Professional Documents
Culture Documents
Name of work: Road branching at Km 30/8 of VKT Road to Pannikkankuppam Road Km 0/000 - 7/800
Sl.No Description Nos Length Breadth Depth Quantity Unit Rate Amount
1 Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings
and trees of girth up to 300mm, removal of stumps of such trees cut earlier and disposal of
unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of
1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per
Technical Specification Clause201.
2 Earthwork excavation for box cutting in all classes of soils except hard rock requiring blasting and
depositing on bank with all leads and lifts as per SS20A, including cost of all labour, equipments and
all incidental charges including clearing the site and disposal of all surplus materials etc, complete as
per relevant standard specification for widening portion
2.4/2
Bell Mouth 4 20.00 1.200 0.450 43.20
0.6/2
Extra widening in Curve Km 1/430 , 2/600 , 6 30.00 0.300 0.450 24.30
3/225 , 4/600 , 4/860 , & 7/560
0.9/2
Extra widening in Curve Km 0/620 , 2/600 , 10 30.00 0.450 0.450 60.75
3/300 , 4/860 , 6/060 , 6/140 , 6/730 , 6/780 ,
7/450 & 7/510
3 Construction of Sub grade and Earthen shoulders with approved materials obtained from borrow pits
with all lifts and leads, transporting to site, spreading grading to required slope and compacted to
meet requirement of Table 300.2 with lead upto 1000m as per Technical specification Clause 303.1
4 Construction of Gravel shoulders by providing well graded material, spreading in uniform layers with
motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and
compacting with three wheel 80 – 100 KN static roller capacity to achieve the desired density,
complete as per Technical Specification and as directed by the Engineer – in –
charge.
6 Providing, laying, spreading and compacting stone aggregates to Wet Mix Macadam specification
including premixng the material with water at OMC in mechanical mixer (Pug Mill), carriage of
mixed material by tipper to site, laying in uniform layers in sub-base / base course on a well prepared
sub-base and compacting with smooth wheel roller of 80 to 100 KN weight to achieve the desired
density including lighting, barricading and maintenance of diversion, etc. as per Tables 400.11 &
400.12 and Technical specification clause 406.
0.9/2
Extra widening in Curve Km 0/620 , 2/600 , 10 30.00 0.450 135.00
3/300 , 4/860 , 6/060 , 6/140 , 6/730 , 6/780 ,
7/450 & 7/510
8 Providing and applying tack coat with Bitumen emulsion (RS – 1) using emulsion distributor at the
rate of 0.275 kg / sqm on the prepared granular surface treated with primer & cleaned With Hydraulic
broom as per Technical Specification clause 503 and as directed by the Engineer – in – charge.
11 Providing and laying bituminous macadam with 40-60 THP hot mix plant using crushed aggregates
of grading as per table 500.4 premixed with bituminous binder, transported to site up to lead of
1000m, laid over a previously prepared surface with paver finisher to the required grade, level and
alignment and rolled achieve the desired compaction clause 504..
12 Providing laying and rolling of open – grade premix carpet of 20 mm thickness composed of 13.2 mm
to 5.6 mm aggregates either using penetration grade bitumen or emulsion to required line, grade and
level to serve as wearing course on a previously prepared base with paver finisher, including mixing
in a suitable plant, laying and rolling with a three wheel 80 – 100 kN static roller capacity,
finished to required level and grades to be followed by seal coat of Type A as per Technical
Specification clause 508 and as directed by the Engineer – in – charge.
14 Providing and fixing of retro – reflectorised cautionary, mandatory and informatory sign as per
IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3 fixed over aluminum
sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed
to the ground by means of properly designed foundation with means of M15 grade cement concrete
450 mm X 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical
Specification Clause 801.
15 Providing and erecting direction and place identfication retro – reflectorised sign as per IRC:67 made
of high intensity grade sheet vide clause 801.3 fixed over aluminum sheeting, 200 mm thick with area
not exceeding 0.90 sqm supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly designed foundation with means of M15 grade cement
concrete 450 mm X 450 mm x 600 mm, 600 mm below ground level as per drawings and Technical
Specification Clause 801.
16 Reinforced cement concrete M15 grade Kilometer stone of standard design as per IRC: 8 fixing in
position including painting and printing, etc as per drawing and Technical Specification Clause1703.
17 Reinforced cement concrete M15 grade Hecta meter stone of standard design as per IRC: 8 fixing in
position including painting and printing, etc as per drawing and Technical Specification Clause1703.
18 Providing and fixing of typical BHARAT NIRMAN informatory sign board with logo as per MORD
specifications and drawing. Three MS plates of 1.6 mm thick, top and middle plate duly welded with
MS flat iron 25mm x 5m size on back on edges. The lower plate will be welded with MS angle iron
frame of 25mm x 25mm x 5mm. the angle iron frame of middle plate will be welded to 2 nos. 75mm
x 75mm of 12 SWG sheet tubes posts duly embedded in cement concrete M -15 grade blocks of
450mm x 450mm x 600mm, 600mm below ground level. The top most diamond plate will be welded
to middle plate by 47mm x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on
both sides Lettering and printing arrows, border etc. will be painted with ready mixed synthetic
enamel paint of superior quality in required shade and colour. All sections of framed posts and steel
tube
Logo will
Boardbe painted with primer and two coats 2of epoxy paint as per drawing Clause 1701 and2 Nos. 5000.00 10000
Annexure 1700.1
Citizen board 2 2 No. 15000.00 30000
19 Provision of rumble strips covered with premix bituminous carpet in approved locations to control
speed marked with white strip of road making paint as per IRC 67 – 2001 as per drawing and
technical specifications of 1703 – 1 No.
20 Provision for Three row pipe culvert and hard bed 637109
17413856
21 Provision for labour welfare fund at 0.3% 52242
Name of work: Road branching at Km 30/8 of VKT Road to Pannikkankuppam Road Km 0/000
- 7/800
2 Earthwork excavation for box cutting in all classes of soils except hard rock requiring
blasting and depositing on bank with all leads and lifts as per SS20A, including cost of
all labour, equipments and all incidental charges including clearing the site and disposal
of all surplus materials etc, complete as per relevant standard specification for widening
portion
3 Construction of Sub grade and Earthen shoulders with approved materials obtained from
borrow pits with all lifts and leads, transporting to site, spreading grading to required
slope and compacted to meet requirement of Table 300.2 with lead upto 1000m as per
Technical specification Clause 303.1
5 Picking the existing BT Surface / WBM up to 50mm deep including all labour charges
for levelling and sectioning all other incidental charges etc. complete
8 Providing and applying primer coat with bitumen emulsion (SS – 1) on prepared surface
of granular base including clearing of road surface and spraying primer at the rate of
0.70 – 1.0 kg / sqm using mechanical means as per Technical Specification clause 502
and as directed by the Engineer – in – charge.
9 Providing and applying tack coat with Bitumen emulsion (RS – 1) using emulsion
distributor at the rate of 0.275 kg / sqm on the prepared granular surface treated with
primer & cleaned With Hydraulic broom as per Technical Specification clause 503 and
as directed by the Engineer – in – charge.
10 Providing and applying tack coat with Bitumen emulsion (RS – 1) using emulsion
distributor at the rate of 0.275 kg / sqm on the prepared granular surface treated with
primer & cleaned With Hydraulic broom as per Technical Specification clause 503 and
as directed by the Engineer – in – charge.
11 Providing and laying bituminous macadam with 40-60 THP hot mix plant using crushed
aggregates of grading as per table 500.4 premixed with bituminous binder, transported
to site up to lead of 1000m, laid over a previously prepared surface with paver finisher
to the required grade, level and alignment and rolled achieve the desired compaction
clause 504.
14 Providing and fixing of retro – reflectorised cautionary, mandatory and informatory sign
as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3
fixed over aluminum sheeting, 1.5 mm thick supported on a mild steel angle iron post 75
mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed
foundation with means of M15 grade cement concrete 450 mm X 450 mm x 600 mm,
600 mm below ground level as per drawings and Technical Specification Clause 801.
15 Providing and erecting direction and place identfication retro – reflectorised sign as per
IRC:67 made of high intensity grade sheet vide clause 801.3 fixed over aluminum
sheeting, 200 mm thick with area not exceeding 0.90 sqm supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly
designed foundation with means of M15 grade cement concrete 450 mm X 450 mm x
600 mm, 600 mm below ground level as per drawings and Technical Specification
Clause 801.
No 4 10000.00 40000
16 Reinforced cement concrete M15 grade Kilometer stone of standard design as per IRC:
8 fixing in position including painting and printing, etc as per drawing and Technical
Specification Clause1703.
No 7 1200.00 8400
17 Reinforced cement concrete M15 grad Hectameter stone of standard design as per IRC:
8 fixing in position including painting and printing, etc as per drawing and Technical
Specification Clause1703.
No 39 350.00 13650
F-6
Sl.No Reach Unit Quantity Rate Amount
18 Providing and fixing of typical BHARAT NIRMAN informatory sign board with logo as
per MORD specifications and drawing. Three MS plates of 1.6 mm thick, top and
middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. the
angle iron frame of middle plate will be welded to 2 nos. 75mm x 75mm of 12 SWG
sheet tubes posts duly embedded in cement concrete M -15 grade blocks of 450mm x
450mm x 600mm, 600mm below ground level. The top most diamond plate will be
welded to middle plate by 47mm x 47mm of 12 SWG steel plate tube. All M.S. will be
stove enameled on both sides Lettering and printing arrows, border etc. will be painted
with ready mixed synthetic enamel paint of superior quality in required shade and
colour. All sections of framed posts and steel tube will be painted with primer and two
coats of epoxy paint as per drawing Clause 1701 and Annexure 1700.1
19 Provision of rumble strips covered with premix bituminous carpet in approved locations
to control speed marked with white strip of road making paint as per IRC 67 – 2001 as
per drawing and technical specifications of 1703 – 1 No.
19 Provision for Three row pipe culvert and hard bed 630827
22 Contigencies 14
DISTRICT : CUDDALORE
BLOCK : PANRUTI
Format - F1
Unconnected habitations
Total
Name of the Block Code No. of 250 - 499
habitations Total Eligible
>1000 500-999 <250 Habitations
Total Eligible
PANRUTI L 051 2 0 0 0 0 0 2
TOTAL 2 0 0 0 0 0 2
1 2 3 4 5 6 7 8
New Connectivity - - - - - - -
Associated Through
- - - - - - -
Route
Upgradation
Other Upgradation - - - - - - -
Total 1 1.000 0 #REF! 6.308 #REF! 2
SUMMARY SHEET
Format - F1
Unconnected habitations
Total
Name of the Block Code No. of 250 - 499
habitations >1000 500-999 <250 Total Eligible
Total Eligible Habitations
1 2 3 4 5 6 7 8
New Connectivity - - - - - - -
Associated Through
- - - - - - -
Route
Upgradation 1 1.000 - #REF! 6.308 #REF! 2
Other Upgradation - - - - - - -
Upgradation
Benifited
Name of the Block
Facility accessed
(A)/
Surface Type *
(U)
Road Length
Picking of existing BT
(Km)
Gravel Shoulder
Road Furniture
Rs.Lakhs
ClearIng &
Grubbing
cut earth
surface
BM
From To Details
N A U SDBC
1 2 3 4 5 5A 5B 6 7 8
Thick
Siruvalayam-Ulianallur
ness 100 50 25
Kodampakkam
(mm)
PANRUTI
1 - - U D 1.000 BT
Cost Rs
in Lakhs 0.532 20.766 5.542 #REF! 3.469 93.868 52.109 16.692 #REF! 1.560 4.727 #REF!
TOTAL 1.000 0.532 20.766 5.542 #REF! 3.469 93.868 52.109 16.692 #REF! 1.560 4.727 #REF!
Bharat Nirman 2012- 2013
ROADS PROPOSED IN BHARAT NIRMAN FOR RURAL CONNECTIVITY (CD STRUCTURES) Format - 2B
Habitations Connected /
Name of the Road
Name of Block
Box/Arch/Sl
Road Length
Box/Arch/Sl Total cost
Block Code
Population
Benifited Hume Pipe ab/Cut Hume Pipe Minor Total
Minor Bridge ab Total Cost of
(Km)
Sl.N Culvert Stone Culvert Bridge Cost of
Culvert of Pavement
o Culvert from theRoad
Details Proposed [18+19)]
CD Format F6
Structures
Lengt Lengt Lengt Lengt
No. Dia No h No h No Dia No h No h
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Pakkiri
1 320
palayam
Pakkiripalayam Road
PANRUTI
L 051
Pakkiri
229
palayam H/C
3.75 m
7.50 m
EARTHEN SHOULDERS
(use A/B/C/D)*
Connecting to
accessed
Total
Facilities
Road Embankment WBM Layer Bituminous Layer
Sl.No
Name of the
Road
Length LCV/Truck/
Road Total Bus Land Road
(in Km)
Motorise Agricultural Width Width
d (m) (m) Thicknes
Tractor/Tra Height Width Width Width Thicknes
s Type **
iler (m) (m) (m) (mm) (m) s (mm)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Pakkiripalayam Worn
1 1.000 ODR D 918 113 10.00 7.50 0.30 7.50 3.75 125 BT 3.75
Road out
Road Connecting to
** Use A = Market B = Educational facilities C = Health centre D = Combination of previous
*** Where actual figure is not available,Estimated may be included
**** type BM/MSS/DMC
Format - F4A
Association of Routes
NIL
TYPICAL CROSS SECTION OF ROAD FOR UPGRADATION
F5
Name of work: Road branching at Km 30/8 of VKT Road to Pannikkankuppam Road Km 0/000 - 7/800
3.75 m
7.50 m
Sl.No Description Nos Length Breadth Depth Quantity Unit Rate Amount
1 Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings
and trees of girth up to 300mm, removal of stumps of such trees cut earlier and disposal of
unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of
1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per
Technical Specification Clause201.
4000.00
Deduct 40% voids -1600.00
2400.00 sqm 3.31 7944
2 Earthwork excavation for box cutting in all classes of soils except hard rock requiring blasting and
depositing on bank with all leads and lifts as per SS20A, including cost of all labour, equipments and
all incidental charges including clearing the site and disposal of all surplus materials etc, complete as
per relevant standard specification for widening portion.
2.4/2
Bell Mouth 2 20.00 1.200 0.450 21.60
0.6/2
Extra widening in Curve Km 0/4 & 0/6 2 30.000 0.300 0.450 8.10
0.9/2
Km 0/8 & 0/10 3 30.000 0.450 0.450 18.23
Total 3750.00
Extra widening in Curve Km 0/4 & 0/6 2 30.000 0.300 0.250 4.50
Km 0/8 & 0/10 3 30.000 0.450 0.250 10.13
Extra widening in Curve Km 0/4 & 0/6 2 30.000 0.300 0.200 3.60
Extra widening in Curve Km 0/4 & 0/6 2 30.000 0.300 0.050 0.90
21 Contingencies
2 Construction of embankment with approved material obtained from borrow pits with a
lift up to 1.5 m, transporting to site, spreading, grading to required slope and
compacting to meet requirements with a lead up to 1000 m as per Technical
Specification clause 303.1 and as directed by the Engineer – in – charge..
20 Contigencies 397
13451639
134.52
F-7
6 Disnandling stone/brick masonry in cement masonry and carefully stascking the use full materials
and removed un wanted materials as directed by the departmental officers
Parapet walls 1 x 2 4.00 0.450 0.500 1.80
Body walls 1 x 2 6.00 0.800 2.000 19.20
av av 21.00 cum 198.36 4165
630827
6.31
RATE ANALYSIS
Lead Chart
Name of work: Road branching at Km 30/8 of VKT Road to Pannikkankuppam Road Km
0/000 - 7/800
Metal To C.M.P Site
M.Kunnathur - Naripalayam Road Km 0/0 - 5/4 5.40
Ulundurpettai - T.V.Nallur Road Km 33/4 - 40/4 7.00
12.40 or 9.00 Km
COST OF MATERIALS
Sl.No. Kind of Lead Cost of Lead Stacking Total
materials materials charges charges
Cost of materials at CMP site
GSB
53 to 9.50 mm IRC Metal 9 710.22 63.45 773.67
(514+689+689+703+665+ 665+965+894+608)/9
9.50 to 2.36 mm IRC Metal 9 430.60 63.45 494.05
(451+451+451+400+400)/5
2.36 mm and below metal 9 400.00 63.45 463.45
WMM
45 to 22.40 mm IRC metal 9 737.40 63.45 800.85
(689+703+665+665+965)/5
22.40 to 2.36 IRC metal 9 602.86 63.45 666.31
(965+894+608+451+451+ 451+400)/7
2.36 to 75 micron 9 400.00 63.45 463.45
BM
25 to 10 mm IRC metal 9 783.00 63.45 846.45
(665+965+894+608)/4
10 to 5 mm IRC metal 9 425.50 63.45 488.95
(451+400)/2
5 mm and below IRC metal 9 400.00 63.45 463.45
PC
13.20 mm-5.50 mm IRC 9 570.40 63.45 633.85
894+608+451+451+451/5
BT Patches
45 mm metal 33 689.00 200.55 889.55
SDBC
11.20 mm 9 553.00 63.45 616.45
6.70 mm 9 411.00 63.45 474.45
2.80 mm 9 364.00 63.45 427.45
Cost of materials at work site
Cost of 11.2 - 2.36 mm metal 33 460.17 200.55 3.15 663.87
((608+451+451+451+400+400)/6)=
RATE ANALYSIS
1 Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth up to 300mm, removal of stumps of such
trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 m including removal
and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause201.
3 Unloading of Earth, sand, Moorum,Manure,flyash by manual means including a lead upto 30m
Unit =cum
Taking output = 5.50 cum
a) Labour
0.005 Mate 213.00 day 1.07
0.125 Mazdoor (Unskilled) 185.00 day 23.13
24.19
b) Machinery
0.166 Truck 433.55 hour 71.97
71.97
4
Construction of Sub grade and Earthen shoulders with approved materials obtained from borrow pits with all lifts and leads, transporting to site, spreading
grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000m as per Technical specification Clause 303.1
Reach km 0/0-2/6
a)Labour
0.04 Mate 213.00 / day 8.52
0.50 Mazdoor 185.00 / day 92.50
Total - (a) 101.02
b)Machinary
1.00 Hydraulic excavator 0.9 cum bucket capacity @ 100 cum per hour 1207.50 / Hr 1207.50
4.50 Tipper 5.5 cum capacity, 4 trips per hour 322.46 / Hr 1451.07
100.00 Loading of earth as per item 2 32.07 / Hr 3207.00
100.00 Un Loading of earth as per item 3 19.67 / Hr 1967.00
0.50 Dozer D-50 for spreading @ 200cum per hour 2045.85 / Hr 1022.93
0.50 Motor grader for grading @ 200cum per hour 1691.65 / Hr 845.83
2.00 Water tanker 6 kl capacity 285.42 / Hr 570.84
1.43 Three Wheel 80-100 kN Static roller @ 70 cum per hour 426.65 / Hr 610.11
Total - (b) 10882.28
c)Materail
12.00 Cost of water 120.00 / 12 1440.00
100.00 Compensation for earth taken from private land 50.00 / 100 5000.00
Total - (c) 6440.00
Total - (a+b+c) 17423.30
Over heads 12.5% on 17423.30 = 2177.91
Total - (a+b+c+d) 19601.21
Cost for 100.00 Cum 19601.21
Cost for 1 cum 196.01 / Cum
F-8
5 Construction of Gravel shoulders by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with three wheel 80 – 100 KN static roller capacity to achieve the desired density, complete as per Technical
Specification and as directed by the Engineer – in – charge.
Reach km 0/0-2/6
a)Labour
0.04 Mate 213.00 / day 8.52
1.00 Mazdoor 185.00 / day 185.00
Total - (a) 193.52
b)Machinary
0.50 Dozer D-50 for spreading @ 200cum per hour 2045.85 / Hr 1022.93
0.50 Motor grader for grading @ 200cum per hour 1691.65 / Hr 845.83
Scarifying existing surface to the required depth and levelling the existing surface to the required line and level all complete as per Technical Specification
clause 301.4 and as directed by the engineer in charge
Unit = sqm
Taking Output = 100 sqm
a) Labour
0.16 Mate 213.00 / day 34.08
4.00 Mazdoor 185.00 / day 740.00
Total - (a) / 100 sqm 774.08
Overheads 12.5% on 774.08 = 96.76
870.84
Scarifying existing surface 8.71 / 1sqm
F-8
6
Construction of Granular Sub-base by providing Grade I material spreading in uniform layers on prepared surface, mixing by mix in place method at OMC and
compacting with vibratory roller to Achieve the desired density, in including all labour charges etc., complete as per clause 401 MORT & h specifications.
Unit = cum
Taking out put = 300 cum
a) Labour
0.48 Mate 213.00 each 102.24
2.00 Mazdoor Gr - I 207.00 each 414.00
10.00 Mazdoor Gr - II 185.00 each 1850.00
2366.24
b) Machinery
6.00 Motor grader 110 Hp 50 cum per hour 1691.62 hour 10149.72
30.00 Three wheeled 80-100 KN Static roller 426.65 hour 12799.50
12.00 Tractor with Rotavator 25 cum per hour 353.00 hour 4236.00
5.00 Water tanker 6kl capacity 250.62 hour 1253.10
28438.32
c) Material
7 Providing, laying, spreading and compacting stone aggregates to Wet Mix Macadam specification including premixng the material with water at OMC in
mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base / base course on a well prepared sub-base and
compacting with smooth wheel roller of 80 to 100 KN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc. as
per Tables 400.11 & 400.12 and Technical specification clause 406.
Unit = cum
Taking out put = 100 cum
a) Labour
0.4 Mate 213.00 each 85.20
8.00 Dresser (skilled) for allignment 207.00 each 1656.00
2.00 Mazdoor (skilled) 207.00 each 414.00
2155.20
b) Machinery
4.00 Front end loader 1 cum capacity wet mix plant(pug mill) 806.00 hour 3224.00
4.00 Wet mix plant(pug mill) 1116.62 hour 4466.48
5.00 Tipper/Dumper (10T capacity) 322.46 1612.30
2.00 Motor grader at 50 cum/hr 1691.62 hour 3383.24
1.33 Water tanker 6kl capacity 106.87 142.14
6.25 Three wheeled 80-100 KN Static roller 426.65 hour 2666.56
15494.72
c) Material
Aggregate
9 Providing and applying primer coat with bitumen emulsion (SS – 1) on prepared surface of granular base including clearing of road surface and spraying primer
at the rate of 0.70 – 1.0 kg / sqm using mechanical means as per Technical Specification and as directed by the Engineer – in – charge.
Unit = sqm
Taking output = 1750 sqm
a) Labour
0.04 Mate 213.00 day 8.52
1.00 Mazdoor (Unskilled) 185.00 day 185.00
193.52
b) Machinery
1.40 Hydraulic broom @1250 sqm per hour 331.20 hour 463.68
1.40 Air compressor 210cfm 296.70 hour 415.38
1.00 Bitumen emulsion pressure distributor @ 1750 sqm 645.00 hour 645.00
0.50 Water tanker 6 kl capacity 1 trip per hour 106.87 hour 53.44
1577.50
c) Material
1.48 Bitumen emulsion (SS-1) @ 0.85 kg per sqm 72876.36 Mt 107857.01
3.00 Water 120.00 kl 360.00
109988.03
Over heads 12.5% on 109988.03 = 13748.50
Cost for 1750 sqm = a+b+c+d 123736.53
Rate per sqm = (a+b+c+d)/1750 70.71
10 Providing and applying tack coat with Bitumen emulsion (RS – 1) using emulsion distributor at the rate of 0.25 to 0.30 kg / sqm on the prepared granular surface
treated with primer & cleaned With Hydraulic broom as per Technical Specification and as directed by the Engineer – in – charge.
Unit = sqm
Taking output = 1750 sqm
a) Labour
0.04 Mate 213.00 day 8.52
1.00 Mazdoor (Unskilled) 185.00 day 185.00
193.52
b) Machinery
1.40 Hydraulic broom @1250 sqm per hour 331.20 hour 463.68
1.40 Air compressor 210cfm 296.70 hour 415.38
1.00 Emulsion pressure distributor @ 1750 sqm per hour 645.00 hour 645.00
1524.06
c) Material
0.48 Bitumen emulsion (RS-1) @ 0.275 kg per sqm 42532.33 mt 20415.52
22133.10
Over heads 12.5% on 22133.10 = 2766.64
11 Providing and applying tack coat with Bitumen emulsion (RS – 1) using emulsion distributor at the rate of 0.225 kg / sqm on the existing BT surface & cleaned
With Hydraulic broom as per Technical Specification and as directed by the Engineer – in – charge.
Unit = sqm
Taking output = 1750 sqm
a) Labour
0.04 Mate 213.00 day 8.52
1.00 Mazdoor (Unskilled) 185.00 day 185.00
193.52
b) Machinery
1.40 Hydraulic broom @1250 sqm per hour 331.20 hour 463.68
1.40 Air compressor 210cfm 296.70 hour 415.38
1.00 Emulsion pressure distributor @ 1750 sqm per hour 645.00 hour 645.00
1524.06
c) Material
0.39 Bitumen emulsion (RS-1) @ 0.225 kg per sqm 42532.33 mt 16587.61
18305.19
Over heads 12.5% on 18305.19 = 2288.15
Cost for 1750 sqm = a+b+c+d 20593.34
Rate per sqm = (a+b+c+d)/1750 11.77
12 Provision of rumble strips covered with premix bituminous carpet in approved locations to control speed marked with white strip of road making paint as per
IRC 67 – 2001 as per drawing and technical specifications of 1703 – 1 No.
Unit = 1 sqm
Taking output = 100 sqm including gap
Length = 100/3.75 = 26.70 or 27 M
No. of strips 28
Area of strips 28 3.75 0.25 26.25 sqm
26.25 Premix carpet 20 mm thick (km 5-6 rate) 119.16 sqm 3127.95
26.25 Painting with Hot Thermoplastic paint (As per Chief Engineer (H),Chennai) 814.00 sqm 21367.50
24495.45
Over heads 12.5% on 24495.45 3061.93
Rate per 100 sqm 27557.38
Rate per 1sqm 275.57
4 Construction of Sub grade and Earthen shoulders with approved materials obtained from borrow pits with all
lifts and leads, transporting to site, spreading grading to required slope and compacted to meet requirement
of Table 300.2 with lead upto 1000m as per Technical specification Clause 303.1
Reach km 0/0-2/6
a)Labour
0.04 Mate 213.00 / day 8.52
1.00 Mazdoor 185.00 / day 185.00
Total - (a) 193.52
b)Machinary
Hydraulic excavator 0.9 cum bucket capacity @
1.00 1302.00 / Hr 1302.00
100 cum per hour
0.50 Dozer D-50 for spreading @ 200cum per hour 2206.00 / Hr 1103.00
2.00 Water tanker 6 kl capacity 251.00 / Hr 502.00
1.43 Three Wheel 80-100 kN Static roller @ 70 cum 460.00 / Hr 657.80
5 Construction of Gravel shoulders by providing well graded material, spreading in uniform layers with motor
grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with
three wheel 80 – 100 KN static roller capacity to achieve the desired density, complete as per Technical
Specification and as directed by the Engineer – in – charge.
a)Labour
0.04 Mate 213.00 / day 8.52
1.00 Mazdoor 185.00 / day 185.00
Total - (a) 193.52
b)Machinary
Hydraulic excavator 0.9 cum bucket capacity @ 1302.00 /
1.00 Hr 1302.00
100
4.50 Tipper 5 cum with 10 T capacity 310.00 / Hr 1395.00
0.50 Dozer D-50 for spreading @ 200cum per hour 2206.00 / Hr 1103.00
0.50 Motor grader for grading @ 200cum per hour 1692.00 / Hr 846.00
2.00 251.00 / Hr 502.00
Water tanker 6 kl capacity
1.43 460.00 / Hr 657.80
Three Wheel 80-100 kN Static roller @ 70 cum
Total - (b) 9865.80
c)Materail
12.00 Cost of water 120.00 / 12 1440.00
100.00 Cost of gravel 190.60 / 100 19060.00
Total - (c) 20500.00
Total - (a+b+c) 30559.32
Over heads 12.5% on 30559.32 = 3819.92
Total - (a+b+c+d) 34379.24
Cost for 100.00 Cum 34379.24
CESS 1.00% 343.79
34723.03
Cost for 1 cum 347.23 / Cum
Scarifying existing surface to the required depth and levelling the existing surface to the required line and
level all complete as per Technical Specification clause 301.4 and as directed by the engineer in charge
Unit = sqm
Taking Output = 100 sqm
a) Labour
0.01 Mate 213.00 / day 2.13
0.25 Mazdoor 185.00 / day 46.25
Total - (a) / 100 sqm 48.38
b)Machinary
0.25 Tractor with trolley 353.00 / Hr 88.25
0.30 Front end loader 806.00 / Hr 241.80
0.68 Tipper 5.5 cum with 4 T capacity 310.00 / Hr 210.80
540.85
589.23
Overheads 12.5% on 589.23 = 73.65
662.88
cess 1.0% 6.63
669.51
Scarifying existing surface 6.70 / 1sqm
Name of work: Road branching at Km 30/8 of VKT Road to Pannikkankuppam Road Km 0/000
- 7/800
Sl.No Reach Unit Quantity Rate Amount
1 Clearing and grubbing road land including uprooting wild vegetation, grass, bushes,
shrubs, saplings and trees of girth up to 300mm, removal of stumps of such trees cut
earlier and disposal of unserviceable materials and stacking of serviceable material to be
used or auctioned, up to a lead of 1000 m including removal and disposal of top organic
soil not exceeding 150 mm in thickness as per Technical Specification Clause201.
No 39 350.00 13650
17 Providing and fixing of typical BHARAT NIRMAN informatory sign board with logo as
per MORD specifications and drawing. Three MS plates of 1.6 mm thick, top and
middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. the
No. 2 5000.00 10000
No. 2 15000.00 30000
18 Provision of rumble strips covered with premix bituminous carpet in approved locations
to control speed marked with white strip of road making paint as per IRC 67 – 2001 as
per drawing and technical specifications of 1703 – 1 No.
sqm 840.00 276.98 232663
19 Provision for Three row pipe culvert and hard bed 630827
21 Contigencies 470
Total cost 17560584
Providing advance patch work using 45mm IRC size HBG chips for
making upto pot holes and patching of 80/100 grade bituminous mix
at the site and placed in the pot holes or in patches after trimming the
pot holes or depression to proper shape and depth side painting with
tack coat and compacting the layers as directed by the Departmental
officers etc., complete
Providing and laying bituminous macadam with 40-60 THP hot mix plant using crushed aggregates of grading as per table 500.4 premixed with
bituminous binder, transported to site up to lead of 1000m, laid over a previously prepared surface with paver finisher to the required grade, level and
alignment and rolled achieve the desired compaction clause 504.
Unit = Cum
Taking out put = 102.50 Cum
a) Labour
0.52 Nos Mate 213.00 / day 110.76
10.00 Nos Mazdoor UnSkilled 185.00 / day 1850
Providing, laying and rolling open grade premix surfacing of 20 mm thickness composed of 13.2 mm to 5.5 mm graded aggregates either using
penetration graded bitumen or cut back bitumen or emulsion to required line and grade ans level to serve as wearing course on a previously prepared
base, includiong mixing in a suitable plant, laying and rolling with a smooth wheeled roller to acheieve the desired compaction specifications complete
in all respects.
Unit = Sqm
Taking out put = 4000.00 Sqm
a) Labour
0.52 Nos Mate 213.00 / day 110.76
10.00 Nos Mazdoor working with HMP, mechanical broom, paver, roller 185.00 / day 1850.00
3.00 Nos Skilled Mazdoor for checking line and levels 207.00 / day 621.00
Total - (a) 2581.76
b) Machinary
6.00 Hour HMP 30/40 t/hr 13909.14 / Hour 83454.84
6.00 Hour Generator 125 KVA 647.45 / Hour 3884.70
6.00 Hour Front end loader 1 cum bucket capacity 806.00 / Hour 4836.00
3.64 Hour Tipper 5.50 cum 10 tonne capacity 322.46 / Hour 1173.75
6.00 Hour Paver finisher 2789.85 / Hour 16739.10
16.00 Hour Three wheeled 80-100 KN Static roller 426.65 / Hour 6826.40
Total - (b) 116914.79
c) Material
108.00 Cum Cost of 13.2 - 5.6 mm 633.85 / Cum 68455.80
5.84 tonne Cost of 60/70 bulk bitumen 40362.71 / tonne 235718.22
Total - (c) 304174.02
Total - (a+b+c) 423670.57
d) Over heads 12.5% on 423670.57 = 52958.82
Total - (a+b+c+d) 476629.39
Cost for 4000.00 Sqm 476629.39
Cost for 1 Sqm 119.16 / Sqm
SEAL COAT TYPE - A:
Providing, laying Seal coat sealing the voids in a bituminous surface laid to specified levels, grade and cross fall using type A seal coat on a previously
prepared base, includiong mixing in a suitable plant, laying and rolling with a smooth wheeled roller to acheieve the desired compaction complete in all
respects.
Unit = Sqm
Taking out put = 7500.00 Sqm
a) Labour
0.24 Nos Mate 213.00 / day 51.12
6.00 Nos Mazdoor 207.00 / day 1242.00
Total - (a) 1293.12
b) Machinary
6.00 Hour Hydraulic self propelled chip spreader 2443.75 / Hour 14662.50
6.00 hour Tipper 5.50 cum 10 tonne capacity 322.46 / hour 1934.76
6.00 Hour Front end loader 1 cum bucket capacity 806.00 / Hour 4836.00
6.00 Hour Bitumen pressure distributor at 1750 Sqm per hour 645.00 / Hour 3870.00
15.00 Hour Three wheeled 80-100 KN Static roller 426.65 / Hour 6399.75
Total - (b) 31703.01
c) Material
67.50 Cum Cost of 11.2 - 2.36 mm 663.87 / Cum 44811.00
7.35 tonne Cost of 60/70 bulk bitumen 40348.72 / tonne 296563.08
Total - (c) 341374.08
Total - (a+b+c) 374370.21
d) Over heads 12.5% on 374370.21 = 46796.28
Total - (a+b+c+d) 421166.49
Cost for 7500.00 Sqm 421166.49
Rate per Sqm 56.16 / Sqm
RATE ANALYSIS
Name of work:-Improvements to Sivalayam- Ullianur to Kodambakkam Km 0/0-4/4
THREE ROW PIPE CULVERT AT CH 0/8
COST OF MATERIALS
Kind of Name of Lead Cost of Conveyance Total
Sl.No materials quarry in km Materials charge
6. Providing and laying RCC pipe NP 3 for culverts on first class bedding on granular material in single row
inclding fixing coller with cement mortar 1:2 excluding excavation protection works,back filling concrete
and masonry b)works in head walls and parapets clause 1106
Labour
0.09 Mate 189.00 day 17.01
0.25 Mason (1st Class) 291.00 day 72.75
2.00 Mazdoor (Unskilled) 165.00 day 330.00
419.76
a) Material
0.04 Sand 192.60 cum 7.70
0.03 Cement 5397.55 Mt 161.93
7.50 RCC Pipe NP 3 2600.00 Rm 19500.00
1.00 Labour 419.76 419.76
20089.39
c) Overheads @ 12.5% on (a+b) 2511.17
Rate per 7.5 m = a+b+c 22600.56
Rate per metre 3013.41
7. Disnandling stone/brick masonry in cement masonry and carefully stascking the use full materials and
removed un wanted materials as directed by the departmental officers
Unit = cum
Out put 1.25 cum
a) Labour
0.03 Mate 189.00 day 5.67
0.75 Mazdoor (Unskilled) 165.00 day 123.75
b) Machinery
0.27 Tractor with trolly 336.95 90.98
220.40
c) Overheads @ 12.5% 27.55
Rate per 1.25 cum 247.95
Rate per 1 cum 198.36
FORMAT F- 9A
Certified that the Land width for the Road is available and that no additional land is
1 a)
required;or
Certified that Land width for the Road is likely to be available as certified by the
b)
Panchayats.
2 a) Certified that no forest land is involved along the entire road way; or
Certified that the case for permission under Forest conservation Act has been moved to
b)
the Forest Department on (Date)
Divisional Engineer,
Head of PIU.
FORMAT F- 9B
1 AE 1 100%
2 ADE 1 100%
3 DE 1 100%
Head of PIU.
PROFORMA - B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) - VIII , BHARATH NIRMAN - PHASE III
PACKAGE SUMMARY
DISTRICT : CUDDALORE
1 PANRUTI Pakkiripalayam Road U 1.000 #REF! - 6.308 #REF! 1.500 #REF! 1.500
Total Estimated cost of the Package Rs.(lakhs) 1.000 #REF! - 6.308 #REF! 1.500 #REF! 1.500
Signature:
Signature: Signature:
Checked By: Co-ordinator: STA
Name: Name:
Signature:
Scrutinized By:
Name:
PROFORMA - B
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY) - VIII , BHARATH NIRMAN - PHASE III
PACKAGE SUMMARY
Package No. : TN - 003 - 52
DISTRICT : CUDDALORE
Pakkiripalaya
1 PANRUTI 0 U 1.000 #REF! -- 0.000 #REF! 1.500 #REF! 1.500
m Road
Total Estimated cost of the Package Rs.(lakhs) 1.000 #REF! -- 0.000 #REF! 1.500 #REF! 1.500
*N- New Connectivity , U - Upgradation
Signature:
Signature: Signature:
Checked By: Co-ordinator: STA
Name: Name:
Signature:
Scrutinized By:
Name:
Format - C
BHARAT NIRMAN PHASE - III
PRADHAN MANTRI GRAM SADAK YOJANA
CHECK LIST FOR P.I.U & S.T.A
( For Individual Road Works )
To be filled by P.I.U
1 Location: Pakkiripalayam State : TamilNadu DISTRICT : CUDDALORE BLOCK : PANRUTI
4 Total Length(Km.) 1.000 Km. In Built up area: 1.062 m In Open area : -0.06 Km
Does the proposed road lead upto the Habitation for which it is supposed to provide
connectivity ( In other words are you sure that the road is not being made partially?)
Whether
(a) Whether the proposed road has the desired Carriage way width, Road way
7 Yes / No
width & Road land width (RLW)
In the Built up Area In the Open Area
(b) Indicate the Actual widths of the following for the proposed road.
(m) (m)
Km 0/0
KM 4/4
0/494 1/137 1.890 2/730 2/853 3/192 3.621 4/029 4/345
Total
Two
Bus/Truc LCV/Mini Cars/ Three Cycle
Days Wheeler Cycles Bullock Carts Motorised Non Motorised
k Bus Jeeps/ Vans Wheelers Rickshaw
s
9 Growth rate adopted (%) = 7.5% Projected Traffic 2.74 CVPD 342
Chainage Km : 0/0-1/0
Design CBR %
11 Cost details
B. Pavement Components
C. Bituminous Layer
BM 50 1195576
SDBC 25 #VALUE!
D CD Works
12 Whether the road has Geometrics as per Rural Road Manual (RRM) Yes / No
14 Whether Cost Estimates pre as per Standard Data Analysis & S.S.R Yes / No
Have You satisfied your self that the proposed road is part of the Core Net work : Yes / No
Is the Un Connected Habitation(s) part of list of Un connected Habitation as per
: Yes / No
CN-6.
Does the Proposal ensure full connectivity to Target Habitation Yes / No
a) If No, the name of Unconected Habitation up to which it is connected Yes / No
b) If such Unconnected Habitation eligble Under PMGSY Yes / No
16 Are You Satisfied with the Following
Engineering Surveys : Yes / No
Soil / Material Investigation : Yes / No
Traffic Surveys / Estimation : Yes / No
Hydraulic studies : Yes / No
17 Is the Design of the following Elements as per RRM / Circulars of NRRDA:
Certified that the Design and Estimation for the Proposed Road work is based on the data and SSR provided by Engineers . The
Proposal may be cleared.
Signature : Signature :
Name : Name :
BHARAT NIRMAN PROGRAME PHASE - III
(Ministry
Name of work:ofRoad
Rural Development
branching at Km ,30/8
Govtof of
VKTIndia)
Road to
Pannikkankuppam Road Km 0/000 - 7/800
Block: Walajabad District: Kancheepuram
Bitumen Boiler
Since the bitumen boiler is attached
with CPM site the separate hire
charges for bitumen boiler is not
necessary
ALL Km
Sl No. QTY UNIT DESCRIPTION OF ITEM UNIT RATE AMOUNT
Vibratory Road Roller
Paver Finisher
Tipper Trucks
Mazdoor Class I
33 207/ E 6831.00
Mazdoor Class II
25 185/E 4625.00
Mazdoor Class I
10 207/E 2070.00
13526 x 10 /2000
67.63
1997.17
Rate per sqm
199.72