Project : New Yangon Specialist Hospital Project Date : 30/12/2020

WORK SCHEDULE FOR CONSTRUCTION OF CONCRETE HOLLOW BLOCK ( PART-B )

Month-Year Month-Year Month-Year Month-Year Month-Year Month-Year


Estimated
No. Description Qty. Duration Week Week Week Week Week Week Week Week Week Week Week Week Remark
(m2) 1-2 3-4 1-2 3-4 1-2 3-4 1-2 3-4 1-2 3-4 1-2 3-4

A. Main Building ( Part B )

1 Ground Floor 850 30 days

2 2nd Floor 800 30 days

3 4th Floor 270 12 days

4 6th Floor 270 12 days

Please note that the above schedule is calculated by the working days duration, not including the waiting times.

And also note that the schedule is subject to the availability of working places given by Taisei Cooperation.