Professional Documents
Culture Documents
4) Webinar Content - DR - KMK-03.05.2020 - 2
4) Webinar Content - DR - KMK-03.05.2020 - 2
EXPERIENCES
Presented by
Dr. K. Muthukkumaran
Professor, Department of Civil Engineering,
National Institute of Technology,
Tiruchirappalli
&
Chairman, IGS Trichy Chapter
CASE STUDY
INSTRUMENTATION IN
PILE FOUNDATION PERFORMANCE
MONITORING UNDER SEVERE LOAD
GEOTECHNICAL EXPLORATION (Contd..)
Soil Parameters
Very Medium Stiff to very Very stiff to
Medium Dense
Dense stiff to Stiff stiff Hard
Dense
Cohesion (kN/m2) -- -- -- 40-80 80-150 150-200
Angle of Internal Friction (Deg) 33 35 38 - - --
Bulk Unit Weight (kN/m3) 18 19 21 14 16 18
Submerged Unit Weight (kN/m3) 9 10 11 6 8 9
Earth ressure Coefficient
- Active 0.29 0.27 0.24 - - --
- Passive 3.39 3.69 4.20 - - --
- At Rest 0.45 0.43 0.38 - - --
Coefficient of Permeability
10-2 to 10-4 10-5 to 10-8
(cm/sec)
Coefficient of Friction
0.30 0.35 0.40 - 0.2 0.40
between soil and concrete
Static Modulus of Elasticity
- 30,000
(kN/m2) 18,000 30,000 60,000 35,000
Poisson’s Ratio 0.27 0.30 0.33 - 0.3 0.4
A Readout unit can be used to read the vibrating wire strain gauges
PILE INSTRUMENTATION (Contd..)
Strain gauge fixing
PILE INSTRUMENTATION (Contd..)
Strain Gauge at
(Left & Right)
-3m
-6m
-9m
-12m
-15m depths
PILE INSTRUMENTATION (Contd..)
INCLINOMETER
(for Lateral pile load test)
Digital inclinometer system is used to measure lateral movement and
deformation of earth works or a structure.
It provides magnitude of inclination or tilt and its variation with time in
structures like retaining/diaphragm walls, piles etc.
The digital inclinometer system consists of a traversing type digital tilt
sensing probe that is connected to a reel unit kept at borehole top.
The reel unit consists of a winding reel that holds the cable and a
wireless Bluetooth relay unit that sends the digital probe data to the
mobile phone.
Inclinometer system, provides significant quantitative data on
magnitude of settlement/heave of foundations and its variation with
time.
It also provides the pattern of deformation, zones of potential danger and
the effectiveness of construction control measures undertaken.
PILE INSTRUMENTATION (Contd..)
Inclinometer casing pipe installation
PILE INSTRUMENTATION (Contd..)
Inclinometer initial reading
Effect of drilling and concreting adjacent to
existing pile
Instrumented Test pile (TP1)
Godown -G7
1 3
Instrumented Test pile (TP2)
2 1
Godown –G11
-2 -2
-4 -4
-6 -6
Depth (m)
Depth (m)
-8 -8
-10 -10
-12 -12
-14 -14
-16
-16
-18 TP 1 TP 2
-18
Deflection of pile after concreting
Deflection (m) Deflection (m)
-0.001 0 0.001 0.002 0.003 -0.01 -0.005 0
0 0
-2 -2
-4 -4
-6 -6
Depth (m)
Depth (m)
-8 -8
-10 -10
-12 -12
-14 -14
-16 -16
TP 1 TP 2
-18
-18
Deflection of pile after 1 week (TP1)
-0.004 -0.002 0 0.002 0.004 Deflection (m)
0
-2
-4
-6
Before Concrete
Depth (m)
-8
After Concrete
-10 13.08.2015
-12
-14
-16
-18
Deflection of pile after 1 week (TP2)
Deflection (m)
-0.01 -0.005 0 0.005 0.01
0
-2
-4
-6
Before Concrete
After Concrete
Depth (m)
-8
13.08.2015
-10
-12
-14
-16
-18
PILE LOAD TEST STUDY
The lateral deflection of the pile at the cut off level was observed using a
dial gauge fixed diametrically opposite to the loading point
From the load-deflection curve, the safe lateral load was taken as least of
the following
(i) one-half of the final load at which total deflection approaches to 12mm
(ii) final load at which total deflection reaches 5mm.
INITIAL LOAD TEST PROGRAM
PILE DESCRIPTION
But the excessive deflection of pile under the applied lateral loads
caused a considerable reduction in the safe lateral load capacity.
Later it was found that the failure of pile load tests were caused
by the inadequate pile capacity and the poor reaction offered by
the very soft clayey deposit at the top few meter length of the pile.
DETAILED LOAD TEST PROGRAM
Two test piles at zone-I – vibrating wire strain gauges – vertical load test
Two test piles along with reaction pile group at zone-II - inclinometer
casing pipe – lateral load test
DETAILED LOAD TEST PROGRAM (Contd.)
INSTRUMENTED VERTICAL PILE LOAD TEST
Vertical Pile load test were conducted as per IS 2911 Part-4 :
1985 (reaffirmed 2010)
DETAILED LOAD TEST PROGRAM (Contd.)
LATERAL PILE LOAD TEST
Lateral Pile load test were conducted as per IS 2911 Part-4
: 1985(reaffirmed 2010)
RESULTS AND DISCUSSIONS
Assessed from
Geotechnical investigation results
Vertical pile load test results
Lateral pile load test results
Observations form Instrumentation data
EFFECTS ON SOIL PROPERTIES
zone-I zone-II
EFFECTS ON SOIL PROPERTIES (Contd.)
Reassessment of soil profile
The undrained shear strength of clay after 1 year of soil filling was found to
be 1.62 times higher than that of initial at 1m depth.
The vertical load capacity of pile after 2 years of earth filling was
found to be 20% higher than that of the initial predicted value.
EFFECTS ON VERTICAL PILE LOAD CAPACITY (Contd.)
Instrumented vertical pile load test results (zone-I)
0.0 m Ground level
15.0 m
15.0 m
21.0 m
Typical axial load distribution curve for each layer
EFFECTS ON VERTICAL PILE LOAD CAPACITY (Contd.)
Design capacity
EFFECTS ON LATERAL PILE LOAD CAPACITY (Contd.)
-2
-4
-6
Initial
-8
190kN Load applied
Depth (m)
-14
-16
-18
SUMMARY OF FINDINDS
The design of vertical and lateral pile capacities were significantly
influenced by the adoption of precise values of soil properties assessed
from various field geotechnical investigations.
For the larger construction projects, the variation of soil strata within the
site boundary, duration of construction and site development process
shall be taken into account during the design of foundation system
The problem associated with the existence of very soft clayey soil layer
shall be eliminated by incorporating effective and compatible design of
suitable ground improvement along with the design of foundation system
The load capacity of the pile was found to be increasing with respect to
time after the earth filling up to a maximum period of 2 years where the
top 2m to 3m clayey soil reaches the maximum degree of consolidation.
The vertical safe load capacity of 600mm diameter pile after 2 years of
consolidation due to 2.5m to 3m earth filling was found to be 15% higher
than that of the initial measured value.
Also, the lateral load capacity of the single pile was 70% higher than that
of the initial measured value.
SUMMARY OF FINDINDS (Contd..)
The ratio between the measured capacity and the predicted capacity
based on actual soil properties was found to vary from 1.05 to 1.2 for
vertical loaded pile.
For laterally loaded pile, the ratio was found to vary between 0.86 and
0.94. In both the cases, the pile capacity was adequate when compared
to the initial required design capacity.
Thus at the end of the construction period of 2.0 years, the load capacity
of a single pile was increased when compared to design capacity based
on initial geotechnical investigations. The chances of negative skin
friction were highly reduced as the soil reached maximum degree of
consolidation and subsequently the consistency of the clay was
increased.
It is clear from the normalized load distribution curve that the down-drag
exist on the consolidating soil layer approaches to zero and offers the
positive shaft resistance once the degree of consolidation reaches
maximum. For the present case study, down-drag becomes null after two
years of filling,
Acknowledgement
Dr. K. Baskar, Profrssor, Department of Civil Engineering, NIT
Trichy
Er. Kannan, CE, TNCSC, Chennai
Er. Gunaseelan, EE, TNCSC, Chennai
My research team:
Dr. Prakash
Mr. Sivaraman
Mr. Keethi Raj
Mr. Vinoth
88 Mr. Karthi
Soft clay is like a BABY –You need to
spend more time to understand the
language of the baby