Professional Documents
Culture Documents
Introduction
This document discusses the range of considerations that will inform a decision to select a
design and construct form of procurement for construction projects.
The traditional procurement method (design, document, tender and construct) provides the
greatest level of lead agency design and quality control and for these and other reasons is
generally preferred for social infrastructure.
However, traditional procurement does not facilitate the fast tracking of projects and there is an
increasing incidence of lead agencies requesting that project delivery be fast tracked. One
approach to fast tracking is to adopt a design and construct procurement which allows early
involvement by the contractor and overlap of the completion of design with the commencement
of construction.
The design and construct contract form requires the contractor to be accountable for the
effective completion of the design and for completing construction to a fixed price and time.
This method facilitates an early construction start date but requires the transfer of the design
control to the contractor and severely constrains the lead agency and end user groups in regard
to variation to the scope of the works. Any change once the contract is entered into can come
at a high cost, putting the approved project budget at risk.
The Department of Planning, Transport and Infrastructure (DPTI) Building Management division
preferred contract conditions for this contract form are the AS 43001995 General conditions
of contract for design and construct.
Traditional Contract
Opportunities Risks
Cost The provision of detailed drawings, The additional time required in
specifications and quantities provides a procuring the works may impact upon
basis for obtaining competitive tenders the lead agency’s budget and
for the work and facilitates the professional service contractor (PSC)
comparison of tenders. costs.
The contract provides for changes and
variations to the design and/or
specification by the lead agency/DPTI
during the works and the contract which
if uncontrolled can lead to cost
blowouts.
Time As a result of sufficient time being Is tendered when design is complete
provided for the detailed design and leading to an extended program.
documentation, the risk associated with Due to the design and construction
the number of design changes required phases of the project being ‘end-on-
during the works is relatively low. end’, with no parallel working, the
Opportunities Risks
overall program is slower.
Scope/Quality The lead agency/DPTI retains control Does not take advantage of the benefits
over design and design services and of integration between the design and
quality can be directly managed. construction processes.
DPTI has the ability to assure project
quality through a system of audits for
both design and construction.
Communication Well understood procurement process As the contracting arrangements are
which facilitates effective more complex (i.e. separate contracts
communication. for lead PSC, cost manager and
building contractor), effective
management and communication is
more challenging.
Scope/Quality Design is reviewed and tested for The contractor has control over the
efficiencies by construction contractor. design process and is interested in low
cost which may result in design quality
being compromised unless the brief of
requirements is fully developed and
robust.
Variations must be limited unless
significant costs are to be incurred and
therefore design construct is often not
suitable for social infrastructure where
the brief of requirements is fluid/subject
to change.
Supervision of the works is by the
contractor with limited opportunity for
DPTI to review quality.
Communication The management of communications The lead agency/DPTI transfers control
between the PSC group and the of the design to the contractor and has
construction contractor is transferred to very limited capacity to intervene without
the contractor. introducing a transfer of risk back to
Government.
Page 2 of 4
Design and Construct vs Traditional Procurement
Budget
Most budgets for construction projects are set on the basis of a traditional procurement
methodology. By selecting a design and construct procurement method there can be budget
risk introduced, depending on the amount of risk that is transferred to the contractor.
Complete risk transfer where the risks of industrial action, inclement weather, latent conditions,
design (no variations), time (no extension of time) and cost (including escalation) are
transferred can result in the contractor pricing these risks higher than allowances in the
traditionally based cost plan with the result that the approved project budget is exceeded.
As one of the purposes in selecting the design and construct procurement method is to provide
certainty to the State on the amount it will pay for the project as briefed, there should be very
careful consideration of proposals to take back risk in order to manage the project budget.
Page 3 of 4
Design and Construct vs Traditional Procurement
Summary
Prior to committing to a design and construct procurement method the following should be
acknowledged and discussed with the lead agency.
It is essential that the project brief is thoroughly detailed prior to tender call so that design
and quality risks are minimised and there is limited scope for contractor claims.
Under the traditional contract the project is fully documented and audited and provides a
rigorous design basis incorporating accepted standards. Under a design and construct
procurement method the State is relying on the quality of the Principal’s Project
Requirements document to fully articulate the performance requirements of the facility.
As this briefing document does not contain the detail included in full documentation, the
lead agency will need to acknowledge and accept the potential impact on the quality in
regard to performance, function, materials and life cycle costs.
Any matter that will potentially delay a design and construct contractor will need final
resolution prior to committing to a design and construct procurement method.
Selection of a contractor to undertake a design and construct contract requires a more
sophisticated and complex tendering process to manage that the successful contractor
has the design and management skills within its team to deliver a successful project. The
process may incorporate an element of design and may even warrant a design
competition with associated payment to the tenderers.
The potential for increased delivery cost should be discussed and factored into the project
budget, ensuring that the planned risk transfer does not unduly affect overall project value
to the State.
Contact
For further information contact:
Brenton Nottage
Manager Building Contracts
Phone: 08 8343 2037
Email: brenton.nottage@sa.gov.au
Page 4 of 4