NATIONAL GRID SA

Title: Checklist Index Number:


CL-NG-6460-003-001
Checklist for Normalization Before Energization Page Number: Revision Number:
1 of 3 01

1.0 Equipment General Data and Information

Substation DAMMAM HOUSING-6 115/13.8KV


Bay/Panel
Equipment ----------- Serial No -----------

2.0 Normalization Check List


Item Description Done Remarks
1. CT Circuits Normalization:
1.1. Make sure that all CT circuits are connected, shorted,
isolated, and single point earthed as per the marked-up Done
drawings.
1.2. Ensure proper connections and tightness for all CT
circuits by a screwdriver, and pull each wire gently to Done
ensure that all CT wires terminated properly.
2. VT Circuits Normalization:
2.1. Make sure that all VT circuits are connected, and isolated
Done
as per the marked-up drawings.
2.2. Ensure proper connections and tightness for all VT
circuits by a screwdriver, and pull each wire gently to Done
ensure that all VT wires terminated properly.
3. Power Transformer & Outdoor Equipment:
3.1. Ensure that there is no temporary grounding or shorting
between phases of any transformer/reactor winding (high N/A
side, low side, and tertiary windings).
3.2. Ensure that all valves are in the correct position for the
safe operation of the power transformed and as per N/A
approved design.
3.3. Confirm that all covers of mechanical protection, outdoor
boxes, and panels are properly closed, tighten, and N/A
sealed.
3.4. Confirm that no oil leakage. N/A
3.5. Confirm that NER grounding is properly earthed. N/A
3.6. Confirm that there is no any temporary shorting across the
primary terminals of the NER. N/A

3.7. Confirm that the on-load tap changer is set on the normal
N/A
tap
NATIONAL GRID SA

Title: Checklist Index Number:


CL-NG-6460-003-001
Checklist for Normalization Before Energization Page Number: Revision Number:
2 of 3 01

3.8. Confirm that capacitor bank door is locked and the key is
N/A
placed on its parking.
3.9. Confirm that all connections of capacitor bank cells are
tightened properly and there is no oil leakage from any N/A
cell.
4. Power Cables:
4.1. Confirm that all power cables and their sheaths are
N/A
terminated properly.
4.2. In the case of using a split-core CT, confirm that all cable
sheaths are connected properly through ring CT according N/A
to TES-P-104.08 figure 08-1.
4.3. Confirm that all cables sheaths are connected to link
N/A
boxes according to approved drawing.
4.4. Confirm that all cables are painted with anti-fire paint. N/A
4.5. Check that all cable entrances are filled with fire stop
N/A
material.
4.6. Check that all cable clamps are fixed properly. N/A
5. Trip Circuits:
5.1. Ensure that all selector switches of instantaneous over
current and earth fault protection relays of bus section and N/A
bus coupler are in (out-position).
5.2. Confirm that all trip links (especially for UV and UF) are
N/A
connected as per approved final settings/drawings.
5.3. Check all test switches visually to ensure that no CABLE
TIE or other materials are available inside it that could Done
isolate trip circuits.
5.4. Confirm that there is no temporary connection in trip
Done
circuits or closing circuits
6. Alarms:
6.1. Confirm that all links for alarms in all panels are closed. Done
6.2. Make sure that there are no alarms on annunciators,
Done
relays, and SAS HMI (as applicable).
6.3. Check all test switches visually to ensure that no CABLE
TIE or other materials are available inside it that could Done
isolate alarms.
7. Auxiliaries:
7.1. Confirm that there is no temporary shorting or grounding
N/A
available at auxiliary transformer & RMU terminals.
NATIONAL GRID SA

Title: Checklist Index Number:


CL-NG-6460-003-001
Checklist for Normalization Before Energization Page Number: Revision Number:
3 of 3 01

7.2. Confirm that no oil leakage from the auxiliary transformer. N/A
7.3. Confirm that all cables are properly connected for ACDB,
N/A
DCDB, RMU, and auxiliary transformers.
7.4. Confirm that RMU fuses (if applicable) are properly
N/A
connected.
7.5. Confirm that the tap changer of the auxiliary transformer
N/A
is set on the normal tap.
8. General Checking:
8.1. Confirm that all panels are closed from the front and rear
sides (especially 13.8 kV MV Switchgear) and there is no Done
tool inside the panels.
8.2. Check that all thermostats are adjusted as per the
approved drawings, and its selector switches are in the Done
Auto position.

CSD T&C Contractor Item Number


Name KHALID AL JEBREEN MOIN KHAN (FAL-008)
Sign.
Date
Name
Sign.
Date