increase in verification of the necessary approvals
unforeseen mandatory costs related to its
conditions achievement
Cleaning and practicability The preparing of the land Increase in costs and time The Concessionaire must be capable to use
results in a much greater cost necessary to complete the and mobilize its resources to cover the
than that envisaged and needs project costs of cleaning and practicability of the
a much longer period of time land
than provided for under the
contract
Property deed Increase in costs and time Increase in costs and time The grantor shall verify the land registries
necessary for the purchase of necessary to complete the and shall take the necessary steps to reserve
land from the owners and/or project the lands necessary for the project.
for granting the right to use
the respective land.

Cultural heritage Increase in costs and Increase in costs and time The Grantor may hire experts in view of
necessary time as a result of necessary to complete the investigating and establishing measures to
discovering some project minimize costs and avoid delays
archaeological sites and/or
national patrimony
Environment (1) The locations for the project Increase in costs and time The Grantor is liable for the activities
show an unknown necessary to complete the conducted on its lands and controls the
contamination degree project process of monitoring the pollution and
penalising the polluter
Environment (2) During the implementation of Decontamination costs The Concessionaire is bound to take all the
the project, contaminations of necessary steps to avoid such events.
adjacent properties occur, Hiring of experts in view of investigating
having effect on the and establishing steps to minimize costs
properties made available for and avoid delays
the project
Availability of the location The access to a certain Delay in implementation and The Concessionaire has the obligation to
location cannot be negotiated increase in costs take all necessary steps to provide the
with its owner access to the locations made available for
the project

Design, construction and reception of the project works

Design The project of the facility Increase in supplementary The Grantor has the right to reduce
does not allow to carry out costs in the long run or payments within the project or to reduce
works at the envisaged cost impossibility to ensure works the right of the Concessionaire to direct
in the long run collections
Construction The occurrence, during Delay in implementation and The Concessionaire shall transfer the risks
construction, of an event increase in costs to the constructor who must have the
leading to the impossibility of resources and the technical capacity to
its completion within the time comply with the execution terms
limit envisaged and at the
estimated cost

Reception of the investment The risk is both physical and Consequences for both The Grantor will not make any payment
operational and refers to a partners. For the until the reception of the investment and
delay in carrying out the Concessionaire and its the beginning of the requested works
reception of the investment financers -accrued income
and loss of profit. For the
Grantor – the delay in
supplying the requested
services

Financer and financing

Interest rates during the The applicable interest rates Increase/decrease in project Provisions relating to this risk may be
investment are subject to change, thus costs. included in the concession contract
modifying the financial terms
of the offer

Incapable financer The concessionaire becomes Failure to carry out the works A fair and in-depth analysis of financial
insolvent or carrying out of requested by the Grantor and resources presented in the offer submitted
works requires a greater losses for participants in the by the prospective Concessionaire
financing than estimated by investment (obligations of the financer). The guarantee
the Concessionaire by the Concessionaire for achieving the
investment (Bank guarantee of good
execution)

Unavailable financing The Concessionaire is not Lack of financing for The Grantor will analyse very carefully the
able to ensure financial and continuation or completion of financial obligations of the Concessionaire
capital resources in due time investment and the correlation with the investment
and in sufficient amounts schedule

Tax changes During the project, the Negative impact on financial The revenues of the Concessionaire must
general tax arrangement shall revenues of the be sufficient as to cover the unfavourable
change against the Concessionaire differences, up to an amount provided for
Concessionaire in the contract by the parties. Any
difference greater than this amount will be
charged to the Grantor, from legal reserves
settled for this purpose

Supplementary financing Due to changes in legislation, The Concessionaire cannot The Concessionaire may partially cover the
politics or of a different financially bear the costs of refinancing, according to the resources
nature, supplementary changes available. The part which remains
financing is necessary for uncovered is borne by the Grantor.
reconstruction, modification,
re-equipment etc

Refinancing profits The completion of the Profitable change in the The Grantor must ensure that the
investment shall be made at a financing of the project Concessionaire cannot exclusively benefit
cost which is smaller than the from this favourable risk
initial one
Operation
Input resources The necessary resources for Increases in costs, and, in The Concessionaire may manage the risk
operation incur a greater cost some cases, negative effects by means of long term supplying contracts,
than the initial estimates, are on the works carried out. with specific terms as regards quality
not of an appropriate quality assurance of the supplies
or are not available in
sufficient quantities
Maintenance and repair The quality of design and/or Increase in cost, with The Concessionaire may manage the risk
of works is not appropriate, negative effects on the up to by means of long term contracts qualified
resulting in unforeseen the moment undertaken appropriate operators that have sufficient
increase of maintenance and actions material capacities and resources
repair costs

Change in the requirements of The Grantor shall change its The change of requirements The Grantor must define as precisely as
the Grantor, beyond the limits requirements after signing the during the investment leads possible its requirements, as early as the
provided for in the contract contract to the modification of the project preparing phase
project and , after reception,
to the increase in capital costs

Operation The Concessionaire is not Impossibility to carry out the The Grantor must examine in detail, as
financially appropriate or works. early as the offer phase, the capacity of the
cannot carry out the works prospective Concessionaire to execute the
according to the contract contract successfully
Obsolete or inappropriate The proposed technical The revenue of the In the offer phase, the prospective
technical solutions solutions are not Concessionaire decreases Concessionaire may propose contractual
technologically appropriate below the data of financial terms providing for the establishment of
as to ensure the achievement closing of the project reserve resources in view of covering
of the project resulting in losses. The possible technological developments
Grantor does not receive the
requested actions
(works/services)

Market

Worsening of general economic Occurrence of fundamental Revenues below prior In the tendering stage, the prospective
conditions and unexpected changes in financial predictions Concessionaire may propose contractual
the general economic terms that ensure conditions for covering
conditions that lead to the the risk
decrease of demand for the
contracted supplies

Competitive changes Another investment, already Revenues below prior The Concessionaire will try to redress
existing, is extended, financial predictions, due to a financially against changes that affect the
improved or re-priced, so that reduction in prices and/or project in a discriminatory manner,
competition as regards the decreasing demand, as a determined by the competition of the
actions (works/services) result of competition Grantor. The Grantor must refrain from
supplied according to the measures that affect the project in a
contract increases discriminatory manner

Competition Emergence on the market of Revenues below prior The Concessionaire must examine carefully
competitors in the field of financial predictions due to a the market conditions. The Grantor must
carried out actions by the reduction in prices and/or refrain from measures that affect the market
Concessionaire, according to decreasing demand, as a
the contract result of competition
Demographic changes A demographic or socio- Revenues below prior The Concessionaire has the obligation to
economic change affects the financial predictions provide, in its calculations, for possible
demand for the contracted changes in revenues
line of actions
Inflation The value of payments in Decrease, in real terms, of The Concessionaire may propose an
time is diminished by project revenues appropriate mechanism to compensate for
inflation the inflation, by means of adjustment of
prices. The Grantor must avoid for the
Concessionaire to benefit from
overcompensations or double payments

Legal and policy risk of the Grantor

Legislation The existence of a statutory Effect on costs and revenues The Concessionaire shall asses the legal
framework of legal rules that system and take the necessary measures
will impair the
Concessionaire
Legislative/political changes (1) Legislative change or change An important increase in The Grantor may reduce the liability for
in the politics of the Grantor operational costs of the such changes by monitoring and limiting
that cannot be foreseen when Concessionaire and/or the the changes that may have such
signing the contract and necessity to incur capital consequences on the project. The
which is addressed directly, expenses in order to be able Concessionaire will perform the changes in
specifically and exclusively to respond to these changes such a way to minimize the financial effect
to the project, leading to on the Grantor
supplementary capital or
operational costs for the
Concessionaire

Legislative/political changes (2) Legislative change or change An important increase in The Grantor may reduce the risks by
in the policy of the Grantor operational costs of the excluding changes, such as those related to
that cannot be foreseen when Concessionaire and/or the taxes or those for which the Concessionaire
signing the contract and that necessity to incur capital is compensated based on an adjustment,
is general in its application expenses in order to be able with the consumer price index and only
(not specific to the project), to respond to these changes based on a „significant amount”, previously
leading to supplementary agreed
capital or operational costs
for the Concessionaire

Withdrawal of complementary The Grantor shall withdraw Consequences on revenues The Concessionaire will try to redress the
support its complementary support, project financially, after changes that affect
the project being negatively the project in a discriminatory manner,
affected especially in the case of projects when the
third user pays

Project assets

Technical depreciation Technical depreciation is Increase in new technology The Concessionaire may take the
greater than foreseen costs appropriate measures to avoid such a
situation

Force majeure

Force majeure Force majeure, as defined by Loss or damage of project The Concessionaire may take measures for
law, prevents the execution assets and the loss/decrease the insurance of project assets and shall
of the contract of the possibility to obtain the pursue their repair or replacement in the
expected revenues shortest time possible

Project profitability

The project proves to be more The balance between Over profits for the The Grantor must include mechanisms for a
profitable than the initial revenues and expenses differs Concessionaire fair allocation of profits obtained over the
predictions significantly from the limit taken into consideration when
predictions establishing financial predictions
ANNEX No. 2

MODELS
Of Contract Notices published in the
Official Gazette of Romania
in accordance with the provisions of art. 20 paragraph (2) and 26 paragraph (2)

Contract Notice for the open tender procedure

1. Designation, address, telephone and fax number, e-mail of the Grantor

2. Designation, address, telephone and fax number and e-mail of the office where
the tender documentation can be requested. If applicable, cost and payment terms
for obtaining the tender documentation.

3. (a) Place of work completion/service performance

(b) Object of the concession; nature and dimension of works/service performance

(c) Finalization term or contract duration

4. (a) Tender submission term

(b) Address where Tenders must be sent

(c) Language or languages in which Tenders must be drafted

(d) Date, time and place of opening tender

5. Personal, technical and financial terms which the Tenderers must fulfil

6. Criteria used for the contract award

7. The minimum percentage of the works which must be granted to third parties, as
applicable.

8. Date of sending the contract notice for publication.

9. Designation and address of the competent body for the solving complaints and, as
applicable, of mediation. Accurate information regarding the deadlines for the
submission of complaints and as applicable, the designation, address, telephone
number, fax number and e-mail address of the office where this information can
be obtained from.
Contract Notice for the restricted tender procedure

1. Designation, address, telephone and fax number, e-mail of the Grantor

2. Designation, address, telephone and fax number and e-mail of the office where
the tender documentation can be requested. If applicable, cost and payment terms
for obtaining the tender documentation.

3. (a) Place of work completion/service performance

(b) Object of the concession; nature and dimension of works/service performance

(c) Finalization term or contract duration;

4. (a) Tender submission term;

(b) Address where Tenders must be sent;

(c) Language or languages in which Tenders must be drafted;

5. Personal, technical and financial terms which the Tenderers must fulfil.

6. Minimum number and, as applicable, maximum number of candidates which


intend to be selected and the selection criteria which will be used.

7. Criteria used for contract award.

8. The minimum percentage of the works which must be granted to third parties, as
applicable.

9. Date of sending the contract notice for publication.

10. Designation and address of the competent body for the solving complaints and, as
applicable, of mediation. Accurate information regarding the deadlines for the
submission of complaints and as applicable, the designation, address, telephone
number, fax number and e-mail address of the office where this information can
be obtained from.
Contract Notice for the competitive dialogue

1. Designation, address, telephone and fax number, e-mail of the Grantor

2. Designation, address, telephone and fax number and e-mail of the office where
the tender documentation can be requested. If applicable, cost and payment terms
for obtaining the tender documentation.

3. (a) Place of work completion/service performance;

(b) Object of the concession; nature and dimension of works/service performance;

(c) Finalization term or contract duration;

4. (a) Tender submission term;

(b) Address where Tenders must be sent;

(c) Language or languages in which Tenders must be drafted;

5. Personal, technical and financial terms which the Tenderers must fulfil.

6. Minimum number and, as applicable, maximum number of candidates which


intend to be selected and the selection criteria which will be used.

7. If applicable, to specify the conducting of the dialogue in successive


rounds/stages, to reduce the number of solutions that is to be discussed.

8. Criteria used for contract award.

9. The minimum percentage of the works which must be granted to third parties, as
applicable.

10. Date of sending the contract notice for publication.

11. Designation and address of the competent body for the solving complaints and, as
applicable, of mediation. Accurate information regarding the deadlines for the
submission of complaints and as applicable, the designation, address, telephone
number, fax number and e-mail address of the office where this information can
be obtained from.
Contract Notice for negotiation

1. Designation, address, telephone and fax number, e-mail of the Grantor

2. Designation, address, telephone and fax number and e-mail of the office where
the tender documentation can be requested. If applicable, cost and payment terms
for obtaining the tender documentation.

3. (a) Place of work completion/service performance;

(b) Object of the concession; nature and dimension of works/service performance;

(c) Finalization term or contract duration;

4. (a) Tender submission term;

(b) Address where Tenders must be sent;

(c) Language or languages in which Tenders must be drafted;

5. Personal, technical and financial terms which the Tenderers must fulfil.

6. Minimum number and, as applicable, maximum number of candidates which


intend to be selected and the selection criteria which will be used.

7. If applicable, to specify the conducting of the dialogue in successive


rounds/stages, to reduce the number of solutions that is to be discussed.

8. Criteria used for contract award.

9. The minimum percentage of the works which must be granted to third parties, as
applicable.

10. Date of sending the contract notice for publication.

11. Designation and address of the competent body for the solving complaints and, as
applicable, of mediation. Accurate information regarding the deadlines for the
submission of complaints and as applicable, the designation, address, telephone
number, fax number and e-mail address of the office where this information can
be obtained from.
ANNEX no. 3

Report regarding the public works and services concession contracts


awarded in the year..........

CONTRACTING AUTHORITY
ADDRESS: ......................................................................
Sole registration code: .......................................................................
Registration no. at the Trade Register: .............
Tel/fax : ....................................................................
E-mail : .....................................................................

Type of contracts Total no. of contracts

Public works concession


contracts

Out of which awarded by:


- competitive dialogue ;
- restricted tender;
- open tender
- negotiation with prior
publication of a contract notice

Services concession contracts

Out of which awarded by:


- competitive dialogue
- restricted tender;
- open tender
- negotiation with prior
publication of a contract notice

TOTAL