Professional Documents
Culture Documents
Sub base 1 Dozer(0790) 1 11.42 2501 28,560.28 Laborer 1 1.00 11.42 11.42 8.27 94.44
Production 2
(10+200) 28,654.72 7,163.68 35,818.402 16.18 980.41 15,862.985 (19,955.416)
3
Total 28,560.28 94.44 -
Sub base 1 Dozer(59282) 1 11.42 2272 25,946.24 Laborer 1 1.00 11.42 11.42 8.27 94.44
Production 2 operator 1 1.00 11.42 11.42 71.17 812.76
(10+200) 26853.4448 6713.3612 33,566.806 16.18 980.41 15,862.985 (17,703.821)
3
Total 25,946.24 907.20 -
Sub base 1 Dozer(60043) 1 2.00 2272 4,544.00 Laborer 1 1.00 2 2 8.27 16.54
Production 2 operator 1 1.00 2 2 71.17 142.34
(10+200) 4702.88 1175.72 5,878.600 16.18 171.70 2,778.106 (3,100.494)
3
Total 4,544.00 158.88 -
Sub base 1 Dozer(58830) 1 9.00 2272 20,448.00 Laborer 1 1.00 9 12 8.27 99.24
Production 2 operator 1 1.00 9 12 71.17 854.04
(10+200) 21401.28 5350.32 26,751.600 16.18 772.65 12,501.477 (14,250.123)
3
Total 20,448.00 953.28 -
1 Dozer(59281) 1 11.00 2272 24,992.00 Laborer 1 1.00 11 12 8.27 99.24
Borrow Production
(19+900) 2 operator 1 1.00 11 12 71.17 854.04
25945.28 6486.32 32,431.600 27.00 701.25 18,933.750 (13,497.850)
3
Total 24,992.00 953.28 -
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(59785) 5 25 14 6,965.000 foreman 1 1.00 12 12 47.61 571.320
Quary rock Hauling
(5+000) 2 D/Truck(59755) 5 9 14 2,507.400 operator 4 1.00 12 48 62.31 2,990.880
18,134.14 4533.535475 22,667.677 37.66 476.00 17,926.160 (4,741.517)
Loader(60049) 0.33 13.67 579 2,611.927
3 Loader(58545) 0.33 12.5 579 2,388.375
Total 14,472.702 3,661.440 -
1 Crusher(45023) 1 2 3600 7,200.000 Laborer 10 1.00 2.67 26.7 8.27 220.809
Base course
crushing (5+000) 2 Crusher(59268) 1 2.67 3600 9,612.000 operator 2 1.00 2.335 4.67 47.99 224.113 17256.9223 4314.230575 21,571.153 179.95 197.00 35,450.150 13,878.997
Sub base 1 Grader(55656) 1 3.17 1115 3,534.550 foreman 1 0.25 12 3 54.49 163.470
Placing(11+120- 2 W/Truck(59807) 1 3.17 300 951.000 Laborer 10 1.00 12 120 8.27 992.400
11+260) 7,243.18 1,810.80 9,053.975 84.58 119.60 10,115.768 1,061.793
operator 2 1.00 12 24 66.74 1,601.760
Total 4,485.550 2,757.630 -
1 Loader(0968) 1 9.83 716 7,038.280 foreman 1 0.60 12 7.2 54.49 392.328
No. D/Truck Km No.Trip Capacity Laborer 10 1.00 12 120 8.27 992.400
1 D/Truck(62148) 5 10 14 2,786.000 operator 7 1.00 12 84 62.31 5,234.040
2 D/Truck(28793) 5 8 13.94 2,219.248
3 D/Truck(27783) 5 8 14 2,228.800
4 D/Truck(32940) 5 8 14 2,228.800
5 D/Truck(16834) 5 10 12.4 2,467.600
6 D/Truck(57038) 5 11 16.74 3,664.386
Sub base Haulling
(16+760-19+800) 7 D/Truck(44662) 5 9 16.56 2,965.896
55,500.78 13875.1945 69,375.973 83.34 2,102.70 175,239.018 105,863.046
8 D/Truck(58803) 5 11 16 3,502.400
9 D/Truck(59782) 5 9 14 2,507.400
10 D/Truck(59932) 5 15 14 4,179.000
11 D/Truck(59777) 5 16 14 4,457.600
12 D/Truck(59933) 5 8 14 2,228.800
13 D/Truck(59948) 5 11 14 3,064.600
14 D/Truck(59964) 5 10 14 2,786.000
15 D/Truck(59742) 5 2 14 557.200
Total 48,882.010 6,618.768 -
1 Grader(59998) 1 11.83 1115 13,190.450 foreman 1 0.50 12 6 54.49 326.940
2 Grader(59992) 1 8.83 1115 9,845.450 Laborer 10 1.00 12 120 8.27 992.400
3 Roller(0620) 1 8.42 812 6,837.040 operator 5 1.00 12 60 65.85 3,951.240
Borrow Placing 4 Roller(0814) 1 7.17 812 5,822.040
(17+220-17+620) 5 Roller(0483) 1 7.92 810 6,415.200 57,730.76 14,432.69 72,163.450 32.72 1,200.00 39,264.000 (32,899.450)
6 W/truck(59801) 1 11.5 300 3,450.000
7 W/truck(59801) 1 11.5 300 3,450.000
8 W/truck(59831) 1 11.5 300 3,450.000
Total 52,460.180 5,270.580 -
1 Grader(60025) 1 10.5 1115 11,707.500 foreman 1 0.50 12 6 54.49 326.940
Sub base Placing 2 Roller(0292) 1 6 812 4,872.000 Laborer 10 1.00 12 120 8.27 992.400
(27+300-27+440) 3 W/truck(59808) 1 11.5 300 3,450.000 operator 3 1.00 12 36 65.26 2,349.480 27,148.32 6,787.08 33,935.400 84.58 418.60 35,405.188 1,469.788
4 W/truck(59805) 1 11.5 300 3,450.000
Total 23,479.500 3,668.820 -
Total Sum 376,377.833 53,390.790 35,847.560 582,020.229 691,492.580 154,337.782
Net Amount
Total - - -
1 Excavator(1149) 1 0 1474 -
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 - Laborer 0 1.00 0 0 8.27 -
Excavation for open 2 D/Truck(59758) 5 0 8 - foreman 1 0.50 0 0 43.46 -
drain (8+020-8+180) 3 D/Truck(59731) 5 0 8 - operator 6 1.00 0 0 43.89 - 0 0 - 92.72 - - -
4 D/Truck(59752) 5 0 8 -
5 D/Truck(59940) 5 0 8 -
6 D/Truck(58982) 5 0 8 -
Total - - -
1 Loader(58555) 1.00 0 579 - Foreman 1 1.00 0 0 43.46 -
pipe Installation 2 Excavator(58756) 1.00 0 1326 - Laborer 15 1.00 0 0 8.27 -
(0+611) 3 operator 2 1.00 0 0 43.89 - - - - 775.79 - - -
4 Mason 5 1.00 0 0 22.78 -
Total - - -
1 Excavator(0815) 1.00 0 1900 - Foreman 1 0.33 0 0 43.46 -
Foundation 2 Labore 1 1.00 0 0 8.27 -
Excavation
(0+160,0+306) 3 - - - 136.61 - - -
4
Total - - -
1 Loader(58546) 1.00 0 579 - Foreman 1 0.33 0 0 43.46 -
Class B bedding 2 Roller(58837) 1.00 0 550 - Labore 14 1.00 0 0 8.27 -
(17+741) 3 D/Truck(59755) 1.00 0 576 - operator 2 1.00 0 0 43.89 - - - - 262.13 - - -
4
Total - - -
1 W/Truck(58998) 0.50 12.00 300 1,800.00 Foreman 2 0.33 12 7.92 54.49 431.561 cement qtl 16.50 185 3,052.5
2 Mixer(59976) 1.00 12.00 718 8,616.00 Laborer 17 1.00 12 204 8.27 1,687.080 sand m3 3.76 350 1,314.6
Class C concrete
(10+9630) carpenter 2 1.00 12 24 22.78 546.720 Aggregate m3 6.09 600 3,654.0
Mason 11 1.00 12 132 22.78 3,006.960 25,707.94 6,426.99 32,134.926 2,569.52 10.00 25,695.200 (6,439.726)
L/ Foreman 3 1.00 12 36 13.13 472.680
operator 2 1.00 12 24 46.91 1,125.840
Total 10,416.000 7,270.841 8,021.1
Total Sum 21,104.000 20,784.281 48,577.100 113,081.726 89,204.384 (23,877.342)
Grand sum 943,764.891 981,287.855 82,388.395
Sub base 1 Dozer(0790) 1 11.50 2501 28,760.35 Laborer 1 1.00 11.5 11.5 8.27 95.11
Production 2
(10+200) 28,855.46 7,213.86 36,069.319 16.18 1,161.00 18,784.980 (17,284.339)
3
Total 28,760.35 95.11 -
1 Dozer(59281) 1 11.50 2272 26,128.00 Laborer 1 1.00 11.5 11.5 8.27 95.11
Borrow Production
(19+900) 2 operator 1 1.00 11.5 11.5 71.17 818.46
27041.56 6760.39 33,801.950 27.00 733.13 19,794.375 (14,007.575)
3
Total 26,128.00 913.56 -
Sub base 1 Dozer(59282) 1 11.00 2272 24,992.00 Laborer 1 1.00 11 11 8.27 90.97
Production 2 operator 1 1.00 11 11 71.17 782.87
(10+200) 25865.84 6466.46 32,332.300 16.18 945.00 15,290.100 (17,042.200)
3
Total 24,992.00 873.84 -
Sub base 1 Dozer(58830) 1 10.50 2272 23,856.00 Laborer 1 1.00 10.5 10.5 8.27 86.84
Production 2 operator 1 1.00 10.5 10.5 71.17 747.29
(10+200) 24690.12 6172.53 30,862.650 16.18 901.00 14,578.180 (16,284.470)
3
Total 23,856.00 834.12 -
1 Dozer(58829) 1 11.33 2272 25,741.760 Laborer 3 1.00 11.33 33.99 8.27 281.097 Dynamite
Quary rock 2 Wagon drill 1 7.5 1200 9,000.000 operator 3 1.00 9 27 50.22 1,356.030 Blasting caps
Production (5+000) 3 Air compresor 1 8.17 450 3,676.500 Quary foreman 1 0.25 11.33 2.83 47.61 134.855 40190.242625 10047.56066 50,237.803 122.34 703.00 86,005.020 35,767.217
4
Total 38,418.260 1,771.983 -
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(59785) 5 30 14 8,358.000 foreman 1 1.00 12 12 47.61 571.320
Quary rock Hauling
(5+000) 2 D/Truck(59755) 5 26 14 7,243.600 operator 4 1.00 12 48 62.31 2,990.880
23,609.88 5902.470625 29,512.353 37.66 784.00 29,525.440 13.087
3 Loader(58545) 0.33 8.25 579 1,576.328
4 Loader(60049) 0.33 14.5 579 2,770.515
Total 19,948.443 3,661.440 -
Base course 1 Crusher(59268) 1 11.75 3600 42,300.000 Laborer 10 1.00 11.75 117.5 8.27 971.725
crushing (5+000) 52921.1675 13230.29188 66,151.459 179.95 579.00 104,191.050 38,039.591
2 operator 1 1.00 11.75 11.75 47.99 563.883
Total 49,500.000 3,421.168 -
1 Crusher(39502) 1 9.25 3600 33,300.000 operator 1 1.00 9.25 9.25 47.99 443.908
Concrete Aggregate
crushing (5+000) 2 Laborer 10 1.00 9.25 92.5 8.27 764.975 34508.8825 8627.220625 43,136.103 336.59 299.00 100,640.410 57,504.307
3
Total 33,300.000 1,208.883 -
Total Sum 244,903.053 12,780.098 - 322,103.938 388,809.555 66,705.617
Date: 14/06/2014 Activity: Earthwork work
Actual cost Revenue
Equipment Man Power Material
Total Direct 25% Excuted Amount Net Amount
Activity Description Equipment No of Workin Hourly Cost Over Head Total Cost Unit Rate (m) Quantity
Description hy Working Hourly Rate Amount Trade Worker U.F g Hour Man Hour Amount Material Unit Quantity (I) Unit(J)Cost Amount (n) o=(m*n)
Hour (A) (B) C=(A*B) F=(D*G) Indexed H=(F*G) Description K=(I*J) L=(C+H+K) Cost
(With Plate No) s (D) (E) Rate(G)
No
1 Grader(55656) 1 10.75 1115 11,986.250 foreman 1 0.50 12 6 54.49 326.940
Borrow Placing 2 Grader(59990) 1 2.5 1115 2,787.500 operator 5 1.00 12 60 64.29 3,857.400
( 0+500- 3 Roller(0552) 1 1.67 810 1,352.700 Laborer 10 1.00 12 120 8.27 992.400
0+640,1+800-
2+060,5+500- 4 Roller(58851) 1 5 550 2,750.000 27,128.19 6,782.05 33,910.238 32.72 1,380.00 45,153.600 11,243.363
5+560) 5 W/truck(60122) 1 1.5 300 450.000
6 W/truck(59807) 1 8.75 300 2,625.000
Total 21,951.450 5,176.740 -
No
Sub base 1 Dozer(0790) 1 6.00 2501 15,005.40 Laborer 1 1.00 6 6 8.27 49.62
Production 2
(10+200) 15,055.02 3,763.76 18,818.775 16.18 606.00 9,805.080 (9,013.695)
3
Total 15,005.40 49.62 -
Sub base 1 Dozer(58830) 1 6.00 2272 13,632.00 Laborer 1 1.00 6 12 8.27 99.24
Production 2 operator 1 1.00 6 12 71.17 854.04
(10+200) 14585.28 3646.32 18,231.600 16.18 515.00 8,332.700 (9,898.900)
3
Total 13,632.00 953.28 -
1 Dozer(58829) 1 5.67 2272 12,882.240 Laborer 3 1.00 5.67 17.01 8.27 140.673 Dynamite
Quary rock
Production 2 Wagon drill 1 4.5 1200 5,400.000 operator 3 1.00 4.81 14.42 50.22 724.220 Blasting caps
(5+000) 3 Air compresor 1 4.25 450 1,912.500 Quary foreman 1 0.25 5.67 1.4175 47.61 67.487 21,127.12 5281.780085 26,408.900 122.34 351.00 42,941.340 16,532.440
4
Total 20,194.740 932.380 -
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(59785) 5 10 12 2,388.000 foreman 1 1.00 12 12 47.61 571.320
Quary rock
Hauling (5+000) 2 D/Truck(59755) 5 12 9 2,149.200 operator 4 1.00 12 48 62.31 2,990.880
11,453.26 2863.314225 14,316.571 37.66 228.00 8,586.480 (5,730.091)
3 Loader(58545) 0.33 4.08 579 2,362.320
4 Loader(60049) 0.33 4.67 579 892.297
Total 7,791.817 3,661.440 -
Base course 1 Crusher(45023) 1 0.58 3600 2,088.000 Laborer 10 1.00 2.75 27.5 8.27 227.425
crushing
(5+000) 2 Crusher(59268) 1 2.75 3600 9,900.000 operator 2 1.00 1.665 3.33 47.99 159.807 21460.7917 5365.197925 26,825.990 179.95 164.17 29,542.212 2,716.222
Total 19,188.000 2,272.792 -
Concrete 1 Crusher(39502) 1 4.33 3600 15,588.000 operator 1 1.00 4.33 4.33 47.99 207.797
Aggregate
crushing 2 Laborer 1 1.00 4.33 4.33 8.27 35.809
15831.6058 3957.90145 19,789.507 336.59 139.86 47,075.141 27,285.634
(5+000)
3
Total 15,588.000 243.606 -
Total Sum 91,399.957 8,113.118 - 124,391.343 146,282.952 21,891.609
Date: 15/06/2014 Activity: Earthwork work
Actual cost Revenue
Equipment Man Power Material
Activity Total Direct 25% Excuted Amount Net Amount
Equipment Working Hourly Rate Amount No of Workin Man Hour Hourly Amount Material Cost Over Head Total Cost Unit Rate (m)
Description Description hy Trade Worker U.F g Hour Indexed Unit Quantity (I) Unit Cost Amount
L=(C+H+K) Cost Quantity (n) o=(m*n)
(With Plate No) Hour (A) (B) C=(A*B) s (D) (E) F=(D*G) Rate(G) H=(F*G) Description (J) K=(I*J)
No
1 Grader(60200) 1 1 1115 1,115.000 foreman 1 0.50 2 1 54.49 54.490
Borrow Placing 2 Grader(59990) 1 6 1115 6,690.000 operator 3 1.00 1.75 5.25 68.22 358.138
( 0+500-0+600-
4+800-4+900- 3 Roller(0552) 1 1 810 810.000
9,327.63 2,331.91 11,659.534 32.72 1,260.00 41,227.200 29,567.666
1+780-2+000) 4 W/truck(60122) 1 1 300 300.000
Sub base 1 Dozer(58830) 1 11.25 2272 25,560.000 Laborer 1 1.00 11.25 12 8.27 99.240 Dynamite
Production 2 operator 1 1.00 11.25 12 71.17 854.040 Blasting caps
(10+200) 26513.28 6628.32 33,141.600 16.18 966.00 15,629.880 (17,511.720)
3
Total 25,560.000 953.280 -
Sub base 1 Dozer(60005) 1 11 2272 24,992.000 Laborer 1 1.00 11 12 8.27 99.240 Dynamite
Production 2 operator 1 1.00 11 12 71.17 854.040 Blasting caps
(24+200) 25945.28 6486.32 32,431.600 16.18 944.35 15,279.583 (17,152.017)
3
Total 24,992.000 953.280 -
1 Dozer(58829) 1 10.67 2272 24,242.240 Laborer 3 1.00 10.67 32.01 8.27 264.723 Dynamite
Quary rock
Production 2 Wagon drill 1 10 1200 12,000.000 operator 3 1.00 10.67 32.01 50.22 1,607.649 Blasting caps
(5+000) 3 Air compresor 1 10.67 450 4,801.500 Quary foreman 1 0.25 10.67 2.6675 47.61 127.000 43043.111275 10760.7778188 53,803.889 122.34 662.00 80,989.080 27,185.191
4
Total 41,043.740 1,999.371 -
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(59785) 1 21 12 1,002.960
Quary rock
Hauling (5+000) 2 D/Truck(59755) 1 13 9 465.660 foreman 1 0.25 12 3 47.61 142.830
10347.285 2586.82125 12,934.106 37.66 369.00 13,896.540 962.434
3 Loader(58545) 0.33 9.83 579 5,691.570 operator 4 1.00 11.5 12 62.31 747.720
4 Loader(60049) 0.33 11.5 579 2,197.305
Total 9,357.495 989.790 -
Base course 1 Crusher(45023) 1 1.33 3600 4,788.000 Laborer 10 1.00 3 30 8.27 248.100
crushing
(5+000) 2 Crusher(59268) 1 3 3600 10,800.000 operator 2 1.00 2.17 4.33 47.99 207.797 25129.4567 6282.364175 31,411.821 179.95 164.17 29,542.212 (1,869.609)
Total - - -
1 Excavator(1149) 1 0 1474 -
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 - Laborer 0 1.00 0 0 8.27 -
Excavation for 2 D/Truck(59758) 5 0 8 - foreman 1 0.50 0 0 43.46 -
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 - operator 6 1.00 0 0 43.89 - 0 0 - 92.72 - - -
4 D/Truck(59752) 5 0 8 -
5 D/Truck(59940) 5 0 8 -
6 D/Truck(58982) 5 0 8 -
Total - - -
1 Loader(58555) 1.00 0 579 - Foreman 1 1.00 0 0 43.46 -
pipe Installation 2 Excavator(58756) 1.00 0 1326 - Laborer 15 1.00 0 0 8.27 -
(0+611) 3 operator 2 1.00 0 0 43.89 - - - - 775.79 - - -
4 Mason 5 1.00 0 0 22.78 -
Total - - -
1 Excavator(0815) 1.00 0 1900 - Foreman 1 0.33 0 0 43.46 -
Foundation 2 Labore 1 1.00 0 0 8.27 -
Excavation
(0+160,0+306) 3 - - - 136.61 - - -
4
Total - - -
1 Loader(58546) 1.00 0 579 - Foreman 1 0.33 0 0 43.46 -
Class B bedding 2 Roller(58837) 1.00 0 550 - Labore 14 1.00 0 0 8.27 -
(17+741) 3 D/Truck(59755) 1.00 0 576 - operator 2 1.00 0 0 43.89 - - - - 262.13 - - -
4
Total - - -
1 Mixer(59976) 0.50 0 250 - Foreman 0 0.33 0 0 43.46 - cement qtl 0.00 185 -
2 Laborer 7 1.00 0 0 8.27 - sand m3 - 350 -
Class C concrete
(0+310-0+350) 3 carpenter 1 1.00 0 0 22.78 - Aggregate m3 - 600 -
- - - 2,569.52 - - -
4 Mason 3 1.00 0 0 22.78 -
5 L/ Foreman 1 1.00 0 0 13.13 - -
Total - - -
Total Sum 6,475.000 7,750.080 9,936.400 30,201.850 15,701.010 (14,500.840)
Grand sum 807,787.670 1,121,380.068 313,592.397
Cost Effectiveness Analysis
Date: 17/06/2014 Activity: Material Production
0
Equipment Man Power Material
Activity Equipment Hourly Hourly
Description Working Amount Working Man Hour Amount Material Quantity Unit
Description U.F Rate Trade U.F Indexed Unit
(With Plate No) Hour (A) (B) C=(A*B) Hour (E) F=(D*G) Rate(G) H=(F*G) Description (I) Cost (J)
No
Sub base 1 Dozer(0790) 1 12.00 2501 30,010.80 Laborer 1 1.00 12 12 8.27 99.24
Production 2
(10+200)
3
Total 30,010.80 99.24
Sub base 1 Dozer(59281) 1 11.17 2272 25,378.24 Laborer 1 1.00 11.17 12 8.27 99.24
Production 2 operator 1 1.00 11.17 12 71.17 854.04
(21+00)
3
Total 25,378.24 953.28
Sub base 1 Dozer(59282) 1 10.50 2272 23,856.00 Laborer 1 1.00 10.5 12 8.27 99.24
Production 2 operator 1 1.00 10.5 12 71.17 854.04
(10+200)
3
Total 23,856.00 953.28
Sub base 1 Dozer(60005) 1 11.5 2272 26,128.000 Laborer 1 1.00 11.5 12 8.27 99.240 Dynamite
Production 2 operator 1 1.00 11.5 12 71.17 854.040 Blasting caps
(24+200)
3
Total 26,128.000 953.280
Borrow 1 Dozer(58830) 1 6.00 2272 13,632.00 Laborer 1 1.00 6 12 8.27 99.24
Production 2 operator 1 1.00 6 12 71.17 854.04
(10+200)
3
Total 13,632.00 953.28
1 Dozer(58829) 1 10.33 2272 23,469.760 Laborer 3 1.00 10.92 32.76 8.27 270.925 Dynamite
Quary rock
Production 2 Wagon drill 1 10.92 1200 13,104.000 operator 3 1.00 10.56 31.67 50.22 1,590.573 Blasting caps
(5+000) 3 Air compresor 1 10.42 450 4,689.000 Quary foreman 1 0.25 10.92 2.73 47.61 129.975
4
Total 41,262.760 1,991.473
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(59785) 5 15 12 3,582.000 foreman 1 1.00 12 12 47.61 571.320
Quary rock
Hauling (5+000) 2 D/Truck(59755) 5 12 9 2,149.200 operator 2 1.00 12 24 62.31 1,495.440
3 Loader(58545) 0.33 9.67 579 5,598.930
4 Loader(60049) 0.33 9.67 579 1,847.647
Total 13,177.777 2,166.000
Base course 1 Crusher(59268) 1 2 3600 7,200.000 Laborer 26 1.00 2 52 8.27 430.040
crushing
(5+000) 2 Crusher(45023) 1 1.58 3600 5,688.000 operator 2 1.00 1.79 3.58 47.99 171.804
Total 20,088.000 2,487.404
Concrete 1 Crusher(39502) 1 7.83 3600 28,188.000 operator 1 1.00 7.83 7.83 47.99 375.762
Aggregate
crushing 2 Laborer 10 1.00 7.83 78.3 8.27 647.541
(5+000)
3
Total 28,188.000 1,023.303
Total Sum 221,721.577 11,580.540
Date: 17/06/2014 Activity: Earthwork work
Actual cost
Equipment Man Power Material
Activity Equipment Hourly No of Hourly
Description Working Amount Working Man Hour Amount Material Quantity Unit
Description hy Hour (A) Rate C=(A*B) Trade Workers U.F Hour (E) F=(D*G) Indexed H=(F*G) Description Unit (I) Cost (J)
(With Plate No) (B) (D) Rate(G)
No
Borrow 1 Grader(60200) 1 2 1115 2,230.000 foreman 1 0.25 12 3 54.49 163.470
Placing(0+220- 2 Roller(0552) 1 4.42 810 3,580.200 Laborer 1 1.00 12 12 8.27 99.240
0+460)
3 W/Truck(60122) 1 1 300 300.000 operator 2 1.00 12 24 66.74 1,601.760
Total 6,110.200 1,864.470
1 Grader(60200) 1 10 1115 11,150.000 foreman 1 0.50 12 6 54.49 326.940
Sub base Placing
(3+200-3+580) 2 W/truck(60122) 1 7 300 2,100.000 Laborer 1 1.00 12 12 8.27 99.240
3 operator 2 1.00 12 24 66.74 1,601.760
Total 13,250.000 2,027.940
No. D/Truck Km No.Trip Capacity foreman 1 0.60 12 7.2 54.49 392.328
1 D/Truck(59973) 7.02 2 9 490.277 operator 4 1.00 12 48 62.31 2,990.880
Borrow Haulling
(10+200-3+180) 2 D/Truck(59926) 7.02 3 9 735.415 Laborer 1 1.00 12 12 8.27 99.240
3 D/Truck(59960) 7.02 3 9 735.415
4 D/Truck(58979) 7.02 3 12 980.554
Total 2,941.661 3,482.448
1 Loader(0396) 1 11.58 716 8,291.280 foreman 1 0.60 12 7.2 54.49 392.328
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(27958) 5.52 9 14 2,698.618
2 D/Truck(27593) 5.52 8 14 2,398.771
3 D/Truck(50143) 5.52 2 13.89 594.981
4 D/Truck(28854) 5.52 7 14.27 2,139.404
Borrow Haulling
(10+200-4+680) 5 D/Truck(27782) 5.52 5 14 1,499.232
6 D/Truck(28263) 5.52 1 14 299.846
7 D/Truck(54263) 5.52 10 18 3,855.168
8 D/Truck(58805) 5.52 7 16 2,398.771
9 D/Truck(53834) 5.52 5 16.74 1,792.653
10 D/Truck(58806) 5.52 10 16 3,426.816
11 D/Truck(62147) 5.52 5 14 1,499.232
Total 30,894.773 491.568
1 Loader(1376) 1 3.5 649 2,271.500 foreman 1 0.60 12 7.2 54.49 392.328
No. D/Truck Km No.Trip Capacity operator 7 1.00 12 84 62.31 5,234.040
1 D/Truck(28854) 21.14 1 14.27 1,170.471 Laborer 1 1.00 12 12 8.27 99.240
2 D/Truck(29177) 21.14 1 14 1,148.325
3 D/Truck(53834) 21.14 1 16.74 1,373.068
4 D/Truck(27782) 21.14 1 14 1,148.325
5 D/Truck(50143) 21.14 1 13.89 1,139.302
6 D/Truck(62147) 21.14 1 14 1,148.325
7 D/Truck(27958) 21.14 1 14 1,148.325
8 D/Truck(58806) 21.14 1 16 1,312.371
Lime Haulling
(24+400-3+260) 9 D/Truck(58805) 21.14 1 16 1,312.371
10 D/Truck(27593) 21.14 1 14 1,148.325
11 D/Truck(54263) 21.14 1 18 1,476.418
5 D/Truck(28263) 21.14 1 14 1,148.325
6 D/Truck(58979) 21.14 1 12 984.278
7 D/Truck(59960) 21.14 1 9 738.209
8 D/Truck(59973) 21.14 1 9 738.209
9 D/Truck(59738) 21.14 1 12 984.278
10 D/Truck(59926) 21.14 1 9 738.209
11 D/Truck(59940) 21.14 1 9 738.209
11 D/Truck(59752) 21.14 1 12 984.278
Total 22,851.121 5,725.608
No. D/Truck Km No.Trip Capacity foreman 1 0.60 12 7.2 54.49 392.328
1 D/Truck(29177) 7.24 1 14 393.277 operator 4 1.00 12 48 62.31 2,990.880
2 D/Truck(53834) 7.24 1 16.74 470.247 Laborer 1 1.00 12 12 8.27 99.240
3 D/Truck(27782) 7.24 1 14 393.277
4 D/Truck(50143) 7.24 1 13.89 390.187
1 D/Truck(62147) 7.24 1 14 393.277
2 D/Truck(27958) 7.24 1 14 393.277
Sub base 3 D/Truck(58805) 7.24 1 16 449.459
Haulling
(10+500-3+260) 4 D/Truck(58806) 7.24 1 16 449.459
5 D/Truck(27593) 7.24 1 14 393.277
6 D/Truck(54263) 7.24 1 18 505.642
7 D/Truck(28263) 7.24 1 14 393.277
8 D/Truck(59960) 7.24 1 9 252.821
9 D/Truck(59973) 7.24 1 9 252.821
10 D/Truck(59752) 7.24 1 12 337.094
11 D/Truck(59940) 7.24 1 9 252.821
Total 5,720.211 3,482.448
1 Excavator(0469) 1 5.50 1474 8,107.00 foreman 1 0.60 12 7.2 47.61 342.792
Under cut No. D/Truck Km No.Trip Capacity operator 3 1.00 12 36 62.31 2,243.160
Haulling 1 D/Truck(59973) 5 19 9 3,403 Laborer 1 1.00 12 12 8.27 99.240
(2+040-2+200)
2 D/Truck(59960) 5 21 9 3,761
3 D/Truck(59940) 5 20 9 3,582
Total 18,853 2,685.192
1 Excavator(0789) 1 7.00 1474 10,318 foreman 1 0.60 12 7.2 47.61 342.792
No. D/Truck Km No.Trip Capacity Laborer 12 1.00 12 144 8.27 1,190.880
1 D/Truck(59758) 5 1 12 238.8 operator 11 1.00 12 132 62.31 8,224.920
2 D/Truck(59741) 5 3 12 716.4
3 D/Truck(59759) 5 1 12 238.8
Cut to waste 4 D/Truck(58978) 5 1 12 238.8
(10+260- 5 D/Truck(59731) 5 1 12 238.8
10+300)
6 D/Truck(59751) 5 1 12 238.8
7 D/Truck(59741) 5 1 12 238.8
8 D/Truck(58980) 5 1 12 238.8
9 D/Truck(60111) 5 2 12 477.6
10 D/Truck(60117) 5 1 12 238.8
11 D/Truck(59788) 5 1 12 238.8
Total 13,661.200 9,758.592
1 Mixer(49110) 1 4.67 718.00 3,353.060 Foreman 1 1.00 12 12 54.49 653.880 cement qtl 99.94 235
Rigid Pavement 2 Mixer(49146) 1 2.83 718.00 2,031.940 Laborer 20 1.00 12 240 8.27 1,984.800 sand m3 11.05 700
(11+415- 3 Mixer(49149) 1 5.17 718.00 3,712.060 operator 3 0.50 12 18 31.51 567.180 Aggregate m3 23.67 650
11+480)
4 Mason 18 1.00 12 216 22.78 4,920.480
5
Total 9,097.060 8,126.340
1 Loader(0905) 1 12 716 8,592.000 foreman 1 0.50 12 6 54.49 326.940
2 Loader(1376) 1 5 649 3,245.000 Laborer 17 1.00 12 204 8.27 1,687.080
No. D/Truck Km No.Trip Capacity operator 13 1.00 12 156 62.31 9,720.360
1 D/Truck(59758) 5 13 12 3,104.400
2 D/Truck(59752) 5 10 12 2,388.000
3 D/Truck(58978) 5 9 12 2,149.200
4 D/Truck(59948) 5 13 9 2,328.300
Borrow Material 5 D/Truck(60117) 5 10 12 2,388.000
Haulling(10+080
-10+260) 6 D/Truck(59759) 5 8 12 1,910.400
7 D/Truck(59731) 5 12 12 2,865.600
8 D/Truck(59751) 5 11 12 2,626.800
9 D/Truck(58980) 5 10 12 2,388.000
10 D/Truck(59741) 5 12 12 2,865.600
11 D/Truck(60111) 5 9 12 2,149.200
12 D/Truck(59788) 5 11 12 2,626.800
13 D/Truck(58979) 5 4 12 955.200
Total 42,582.500 11,734.380
Borrow 1 Grader(59990) 1 11.5 1115 12,822.500 foreman 1 0.25 12 3 54.49 163.470
Placing(10+100- 2 Laborer 10 1.00 12 120 8.27 992.400
10+180)
3 operator 1 1.00 12 12 71.17 854.040
Total 12,822.500 2,009.910
1 Grader(55656) 1 11.5 1115 12,822.500 foreman 1 0.25 12 3 54.49 163.470
Sub base 2 Roller(0498) 1 6.58 810 5,329.800 Laborer 10 1.00 12 120 8.27 992.400
Placing(12+400-
12+600-12+600- 3 Roller(0283) 1 5.58 697 3,889.260 operator 2 1.00 12 24 66.74 1,601.760
12+740) 4 W/Truck(59807) 1 11.5 300 3,450.000
5
Total 25,491.560 2,757.630
Caaping No. D/Truck Km No.Trip Capacity foreman 1 0.60 12 7.2 54.49 392.328
Haulling 1 D/Truck(62148) 5 1 14 278.600 Laborer 10 1.00 12 120 8.27 992.400
(17+600- 2 D/Truck(34083) 5 1 13.67 272.033
17+800)
3 D/Truck(57038) 5 1 16.74 333.126
Total 883.759 1,384.728
1 Loader(0968) 1 8.17 716 5,849.720 foreman 1 0.50 12 6 54.49 326.940
No. D/Truck Km No.Trip Capacity Laborer 1 1.00 12 12 8.27 99.240
1 D/Truck(16834) 7.02 6 12.4 2,026.477
Sub base 2 D/Truck(28793) 7.02 6 13.94 2,278.153
haulling 4 D/Truck(62148) 7.02 5 14 1,906.632
(17+220- 5 D/Truck(57038) 7.02 4 16.74 1,823.830
10+200)
6 D/Truck(34083) 7.02 1 13.67 372.338
7 D/Truck(27783) 7.02 5 14 1,906.632
8 D/Truck(44662) 7.02 2 16.56 902.109
9 D/Truck(32940) 7.02 5 14 1,906.632
Total 18,972.523 426.180
1 Grader(59998) 1 11.08 1115 12,354.200 foreman 1 0.50 12 6 54.49 326.940
2 Grader(59992) 1 10.67 1115 11,897.050 Laborer 10 1.00 12 120 8.27 992.400
3 Grader(60025) 1 10.17 1115 11,339.550 operator 7 1.00 12 84 66.11 5,553.000
Sub base Placing 4 Roller(0292) 1 8 812 6,496.000
(17+220- 5 Roller(0620) 1 8.33 812 6,763.960
17+800-26+500- 6 Roller(0483) 1 9.75 810 7,897.500
26+720)
7 W/truck(59805) 1 11.5 300 3,450.000
8 W/truck(59801) 1 11.5 300 3,450.000
9 W/truck(59801) 1 11.5 300 3,450.000
10 W/truck(59831) 1 11.5 300 3,450.000
Total 70,548.260 6,872.340
Total Sum 294,680.328 62,829.774
Date: 10/06/2014 Activity: Structure construction
Actual cost
Equipment Man Power Material
Activity Equipment Hourly No of Hourly
Description Description Working Rate Amount Workers Working Man Hour Indexed Amount Material Quantity Unit
U.F Hour (A) C=(A*B) Trade U.F Hour (E) F=(D*G) H=(F*G) Description Unit (I) Cost (J)
No (With Plate No) (B) (D) Rate(G)
1 W/ truck (58998) 1.00 11.5 300 3,450.000 Foreman 2 1.00 12 24 54.49 1,307.760 cement qtl 54.00 185
2 Laborer 14 1.00 12 168 8.27 1,389.360 sand m3 11.28 350
Masonry 3 Mason 11 1.00 12 132 22.78 3,006.960 stone m3 30.42 500
construction
(18+480-900) 4 carpenter 2 1.00 12 24 22.78 546.720
5 L. Foreman 2 1.00 12 24 13.13 315.120
Masonry
construction
(18+480-900)
Total - -
1 Excavator(1149) 1 0 1474 -
No. D/Truck Km No.Trip Capacity
1 D/Truck(58978) 5 0 8 - Laborer 0 1.00 0 0 8.27 -
Excavation for 2 D/Truck(59758) 5 0 8 - foreman 1 0.50 0 0 43.46 -
open drain
(8+020-8+180) 3 D/Truck(59731) 5 0 8 - operator 6 1.00 0 0 43.89 -
4 D/Truck(59752) 5 0 8 -
5 D/Truck(59940) 5 0 8 -
6 D/Truck(58982) 5 0 8 -
Total - -
1 Loader(58555) 1.00 0 579 - Foreman 1 1.00 0 0 43.46 -
pipe Installation 2 Excavator(58756) 1.00 0 1326 - Laborer 15 1.00 0 0 8.27 -
(0+611) 3 operator 2 1.00 0 0 43.89 -
4 Mason 5 1.00 0 0 22.78 -
Total - -
1 Excavator(0815) 1.00 0 1900 - Foreman 1 0.33 0 0 43.46 -
Foundation 2 Labore 1 1.00 0 0 8.27 -
Excavation
(0+160,0+306) 3
4
Total - -
1 Loader(58546) 1.00 0 579 - Foreman 1 0.33 0 0 43.46 -
Class B bedding 2 Roller(58837) 1.00 0 550 - Labore 14 1.00 0 0 8.27 -
(17+741) 3 D/Truck(59755) 1.00 0 576 - operator 2 1.00 0 0 43.89 -
4
Total - -
1 Mixer(59976) 0.50 0 250 - Foreman 0 0.33 0 0 43.46 - cement qtl 0.00 185
2 Laborer 7 1.00 0 0 8.27 - sand m3 - 350
Class C concrete
(0+310-0+350) 3 carpenter 1 1.00 0 0 22.78 - Aggregate m3 - 600
4 Mason 3 1.00 0 0 22.78 -
5 L/ Foreman 1 1.00 0 0 13.13 -
Total - -
Total Sum 11,796.000 11,396.480
Grand sum
Revenue
Material
Total Direct 25% Net Amount
Cost Over Head Unit Rate Excuted Amount
Amount Total Cost (m) Quantity (n) o=(m*n)
K=(I*J) L=(C+H+K) Cost
-
- 291,627.647 282,162.429 (9,465.218)
Revenue
Material
Total Direct 25% Net Amount
Unit Rate Excuted Amount
Amount Cost Over Head Total Cost (m) Quantity (n) o=(m*n)
K=(I*J) L=(C+H+K) Cost
-
21,538.19 5384.548 26,922.740 26.42 540.00 14,266.800 (12,655.940)
-
23,485.007
7,731.906
15,384.915
63825.23 15956.307 79,781.535 1,426.08 77.35 110,307.288 30,525.753
46,601.828
-
46,601.828 505,139.912 739,595.602 234,455.690
Revenue
Material
Total Direct 25% Net Amount
Unit Rate Excuted Amount
Amount Cost Over Head Total Cost (m) Quantity (n) o=(m*n)
K=(I*J) L=(C+H+K) Cost
9,990.000
3,948.000
15,210.000
39,911.64 9,977.91 49,889.550 1,207.77 45.00 54,349.650 4,460.100
39,911.64 9,977.91 49,889.550 1,207.77 45.00 54,349.650 4,460.100
29,148.000
-
-
-
- - - 2,113.22 - - -
-
-
4,070.000
1,108.800
2,692.800
41,170.84 10,292.71 51,463.551 420.00 96.00 40,320.000 (11,143.551)
20,870.400
28,742.000
- - - 88.26 - - -
0 0 - 92.72 - - -
- - - 775.79 - - -
- - - 136.61 - - -
- - - 262.13 - - -
-
-
-
-
- - - 2,569.52 - - -
-
-
57,890.000 101,353.101 94,669.650 (6,683.451)
898,120.659 1,116,427.681 218,307.022
Cost Effectiveness Analysis
Date: 11/06/2014 Activity: Material Production
0
Equipment Man Power Material
Activity Equipment Hourly Hourly
Description Working Amount Working Man Hour Amount Material Quantity
Description U.F Hour (A) Rate C=(A*B) Trade U.F Hour (E) F=(D*G) Indexed H=(F*G) Description Unit (I)
No (With Plate No) (B) Rate(G)
Sub base 1 Dozer(0790) 1 11.83 2501 29,585.65 Laborer 1 1.00 11.83 11.83 8.27 97.83
Production 2
(10+200)
3
Total 29,585.65 97.83
Sub base 1 Dozer(59281) 1 11.25 2272 25,560.00 Laborer 1 1.00 11.25 12 8.27 99.24
Production 2 operator 1 1.00 11.25 12 71.17 854.04
(21+00)
3
Total 25,560.00 953.28
Sub base 1 Dozer(59282) 1 11.50 2272 26,128.00 Laborer 1 1.00 11.5 12 8.27 99.24
Production 2 operator 1 1.00 11.5 12 71.17 854.04
(10+200)
3
Total 26,128.00 953.28
Sub base 1 Dozer(60005) 1 11.5 2272 26,128.000 Laborer 1 1.00 11.5 12 8.27 99.240 Dynamite
Production 2 operator 1 1.00 11.5 12 71.17 854.040 Blasting caps
(24+200)
3
Total 26,128.000 953.280
Borrow 1 Dozer(58830) 1 5.00 2272 11,360.00 Laborer 1 1.00 5 12 8.27 99.24
Production 2 operator 1 1.00 5 12 71.17 854.04
(10+200)
3
Total 11,360.00 953.28
1 Dozer(58829) 1 10.08 2272 22,901.760 Laborer 3 1.00 10.08 30.24 8.27 250.085 Dynamite
Quary rock
Production 2 Wagon drill 1 8.67 1200 10,404.000 operator 3 1.00 9.22 27.67 50.22 1,389.680 Blasting caps
(5+000) 3 Air compresor 1 8.92 450 4,014.000 Quary foreman 1 0.25 10.08 2.52 47.61 119.977
4
Total 37,319.760 1,759.742
Revenue
Material
Total Direct 25% Net Amount
Unit Rate Excuted Amount
Unit Amount Cost Over Head Total Cost (m) Quantity (n) o=(m*n)
Cost (J) K=(I*J) L=(C+H+K) Cost
-
73,286.22 18,321.55 91,607.772 32.72 1,740.00 56,932.800 (34,674.972)
-
#REF! 372,218.753 1,225,273.337 853,054.584
Revenue
Material
Total Direct 25% Unit Rate Excuted Amount Net Amount
Unit Amount Cost Over Head Total Cost
L=(C+H+K) Cost (m) Quantity (n) o=(m*n)
Cost (J) K=(I*J)
185 2,886.000
350 1,166.760
500 3,910.000
18,959.08 4,739.77 23,698.850 1,207.77 12.00 14,493.240 (9,205.610)
7,962.760
185 -
350 -
600 -
- - - 2,113.22 - - -
21740 -
-
185 4,070.000
350 1,108.800
600 2,692.800
37,573.84 9,393.46 46,967.301 420.00 96.00 40,320.000 (6,647.301)
21740 20,870.400
28,742.000
0 0 - 92.72 - - -
- - - 775.79 - - -
- - - 136.61 - - -
- - - 262.13 - - -
-
185 -
350 -
600 -
- - - 2,569.52 - - -
-
-
36,704.760 73,916.751 67,522.680 (6,394.071)
648,325.632 1,408,753.967 760,428.335
Cost Effectiveness Analysis Summary
Note:
*Rental rates are used to calculate the cost of ERCC dump trucks
*Contract rates are used to calculate the cost of ERCC machineries other than dump trucks