1. Scope:
a. Project objectives:
- To construct a Tea-house within eight months from November 20th, 2019 to July 20th, 2020 at a cost
not to exceed 10 billion VND.
b. Deliverables:
Deliverables Description Quantity
Finished shop 1000 square meters, 2 restrooms, 1 kitchen, guest space
c. Milestones:
• Complete land lease agreement: 20th November 2019
• Permit Appraisal and Approved: 2nd January 2020
• Design Approved: 15th January 2020
• Feasibility start: 20th February 2020
• Constructing and Preparing: 15th April 2020
• Interior decorating: 1st July 2020
• Final Check and Repair: 16th July 2020
• Feasibility End: 20th July 2020
4. Technical requirements:
4.1 Equipment:
a. Electric Glass Tea Kettle- KitchenAid.
This tea machine gives a good ability to make tea at an affordable price.
- Glass kettle.
- Automated cleaning system
- Five specialty tea modes to preserve each tea’s unique flavors and aromas: green, white, oolong,
black, and herbal, with a pre-defined temperature for each.
- "keep warm" mode
b. Tea Infuser Set
Reusable Stainless-Steel Strainers & Steepers- Chefast brand
The infusers are made with an extra-fine, premium-grade stainless steel mesh that will not rust or break
easily
4.2. Software/Security
the software that will work best with our business is called the coffee shop manager HQ 3.0. This
program allows for the security of transactional sales, a menu, inventory, and labor information on a
central reporting system. Also, the already built-in technology of this program will allow us the ability
to expand to more tea houses as we grow in the future.
The best fitting for the company would be Mocha Touchscreen Package. This system includes:
• Tea House Manager POS Software
o Menu Preparation
o Training
o Initial Month of Support Included
• Tea House Manager Back Office
• Pioneer 15" Touchscreen Terminal with OEM licensed Window 10
• Electronic Cash Drawer
• Additional Drawer Insert
• Integrated Magnetic Credit Card Reader
• Thermal Receipt Printer
The package is priced at 120.000.000, and will also cover all operation programs needed for the
manager to keep track of things.
4.3. Furniture
The last thing we are in need of for the business is going to be furniture. For this, I suggest we stay
local and go to a store called "Ngoi Nha Xinh" in Dalat. They provide furniture for restaurants, hotels,
and commercials. For the outside seating, we should go for something comfortable but weather
resistant. The Cape Cod-style from American would work best. They are a good look, modern, and
very unique. A perfect fit for the Dalat weather and life style. We would need roughly 20 chairs for
the seating of 10 people outside.
For the inside chair, we need several different types of chairs. I would say Braxton
Studio Halifax Beige Linen chairs for around the fireplace from Noi That Pho Xinh. They offer a more
comfortable feel for those that are wishing to stay awhile and read. The normal tables need something
that is a bit more resilient to tea stains and busy flow. The chair that would work best is the Midtown
Diner Chair from Ngoi Nha Xinh. It still has a high-end feel, yet goes well with the other chairs by the
fireplace. I would suggest a Braxton Studio White Le Corbusier Petite Sofa from Ngoi Nha Xinh.
Lastly, we need tables. Noi That Pho Xinh offers many different types of tabletops and bottoms.
Therefore, I would find it in our best interest to go to the store and have them pull together some
samples for us to all agree on.
• Working time for contractor and housebuilder is from Monday to Saturday, between 7
am to 5 pm.
• Contractor is responsible for subcontracted work.
g. Customer review
Ms. Chau and Ms. Hoa
Constrain x
Enhance x
Accept x
Because this project is a tea service-business, to ensure future revenue, the project needs to
accomplish the performance goal - to provide a perfect space for tea lovers and attract customers,
customers choose whether to use the project's product or not is largely depend on space and
associated services. That is the reason why we have to pay attention to this character.
Cost is the factor that we consider the second priority because we want the project to be completed
within the capital of the investor, minimize expenses.
Because the project is constructed during the Tet holiday and rainy season in Da Lat, the weather
element will partly affect the progress of the project. Moreover, we set the priority for performance
then cost, so we will extense time if it is needed for those 2 above dimensions.
1. Concept
2. Planning
3. Design
3.2 Branding
4. Construction
4.1 Foundation
4.1.1 Excavation
4.1.3 Formwork
4.1.4 Concreting
4.2.3 Roofing
5. Decoration
6. Operation
6.2 Administration
1 Concept 1
2. Planning
3 Design
3.2 Branding
3.2.1 Logo design 3 days Q18 K11 28 31 235 238 207
4 Construction
5 Decoration
5.1.1 Purchase and install 10 days W24 V22 176 186 176 186
furniture
5.2 Decorate and finish 8 days X25 W23 186 194 230 238 44
6 Operation
6.1.1 Check and take over works 5 days Y26 W23 186 191 108 193 2
6.1.2 Liquidate and terminate 7days Z27 W23 186 193 186 193
contract
6.1.3 Write final project report 3 days AA28 Y,Z25,26 193 196 193 196
6.1.4 Organise meeting, evaluate 3 days AB29 AA27 196 199 196 199
project
6.2 Administration
6.2.1 Set up operation plan 6 days AC30 AB28 199 205 232 238 33
6.2.2 Inform recruitment 10 days AD31 AB28 199 209 199 209
6.2.3 Training employees 7 days AE32 AD30 209 216 209 216
6.2.4 Perform marketing program 15 days AF33 AE31 216 231 216 231
6.2.5 Soft opening 5 days AG34 AF32 231 236 231 236
6.2.6 Grand opening 2 days AH355 AG33 236 238 236 238
Appendix 1
1 Concept
1.3 Find project 7 days 10.000.000 Nha dat Da Lat Phuong and 1 day
location Oanh
2. Planning
3 Design
3.1.1 Create concept 5 days 100.000.000 Bob Bergs Design All group
company
3.2.1 Logo design 3 days 20.000.000 Bob Bergs Design Phuong 1 day
company
3.2.2 Uniform design 2days 15.000.000 Bob Bergs Design Hoai 1 day
company
3.2.3 Menu design 4 days 10.000.000 Bob Bergs Design Anh 1 day
company
4 Construction
5 Decoration
6 Operation
6.1 Project contract
6.2 Administration
TOTAL 5.930.300.000