ABSTRACT ESTIMATE

Reconstruction of Narrow (single row pipe) culvert at km 3/6 of


Name of work :
Kurinjipadi- Palur road

ESTIMATE AMOUNT RS. 2.00 Lakhs


Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

4.84 m3 PCC 242.00 1171.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

48.76 m3 km 3/6 pipe culvert 122.20 5958.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

4.42 m3 km 3/6 pipe culvert 448.77 1984.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

7.90 m3 km 3/6 pipe culvert 3880.98 30660.00

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:4


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)

10.14 m3 km 3/6 (Below sill) pipe culvert 5068.99 51400.00

10.16 m3 km 3/6 (Above sill) pipe culvert 5128.99 52111.00

Supply of RCC NP3 class pipes and collars of 900 mm dia of


6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

12.50 m3 km 3/6 pipe culvert 2600.00 32500.00


Hoisting and fixing of 100mm dia pipes NH3 class to proper
7 including all labour charges and other incidental charges etc,.
Complete

12.50 m3 km 3/6 pipe culvert 66.55 832.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

17.43 m3 km 3/6 pipe culvert 362.70 6322.00

Providing and laying spreading and compacating graded stone


aggregates to Wet Mix Macadam 250mm thick specification
including premixing the materials with water at OMC in
mechanical mix plant carriage of mixed material by tipper to
site laying in uniform layers with pavers in sub base /Base
9
course on well prepared surface and compacting with vibratory
roller to achieve the desired density including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 406 of MORTH
Rev-5.

3.50 m3 km 3/6 pipe culvert 1572.66 5504.00

Providing and laying Prime coat over WBM/WMM surface


using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
preparatory to another bituminous construction over it,
11
including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete
as per clause 502 of MORTH Rev-5

11.00 m2 km 3/6 pipe culvert 66.40 730.00

Providing and laying Tack coat over WBM/WMM


surface(treated with primer) using 2.50kg of Bituminous
Emulsion (RS1) per 10sqm for preparatory to another
12 bituminous construction over it, including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 502 of MORTH
Rev-5
11.00 m2 km 3/6 pipe culvert 13.39 147.00

Providing and laying 50mm consolidated thick Dense


bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below
and with 53.20kgs of VG30/VG40 bitumen for premixing per
10sqm including cost and conveyance of all materials to CMP
site, heating bitumen and agrregate to required temperature
and mixing them in required temperature central hot mix plant
20-30 to capacity, conveying the mix by tipper trucks to work
site, spreading the mix to uniform thickness of 50mm with
13
pavert to the specifited grades and cross sections and
compacted by vibratory/pneumatic roller to the required density
etc., incluidng labour for attending to paver at site etc.,
including hite charges and fuel charges for 20-30 to CMP with
bitumen boiler, tipper trucks, paver finisher/9m paver finisher,
vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc.,
complete as per specification using CMP as per clause 505 of
MORTH Rev-5.

0.55 m3 km 3/6 pipe culvert 6731.52 3702.00


Providing and laying Bituminous Concrete 30mm thick using
0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and 0.26cum
of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to
required temperature and mixing them in required temperature
in central hot mix plant 20-30 to capacity, conveying the mix by
tipper trucks to paver site, spreading the mix to uniform
14 thickness of 40mm with mechanical paver to the specifited
grades and cross sections and consolidated b10 tonne
vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hire charges
and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic
rollers and all other tools and plant required, including fuel and
all other incidental charges etc., complete as per specification
using CMP as per clause 507 of MORTH Rev-5.

0.44 m3 km 3/6 pipe culvert 7246.53 3188.00


196209.00
15 Provision for manual labour welfare fund 1.00 % 1962
16 Provision for P.S. charges 2.50% 1829

Total 200000

Assistant Divisional Engineer, Assistant Engineer,


Highways, (C&M), Highways, (C&M),
Kurinjipadi. Kurinjipady.
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (single row pipe) culvert at km 3/6 of
Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall 1 x 2x 4.60 x 1.60 x 1.50 22.08

pipe portion 1 x 1x 1.50 x 10.40 + 10.22 x 1.725 26.68


(crudle portion) 2 48.76

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall 1 x 2x 4.60 x 1.60 x 0.30 4.42

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall 1 x 2x 4.60 x 1.60 x 0.30 4.42

cradleportion 1 x 1x 1.50 x 10.40 + 10.22 x 0.225 3.48


2
7.90

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall 1 x 2x 4.60 x 1.40 + 1.05 x 0.90 10.14
2
Above Sill
3b
Body wall x x
1 2 x 4.60 1.05 + 0.45 1.60 11.04
2

parapet 1 2 x 1.50 x 0.35 x 0.40 0.42

Deduct for pipe


1 2 x 3.14 x (1.00*1.00)/4 x (1.05+0.60)/2 x -1.30
portion

10.16
Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete
N P3 1000 1 x 5 2.50 - 12.50
mm

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete

N P3 1000 1 x 5 2.50 - 12.50


mm

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe tren 1 x 1 x 1.50 x (10.40+11.20)/2 x 1.60 25.92

Deduct for pipe


1 x 1 x 3.14 x (1.00*1.00)/4 x (10.40+11.20)/2 -8.49
portion

17.43

Providing and laying spreading and compacating graded stone aggregates to Wet Mix Macadam 250mm thick
specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed
7 material by tipper to site laying in uniform layers with pavers in sub base /Base course on well prepared surface
and compacting with vibratory roller to achieve the desired density including cost of material, labour charges,
rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5.

Overpipes 1 x 1x 2.00 x 7.00 x 0.250 3.50

Providing and laying Prime coat over WMM surface using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
8 preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH Rev-5

1 x 1x 2.00 x 5.50 11.00

Providing and laying Tack coat over WBM/WMM surface(treated with primer) using 2.50kg of Bituminous Emulsion
(RS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour
9 charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH
Rev-5

1 x 1x 2.00 x 5.50 11.00


Providing and laying 50mm consolidated thick Dense bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all materials to CMP site, heating bitumen and agrregate to
required temperature and mixing them in required temperature central hot mix plant 20-30 to capacity, conveying
the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with pavert to the specifited
10 grades and cross sections and compacted by vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hite charges and fuel charges for 20-30 to CMP with bitumen
boiler, tipper trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause
505 of MORTH Rev-5.

1 x 1x 2.00 x 5.50 x 0.050 0.55

Providing and laying Bituminous Concrete 40mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and
0.26cum of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and
conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing
them in required temperature in central hot mix plant 20-30 to capacity, conveying the mix by tipper trucks to paver
site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specifited grades and cross
11 sections and consolidated b10 tonne vibratory/pneumatic roller to the required density etc., incluidng labour for
attending to paver at site etc., including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant required, including
fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH
Rev-5.

1 x 1x 2.00 x 5.50 x 0.040 0.44

Dismantling of existing structures by Mechanical Means like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever
12 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material
with all lifts and lead as per requirment as per Technical specifications and as directed by the Engineer-in-charge.

Parapet 1 x 2x 2.50 x 0.35 x 0.400 0.70

Body walls 1 x 2x 1.50 x 0.80 x 1.725 4.14

4.84

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
ABSTRACT ESTIMATE
Reconstruction of Narrow (single row pipe) culvert at km 3/2 of
Name of work :
Kurinjipadi- Palur road

ESTIMATE AMOUNT RS. 2.00 Lakhs


Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

4.84 m3 PCC 242.00 1171.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

48.76 m3 km 3/2 pipe culvert 122.20 5958.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

4.42 m3 km 3/2 pipe culvert 448.77 1984.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

7.90 m3 km 3/2 pipe culvert 3880.98 30660.00

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:4


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)

10.14 m3 km 3/2 (Below sill) pipe culvert 5068.99 51400.00

10.16 m3 km 3/2 (Above sill) pipe culvert 5128.99 52111.00

Supply of RCC NP3 class pipes and collars of 900 mm dia of


6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

12.50 m3 km 3/2 pipe culvert 2600.00 32500.00


Hoisting and fixing of 100mm dia pipes NH3 class to proper
7 including all labour charges and other incidental charges etc,.
Complete

12.50 m3 km 3/2 pipe culvert 66.55 832.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

17.43 m3 km 3/2 pipe culvert 362.70 6322.00

Providing and laying spreading and compacating graded stone


aggregates to Wet Mix Macadam 250mm thick specification
including premixing the materials with water at OMC in
mechanical mix plant carriage of mixed material by tipper to
site laying in uniform layers with pavers in sub base /Base
9
course on well prepared surface and compacting with vibratory
roller to achieve the desired density including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 406 of MORTH
Rev-5.

3.50 m3 km 3/2 pipe culvert 1572.66 5504.00

Providing and laying Prime coat over WBM/WMM surface


using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
preparatory to another bituminous construction over it,
11
including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete
as per clause 502 of MORTH Rev-5

11.00 m2 km 3/2 pipe culvert 66.40 730.00

Providing and laying Tack coat over WBM/WMM


surface(treated with primer) using 2.50kg of Bituminous
Emulsion (RS1) per 10sqm for preparatory to another
12 bituminous construction over it, including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 502 of MORTH
Rev-5
11.00 m2 km 3/2 pipe culvert 13.39 147.00

Providing and laying 50mm consolidated thick Dense


bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below
and with 53.20kgs of VG30/VG40 bitumen for premixing per
10sqm including cost and conveyance of all materials to CMP
site, heating bitumen and agrregate to required temperature
and mixing them in required temperature central hot mix plant
20-30 to capacity, conveying the mix by tipper trucks to work
site, spreading the mix to uniform thickness of 50mm with
13
pavert to the specifited grades and cross sections and
compacted by vibratory/pneumatic roller to the required density
etc., incluidng labour for attending to paver at site etc.,
including hite charges and fuel charges for 20-30 to CMP with
bitumen boiler, tipper trucks, paver finisher/9m paver finisher,
vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc.,
complete as per specification using CMP as per clause 505 of
MORTH Rev-5.

0.55 m3 km 3/2 pipe culvert 6731.30 3702.00


Providing and laying Bituminous Concrete 30mm thick using
0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and 0.26cum
of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to
required temperature and mixing them in required temperature
in central hot mix plant 20-30 to capacity, conveying the mix by
tipper trucks to paver site, spreading the mix to uniform
14 thickness of 40mm with mechanical paver to the specifited
grades and cross sections and consolidated b10 tonne
vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hire charges
and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic
rollers and all other tools and plant required, including fuel and
all other incidental charges etc., complete as per specification
using CMP as per clause 507 of MORTH Rev-5.

0.44 m3 km 3/2 pipe culvert 7246.28 3188.00


196209.00
15 Provision for manual labour welfare fund 1.00 % 1962
16 Provision for P.S. charges 2.50% 1829

Total 200000

Assistant Divisional Engineer, Assistant Engineer,


Highways, (C&M), Highways, (C&M),
Kurinjipadi. Kurinjipady.
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (single row pipe) culvert at km 3/2 of
Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall 1 x 2x 4.60 x 1.60 x 1.50 22.08

pipe portion 1 x 1x 1.50 x 10.40 + 10.22 x 1.725 26.68


(crudle portion) 2 48.76

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall 1 x 2x 4.60 x 1.60 x 0.30 4.42

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall 1 x 2x 4.60 x 1.60 x 0.30 4.42

cradleportion 1 x 1x 1.50 x 10.40 + 10.22 x 0.225 3.48


2
7.90

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall 1 x 2x 4.60 x 1.40 + 1.05 x 0.90 10.14
2
Above Sill
3b
Body wall x x
1 2 x 4.60 1.05 + 0.45 1.60 11.04
2

parapet 1 2 x 1.50 x 0.35 x 0.40 0.42

Deduct for pipe


1 2 x 3.14 x (1.00*1.00)/4 x (1.05+0.60)/2 x -1.30
portion

10.16
Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete
N P3 1000 1 x 5 2.50 - 12.50
mm

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete

N P3 1000 1 x 5 2.50 - 12.50


mm

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe tren 1 x 1 x 1.50 x (10.40+11.20)/2 x 1.60 25.92

Deduct for pipe


1 x 1 x 3.14 x (1.00*1.00)/4 x (10.40+11.20)/2 -8.49
portion

17.43

Providing and laying spreading and compacating graded stone aggregates to Wet Mix Macadam 250mm thick
specification including premixing the materials with water at OMC in mechanical mix plant carriage of mixed
7 material by tipper to site laying in uniform layers with pavers in sub base /Base course on well prepared surface
and compacting with vibratory roller to achieve the desired density including cost of material, labour charges,
rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5.

Overpipes 1 x 1x 2.00 x 7.00 x 0.250 3.50

Providing and laying Prime coat over WMM surface using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
8 preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH Rev-5

1 x 1x 2.00 x 5.50 11.00

Providing and laying Tack coat over WBM/WMM surface(treated with primer) using 2.50kg of Bituminous Emulsion
(RS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour
9 charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH
Rev-5

1 x 1x 2.00 x 5.50 11.00


Providing and laying 50mm consolidated thick Dense bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all materials to CMP site, heating bitumen and agrregate to
required temperature and mixing them in required temperature central hot mix plant 20-30 to capacity, conveying
the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with pavert to the specifited
10 grades and cross sections and compacted by vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hite charges and fuel charges for 20-30 to CMP with bitumen
boiler, tipper trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause
505 of MORTH Rev-5.

1 x 1x 2.00 x 5.50 x 0.050 0.55

Providing and laying Bituminous Concrete 40mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and
0.26cum of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and
conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing
them in required temperature in central hot mix plant 20-30 to capacity, conveying the mix by tipper trucks to paver
site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specifited grades and cross
11 sections and consolidated b10 tonne vibratory/pneumatic roller to the required density etc., incluidng labour for
attending to paver at site etc., including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant required, including
fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH
Rev-5.

1 x 1x 2.00 x 5.50 x 0.040 0.44

Dismantling of existing structures by Mechanical Means like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever
12 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material
with all lifts and lead as per requirment as per Technical specifications and as directed by the Engineer-in-charge.

Parapet 1 x 2x 2.50 x 0.35 x 0.400 0.70

Body walls 1 x 2x 1.50 x 0.80 x 1.725 4.14

4.84

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
ABSTRACT ESTIMATE

Construction of Reconstruction of retaining wall at km


Name of work : 1/2,2/4 & 2/6 of Mettupalayam-Ayeethurai road to Sirupalayur
(via) Theerthanagiri road .

ESTIMATE AMOUNT RS. #REF!


Slno Qty Description of Item Rate Amount

Earth work excavation in all classes of soils except


hard rock requiring blasting for box cutting including
all labour charges for excavation all labour charges
for excavation Involving an average horizontal throw
1 111.20
up to 2.0m and an average lift up to 0.5m including
breaking charges etc., complete as per cause 301-
305 of MORT & H specifications FOR BOX CUTTING
.

17.10 m3 km.1/2 111.20 1902.00

Sand filling with good dry river sand from approved


quarry including cost and conveyance of all materials
2 #REF!
to site including all labour charges for filling watering
and consolidation etc., complete.

5.70 m3 km.1/2 423.30 2413.00

Vibrated Cement Concrete M.15 grade Nominal mix


using 40mm ISS HBG metal including cost and
conveyance of all materials to site,.including cost and
3 #REF!
labour charges for formwork and centering and labour
charges compacting curing and all other incidental
charges etc., complete

10.50 m3 km.1/2 4684.61 49188.00

Vibrated Cement Concrete M.15 grade Nominal mix


using 40mm ISS HBG metal including cost and
conveyance of all materials to site,.including cost and
4 #REF!
labour charges for formwork and centering and labour
charges compacting curing and all other incidental
charges etc., complete .,Above sill

17.72 m3 km.1/2 4744.61 84074.00

Providing and fixing 110mm dia PVC Seepage Pipes


of required length for abutment and wing , retaining
wall including cost and conveyance of all materials to
worksite , cost and labour for semi-Sperical backfill
5 180.00
arrangements with 100mm size broken granite stones
ate the periphery and labour charges for fixing etc.,
complete to draing the backfill as per standard
specification.
= Nos km.1/2 180.00 #VALUE!

Excavation including removal and satisfactory


disposal of all materials necessary for the
construction of roadway and side drains in
6 82.80
accordance with the specification and the lines and
cross sections shown in the drawings or as indicated
by the Engineer.

a. Filling Earth Between Retaining wall and Road


Berms as per SS 20 A.
128.00 m3 km.1/2 19.50 2496.00
Total #REF!

Assistant Divisional Engineer (H), Assistant Engineer (H),


C&M, Kurinjipadi. C&M, Kurinjipadi.
Name of Work : Construction of Retaining wall at km 0/10 of Mettupalayam
Ayeethurai to Sirupaliyur Road Km 0/0 - 3/2

Detailed Estimate

S. No Description of Work Nos L B D Qty

1
Earthwork excavation inall classes of soils exect hard roak requireing blasting and
depositing on bank with all leads and lifts as per SS 20B including cost of all labour
meterials, tools, equipments and all incidental charges and sheeting, shoring
struuting bailing out water forming protective etc., coffer dams wherever necessry
for dresssing the bed below sill level etc. complete. for Foundation.

Retaining Foundation

Km 0/10 1 x 1 10.00 1.90 0.90 = 17.10

17.10
Cum

2
Sand filling with good dry river sand from approved quarry including cost and
conveyance of all materials to site including all labour charges for filling watering
and consolidation etc., complete.

Retaining Foundation

Km 0/10 1 x 1 10.00 1.90 0.30 = 5.70

5.70
Cum

3 Vibrated cement concrete M15 (1:2:4)nominal mix using 40 mm ISS HBG metal
including cost and conveyance of all materials to site including cement complying to
the required standared and specification including cost of form work mixing laying
compacting using vibrated including hire and fuel charges for all tools and plants
engaged in curing and all other incidental charges such balling out water where ever
necessary forming protective bunds coffer dams etc., complete a foundation. For
Below Sill Level.

Km 0/10

Retaining Foundation

step 1 1 x 1 10.00 1.90 0.30 = 5.70

step 2 1 x 1 10.00 1.60 0.30 = 4.80

10.50
Cum
4 Vibrated cement concrete M15 (1:2:4)nominal mix using 40 mm ISS HBG metal
including cost and conveyance of all materials to site including cement complying to
the required standared and specification including cost of form work mixing laying
compacting using vibrated including hire and fuel charges for all tools and plants
engaged in curing and all other incidental charges such balling out water where ever
necessary forming protective bunds coffer dams etc., complete a foundation. For
Above Sill Level

Km 0/10

Retaining wall 1 x 1 10.00 (1.3 + 0.45)/2 2.00 = 17.50

Guide Post 1 x 4 0.35 0.35 0.45 = 0.22

17.72
Cum

5 Providing and fixing 100mm dia PVC Seepage Pipes of required length for
abutment and wing , retaining wall including cost and conveyance of all materials to
worksite , cost and labour for semi-Sperical backfill arrangements with 100mm size
broken granite stones ate the periphery and labour charges for fixing etc., complete
to draing the backfill as per standard specification.

Km 0/10 1 x 10 = 10

10.00
Nos

6 Excavation including removal and satisfactory disposal of all materials necessary for
the construction of roadway and side drains in accordance with the specification and
the lines and cross sections shown in the drawings or as indicated by the Engineer.

a. Filling Earth Between Retaining wall and Road Berms as per SS 20 A.

(0.5+3.50/2)

Km 0/10 1 x 1 10.00 2.00 2.00 = 40.00

40.00
Cum
ABSTRACT ESTIMATE
Reconstruction of Narrow (Widening R/L single row pipe) culvert at
Name of work :
km 3/2 of Kurinjipadi- Palur road
ESTIMATE AMOUNT RS. 134774.40

Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

0.84 m3 km 3/2 pipe culvert 242.00 203.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

24.53 m3 km 3/2 pipe culvert 122.20 2997.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

3.46 m3 km 3/2 pipe culvert 447.07 1545.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

4.40 m3 km 3/2 pipe culvert 4007.85 17639.00

Vibrated Cement Concrete M.20 grade Nominal mix 1:1.5:3


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)

7.94 m3 km 3/2 (Below sill) pipe culvert 5202.85 41300.00

7.72 m3 km 3/2 (Above sill) pipe culvert 5262.85 40652.00


Supply of RCC NP3 class pipes and collars of 900 mm dia of
6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

5.00 m3 km 3/2 pipe culvert 2600.00 13000.00

Hoisting and fixing of 100mm dia pipes NH3 class to proper


7 including all labour charges and other incidental charges etc,.
Complete

5.00 m3 km 3/2 pipe culvert 66.55 333.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

5.33 m3 km 3/2 pipe culvert 360.80 1922.00

Providing and Laying Granular Sub-Base Grade- V consisting


of well graded Material confirming to the grading given in Table
No.400-1, mixing in a mechanical mix plant at OMC, carriage
of mixed Material to work site, spreading in uniform layers with
9
motor grader on prepared surface and compacting with
vibratory roller to achieve the desired density, etc., complete
as directed by the Engineer. as per MORTH No. 111, 112,
401, 900.

4.20 m3 km 3/2 pipe culvert 1448.04 6082.00

Providing and laying Prime coat over WBM/WMM surface


using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
preparatory to another bituminous construction over it,
11
including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete
as per clause 502 of MORTH Rev-5

11.00 m2 km 3/2 pipe culvert 66.40 730.00

Providing and laying Tack coat over WBM/WMM


surface(treated with primer) using 2.50kg of Bituminous
Emulsion (RS1) per 10sqm for preparatory to another
12 bituminous construction over it, including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 502 of MORTH
Rev-5

11.00 m2 km 3/2 pipe culvert 13.39 147.00


Providing and laying 50mm consolidated thick Dense
bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below
and with 53.20kgs of VG30/VG40 bitumen for premixing per
10sqm including cost and conveyance of all materials to CMP
site, heating bitumen and agrregate to required temperature
and mixing them in required temperature central hot mix plant
20-30 to capacity, conveying the mix by tipper trucks to work
site, spreading the mix to uniform thickness of 50mm with
13
pavert to the specifited grades and cross sections and
compacted by vibratory/pneumatic roller to the required density
etc., incluidng labour for attending to paver at site etc.,
including hite charges and fuel charges for 20-30 to CMP with
bitumen boiler, tipper trucks, paver finisher/9m paver finisher,
vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc.,
complete as per specification using CMP as per clause 505 of
MORTH Rev-5.

0.55 m3 km 3/2 pipe culvert 6731.30 3702.00

Providing and laying Bituminous Concrete 30mm thick using


0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and 0.26cum
of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to
required temperature and mixing them in required temperature
in central hot mix plant 20-30 to capacity, conveying the mix by
tipper trucks to paver site, spreading the mix to uniform
14 thickness of 40mm with mechanical paver to the specifited
grades and cross sections and consolidated b10 tonne
vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hire charges
and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic
rollers and all other tools and plant required, including fuel and
all other incidental charges etc., complete as per specification
using CMP as per clause 507 of MORTH Rev-5.

0.44 m3 km 3/2 pipe culvert 7246.28 3188.00


133440.00
15 Provision for manual labour welfare fund 1.00 % 1334
16 Provision for P.S. charges 2.50%
Total 134774.40

Assistant Divisional Engineer, Assistant Engineer,


Highways, (C&M), Highways, (C&M),
Kurinjipadi. Kurinjipady.
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (Widening R/L single row pipe) culvert at
km 3/2 of Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall R/L 1 x 2x 3.60 x 1.60 x 1.50 17.28

pipe portion R/L 1 x 2x 1.50 x 1.44 + 1.36 x 1.725 7.25


(cradle portion) 2 24.53 122.4 3001.86

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall 1 x 2x 3.60 x 1.60 x 0.30 3.46 447.07 1545.0739

Vibrated cement Concrete M.15 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall R/L 1 x 2x 3.60 x 1.60 x 0.30 3.46

cradleportion R/L 1 x 2x 1.50 x 1.44 + 1.36 x 0.225 0.95


2
4.40 4007.85 17638.548

Vibrated Cement Concrete M.15 grade Nominal mix 1:1.5:3 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall 1 x 2x 3.60 x 1.40 + 1.05 x 0.90 7.94 5202.85 41300.223
2
Above Sill
3b
Body wall x x
1 2 x 3.60 1.05 + 0.45 1.60 8.64
2

parapet 1 2 x 1.50 x 0.35 x 0.40 0.42

Deduct for pipe portion 1 2 x 3.14 x (1.00*1.00)/4 x (1.05+0.65)/2 x -1.34

7.72 5262.85 40651.757

Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete

N P3 1000 mm 1 x 2 2.50 - 5.00


R/L 2600 13000

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete
N P3 1000 mm 1 x 2 2.50 - 5.00
R/L 66.55 332.75

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe trench R/L 1 x 2 x 1.50 x


1.44 + 1.86 x 1.600 7.92

Deduct for pipe portion R/L 1 2 x 3.14 x (1.00*1.00)/4 x (1.44+1.86)/2 x -2.59

5.33 360.80 1922.0331

Construction of Granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC,
7 carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 Grade V

Overpipes 1 x 1x 2.00 x 7.00 x 0.300 4.20 1448.23 6082.566

Providing and laying Prime coat over WMM surface using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
8 preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH Rev-5

1 x 1x 2.00 x 5.50 11.00 66.65 733.15

Providing and laying Tack coat over WBM/WMM surface(treated with primer) using 2.50kg of Bituminous Emulsion
(RS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour
9 charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH
Rev-5

1 x 1x 2.00 x 5.50 11.00 13.44 147.84

Providing and laying 50mm consolidated thick Dense bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all materials to CMP site, heating bitumen and agrregate to
required temperature and mixing them in required temperature central hot mix plant 20-30 to capacity, conveying
the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with pavert to the specifited
10 grades and cross sections and compacted by vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hite charges and fuel charges for 20-30 to CMP with bitumen
boiler, tipper trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc., complete as per specification using CMP as per
clause 505 of MORTH Rev-5.

1 x 1x 2.00 x 5.50 x 0.050 0.55 6743.12 3708.716


Providing and laying Bituminous Concrete 40mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and
0.26cum of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and
conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing
them in required temperature in central hot mix plant 20-30 to capacity, conveying the mix by tipper trucks to paver
site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specifited grades and cross
11 sections and consolidated b10 tonne vibratory/pneumatic roller to the required density etc., incluidng labour for
attending to paver at site etc., including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant required, including
fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH
Rev-5.

1 x 1x 2.00 x 5.50 x 0.040 0.44 7261.05 3194.862

Dismantling of existing structures by Mechanical Means like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever
12 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead as per requirment as per Technical specifications and as directed by the Engineer-
in-charge. Dismantling parapet pcc

Parapet 1 x 2x 3.00 x 0.35 x 0.400 0.84 242 203.28

133462.66

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
ABSTRACT ESTIMATE
Reconstruction of Narrow (Widening L/S Three row pipe) culvert at
Name of work
km 10/4 of Kurinjipadi- Palur road

ESTIMATE AMOUNT RS. 2.00 Lakhs


Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

0.37 m3 km 10/4 pipe culvert 242.00 90.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

40.63 m3 km 10/4 pipe culvert 122.20 4965.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

5.95 m3 km 10/4 pipe culvert 421.09 2505.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

7.37 m3 km 10/4 pipe culvert 3845.25 28339.00

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:3


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)

13.67 m3 km 10/4 (Below sill) pipe culvert 5033.18 68804.00

13.51 m3 km 10/4 (Above sill) pipe culvert 5093.18 68809.00


Supply of RCC NP3 class pipes and collars of 1000 mm dia of
6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

7.50 m3 km 10/4 pipe culvert 2600.00 19500.00

Hoisting and fixing of 100mm dia pipes NH3 class to proper


7 including all labour charges and other incidental charges etc,.
Complete

7.50 m3 km 10/4 pipe culvert 66.55 499.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

7.99 m3 km 10/4 pipe culvert 306.35 2448.00

Providing and laying U.S gravel including cost and


conveyance of U.S gravel from approved quarry to work site
9 including spreading watering with all leads and consolidation
by power roller and all other incidental charges etc., complete
as per standard specification for Shoulders

1.05 m3 km 10/4 pipe culvert 387.55 407.00


196366.00
10 Provision for manual labour welfare fund 1.00 % 1965
11 Provision for P.S. charges 1669

Total 200000

Assistant Divisional Engineer, Assistant Engineer,


Highways, (C&M), Highways, (C&M),
Kurinjipadi. Kurinjipady.
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (Widening L/S Three row pipe) culvert at
km 10/4 of Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall L/S 1 x 1x 12.40 x 1.60 x 1.50 29.76

pipe portion L/S 1 x 1x 4.50 x 1.44 + 1.36 x 1.725 10.87


(cradle portion) 2 40.63

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall L/S 1 x 1x 12.40 x 1.60 x 0.30 5.95

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall L/S 1 x 1x 12.40 x 1.60 x 0.30 5.95

cradleportion L/S 1 x 1x 4.50 x 1.44 + 1.36 x 0.225 1.42


2
7.37

Vibrated Cement Concrete M.15 grade Nominal mix 1:2:4 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall 1 x 1x 12.40 x 1.40 + 1.05 x 0.90 13.67
2
Above Sill
3b
Body wall x x
1 1 x 12.40 1.05 + 0.45 1.60 14.88
2

parapet 1 1 x 4.50 x 0.35 x 0.40 0.63

Deduct for pipe portion 3 1 x 3.14 x (1.00*1.00)/4 x (1.05+0.65)/2 x -2.00

13.51
Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete

N P3 1000 mm 3 x 1 2.50 - 7.50


L/S

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete

N P3 1000 mm 3 x 1 2.50 - 7.50


L/S

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe trench L/S 1 x 1 x 4.50 x 1.44 + 1.86 x 1.600 11.88

Deduct for pipe portion 3 1 x 3.14 x (1.00*1.00)/4 x (1.44+1.86)/2 x -3.89

7.99

Providing and laying U.S gravel including cost and conveyance of U.S gravel from approved quarry to work site
7 including spreading watering with all leads and consolidation by power roller and all other incidental charges etc.,
complete as per standard specification for Shoulders

1 x 1x 7.00 x 1.50 x 0.100 1.05

Dismantling of existing structures by Mechanical Means like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever
8 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead as per requirment as per Technical specifications and as directed by the Engineer-
in-charge.Dismantling pcc

Parapet 1 x 1x 3.00 x 0.35 x 0.350 0.37

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
ABSTRACT ESTIMATE
Reconstruction of Narrow (Widening R/S single row pipe) culvert at
Name of work :
km 3/6 of Kurinjipadi- Palur road

ESTIMATE AMOUNT RS. 60848.46


Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

0.42 m3 km 3/6 pipe culvert 242.00 102.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

1.73 m3 km 3/6 pipe culvert 122.20 211.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

1.73 m3 km 3/6 pipe culvert 447.07 773.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

2.20 m3 km 3/6 pipe culvert 4007.85 8819.00

Vibrated Cement Concrete M.20 grade Nominal mix 1:1.5:3


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)

3.97 m3 km 3/6 (Below sill) pipe culvert 5202.85 20650.00

3.86 m3 km 3/6 (Above sill) pipe culvert 5262.85 20326.00


Supply of RCC NP3 class pipes and collars of 900 mm dia of
6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

2.50 m3 km 3/6 pipe culvert 2600.00 6500.00

Hoisting and fixing of 100mm dia pipes NH3 class to proper


7 including all labour charges and other incidental charges etc,.
Complete

2.50 m3 km 3/6 pipe culvert 66.55 166.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

2.66 m3 km 3/6 pipe culvert 360.80 961.00

1.20 m3 km 3/6 pipe culvert 1448.04 1738.00


60246.00
15 Provision for manual labour welfare fund 1.00 % 602
16 Provision for P.S. charges 2.50%
Total 60848.46

Assistant Divisional Engineer, Assistant Engineer,


Highways, (C&M), Highways, (C&M),
Kurinjipadi. Kurinjipady.
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (Widening R/S single row pipe) culvert at km 3/6 of
Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall R/S 1 x 1x 3.60 x 1.60 x 1.50 8.64

pipe portion R/S 1 x 1x 1.50 x 1.44 + 1.36 x 1.725 3.62


(cradle portion) 2 12.26 122.40 1500.93

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall 1 x 1x 3.60 x 1.60 x 0.30 1.73 447.07 772.53696

Vibrated cement Concrete M.15 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall R/S 1 x 1x 3.60 x 1.60 x 0.30 1.73

cradleportion R/S 1 x 1x 1.50 x 1.44 + 1.36 x 0.225 0.47


2
2.20 4007.85 8819.2739

Vibrated Cement Concrete M.15 grade Nominal mix 1:1.5:3 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall R/S 1 x 1x 3.60 x 1.40 + 1.05 x 0.90 3.97 5202.85 20650.112
2
Above Sill
3b
Body wall R/S x x
1 1 x 3.60 1.05 + 0.45 1.60 4.32
2

parapet R/S 1 1 x 1.50 x 0.35 x 0.40 0.21

Deduct for pipe portion 1 1 x 3.14 x (1.00*1.00)/4 x (1.05+0.65)/2 x -0.67

3.86 5262.85 20325.879

Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete

N P3 1000 mm 1 x 1 2.50 - 2.50


R/S 2600 6500

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete
N P3 1000 mm 1 x 1 2.50 - 2.50
R/S 66.55 166.375

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe trench R/S 1 x 1 x 1.50 x


1.44 + 1.86 x 1.600 3.96

Deduct for pipe portion R/S 1 1 x 3.14 x (1.00*1.00)/4 x (1.44+1.86)/2 x -1.30

2.66 360.6 960.48386

Construction of Granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC,
7 carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 Grade V

1448.23
Overpipes 1 x 1x 2.00 x 2.00 x 0.300 1.20 1737.876

8
DISMANTLING pcc
242.00
Parapet 1 x 1x 3.00 x 0.35 x 0.400 0.42 101.64

61535.106

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
ABSTRACT ESTIMATE
Reconstruction of Narrow (single row pipe) culvert at km 3/8 of
Name of work :
Kurinjipadi- Palur road

ESTIMATE AMOUNT RS. 147.00


Slno Qty Description of Item Rate Amount

Dismantling of existing structures by Mechanical Means like


culverts, bridges, retaining walls and other structure comprising
of masonry, cement concrete, wood work, steel work, including
T&P and scaffolding wherever necessary, sorting the
1
dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead as per
requirment as per Technical specifications and as directed by
the Engineer-in-charge.

4.84 m3 PCC 242.00 1171.00

Earth work excavation in all classes of soils except hard rock


requiring blasting for box cutting including all labour charges
for excavation all labour charges for excavation Involving an
2
average horizontal throw up to 2.0m and an average lift up to
0.5m including breaking charges etc., complete as per cause
301-305 of MORT & H specifications FOR BOX CUTTING .

47.80 m3 km 3/8 pipe culvert 122.20 5841.00

Sand filling with good dry river sand from approved quarry
including cost and conveyance of all materials to site including
3
all labour charges for filling watering and consolidation etc.,
complete.

4.22 m3 km 3/8 pipe culvert 447.07 1888.00

Vibrated cement Concrete M.10 grade Nominal mix 1:3:6 using


40 mm ISS HBG metal including cost and conveyance of all
4 materials to site, including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc,.Foundation concrete.

7.70 m3 km 3/8 pipe culvert 4002.01 30830.00

Vibrated Cement Concrete M.20 grade Nominal mix 1:1.5:3


using 40mm ISS HBG metal including cost and conveyance of
5 all materials to site,.including cost and labour charges for
formwork and centering and labour charges compacting curing
and all other incidental charges etc., complete ., (Below Sill)
9.70 m3 km 3/8 (Below sill) pipe culvert 5197.01 50421.00

9.68 m3 km 3/8 (Above sill) pipe culvert 5257.01 50907.00

Supply of RCC NP3 class pipes and collars of 900 mm dia of


6 standard length and cut length including cost and conveyance
to the work site and all other incidental charges etc., complete

12.50 m3 km 3/8 pipe culvert 2600.00 32500.00

Hoisting and fixing of 100mm dia pipes NH3 class to proper


7 including all labour charges and other incidental charges etc,.
Complete

12.50 m3 km 3/8 pipe culvert 66.55 832.00

FILING GRAVEL for pipe portion with clean good gritty gravel
including cost and conveyance to site including labour charges
8
for filling in layers. Watering tamping under optimum moisture
content to get the maximum density all incidental charges.

17.43 m3 km 3/8 pipe culvert 449.47 7836.00

Providing and laying spreading and compacating graded stone


aggregates to Wet Mix Macadam 250mm thick specification
including premixing the materials with water at OMC in
mechanical mix plant carriage of mixed material by tipper to
site laying in uniform layers with pavers in sub base /Base
9
course on well prepared surface and compacting with vibratory
roller to achieve the desired density including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 406 of MORTH
Rev-5.

4.20 m3 km 3/8 pipe culvert 1438.86 6043.00

Providing and laying Prime coat over WBM/WMM surface


using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
preparatory to another bituminous construction over it,
11
including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete
as per clause 502 of MORTH Rev-5

11.00 m2 km 3/8 pipe culvert 62.66 689.00

Providing and laying Tack coat over WBM/WMM


surface(treated with primer) using 2.50kg of Bituminous
Emulsion (RS1) per 10sqm for preparatory to another
12 bituminous construction over it, including cost of material,
labour charges, rentals for machinery, fuel and all other
incidental charges etc., complete as per clause 502 of MORTH
Rev-5
11.00 m2 km 3/8 pipe culvert 13.39 147.00

Providing and laying 50mm consolidated thick Dense


bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below
and with 53.20kgs of VG30/VG40 bitumen for premixing per
10sqm including cost and conveyance of all materials to CMP
site, heating bitumen and agrregate to required temperature
and mixing them in required temperature central hot mix plant
20-30 to capacity, conveying the mix by tipper trucks to work
site, spreading the mix to uniform thickness of 50mm with
13
pavert to the specifited grades and cross sections and
compacted by vibratory/pneumatic roller to the required density
etc., incluidng labour for attending to paver at site etc.,
including hite charges and fuel charges for 20-30 to CMP with
bitumen boiler, tipper trucks, paver finisher/9m paver finisher,
vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc.,
complete as per specification using CMP as per clause 505 of
MORTH Rev-5.

0.55 m3 km 3/8 pipe culvert 6720.60 3696.00

Providing and laying Bituminous Concrete 30mm thick using


0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and 0.26cum
of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all
materials to CMP site, heating the bitumen and aggregate to
required temperature and mixing them in required temperature
in central hot mix plant 20-30 to capacity, conveying the mix by
tipper trucks to paver site, spreading the mix to uniform
14 thickness of 40mm with mechanical paver to the specifited
grades and cross sections and consolidated b10 tonne
vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hire charges
and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic
rollers and all other tools and plant required, including fuel and
all other incidental charges etc., complete as per specification
using CMP as per clause 507 of MORTH Rev-5.

0.44 m3 km 3/8 pipe culvert 7235.90 3184.00


195985.00
15 Provision for manual labour welfare fund 1.00 % 1960
16 Provision for P.S. charges 2.50% 2055

Total 200000
Detailed Estimate (CD Work)
Name Of Road : Reconstruction of Narrow (single row pipe) culvert at km 3/8 of
Kurinjipadi- Palur road

Earth work excavation in all classes of soils except hard rock requiring blasting for box cutting including all labour charges for
1 excavation all labour charges for excavation Involving an average horizontal throw up to 2.0m and an average lift up to 0.5m
including breaking charges etc., complete as per cause 301-305 of MORT & H specifications FOR BOX CUTTING .

Body wall 1 x 2x 4.40 x 1.60 x 1.50 21.12

pipe portion 1 x 1x 1.50 x 10.40 + 10.22 x 1.725 26.68


(crudle portion) 2 47.80

Sand filling with good dry river sand from approved quarry including cost and conveyance of all materials to site including all
2
labour charges for filling watering and consolidation etc., complete.

Body wall 1 x 2x 4.40 x 1.60 x 0.30 4.22

Vibrated cement Concrete M.15 grade Nominal mix 1:3:6 using 40 mm ISS HBG metal including cost and conveyance of all
3 materials to site, including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc,.Foundation concrete.

Body wall 1 x 2x 4.40 x 1.60 x 0.30 4.22

cradleportion 1 x 1x 1.50 x 10.40 + 10.22 x 0.225 3.48


2
7.70

Vibrated Cement Concrete M.15 grade Nominal mix 1:1.5:3 using 40mm ISS HBG metal including cost and conveyance of all
3a materials to site,.including cost and labour charges for formwork and centering and labour charges compacting curing and all
other incidental charges etc., complete .,

Below sill
Body wall 1 x 2x 4.40 x 1.40 + 1.05 x 0.90 9.70
2
Above Sill
3b
Body wall x x
1 2 x 4.40 1.05 + 0.45 1.60 10.56
2

parapet 1 2 x 1.50 x 0.35 x 0.40 0.42

Deduct for pipe


1 2 x 3.14 x (1.00*1.00)/4 x (1.05+0.60)/2 x -1.30
portion

9.68
Supply of RCC NP3 class pipes and collars of 1000 mm dia of standard length and cut length including cost and conveyance to
4
the work site and all other incidental charges etc., complete
N P3 1000 1 x 5 2.50 - 12.50
mm

Hoisting and fixing of 1000mm dia pipes NP3 class to proper including all labour charges and other incidental charges etc,.
5
Complete

N P3 1000 1 x 5 2.50 - 12.50


mm

FILING GRAVEL for pipe portion with clean good gritty gravel including cost and conveyance to site including
6 labour charges for filling in layers. Watering tamping under optimum moisture content to get the maximum density
all incidental charges.

Pipe tren 1 x 1 x 1.50 x (10.40+11.20)/2 x 1.60 25.92

Deduct for pipe


1 x 1 x 3.14 x (1.00*1.00)/4 x (10.40+11.20)/2 -8.49
portion

17.43

Construction of Granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC,
7 carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and
compacting with vibratory power roller to achieve the desired density, complete as per clause 401 Grade V

Overpipes 1 x 1x 2.00 x 7.00 x 0.300 4.20

Providing and laying Prime coat over WMM surface using 7kg of Emulsion Bitumen (SSI) per 10 sqm for
8 preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for
machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH Rev-5

1 x 1x 2.00 x 5.50 11.00

Providing and laying Tack coat over WBM/WMM surface(treated with primer) using 2.50kg of Bituminous Emulsion
(RS1) per 10sqm for preparatory to another bituminous construction over it, including cost of material, labour
9 charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 502 of MORTH
Rev-5

1 x 1x 2.00 x 5.50 11.00


Providing and laying 50mm consolidated thick Dense bituminous Macadam using 0.24cum of 26.50-13.20mm,
0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20kgs of VG30/VG40 bitumen for
premixing per 10sqm including cost and conveyance of all materials to CMP site, heating bitumen and agrregate to
required temperature and mixing them in required temperature central hot mix plant 20-30 to capacity, conveying
the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with pavert to the specifited
10 grades and cross sections and compacted by vibratory/pneumatic roller to the required density etc., incluidng
labour for attending to paver at site etc., including hite charges and fuel charges for 20-30 to CMP with bitumen
boiler, tipper trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant
required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause
505 of MORTH Rev-5.

1 x 1x 2.00 x 5.50 x 0.050 0.55

Providing and laying Bituminous Concrete 40mm thick using 0.13cum of 19.00-9.50mm, 0.17cum of 2.36mm and
0.26cum of 2.36 and below tih 5.30kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and
conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing
them in required temperature in central hot mix plant 20-30 to capacity, conveying the mix by tipper trucks to paver
site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specifited grades and cross
11 sections and consolidated b10 tonne vibratory/pneumatic roller to the required density etc., incluidng labour for
attending to paver at site etc., including hire charges and fuel charges for 20-30 to CMP with bitumen boiler, tipper
trucks, paver finisher/9m paver finisher, vibratory/pneumatic rollers and all other tools and plant required, including
fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH
Rev-5.

1 x 1x 2.00 x 5.50 x 0.040 0.44

12 Dismantling PCC

Parapet 1 x 2x 2.50 x 0.35 x 0.400 0.70

Body walls 1 x 2x 1.50 x 0.80 x 1.725 4.14

4.84

Assistant Divisional Engineer, Assistant Engineer,


Highways,(C&M), Highways,(C&M),
Kurinjipadi. Kurinjipadi.
Cost of cement
As PWD Rate 6850
Deduct loading / Unloading -176.8
6673.20
Rate+Vat (14.50%) 6673.20
Rate 5828.12
Rate 5828.12
Central Excise Duty for cement - 12.50% 5180.55
Basic rate of cement 5180.55
Add storage (5%) 259.03

Total Cost of Cement 7109.03 7109.03 Cement

Cost of steel
As PWD Rate 43500
Deduct loading / Unloading -176.8
43323.20
Rate+Vat (14.50%) 43323.20
Rate 41260.19
Rate 41260.19
Central Excise Duty for Steel- 12.50% 36675.72
Basic rate of cement 36675.72
Add storage (5%) 1833.79

Total Cost of Steel 45333.79 45333.79 Steel