DETAILS OF MEASUREMENT

Name of work :- Improvement of Macha Leima Awang Leirak road

1 Providing laying and compacting granular base/sub-base according to lines grades and cross
section by using naturally occurred sand gravel/conforming to IRC grade (ii) of MOST
specification free from organic or other deleterious constituent compacted by rolling with
power roller of 8 to 10 tonnes capacity in layers not exceeding 150mm (spread thickness) i/c
rolling of the road surface to proper level and grades 30 cm width edging 30 cm width on both
sides etc complete as directed by the Engineer in charge with carriage of all material
complete.
3
1 No. X 280 X 3.75 X 0.15 = 157.5 m

2 Providing and laying one layer WBM 7.5cm consolidated thickness using1.00 cum of stone
agregare conforming to IRC grade per 10 sqm of road surface and 0.23 cum of binder
materials of approved quality per 10 sqm of road surface I/c coinsdolidation of the same
rolling of the surface to camber superelevation and grade by using template straight edges
and spirit level in layer not exceeding 100mm to 130mm thick (spread) thickness dry and wet
rolling with 8 to 10 tonne roller i/c earth edging 30 cm width on both side and applying binding
materials as specified with carriage charge of all materials complete.
a) I.R.C. Grade-III
3
1 No.X 280 X 3.75 X 0.075 = 78.75 m

3 Providing and laying bituminous macadam of 50 mm as per clause 504.1 of "MOST"


specification for base course with binder content @ 4% by weight of total mix including
preparation of bases including filling of pot holes, cleaning the surface with wire brushes etc.
and providing suitable edge supports heating of binder and aggregate handling of materials,
screening, mixing, in hot mix plant conforming and transporting laying and finishing with paver
finisher to the required level, grade and camber, rolling by power roller etc. complete including
running expenses of all plantspreparing surface by brushing with wire brushes for remaining
caked mud etc sweeping with brooms and finally fanning the clearned surface with gunny
bags to remove all loose dirt etc (a) B.T. Surface and providing and applying evenly a
priming/tack coat with bitumen 80/100 @ 5 kg/10 sqm.

2
1 No. X 280 X 3.75 = 1050 m

5 Providing 25mm thick semi-dense carpeting course aggregate fine aggregate and filler
required grading conforming to Table 500.11 of IRC specification in sufficient to yield
specified thickness after compaction including through dressing of surface, screening and
cleaning of stone materials making component including coarse aggregate, fine aggregate
and filler to obtain homogeneous mixture with requisite quantity of binder @ 5.50% by weight
to mix, mixing the quantity in hot mix plant conforming to IS 3066 and laying the mixture
uniformly to specified grade line and cross section over the existing surface.

1 No. X 280.00 X 3.75 = 1050 m2