Name of Work :- Construction of BOX Culvert of 1.5 M X 1.

5 M at km 18/6 of NH 219

Sl
Qty Description of Work Rate / Per Amount
No.
Earthwork excavation in all classes of soil except
soft rock not requiring blasting and hard rock
requiring blasting and depositing on bank with all
leads and lifts, including cost of all labour,
equipments and all incidental charges such as
baling our water, providing and maintaining
necessary cofferdams, sheeting, shoring bracing
and their subsequent removal, removal of all logs,
stumps, grubs and other deleterious matter and
1 121.72 cu.m obstructions, trimming bottom of excavation 110.27 /cu.m 13422
backfilling, and clearing the site and disposal of
all surplus materials etc., complete as per relevant
standard specification for foundation

Vibrated Cement concrete in M-20 using ISS


HBG including cost and conveyance of all
materials to site and cost of cement at site
including soft water, labour charges for mixing,
transporting, laying and curing concrete, tools
and plants and incidental charges as baling out
2 14.43 cu.m water, maintaining of protective bunds, 8655.58 /cu.m 124900
cofferdams, shorting, strutting etc., complete as
per relevant standard specification for
foundation.

Vibrated Reinforced Cement concrete in M20


using ISS graded HBG metal including cost and
conveyance of all materials to site and cost of
cement at site including soft water, labour
charges for form work, centering, mixing,
transporting, laying and curing concrete, tools
3 46.49 cu.m and plants and incidental charges excluding cost 9271.67 /cu.m 431040
of steel etc., complete as per relevant standard
specification for CELL BOX

Providing and applying tack coat with bitumen


emulsion using emulsion pressure distributor at
the rate of 0.30 Kg/sqm on the Concrete surface
5 29.61 Sqm cleaded with mechanical broom all complete as 12.98 /Sqm 384
per Technical Specification MoRTH503
Providing and laying Bituminous concrete using
CRMB with 100 - 120 THP hot mix plant
producing an average output of 75 tonnes per
hour using crushed aggregates of specified
grading premixed with bituminous binder as
specified by Job Mix Formula(JMF) by weight of
total mix and filler, trnsporting the hot mix to site,
laid over a previously prepared surface with a
hydrostatic paver finisher with sensor control to
6 1.48 cu.m the required grade, level and alignment and rolled 10391.26 /cu.m 15379
with smooth wheeled, vibratory and tandom
rollers to acheieve the desired compaction as per
clause 507 of MORT & H specifications complete
in all respects. - Grading II

Supply and fabrication of Fe – 415 steel with high


strength corrosion resistant rebar (TMT Her Grade
M) required for all RCC items of works involved in
the schedule cost of steel at site fabrication,
labour charges for cleaning the rods straightening,
cutting, bending, tying grills, including
overlapping to the required length whenever
necessary and placing the reinforcement in
4 3.69 mt position as specified in the drawings, including 73069.93 /1 mt 269628
cost of binding wire, provision of spacer bars,
cover blocks and all other incidental charges etc.
complete.
Providing and fixing of G.I. Drainage spouts
100mm dia as per MOST drawing No.SD/205 with
grating arrangements at top as shown in the
drawing including cost and conveyance of GI pipes
7 2.00 Nos 402.79 / each 806
and flats and fixing them in position etc.,
complete

Vibrated cement concrete of grade M20 using ISS


HBG metal including cost and conveyance of all
materials to site including cost of cement at site
including cost of form work, soft water, labour
charges for mixing transporting, laying, and
curing concrete, working at depths, tools and
plants and maintaining of protective bunds,
8 48.13cu.m cofferdams, shoring, strutting, etc, complete as 9154.94 / cu.m 440627
per relevent standard specifications for Wings
walls, Toe walls, Curtain walls & parapet wall..

Sub Total Rs. ` 1296186


Name of Work :- Construction of BOX Culvert of 1.5 M X 1.5 M at km 18/6 of NH 219

DETAILED ESTIMATE

Measurements
Sl No Description of Work No Contents
L B D
1 Earthwork excavation in all classes of soil except hard rock requiring
blasting and depositing on bank with all leads and lifts as per SS20B
including cost of all labour equipment and all incidental charges such as
baling out water, providing and maintaining necessary coffer dams,
sheeting, shoring, bracing and their subsequent removal. Removal of all
logs, stumps grubs and other deleterious matter and obstruction, trimming
bottom of excavation, back filling, and clearing the site and disposal of all
surplus material etc., complete as per relevant standard specification for
foundation.
foundation for Base 1 x 1 3.30 15.20 0.53 26.58
Slab
1 x 2 0.30 3.30 0.67 1.33
(0.82/2)
1 x 2 0.41 3.30 0.67 1.81
For Wing Walls 1 2 x 2 5.00 2.30 2.00 92.00
121.72
(or) 121.72 cu.m
2 Vibrated Cement concrete in M-20, using ISS HBG including cost and
conveyance of all materials to site and cost of cement at site including soft
water, labour charges for mixing, transporting, laying and curing concrete,
tools and plants and incidental charges as baling out water, maintaining of
protective bunds, cofferdams, shorting, strutting etc., complete as per
relevant standard specification for foundation.

foundation of Base Slab 1 x 1 3.30 12.96 0.15 6.42

for key slab 1 x 2 0.30 3.30 0.15 0.30


for key slab 1 x 2 0.82 3.30 0.15 0.81
For Wing walls
2 x 2 5.00 2.30 0.15 6.90
14.43
(or) 14.43 cu.m
3 Vibrated Reinforced Cement concrete in M20 using ISS graded HBG metal
including cost and conveyance of all materials to site and cost of cement at
site including soft water, labour charges for form work, centering, mixing,
transporting, laying and curing concrete, tools and plants and incidental
charges excluding cost of steel etc., complete as per relevant standard
specification for CELL BOX

Base slab 1 x 1 3.10 15.00 0.38 17.67

(1.12+0.3)/2
for key slab 1 x 2 3.10 0.710 0.82 3.61
Side walls 1 x 2 0.30 15.00 1.50 13.50

1/2 *.15*.15
haunch 1 x 4 15.00 0.15 0.075 0.68
Deck Slab 1 x 1 2.10 15.00 0.35 11.03
46.49
(or) 46.49 cu.m
4 Providing and applying tack coat with bitumen emulsion using emulsion
pressure distributor at the rate of 0.30 Kg/sqm on the Concrete surface
cleaded with mechanical broom all complete as per Technical
Specification MoRTH503

over the Deck slab 1 x 1 2.10 14.10 - 29.61


(or) 29.61 Sqm

5 Providing and laying Bituminous concrete using CRMB with 100 - 120 THP
hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading premixed with bituminous binder
as specified by Job Mix Formula(JMF) by weight of total mix and filler,
trnsporting the hot mix to site, laid over a previously prepared surface with
a hydrostatic paver finisher with sensor control to the required grade, level
and alignment and rolled with smooth wheeled, vibratory and tandom
rollers to acheieve the desired compaction as per clause 507 of MORT & H
specifications complete in all respects. - Grading II

over the Deck slab 1 x 1 2.10 14.10 0.050 1.48


(or) 1.48 cu.m
6 Supply and fabrication of Fe – 415 steel with high strength corrosion
resistant rebar (TMT Her Grade M) required for all RCC items of works
involved in the schedule cost of steel at site fabrication, labour charges for
cleaning the rods straightening, cutting, bending, tying grills, including
overlapping to the required length whenever necessary and placing the
reinforcement in position as specified in the drawings, including cost of
binding wire, provision of spacer bars, cover blocks and all other incidental
charges etc. complete.
(As per drawing No. SD - 1 x 1 3.693 3.69
108 of MoST and schedule
enclosed)

3.69
(or) 3.69 mt
7 Providing and fixing of G.I. Drainage spouts 100mm dia as per MOST
drawing No.SD/205 with grating arrangements at top as shown in the
drawing including cost and conveyance of GI pipes and flats and fixing
them in position etc., complete

In deck slab (diagonally) 1 x 2 - - - 2 Nos

8 Vibrated cement concrete of grade M20 using ISS HBG metal including
cost and conveyance of all materials to site including cost of cement at site
including cost of form work, soft water, labour charges for mixing
transporting, laying, and curing concrete, working at depths, tools and
plants and maintaining of protective bunds, cofferdams, shoring, strutting,
etc, complete as per relevent standard specifications for Wings walls, Toe
walls, Curtain walls & parapet wall.

Wing walls (2.1+0.45)/2


2 x 2 5.00 1.275 1.85 47.18
Parapet wall over deck 1 x 2 2.10 0.45 0.50 0.95
slab
48.13 cu.m
(or) 48.13 cu.m
1.12 0.30

0.125
Haunch 150 x 150mm
0.50

0.35
L= 15.00
a= 1.50
b= 1.50
1.50 c= 0.50
0.30 1.50 0.30 d= 0.35
e= 0.38
f= 0.30

0.50 0.50

0.10 0.38
0.10
0.15

3.10
Wingwall Length= 5.00
3.30
0.45
15.00 0.50

0.54
0.35

1.50 1.85

0.38
1.20 1.12 12.76 2.10
0.15
0.82 0.82 0.15
0.10 0.30 2.30
0.82 Cross Section of PCC Wing wall
Name of Work :- Construction of BOX Culvert of 1.5 M X 1.5 M at km 18/6 of NH 219
BAR BENDING SCHEDULE - ( as per SD 108)Name of Work :- Construction of BOX Culvert of 1.5 M X 1.5 M at
km 18/6 of NH 219
TOTAL UNIT
Sl No SHAPE OF BARS TYPE OF DIA IN SPACING LENGTH Nos LENGTH (in WEIGHT ( in TOTAL WEIGHT ( in Kg)
BARS ‘mm’ IN ‘mm’ (in ‘m’) ‘m’) Kg/ m)
1 1 10 250 3.500 61 213.50 0.617 131.730
0.78 0.78
2.00
2 0.7 0.7 2 16 250 3.434 122 418.95 1.578 661.103

2.13
3 3 0 200 1.050 76 79.80 0 0.000

1.05
4 3.00 4 16 250 3.464 61 211.30 1.578 333.431
0.28 0.28

5 5 16 250 3.086 122 376.49 1.578 594.101

0.2 2.13

0.70
6 2.00 6 16 250 2.354 61 143.59 1.578 226.585
0.225 0.225

7 7 0 200 1.050 3 3.15 0 0.000

1.05
8 2.00 8 10 250 3.440 61 209.84 0.617 129.471
0.75 0.75

9 0.2 9 10 250 1.558 122 190.08 0.617 117.279


1.158
0.2
10 0.2 10 12 250 1.558 122 190.08 0.888 168.791
1.158
0.2
11 14.90 11 10 250 15.360 12 184.32 0.617 113.725
0.26 0.26
12 14.90 12 10 250 15.260 12 183.12 0.617 112.985
0.21 0.21

13 14.90 13 10 250 15.260 12 183.12 0.617 112.985


0.21 0.21

14 14.90 14 10 - 15.160 12 181.92 0.617 112.245


0.16 0.16

15 14.90 15 10 250 15.260 12 183.12 0.617 112.985


0.21 0.21

16 16 12 - 14.900 10 149.00 0.888 132.312

14.90
17 1.006 17 12 250 2.772 122 338.18 0.888 300.304

1.268

18 0.16 0.16 18 10 - 15.160 4 60.64 0.617 37.415

14.90
19 0.16 0.16 19 10 - 15.160 8 121.28 0.617 74.830

14.90
20 1.30 20 10 150 4.207 26 109.38 0.617 67.487

1.1 1.556

0.20
21 0.16 0.16 21 10 - 3.260 20 65.20 0.617 40.228

3.00
22 0.21 0.21 22 10 250 15.260 12 183.12 0.617 112.985

14.90
3692.977
3692.98 Kg
(or) 3.693 mt
COMMON DATA 2019 - 20 WITH SOR 2019-20
ROAD DATA AS ON 01.07.2019-HILLS-NH-181 EXTN- KM-50/0
- 171/4

GOBICHETTIPALAYAM( NATIONAL HIGHWAYS) DIVISION

S. No. Description of item Rate per

Loading and unloading of stone boulder / Stone


1.1 aggregate / sand / Kankar / Moorum - unloading to 119.79 / Cum
be done by tipping

Loading and unloading of stone boulders by Manual


1.2 175.49 /Cum
means

Loading and unloading of cement or steel by Manual


1.3 241.48 / Cum
means and stacking

Cutting trees, including cutting of trunks, branches


2.1. 453.79 /tree
and removal

(ii) GIRTH FROM 600 mm TO 900 mm 785.43 /tree

(iii) GIRTH FROM 900 mm TO 1800 mm 1565.84 /tree

(iii) GIRTH ABOVE TO 1800 mm: 3001.97 /tree

2.2 Clearing Grass and removal of rubbish: 37572.92 /hectare

2.3. Clearing and grubbing road land: 113367.32 /hectare

B) In area of throny jungle 151588.80 /hectare

II By Mechanical means

A) In area of light jungle 49803.80 /hectare

B) In area of throny jungle 60860.87 /hectare

2.4. Dismantling Structures:

2.4 (i) Dismantling Lime / Cement Concrete


Dismantling Lime concrete, cement concrete grade M
A.
10 and below:
1 By Manual Means: 662.66 / Cum

B) Dismantling Cement concrete grade M 15 & M20: 793.30 / Cum

Dismantling Prestressed / rerinforced Cement


C) 2138.67 / Cum
concrete grade M 20 & above:

II. BY MECHANICAL MEANS:

A) Dismantling Cement concrete grade M 15 & M20: 727.14 / Cum

Dismantling Prestressed / rerinforced Cement


B) 1296.14 / Cum
concrete grade M 20 & above:

2.4 (ii). A. Dismantling Brick / Tile work in lime mortar: 401.37 / Cum

2.4 (ii). B. Dismantling Brick / Tile work in cement mortar: 532.02 / Cum

2.4 (ii). C. Dismantling Brick / Tile work in mud mortar: 349.12 / Cum

C. Dismantling Dry brick pitching or brick soling: 322.98 / Cum

2.4. (iii) Dismantling Stone masonry:

A. Dismatling Rubble stone masonry in lime mortar: 453.62 / Cum

B. Dismantling Rubble stone masonry in cement mortar: 532.02 / Cum

C. Dismantling Rubble stone masonry in mud mortar: 401.37 / Cum

D. Dry Rubble masonry: 375.25 / Cum

E. Dismantling stone pitching / dry stone spalls: 349.12 / Cum

Dismantling boulders laid in wire crates including


F. 401.37 / Cum
opening of crates and stacking dismantled materials:

Dismantling wood work wrought framed and fixed in


2.4. (iv) frames of trusses upto a height of 5 m above plinth 1087.24 / Cum
level:

Dismantling Steel work in all types of sections upto


2.4. (v) height of 5 m above plinth level excluding cutting of
rivet:
A. Including dismembering: 2653.31 /tonne

B. Excluding dismembering: 1975.61 /tonne

C. Extra over 2.4 (V) A and B for cutting rtivets: 19.49 /rivet

Scraping of bricks dismantled from brick work in lime /


2.4. (vi). A. 2.29 number
cement mortar including stacking:

Scraping of bricks dismantled from brick work in mud


2.4. (vi). B. 0.82 number
mortar including stacking:

Scraping of stone from dismantled stone masonry in


2.4. (vii). A. 917.47 / Cum
lime / cement mortar including stacking:

Scraping of stone from dismantled stone masonry in


2.4. (vii). B. 194.47 / Cum
mud mortar including stacking:

Scraping plaster in lime or cement mortar from brick /


2.4. (viii). 28.20 / Sqm
stone masonry:

Removing all types of Hume pipes and stacking


2.4. (ix). within a lead of 1000 metres including earthwork and 339.06 / Rm
dismantling of masonry works:

B. Dismantling 600 mm to 900 mm dia pipes: 458.73 / Rm

C. Dismantling above 900 mm dia: 785.33 / Rm

Dismantling of flexible pavements and disposal of


dismantled materials upto ma lead of 1000 m,
2.5.
stacking serviceable and unserviceable materials
separately:

I. By Manual means:

A. Dismantling Bituminous courses: 1226.26 / Cum

B. Dismantling Granular courses: 867.23 / Cum

II. By Mechanical means:

A. Dismantling Bituminous courses: 451.95 / Cum

2.6. Dismantling CC pavements 2124.86 / Cum


2.7. Dismantling guard rails 130.42 / Rm

2.8. Dismantling kerb stones 23.07 / Rm

3.1. Excavation in soil by manual means:

in Ordinary soil 291.13 /cum

3.2. Excavation in ordinary rock by manual means: 427.22 /cum


Excavation in soil with Dozer with lead upto 100
3.3. 161.09 /cum
metres:
Excavation in ordinary rock with Dozer with lead upto
3.4. 274.53 /cum
100 metres:

Excavation in hard rock [requiring blasting] with


3.5. 318.68 /cum
disposal upto 1000 metres:

3.13. Excavation for structures:

A. By manual means excluding dewatering 522.57 /cum

Add extra 10 % for dewatering

B. By mechanical means 63.04 /cum

Add extra 5 % of (a+b) for dewatering

(ii) Earth work in ordinary rock not requiring blasting:

A. By manual means 653.21 /cum

Add extra 10 % for dewatering

B. By mechanical means 81.50 /cum

(iii) Earth work in hard rock requiring blasting:

A. Manual means: 958.10 /cum

Cost for Scarifying existing granular surface to a


3.14. 43.49 /cum
depth of 50 mm by manual means
Scarifying existing bituminous road surface to 50 mm
3.15. 6.35 /cum
depth

Construction of embankment with material from


3.16. 279.70 /cum
borrowpits

Construction of embankment with material deposited


3.17. 157.25 /cum
from roadway cutting:

3.18. Construction of subgrade and earthern shoulders: 588.81 /cum(grave

3.19. Compacting original ground supporting subgrade: 95.83 /cum

3.19. Compacting original ground supporting embankment: 49.87 /cum

3.22. Turfing with sods: 59.32 /Sqm

3.24. Surface drains in soil: 91.60 /Rm

Construction of embankment with flyash / Pond ash


3.36. available from cost or lignite burning Thermal plnts as 296.31 /Cum
waste material:

Granular sub - base with close graded material [Table


4.1
- 400-1]

A. Mixing by wet mix plant

For material grading - I 3218.47 /Cum

For material grading - II 3160.74 /Cum

For material grading - III 2890.40 /Cum

B. Mixing in place method

For material grading - I 3046.55 /Cum

For material grading - II 2988.82 /Cum

For material grading - III 2718.48 /Cum

4.3. Lime stabilisation for improving sub grade: 280.90 /Cum

4.7 Making 50 mm X 50 mm furrows cutting: 6.84 /Sqm


4.9. WATER BOUND MACADAM - [gravel as binder]

A. By Manual means

For material grading - I 3293.42 /Cum

For material grading - II 3482.57 /Cum

For material grading - III 3737.33 /Cum

WATER BOUND MACADAM - [Sand gravel as


4.9.
binder]

For materials Grade -I 3401.37

For material grading - II 3590.52 /Cum

For material grading - III 3845.28 /Cum

5.1 PRIME COAT: 35.77 /Sqm

5.2 TACK COAT (over BM) : 9.39 /Sqm

BITUMINOUS MACADAM:GradingII Layer thickness


5.3 7995.91 /Cum
50-75mm

5.5. BUILT UP SPRAY GROUT: 402.31 /Sqm

DENSE GRADED BITUMINOUS MACADAM Grading


5.6. 9258.97 /Cum
II 50-75mm
SEMI DENSE BITUMINOUS CONCRETE:Grading II
5.7. 9543.84 /Cum
25-30mm
5.8 BITUMINOUS CONCRETE:Grading II 30 - 45 mm 10391.26 /Cum

5.10. OPEN GRADED PREMIX SURFACING: 154.68 /Sqm

5.13 SEAL COAT TYPE - A: 63.01 /Sqm

GRANITE ROUGH STONE DRY PACKING 3321.08 /Cum

GRAVEL PACKING TO GRANITE ROUGH STONE


1172.46 /Cum
DRY PAKCING

Dismantling Brick sone masonry in lime mortar


191.80 /Cum
[SI No: 12]
Dismantling Brick sone masonry in cement mortar
235.20 /Cum
[SI No: 14]

Dismantling cut stone slab [SI No: 18] 980.00 /Cum

Dismantling lime concrete [SI No: 36] 295.40 /Cum

Dismantling cement concrete [SI No: 37] 404.60 /Cum

Dismantling RCC [SI No: 38] 6146.00 /Cum

5.16 TACK COAT (existing BT) : 11.18 /Sqm

TACK COAT (existing concrete surface) : 12.98 /Sqm


BITUMINOUS MACADAM:Grading I Layer thickness
/Cum
80-100mm 8134.58
WET MIX MACADAM /Cum
3251.90
DENSE GRADED BITUMINOUS MACADAM Grading
I 75-100mm
8438.65 /Cum
TACK COAT ( Existing BT with VG 10( 80/100)
12.04 /Sqm
Bitumen
Stone Matrix Asphalt /Cum
15795.45
174

Common data for 2019-2020 for bridge and culvert works


2019-2020 SOR and 01.07.2019 Bitumen

Circle: SALEM
NH - 181 - Hills Km 50/0 - 171/4

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts

1 Earthwork for foundation in ordinary soil:


A. By manual means

i) Depth up to 3 m excluding 298.88 / Cum 286.92 / Cum


dewatering
ii) Depth up to 3 m including 328.76 / Cum 315.61 / Cum
dewatering
iii) Depth 3 m to 6 m including 441.91 / Cum 424.23 / Cum
dewatering
iv) Depth 3 m to 6 m including 441.91 / Cum 424.23 / Cum
dewatering
iv) Depth above 6 m including 614.83 / Cum 590.24 / Cum
dewatering
B. By Mechanical means
i) Depth upto 3 m including 97.92 / Cum 94.01 / Cum
dewatering
ii) Depth 3 to 6 m including 114.58 / Cum 109.99 / Cum
dewatering
iii) Depth above 6 m including 147.22 / Cum 141.33 / Cum
dewatering
2 Earthwork for foundation in ordinary rock
not requiring blasting
A. Manual means

i) Depth upto 3 m excluding 426.97 / Cum 409.89 / Cum


dewatering

B. Mechanical means:

i) Depth upto 3 m excluding 114.86 / Cum 110.27 / Cum


dewatering and not requiring
blasting

497234822.xlsxabstract (2)
175

ii) Depth upto 3 m excluding 941.90 / Cum 904.23 / Cum


dewatering and requiring
blasting
3 Sand filling 3988.52 / Cum 3828.98 / Cum

4 PCC 1:3:6 for foundation 7359.95 / Cum 7065.55 / Cum

5 Cement mortar 1:3 without 6011.56 / Cum


contractor profit and overheads
6 Brickwork in CM 1:3 for 8657.54 / Cum 8311.23 / Cum
foundation
7 Stone masonry in CM 1:3 for 8382.09 / Cum 8046.81 / Cum
foundation
8 Random rubble masonry in 8213.03 / Cum 7884.51 / Cum
CM 1:3
9 PCC M 15 for foundation 8381.27 / Cum 8046.01 / Cum

10 PCC M 20 for foundation using 9016.23 / Cum 8655.58 / Cum


concrete mixer
11 PCC M 25 for foundation

a. Using concrete mixer 9470.34 / Cum 9091.52 / Cum

b. Using batching plant 8437.47 / Cum 8099.97 / Cum

12 PCC M 30 for foundation

a. Using concrete mixer 9498.98 / Cum 9119.02 / Cum

b. Using batching plant 8463.60 / Cum 8125.06 / Cum

13 RCC M 20 for foundation

a. Using concrete mixer 9131.19 / Cum 8765.94 / Cum

b. Using batching plant 8092.24 / Cum 7768.55 / Cum

14 RCC M 25 for foundation

a. Using concrete mixer 9590.75 / Cum 9207.12 / Cum

b. Using batching plant 8554.30 / Cum 8212.13 / Cum

15 RCC M 30 for foundation

497234822.xlsxabstract (2)
176

a. Using concrete mixer 9596.23 / Cum 9212.38 / Cum

b. Using batching plant 8563.71 / Cum 8221.16 / Cum

16 RCC M 35 for foundation

a. Using concrete mixer 9680.76 / Cum 9293.53 / Cum

b. Using batching plant 8653.23 / Cum 8307.10 / Cum

17 Cast in situ 750 mm dia pipein RCC M 35 grade

a. Using concrete mixer 9502.60 / Cum 9122.50 / Cum

Using batching plant 9291.12 / Cum 8919.48 / Cum

18 Cast in situ 1000 mm dia pipein RCC M 35 grade

a. Using concrete mixer 15634.64 / Cum 15009.25 / Cum

Using batching plant 15282.08 / Cum 14670.80 / Cum

19 Cast in situ 1200 mm dia pipein RCC M 35 grade

a. Using concrete mixer 19974.59 / Cum 19175.61 / Cum

b. Using batching plant 19467.09 / Cum 18688.40 / Cum

20 Pile load test

21 Initial load test 300.00 / MT

22 Latreral load test 5000.00 / MT

23 Pile cap in RCC M 20

a. Using concrete mixer 9138.68 / Cum 8773.13 / Cum

b. Using batching plant 8133.09 / Cum 7807.76 / Cum

24 Pile cap in RCC M 25

a. Using concrete mixer 9638.59 / Cum 9253.05 / Cum

b. Using batching plant 8633.00 / Cum 8287.68 / Cum

497234822.xlsxabstract (2)
177

25 Pile cap in RCC M 30

a. Using concrete mixer 9701.80 / Cum 9313.72 / Cum

b. Using batching plant 8696.20 / Cum 8348.36 / Cum

26 Pile cap in RCC M 35

a. Using concrete mixer 9833.96 / Cum 9440.60 / Cum

b. Using batching plant 8828.36 / Cum 8475.23 / Cum

27 Levelling course below pile cap 8058.91 / Cum 7736.55 / Cum


using concrete mixer
28 HYSD reinforcement for piles 75755.31 / MT 72725.09 / MT

29 MS reinforcement for piles 76432.33 / MT 73375.04 / MT

30 Brickwork in CM 1:3 8369.55 / Cum 8034.76 / Cum

31 Poinmting Brickwork in CM 1:3 131.94 / Sqm 126.67 / Sqm

32 Plastering in CM 1:3 226.17 / Sqm 217.13 / Sqm

33 RR masonry in CM 1:3 8053.55 / Sqm 7731.42 / Sqm

34 CR masonry in CM 1:3 8536.97 / Sqm 8195.48 / Sqm

35 PCC M 15 for substructure

a. Height upto 5m 8864.80 / Cum 8510.21 / Cum

b. Height 5m to 10 m 9025.98 / Cum 8664.94 / Cum

36 PCC M 20 for substructure using concrete mixer

a. Height upto 5m 9536.40 / Cum 9154.94 / Cum

b. Height 5m to 10 m 9883.17 / Cum 9487.85 / Cum

37 PCC M 25 for substructure using concrete mixer

a. Height upto 5m 10040.84 / Cum 9639.20 / Cum

497234822.xlsxabstract (2)
178

b. Height 5m to 10 m 10405.96 / Cum 9989.72 / Cum

38 PCC M 25 for substructure using batching plant

a. Height upto 5m 8945.75 / Cum 8587.92 / Cum

b. Height 5m to 10 m 9271.05 / Cum 8900.21 / Cum

39 PCC M 30 for substructure using concrete mixer

a. Height upto 5m 10095.54 / Cum 9691.71 / Cum

b. Height 5m to 10 m 10462.65 / Cum 10044.14 / Cum

40 PCC M 30 for substructure using batching plant

a. Height upto 5m 8995.13 / Cum 8635.33 / Cum

b. Height 5m to 10 m 9322.23 / Cum 8949.34 / Cum

41 RCC M 20 for substructure using concrete mixer

a. Height upto 5m 9657.99 / Cum 9271.67 / Cum

b. Height 5m to 10 m 10009.19 / Cum 9608.82 / Cum

42 RCC M 20 for substructure using batching plant

a. Height upto 5m 8559.10 / Cum 8216.74 / Cum

b. Height 5m to 10 m 8870.34 / Cum 8515.53 / Cum

43 RCC M 25 for substructure using concrete mixer

a. Height upto 5m 10168.51 / Cum 9761.77 / Cum

b. Height 5m to 10 m 10501.29 / Cum 10081.24 / Cum

44 RCC M 25 for substructure using batching plant

a. Height upto 5m 9069.62 / Cum 8706.84 / Cum

b. Height 5m to 10 m 9366.45 / Cum 8991.79 / Cum

45 RCC M 30 for substructure using concrete mixer

497234822.xlsxabstract (2)
179

a. Height upto 5m 10198.89 / Cum 9790.94 / Cum

b. Height 5m to 10 m 10486.32 / Cum 10066.87 / Cum

46 RCC M 30 for substructure using batching plant

a. Height upto 5m 9101.53 / Cum 8737.47 / Cum

b. Height 5m to 10 m 9358.03 / Cum 8983.71 / Cum

47 RCC M 35 for substructure using concrete mixer

a. Height upto 5m 10338.68 / Cum 9925.13 / Cum

b. Height 5m to 10 m 10564.25 / Cum 10141.68 / Cum

48 RCC M 35 for substructure using batching plant

a. Height upto 5m 9241.31 / Cum 8871.66 / Cum

b. Height 5m to 10 m 9442.94 / Cum 9065.23 / Cum

49 HYSD bar reinforcement for sub 76114.51 / MT 73069.93 / MT


structure
50 MS bar reinforcement for sub 74760.47 / MT 71770.05 / MT
structure
51 Weep holes 230.41 / Nos. 221.19 / Nos.

52 Back filling behind abutment, 1166.36 / Cum 1119.71 / Cum


wing and return walls
53 Filter media behind abutment, 3843.77 / Cum 3690.02 / Cum
wing and return walls
54 RC C M 20 Solid Slab Superstructure using concrete
mixer
a. For height upto 5 m 10476.32 / Cum 10057.26 / Cum

b. For height 5 - 10 m 10912.83 / Cum 10476.32 / Cum

55 RC C M 25 T beam & slab Superstructure using


concrete mixer
a. For height upto 5 m 10912.83 / Cum 10476.32 / Cum

b. For height 5 - 10 m 11349.34 / Cum 10895.37 / Cum

497234822.xlsxabstract (2)
180

56 RC C M 20 Solid Slab Superstructure using batching


plant
a. For height upto 5 m 9275.87 / Cum 8904.84 / Cum

b. For height 5 - 10 m 9662.37 / Cum 9275.87 / Cum

57 RC C M 20 T beam & slab Superstructure using


batching plant
a. For height upto 5 m 9662.37 / Cum 9275.87 / Cum

b. For height 5 - 10 m 10048.86 / Cum 9646.91 / Cum

58 RC C M 25 solid slab Superstructure using concrete


mixer
a. For height upto 5 m 11053.14 / Cum 10611.01 / Cum

b. For height 5 - 10 m 11513.68 / Cum 11053.14 / Cum

59 RCC M 25 T-Beam and slab Superstructure using


concrete mixer
a. For height upto 5 m 11513.68 / Cum 11053.14 / Cum

b. For height 5 - 10 m 11974.23 / Cum 11495.26 / Cum

60 RC C M 25 solid slab Superstructure using batching


plant
a. For height upto 5 m 9864.72 / Cum 9470.13 / Cum

b. For height 5 - 10 m 10275.75 / Cum 9864.72 / Cum

61 RCC M 25 T-Beam and slab Superstructure using


batching plant
a. For height upto 5 m 10275.75 / Cum 9864.72 / Cum

b. For height 5 - 10 m 10686.78 / Cum 10259.31 / Cum

62 RC C M 30 solid slab Superstructure using concrete


mixer
a. For height upto 5 m 11194.38 / Cum 10746.61 / Cum

b. For height 5 - 10 m 11660.81 / Cum 11194.38 / Cum

63 RCC M 30 T-Beam and slab Superstructure using


concrete mixer

497234822.xlsxabstract (2)
181

a. For height upto 5 m 11660.81 / Cum 11194.38 / Cum

b. For height 5 - 10 m 12127.25 / Cum 11642.16 / Cum

64 RC C M 30 solid slab Superstructure using


batchingplant
a. For height upto 5 m 9955.32 / Cum 9557.11 / Cum

b. For height 5 - 10 m 10370.13 / Cum 9955.32 / Cum

65 RCC M 30 T-Beam and slab Superstructure using


batching plant
a. For height upto 5 m 10370.13 / Cum 9955.32 / Cum

b. For height 5 - 10 m 10784.93 / Cum 10353.53 / Cum

66 RC C M 35 solid slab Superstructure using concrete


mixer
a. For height upto 5 m 11157.76 / Cum 10711.45 / Cum

b. For height 5 - 10 m 11630.55 / Cum 11165.32 / Cum

67 RCC M 35 T-Beam and slab Superstructure using


concrete mixer
a. For height upto 5 m 11630.55 / Cum 11165.32 / Cum

b. For height 5 - 10 m 12103.33 / Cum 11619.20 / Cum

68 RC C M 35 solid slab Superstructure using


batchingplant
a. For height upto 5 m 9921.81 / Cum 9524.93 / Cum

b. For height 5 - 10 m 10342.22 / Cum 9928.53 / Cum

69 RCC M 35 T-Beam and slab Superstructure using


batching plant
a. For height upto 5 m 10342.22 / Cum 9928.53 / Cum

b. For height 5 - 10 m 10762.64 / Cum 10332.13 / Cum

70 HYSD bar reinforcement for 78515.95 / MT 75375.31 / MT


superstructure
71 MS bar reinforcement for 74760.47 / MT 71770.05 / MT
superstructure

497234822.xlsxabstract (2)
182

72 CC Wearing coat in M 30 9451.65 / Sqm 9073.59 / Sqm


Concrete using concrete mixer
73 Wearing coat in Mastic Asphalt 319.69 / Sqm 306.91 / Sqm

74 RCC M 30 Railing cast in casting 1695.20 / Rm


yard
75 RCC M 30 Railing cast in situ 2233.51 / Rm 2144.17 / Rm

76 Drainage spout 419.57 / Each 402.79 / Each

77 PCC M 15 levelling course below 8058.91 / Cum 7736.55 / Cum


approach slab

78 RCC M 30 approach slab using 13438.73 / Cum 12901.17 / Cum


concreete mixer including
reinforcement

79 Copper plate expansion joint 1200.88 / Rm 1152.85 / Rm

80 20 mm thick fibre board 263.01 / Rm 252.49 / Rm


expansion joint
81 20 mm thick premoulded joint 318.82 / Rm 306.07 / Rm
filler
82 Joint sealing compound 1 cm 43.78 / Rm 42.03 / Rm
depth
83 Boulder without wire crates 3327.71 / cum 3194.60 / cum

84 PCC M 15 for CC blocks for 8220.09 / cum 7891.28 / cum


apron
85 Pitching side slopes with 3327.71 / cum 3194.60 / cum
boulders
86 Pitching side slopes with CC 8220.09 / cum 7891.28 / cum
blocks
87 Filter materials below side slope 4190.77 / cum 4023.14 / cum
pitching
88 Rubble stone laid in CM 1:3 10989.65 / cum 10550.06 / cum

89 Flooring with CC blocks M 15 14384.71 / cum 14046.10 / cum

90 Dry rubble stone Flooring 4201.26 / cum 4033.21 / cum

91 Flexible apron 1 m thick Dry 3449.83 / cum 3311.84 / cum


rubble stone Flooring
92 Dismantling CC wearing course 188.84 / cum 181.28 / cum

93 Dismantling AC wearing course 142.20 / cum 136.51 / cum

497234822.xlsxabstract (2)
183

94 Gravel packing to rough stone 1327.74 / cum 1274.63 / cum


dry packing
95 Rough stone dry packing for 3773.95 / cum 3622.99 / cum
revetment
96 Slurry seal for 5 mm thickness 63.03 / Sqm

97 Slurry seal for 3 mm thickness 42.69 / Sqm

98 Slurry seal for 1.5 mm thickness 25.60 / Sqm

99 Fog spray 30.22 / Sqm

100 Crack prevention course SAM 57.13 / Sqm


for less than 6 mm crack
101 Crack prevention course SAM 67.02 / Sqm
for 6 mm to 9 mmcrack
102 Crack prevention course SAM 86.06 / Sqm
for more than 9 mm crack
103 Cement Kerb M 20 458.98 / Rm

104 20 mm thick PC 193.64 / Sqm

105 5th KM stone including painting, 5189.77 / each


lettering and fixing
106 KM stone including painting, 3100.12 / each
lettering and fixing
107 HM stone including painting, 839.73 / each
lettering and fixing
108 Boundary pillar including 880.15 / each
painting, lettering and fixing
109 Pipe culverts:
a. Foundation in CC 1:3:6 6523.96 / cum

b. Supply of NP4 1000 mm RCC 2750.00 / Rm


pipes
c. Fixing of NP4 1000 mm single 330.35 / Rm
row RCC pipes
d. Fixing of NP4 1000 mm two row 660.69 / Rm
RCC pipes