FACULTY OF CIVIL ENGINEERING AND BUILT ENVIRONMENT

DOUBLE-STOREY BUILDING CONSTRUCTION WORKS

GROUP PROJECT

COURSE CODE BFC43201


COURSE NAME MICROSOFT PROJECT
SEMESTER/SESSION 1 2022/2023
GROUP MEMBERS MUHAMMAD HASIQ BIN MD ANIS (AF190033)
MOHAMAD RASYID BIN ROSLY (AF190073)
MUHAMMAD ALIFF IMAN B SHAMSUDIN (AF190161)
MUHAMMAD HAIQAL RAFIQ BIN ROSLI (AF190027)
NUR IZZATI BINTI MOHD BASRI (AF190181)
GROUP 3
SECTION 4
LECTURER’S NAME ENCIK ISHAM BIN ISMAIL
SUBMISSION DATE 20 DECEMBER 2022
1.0 INTRODUCTION
Over the century, there were lots of successful projects have been done in the
construction industry. The management of a project must be well-organized and on
schedule if it is to be successful. By minimising the expense of making a mistake that
could delay the project, this aids in finishing it within the allotted time. Project
management in construction aids in keeping the entire construction process well-
organized, from planning and design to resource management, budget management,
and more.
Project management in the construction industry entails managing each
component of the project throughout its life cycle, including its conception, planning,
execution, monitoring, and control phases. Applying Microsoft Project to the project
management of construction helps reduce errors by ensuring that this phase goes off
without a hitch.A project manager can use Microsoft Project to help with scheduling,
allocating resources to projects, monitoring progress, controlling costs, and analysing
workloads. Microsoft Project software will be used in this project report to
accomplish goals and gain practical knowledge with how to use Microsoft Project for
project management.

1.1 Project Background


In this project, the Double Storey Terrace at Taman Putera Indah Tongkang
Pecah Batu Pahat Johor Bahru was proposed with a cost estimation of RM1 396 000.
The estimated duration of this project is above 8 months which will be started on 1st
January 2023 and expected to be done on 29th December 2024. This project will
involve the site supervisor, project manager, civil engineer, and mechanical and
electrical engineering with above 100 men power. Working hour for this project is
from 8.00 am to 6.00 pm with 1 hour of rest.

Figure 1.1: Location of the project

1
NO PUBLIC HOLIDAY DATE DAY
1. Chinese New Year Day 22/1/23 Sunday
2. 2nd Chinese New Year Day 23/1/23 Monday
3. Thaipusam Day 5/2/23 Sunday
4. Sultan Johor Birthday 23/3/23 Thursday
5. Ramadan Mubarak Day 23/3/23 Thursday
6. Aidilfitri Day 22/4/23 Sunday
7. 2 AidilfitriDay 23/4/23 Monday
nd

8. Labour Day 1/5/23 Monday


9. Wesak Day 4/5/23 Thursday
10. Birthday of Seri Paduka Baginda Yang di-Pertuan Agong 5/6/23 Monday
11. Hari Raya Qurban 29/6/23 Thursday
12. Ma’al Hijrah 19/7/23 Wednesday
13. Hari Hol Almarhum Sultan Iskandar 23/8/23 Wednesday
14. Malaysia’s National Day 31/8/23 Thursday
15. Malaysia Day 16/9/23 Saturday
16. Maulidur Rasul 28/9/23 Thursday
17. Deepavali Day 12/11/23 Sunday
18. Christmas Day 24/12/23 Sunday
19. New Year Eve 1/1/24 Monday
20. Chinese New Year 22/1/24 Monday
21. 2nd Chinese New Year Day 23/1/24 Tuesday
22. Thaipusam Day 5/2/24 Monday

Table 1.1: Johor’s Public Holiday 2023-2024

2
1.2 Scope of Project
We are required to prepare a building construction proposal for this project. The work
breakdown structure (WBS), working time, duration estimation table, Gantt chart, and
comparison of physical and financial S-curves are all part of the project's scope. We
decided to create a three-story bungalow for our building construction project. This
project's work breakdown structure (WBS) contains up to four levels, a cost of at least
RM 800,000, and a construction time of at least (8) months. The minimum list of
activities necessary to finish the project is 80 activities, with a maximum list of 100
activities. The physical and financial S-curves will be shown in weekly percentages,
whilst the cash flow report will be presented in quarterly cash flow.

1.2.1 Objectives
The project's objectives are as follows:
i. To make sure the project requires a minimum of 80 activities and a maximum of
100 activities with at least four (4) levels of WBS.
ii. To ensure that the project's minimal cost is RM800,000.00.
iii. To make sure that the minimum project duration is eight (8) months.

1.2.2 Progress of the project


Microsoft Project contains the intended project, which aids a project manager in
setting a timetable, allocating task resources, tracking project progress, managing the
budget, and assessing workloads. Project managers can use Microsoft Project to
handle the projects.

3
2.0 METHODOLOGY

Microsoft Project is useful to create a detailed project plan and manage resources by
requesting and assigning tasks. This method is intended to make the construction process
more efficient and far more practicable for all parties involved. Figure below illustrates the
steps of using this software.

Determine the objectives


and project requirement

Planning and estimating the


project duration and cost

Implement data into


Microsoft Project

Applying the Work Breakdown


Structure (WBS), Gantt Chart, and
S-Curve

Comparison of physical and


financial S-Curve

Data analysis

Figure 2.1: Flowchart of Microsoft Project.

4
With the aid of the Work Breakdown Structure (WBS) project management tool, it divides
the project into manageable bits, making it less overwhelming and more controllable.
Determine the objectives and project requirement Planning and estimating the project
duration and cost Implement data into Microsoft Project Applying the Work Breakdown
Structure (WBS), Gantt Chart, and S-Curve Comparison of physical and financial S-Curve
Data analysis 5 Moreover, it serves as a road map for the various teams involved in the
project in completing their specific tasks. Furthermore, a WBS is an excellent tool to measure
work progress, classify milestones, and allocate budget resources. Figure below shows the
steps in creating WBS.

Determine the project

Set project boundaries

Identify project deliverable

Define level 1 elements

Break down each of the Level


1 elements

Identify team members

5
Set project boundaries

Figure 2.2: Steps of creating the WBS

6
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
1 1 Proposed to Build Double 590 days Sun 1/1/23 Sun 12/29/24
Storey Terrace at Taman
Putera Indah Tongkang Pecah
Batu Pahat Johor
2 1.1 Project Start 0 days Sun 1/1/23 Sun 1/1/23
3 1.2 Planning 337 days Sun 1/1/23 Fri 2/23/24 2
4 1.2.1 Detailed Drawing 20 days Sun 1/1/23 Fri 1/27/23 2SS
5 1.2.2 Budget 15 days Wed 1/25/23 Mon 2/13/23 4
6 1.2.3 Schedule 7 days Tue 2/14/23 Tue 2/21/23 5
7 1.2.4 Bidding 10 days Wed 2/22/23 Sun 3/5/23 6
8 1.2.5 Preliminaries Work 319 days Wed 1/25/23 Fri 2/23/24 2
9 1.2.5.1 Performance Bond and 2 days Mon 3/6/23 Tue 3/7/23 7
Insurance
10 1.2.5.2 Temporary Facilities 10 days Wed 3/8/23 Sun 3/19/23 9
11 1.2.5.3 Site cleaning 7 days Mon 3/20/23 Wed 3/29/23 10
12 1.2.5.4 Site Investigation 5 days Wed 3/29/23 Tue 4/4/23 11
13 1.2.5.5 Retaining System 9 days Wed 4/5/23 Fri 4/14/23 12
14 1.2.5.6 Haording Installation 2 days Sun 4/16/23 Mon 4/17/23 13
15 1.2.5.7 Excavation 5 days Tue 4/18/23 Wed 4/26/23 14 Excavation team
16 1.2.5.8 Monthly Report and 319 days Wed 1/25/23 Fri 2/23/24
Progress Photograph
31 1.3 Building Works Phase 1 239 days Tue 4/18/23 Mon 2/12/24
32 1.3.1 Relocation services 5 days Tue 4/18/23 Wed 4/26/23 14
(Client work)

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
33 1.3.2 Sub structure 41 days Tue 4/25/23 Thu 6/15/23
34 1.3.2.1 Piling and Pile Cap 4 days Tue 4/25/23 Fri 4/28/23 15 Structural team
35 1.3.2.2 Stump 29 days Tue 5/9/23 Thu 6/15/23 34 Structural team
36 1.3.3 Super structure 197 days Wed 6/14/23 Mon 2/12/24 Excavation team
37 1.3.3.1 Ground Floor 29 days Wed 6/14/23 Fri 7/21/23
38 1.3.3.1.1 Formwork Installation5 days Wed 6/14/23 Mon 6/19/23 35 Structural team
39 1.3.3.1.2 Rebar Installation 5 days Tue 6/20/23 Sun 6/25/23 38 Structural team
40 1.3.3.1.3 Column 5 days Mon 6/26/23 Mon 7/3/23 39 Structural team
41 1.3.3.1.4 Beam and Slab 8 days Sun 7/2/23 Tue 7/11/23 40 Structural team
42 1.3.3.1.5 Brickwalls 0 days Wed 7/12/23 Wed 7/12/23 41
43 1.3.3.1.6 Staircase 6 days Wed 7/12/23 Thu 7/20/23 42 Structural team
44 1.3.3.1.7 Dismantle of Formwork2 days Thu 7/20/23 Fri 7/21/23 43 Structural team
45 1.3.3.2 First Floor 37 days Sun 7/23/23 Tue 9/5/23
46 1.3.3.2.1 Formwork Installation5 days Sun 7/23/23 Thu 7/27/23 44 Structural team
47 1.3.3.2.2 Rebar Installation 5 days Thu 7/27/23 Wed 8/2/23 46 Structural team
48 1.3.3.2.3 Column 5 days Thu 8/3/23 Tue 8/8/23 47 Structural team
49 1.3.3.2.4 Beam and Slab 8 days Wed 8/9/23 Thu 8/17/23 48 Structural team
50 1.3.3.2.5 Brickwalls 5 days Sun 8/20/23 Thu 8/24/23 49 Masonry team
51 1.3.3.2.6 Staircase 6 days Thu 8/24/23 Fri 9/1/23 50 Structural team
52 1.3.3.2.7 Dismantle of Formwork2 days Mon 9/4/23 Tue 9/5/23 51 Structural team
53 1.3.3.3 Second Floor 29 days Mon 9/4/23 Tue 10/10/23 Masonry team
54 1.3.3.3.1 Formwork Installation5 days Mon 9/4/23 Fri 9/8/23 52 Structural team
55 1.3.3.3.2 Rebar Installation 5 days Sun 9/10/23 Sun 9/17/23 54 Structural team

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
56 1.3.3.3.3 Column 5 days Sun 9/17/23 Thu 9/21/23 55 Structural team
57 1.3.3.3.4 Beam and Slab 8 days Sun 9/24/23 Wed 10/4/23 56 Structural team
58 1.3.3.3.5 Brickwalls 5 days Mon 10/2/23 Sun 10/8/23 57 Masonry team
59 1.3.3.3.6 Dismantle of Formwork
2 days Mon 10/9/23 Tue 10/10/23 58 Structural team
60 1.3.3.4 Roof 20 days Wed 10/11/23 Thu 11/2/23
61 1.3.3.4.1 Roof beam 6 days Wed 10/11/23 Tue 10/17/23 59 Roofing team
62 1.3.3.4.2 Roof truss 8 days Wed 10/18/23 Fri 10/27/23 61 Roofing team
63 1.3.3.4.3 Roof Installation 5 days Sun 10/29/23 Thu 11/2/23 62 Roofing team
64 1.3.3.5 Mechanical and 15 days Sun 11/5/23 Tue 11/21/23
Electrical Works
65 1.3.3.5.1 Plumbing 5 days Sun 11/5/23 Thu 11/9/23 63 Service team
66 1.3.3.5.2 Electrical 5 days Thu 11/9/23 Tue 11/14/23 65 Service team
67 1.3.3.5.3 Fire Protection 3 days Wed 11/15/23 Fri 11/17/23 66 Service team
Installation
68 1.3.3.5.4 HVAC System 3 days Sun 11/19/23 Tue 11/21/23 67 Service team
69 1.3.3.6 Finishes 55 days Wed 11/22/23 Fri 1/26/24
70 1.3.3.6.1 Plastering 10 days Wed 11/22/23 Sun 12/3/23 68 Masonry team
71 1.3.3.6.2 Floor Screeding 10 days Mon 12/4/23 Thu 12/14/23 70 Architecture Floor
72 1.3.3.6.3 Ceiling 6 days Sun 12/17/23 Fri 12/22/23 71 Architecture Ceiling
73 1.3.3.6.4 Tiling 15 days Sun 12/24/23 Sun 1/14/24 72 Architecture Floor
74 1.3.3.6.5 Door and Window 5 days Sun 1/14/24 Thu 1/18/24 73 Architecture Door and
Installaion Window
75 1.3.3.6.6 Painting 8 days Thu 1/18/24 Fri 1/26/24 74 Others
76 1.3.3.7 External Works 168 days Sun 7/23/23 Mon 2/12/24

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
77 1.3.3.7.1 Ramp and Apron 3 days Wed 1/31/24 Fri 2/2/24 75 Others
78 1.3.3.7.2 Drainage 5 days Sun 7/23/23 Thu 7/27/23 44 Others
79 1.3.3.7.3 Access Road 3 days Sun 2/4/24 Tue 2/6/24 77 Others
80 1.3.3.7.4 Landscape 5 days Wed 2/7/24 Mon 2/12/24 79 Others
81 1.4 Building Works Phase 2 502 days Tue 4/18/23 Sun 12/29/24
82 1.4.1 Relocation services 5 days Tue 4/18/23 Wed 4/26/23 80
(Client work)
83 1.4.2 Sub structure 41 days Tue 4/25/23 Thu 6/15/23
84 1.4.2.1 Piling and Pile Cap 4 days Tue 4/25/23 Fri 4/28/23 82 Structural team
85 1.4.2.2 Stump 29 days Tue 5/9/23 Thu 6/15/23 84 Structural team
86 1.4.3 Super structure 460 days Wed 6/14/23 Sun 12/29/24 Excavation team
87 1.4.3.1 Ground Floor 29 days Wed 6/14/23 Fri 7/21/23
88 1.4.3.1.1 Formwork Installation5 days Wed 6/14/23 Mon 6/19/23 85 Structural team
89 1.4.3.1.2 Rebar Installation 5 days Tue 6/20/23 Sun 6/25/23 88 Structural team
90 1.4.3.1.3 Column 5 days Mon 6/26/23 Mon 7/3/23 89 Structural team
91 1.4.3.1.4 Beam and Slab 8 days Sun 7/2/23 Tue 7/11/23 90 Structural team
92 1.4.3.1.5 Brickwalls 0 days Wed 7/12/23 Wed 7/12/23 91
93 1.4.3.1.6 Staircase 6 days Wed 7/12/23 Thu 7/20/23 92 Structural team
94 1.4.3.1.7 Dismantle of Formwork2 days Thu 7/20/23 Fri 7/21/23 93 Structural team
95 1.4.3.2 First Floor 37 days Sun 7/23/23 Tue 9/5/23
96 1.4.3.2.1 Formwork Installation5 days Sun 7/23/23 Thu 7/27/23 94 Structural team
97 1.4.3.2.2 Rebar Installation 5 days Thu 7/27/23 Wed 8/2/23 96 Structural team
98 1.4.3.2.3 Column 5 days Thu 8/3/23 Tue 8/8/23 97 Structural team
99 1.4.3.2.4 Beam and Slab 8 days Wed 8/9/23 Thu 8/17/23 98 Structural team
Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
100 1.4.3.2.5 Brickwalls 5 days Sun 8/20/23 Thu 8/24/23 99 Masonry team
101 1.4.3.2.6 Staircase 6 days Thu 8/24/23 Fri 9/1/23 100 Structural team
102 1.4.3.2.7 Dismantle of Formwork2 days Mon 9/4/23 Tue 9/5/23 101 Structural team
103 1.4.3.3 Second Floor 29 days Mon 9/4/23 Tue 10/10/23 Masonry team
104 1.4.3.3.1 Formwork Installation5 days Mon 9/4/23 Fri 9/8/23 102 Structural team
105 1.4.3.3.2 Rebar Installation 5 days Sun 9/10/23 Sun 9/17/23 104 Structural team
106 1.4.3.3.3 Column 5 days Sun 9/17/23 Thu 9/21/23 105 Structural team
107 1.4.3.3.4 Beam and Slab 8 days Sun 9/24/23 Wed 10/4/23 106 Structural team
108 1.4.3.3.5 Brickwalls 5 days Mon 10/2/23 Sun 10/8/23 107 Masonry team
109 1.4.3.3.6 Dismantle of Formwork2 days Mon 10/9/23 Tue 10/10/23 108 Structural team
110 1.4.3.4 Roof 20 days Wed 10/11/23 Thu 11/2/23
111 1.4.3.4.1 Roof beam 6 days Wed 10/11/23 Tue 10/17/23 109 Roofing team
112 1.4.3.4.2 Roof truss 8 days Wed 10/18/23 Fri 10/27/23 111 Roofing team
113 1.4.3.4.3 Roof Installation 5 days Sun 10/29/23 Thu 11/2/23 112 Roofing team
114 1.4.3.5 Mechanical and 15 days Sun 11/5/23 Tue 11/21/23
Electrical Works
115 1.4.3.5.1 Plumbing 5 days Sun 11/5/23 Thu 11/9/23 113 Service team
116 1.4.3.5.2 Electrical 5 days Thu 11/9/23 Tue 11/14/23 115 Service team
117 1.4.3.5.3 Fire Protection 3 days Wed 11/15/23 Fri 11/17/23 116 Service team
Installation
118 1.4.3.5.4 HVAC System 3 days Sun 11/19/23 Tue 11/21/23 117 Service team
119 1.4.3.6 Finishes 331 days Wed 11/22/23 Sun 12/29/24
120 1.4.3.6.1 Plastering 10 days Wed 11/22/23 Sun 12/3/23 118 Masonry team
121 1.4.3.6.2 Floor Screeding 10 days Mon 12/4/23 Thu 12/14/23 120 Architecture Floor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
ID Task WBS Task Name Duration Start Finish Predecessors Resource Names Qtr 4, 2022
Mode Dec
122 1.4.3.6.3 Ceiling 6 days Sun 12/17/23 Fri 12/22/23 121 Architecture Ceiling
123 1.4.3.6.4 Tiling 15 days Sun 12/24/23 Sun 1/14/24 122 Architecture Floor
124 1.4.3.6.5 Door and Window 5 days Sun 1/14/24 Thu 1/18/24 123 Architecture Door and
Installaion Window
125 1.4.3.6.6 Painting 17 days Thu 1/18/24 Sun 12/29/24 124 Others
126 1.4.3.7 External Works 168 days Sun 7/23/23 Mon 2/12/24
127 1.4.3.7.1 Ramp and Apron 3 days Wed 1/31/24 Fri 2/2/24 125 Others
128 1.4.3.7.2 Drainage 5 days Sun 7/23/23 Thu 7/27/23 94 Others
129 1.4.3.7.3 Access Road 3 days Sun 2/4/24 Tue 2/6/24 127 Others
130 1.4.3.7.4 Landscape 5 days Wed 2/7/24 Mon 2/12/24 129 Others
131 1.5 Testing and Commisioning 4 days Tue 2/13/24 Sun 2/18/24
132 1.5.1 RI Inspection 4 days Tue 2/13/24 Fri 2/16/24 80,130
133 1.5.2 Certificate of Statutory 0 days Sun 2/18/24 Sun 2/18/24 132
Completion (CSC)
134 1.6 Project Finish 0 days Sun 2/18/24 Sun 2/18/24 133
135 1.7 Project Handover 0 days Sun 2/18/24 Sun 2/18/24 134

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

1/1

Excavation team

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

Structural team
Structural team

Structural team
Structural team
Structural team
Structural team
7/12
Structural team
Structural team

Structural team
Structural team
Structural team
Structural team
Masonry team
Structural team
Structural team

Structural team
Structural team

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Structural team
Structural team
Masonry team
Structural team

Roofing team
Roofing team
Roofing team

Service team
Service team
Service team

Service team

Masonry team
Architecture Floor
Architecture Ceiling
Architecture Floor
Architecture Door and Window

Others

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Others
Others
Others
Others

Structural team
Structural team

Structural team
Structural team
Structural team
Structural team
7/12
Structural team
Structural team

Structural team
Structural team
Structural team
Structural team

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 10
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Masonry team
Structural team
Structural team

Structural team
Structural team
Structural team
Structural team
Masonry team
Structural team

Roofing team
Roofing team
Roofing team

Service team
Service team
Service team

Service team

Masonry team
Architecture Floor

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 11
Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
Architecture Ceiling
Architecture Floor
Architecture Door and Window

Others

Others
Others
Others
Others

2/18

2/18
2/18

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: MS PROJECT ASSIGNM
Summary Manual Summary Rollup Progress
Date: Sun 12/18/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 12
4.0 DATA AND RESULT

4.1 Work Breakdown Structure

No. of Duration Cost


Level 1 Level 2 Level 3 Level 4
Activities (days) (RM)
Proposed to Project
1 Build Double 0
Start
Storey Terrace Detailed
2 at Tongkang Drawing 20 100000
Pecah, Taman
3 Batu Pahat, Budget 15
Planning
4 Johor Schedule 7
5 Bidding 10
Performance
6 Bond and 2 35000
Insurance
Temporary
7 Facilities 10 10000
8 Site cleaning 7 12000
Preliminaries Site
9 Work Investigation 5 10000
Retaining
10 System 9 11000
Hoarding
11 Installation 2 2000
12 Excavation 5 5000
Monthly Report
14 and Progress 1 1000
Photograph 1
Monthly Report
15 and Progress 1 1000
Photograph 2
Monthly Report
16 and Progress 1 1000
Photograph 3
Monthly
Report and Monthly Report
Progress and Progress
17 Photograph 1 1000
Photograph 4

Monthly Report
18 and Progress 1 1000
Photograph 5
Monthly
19 Report and 1 1000
Progress

16
Photograph 6
Monthly
Report and
20 1 1000
Progress
Photograph 7
Monthly
Report and
21 1 1000
Progress
Photograph 8
Monthly
Report and
22 1 1000
Progress
Photograph 9
Monthly
Report and
23 1 1000
Progress
Photograph 10
Monthly
Report and
24 1 1000
Progress
Photograph 11
Monthly
Report and
25 1 1000
Progress
Photograph 12
Monthly
Report and
26 1 1000
Progress
Photograph 13
Monthly
Report and
27 1 1000
Progress
Photograph 14
Relocation
28 services 5 2500
(Client work)
Piling and Pile
29 4 21000
Cap
30 Stump 29 16000
Formwork
31 Building Works 5 2000
Installation
Phase 1
Rebar
32 5 10000
Installation
Ground Floor
33 Column 5 10000
Beam and
34 8 10000
Slab
35 Brick walls 0 16000

17
36 Staircase 6 13000
Dismantle
of 10000
37 2
Formwork
Formwork
38 Installation 5 2000
Rebar
39 Installation 5 10000
40 Column 5 10000
Beam and
41 First Floor 8 10000
Slab
42 Brick walls 5 16000
43 Staircase 6 13000
Dismantle
of
44 2 10000
Formwork
Formwork
45 Installation 5 2000
Rebar
46 Installation 5 10000
47 Column 5 10000
Second Floor Beam and
48 Slab 8 10000
49 Brick walls 5 16000
Dismantle
of
50 2 10000
Formwork
51 Roof beam 6 5000
52 Roof truss 8 15000
Roof
Roof
53 Installation 5 20000

54 Plumbing 5 18000

55 Electrical 5 20000
Mechanical
and Electrical Fire
56 Works Protection 3 10000
Installation
HVAC
57 3 12000
System
1
58 Plastering 40000
0
Floor 1 35000
59 Screeding
Finishes 0

60 Ceiling 6 30000
1
61 Tiling 30000
5

18
Door and
62 Window 5 36000
Installation

63 Painting 8 15000
Ramp and
64 Apron 3 15000
Drainage 5 10000
65
External Works
Access Road 3 15000
66
Landscape 5 25000
67
Relocation
68 Services (Client 5 2500
work)
Piling and Pile
69 Cap 4 21000

70 Stump 29 16000
Formwork
71 Installation 5 2000
Rebar
72 Installation 5 10000

73 Column 5 10000
Beam and
74 Ground Floor 8 10000
Slab

75 Building Works Brick Walls 0 16000


Phase 2
76 Staircase 6 13000
Dismantle of
77 Formwork 2 10000
Formwork
78 Installation 5 2000
Rebar
79 Installation 5 10000

80 Column 5 10000
Beam and
81 First Floor 8 10000
Slab

82 Brick Walls 5 16000

83 Staircase 6 13000
Dismantle of
84 Formwork 2 10000

19
Formwork
85 Installation 5 2000
Rebar
86 Installation 5 10000

87 Column 5 10000
Second Floor
Beam and
88 Slab 8 10000

89 Brick Walls 5 16000


Dismantle of
90 Formwork 2 10000

91 Roof Beam 6 5000


92 Roof Roof Truss 8 15000
Roof
93 Installation 5 20000
94 Plumbing 5 18000
95 Electrical 5 20000
Mechanical
Fire
and Electrical
96 Works Protection 3 10000
Installation
HVAC
97 3 12000
System
98 Plastering 10 40000
Floor
99 10 35000
Screeding
100 Ceiling 6 30000
101 Finishes Tiling 15 30000
Door and
102 Window 5 36000
Installation
103 Painting 8 15000
Ramp and
104 Apron 3 15000
105 External Works Drainage 5 10000
106 Access Road 3 15000
107 Landscape 5 25000
108 RI Inspection 4 18000
Certificate of
Testing and
Statutory
109 Commissioning 0
Completion
(CSC)
Project
110 Project Finish 0
Handover
Total Cost (RM) 1396000

20
4.2 Task Duration Estimation

Act. Act. Act. %


Task Name Act. Cost Act. Work
Duration Start Finish Comp.
Proposed to
Build double
storey terrace at
590 Sun Sun
Tongkang 100% RM1,396,000.00 3,376 hrs
days 1/1/23 12/29/24
Pecah, Taman
Batu Pahat,
Johor
Sun Sun
Project Start 0 days 100% RM0.00 0 hrs
1/1/23 1/1/23
337 Sun Fri
Planning days 100% RM197,000.00 40 hrs
1/1/23 2/23/24
Detailed Sun Fri
20 days 100% RM0.00 0 hrs
Drawing 1/1/23 1/27/23
Wed Mon
Budget 15 days 100% RM0.00 0 hrs
1/25/23 2/13/23
Tue Tue
Schedule 7 days 100% RM0.00 0 hrs
2/14/23 2/21/23
Wed Sun
Bidding 10 days 100% RM0.00 0 hrs
2/22/23 3/5/23
Preliminaries 319 Wed Fri
100% RM97,000.00 40 hrs
Work days 1/25/23 2/23/24
Performance
Mon Tue
Bond and 2 days 100% RM35,000.00 0 hrs
3/6/23 3/7/23
Insurance
Temporary Wed Sun
10 days 100% RM10,000.00 0 hrs
Facilities 3/8/23 3/19/23
Mon Wed
Site cleaning 7 days 100% RM12,000.00 0 hrs
3/20/23 3/29/23
Wed Tue
Site Investigation 5 days 100% RM10,000.00 0 hrs
3/29/23 4/4/23
Retaining Wed Fri
9 days 100% RM11,000.00 0 hrs
System 4/5/23 4/14/23
Hoarding Sun Mon
2 days 100% RM2,000.00 0 hrs
Installation 4/16/23 4/17/23
Tue Wed
Excavation 5 days 100% RM5,000.00 40 hrs
4/18/23 4/26/23
Monthly Report
319 Wed Fri
and Progress 100% RM12,000.00 40 hrs
days 1/25/23 2/23/24
Photograph
Monthly Report
Wed Wed
and Progress 1 day 100% RM1,000.00 0 hrs
1/25/23 1/25/23
Photograph 1
Monthly Report
Thu Thu
and Progress 1 day 100% RM1,000.00 0 hrs
2/23/23 2/23/23
Photograph 2

21
Monthly Report
Fri Fri
and Progress 1 day 100% RM1,000.00 0 hrs
3/24/23 3/24/23
Photograph 3
Monthly Report
Tue Tue
and Progress 1 day 100% RM1,000.00 0 hrs
4/25/23 4/25/23
Photograph 4
Monthly Report
Tue Tue
and Progress 1 day 100% RM1,000.00 0 hrs
5/23/23 5/23/23
Photograph 5
Monthly Report
Sun Sun
and Progress 1 day 100% RM1,000.00 0 hrs
6/25/23 6/25/23
Photograph 6
Monthly Report
Sun Sun
and Progress 1 day 100% RM1,000.00 0 hrs
7/23/23 7/23/23
Photograph 7
Monthly Report
Wed Wed
and Progress 1 day 100% RM1,000.00 0 hrs
8/23/23 8/23/23
Photograph 8
Monthly Report
Sun Sun
and Progress 1 day 100% RM1,000.00 0 hrs
9/24/23 9/24/23
Photograph 9
Monthly Report
Mon Mon
and Progress 1 day 100% RM1,000.00 0 hrs
10/23/23 10/23/23
Photograph 10
Monthly Report
Thu Thu
and Progress 1 day 100% RM1,000.00 0 hrs
Photograph 11 11/23/23 11/23/23
Monthly Report
Sun Sun
and Progress 1 day 100% RM1,000.00 0 hrs
12/24/23 12/24/23
Photograph 12
Monthly Report
Tue Tue
and Progress 1 day 100% RM1,000.00 0 hrs
1/23/24 1/23/24
Photograph 13
Monthly Report
Fri Fri
and Progress 1 day 100% RM1,000.00 0 hrs
2/23/24 2/23/24
Photograph 14
239 Tue Mon
Building Works 100% RM590,500.00 3,336
days 4/18/23 2/12/24
Phase 1 hrs
Relocation
Tue Wed
services (Client 5 days 100% RM2,500.00 0 hrs
4/18/23 4/26/23
work)
Tue Thu
Sub structure 41 days 100% RM37,000.00 264 hrs
4/25/23 6/15/23
Piling and Pile Tue Fri
4 days 100% RM21,000.00 32 hrs
Cap 4/25/23 4/28/23
Tue Thu
Stump 29 days 100% RM16,000.00 232 hrs
5/9/23 6/15/23
197 Wed Mon
Super structure days 100% RM551,000.00 3,072
6/14/23 2/12/24
hrs

22
Wed Fri
Ground Floor 29 days 100% RM71,000.00 248 hrs
6/14/23 7/21/23
Formwork Wed Mon
5 days 100% RM2,000.00 40 hrs
Installation 6/14/23 6/19/23
Rebar Tue Sun
5 days 100% RM10,000.00 40 hrs
Installation 6/20/23 6/25/23
Mon Mon
Column 5 days 100% RM10,000.00 40 hrs
6/26/23 7/3/23
Sun Tue
Beam and Slab 8 days 100% RM10,000.00 64 hrs
7/2/23 7/11/23
Wed Wed
Brickwalls 0 days 100% RM16,000.00 0 hrs
7/12/23 7/12/23
Wed Thu
Staircase 6 days 100% RM13,000.00 48 hrs
7/12/23 7/20/23
Dismantle of Thu Fri
2 days 100% RM10,000.00 16 hrs
Formwork 7/20/23 7/21/23
Sun Tue
First Floor 37 days 100% RM71,000.00 288 hrs
7/23/23 9/5/23
Formwork Sun Thu
5 days 100% RM2,000.00 40 hrs
Installation 7/23/23 7/27/23
Rebar Thu Wed
5 days 100% RM10,000.00 40 hrs
Installation 7/27/23 8/2/23
Thu Tue
Column 5 days 100% RM10,000.00 40 hrs
8/3/23 8/8/23
Wed Thu
Beam and Slab 8 days 100% RM10,000.00 64 hrs
8/9/23 8/17/23
Sun Thu
Brickwalls 5 days 100% RM16,000.00 40 hrs
8/20/23 8/24/23
Thu Fri
Staircase 6 days 100% RM13,000.00 48 hrs
8/24/23 9/1/23
Dismantle of Mon Tue
2 days 100% RM10,000.00 16 hrs
Formwork 9/4/23 9/5/23
Mon Tue
Second Floor 29 days 100% RM58,000.00 480 hrs
9/4/23 10/10/23
Formwork Mon Fri
5 days 100% RM2,000.00 40 hrs
Installation 9/4/23 9/8/23
Rebar Sun Sun
5 days 100% RM10,000.00 40 hrs
Installation 9/10/23 9/17/23
Sun Thu
Column 5 days 100% RM10,000.00 40 hrs
9/17/23 9/21/23
Sun Wed
Beam and Slab 8 days 100% RM10,000.00 64 hrs
9/24/23 10/4/23
Mon Sun
Brickwalls 5 days 100% RM16,000.00 40 hrs
10/2/23 10/8/23
Dismantle of Mon Tue
2 days 100% RM10,000.00 16 hrs
Formwork 10/9/23 10/10/23
Wed Thu
Roof 20 days 100% RM40,000.00 152 hrs
10/11/23 11/2/23

23
Wed Tue
Roof beam 6 days 100% RM5,000.00 48 hrs
10/11/23 10/17/23
Wed Fri
Roof truss 8 days 100% RM15,000.00 64 hrs
10/18/23 10/27/23
Sun Thu
Roof Installation 5 days 100% RM20,000.00 40 hrs
10/29/23 11/2/23
Mechanical and
Sun Tue
Electrical 15 days 100% RM60,000.00 128 hrs
11/5/23 11/21/23
Works
Sun Thu
Plumbing 5 days 100% RM18,000.00 40 hrs
11/5/23 11/9/23
Thu Tue
Electrical 5 days 100% RM20,000.00 40 hrs
11/9/23 11/14/23
Fire Protection Wed Fri
3 days 100% RM10,000.00 24 hrs
Installation 11/15/23 11/17/23
Sun Tue
HVAC System 3 days 100% RM12,000.00 24 hrs
11/19/23 11/21/23
Wed Fri
Finishes 55 days 100% RM186,000.00 432 hrs
11/22/23 1/26/24
Wed Sun
Plastering 10 days 100% RM40,000.00 80 hrs
11/22/23 12/3/23
Mon Thu
Floor Screeding 10 days 100% RM35,000.00 80 hrs
12/4/23 12/14/23
Sun Fri
Ceiling 6 days 100% RM30,000.00 48 hrs
12/17/23 12/22/23
Sun Sun
Tiling 15 days 100% RM30,000.00 120 hrs
12/24/23 1/14/24
Door and Window Sun Thu
5 days 100% RM36,000.00 40 hrs
Installation 1/14/24 1/18/24
Thu Fri
Painting 8 days 100% RM15,000.00 64 hrs
1/18/24 1/26/24
168 Sun Mon
External Works days 100% RM65,000.00 128 hrs
7/23/23 2/12/24
Wed Fri
Ramp and Apron 3 days 100% RM15,000.00 24 hrs
2/31/24 2/2/24
Sun Thu
Drainage 5 days 100% RM10,000.00 40 hrs
7/23/23 7/27/23
Sun Tue
Access Road 3 days 100% RM15,000.00 24 hrs
2/4/24 2/6/24
Wed Mon
Landscape 5 days 100% RM25,000.00 40 hrs
2/7/24 2/12/24
Building Works Tue Sun
502 days 100% RM 590,500.00 3,336 hrs
Phase 2 4/18/23 12/29/24
Relocation
Tue Wed RM 2,500.00 0 hrs
Services (Client 5 days 100%
4/18/23 4/26/23
work)
Tue Thu
Sub structure 41 days 100% RM 37,000.00 264 hrs
4/25/23 6/15/23

24
Piling and Pile Tue Fri
4 days 100% RM 21,000.00 32 hrs
Cap 4/25/23 4/28/23
Tue Thu
Stump 29 days 100% RM 16,000.00 232 hrs
5/9/23 6/15/23
Wed Sun
Super structure 460 days 100% RM 551,000.00 3,072 hrs
6/14/23 12/29/24
Wed Fri
Ground Floor 29 days 100% RM 71,000.00 248 hrs
6/14/23 7/21/23
Formwork Wed Mon
5 days 100% RM 2,000.00 40 hrs
Installation 6/14/23 6/19/23
Tue Sun
Rebar Installation 5 days 100% RM 10,000.00 40 hrs
6/20/23 6/25/23
Mon Mon
Column 5 days 100% RM 10,000.00 40 hrs
6/26/23 7/3/23
Sun Tue
Beam and Slab 8 days 100% RM 10,000.00 64 hrs
7/2/23 7/11/23
Wed Wed
Brickwalls 0 days 100% RM 16,000.00 0 hrs
7/12/23 7/12/23
Wed Thu
Staircase 6 days 100% RM 13,000.00 48 hrs
7/12/23 7/20/23
Dismantle of Thu Fri
2 days 100% RM 10,000.00 16 hrs
Formwork 7/20/23 7/21/23
Sun Tue
First Floor 37 days 100% RM 71,000.00 288 hrs
7/23/23 9/5/23
Formwork Sun Thu
5 days 100% RM 2,000.00 40 hrs
Installation 7/23/23 7/27/23
Thu Wed
Rebar Installation 5 days 100% RM 10,000.00 40 hrs
7/27/23 8/2/23
Thu Tue
Column 5 days 100% RM 10,000.00 40 hrs
8/3/23 8/8/23
Wed Thu
Beam and Slab 8 days 100% RM 10,000.00 64 hrs
8/9/23 8/17/23
Sun Thu
Brickwalls 5 days 100% RM 16,000.00 40 hrs
8/20/23 8/24/23
Thu Fri
Staircase 6 days 100% RM 13,000.00 48 hrs
8/24/23 9/1/23
Dismantle of Mon Tue
2 days 100% RM 10,000.00 16 hrs
Formwork 9/4/23 9/5/23
Mon Tue
Second Floor 29 days 100% RM 58,000.00 480 hrs
9/4/23 10/10/23
Formwork Mon Fri
5 days 100% RM 2,000.00 40 hrs
Installation 9/4/23 9/8/23
Sun Sun
Rebar Installation 5 days 100% RM 10,000.00 40 hrs
9/10/23 9/17/23
Sun Thu
Column 5 days 100% RM 10,000.00 40 hrs
9/17/23 9/21/23
Sun Wed
Beam and Slab 8 days 100% RM 10,000.00 64 hrs
9/24/23 10/4/23

25
Mon Sun
Brickwalls 5 days 100% RM 16,000.00 40 hrs
10/2/23 10/8/23
Dismantle of Mon Tue
2 days 100% RM 10,000.00 16 hrs
Formwork 10/9/23 10/10/23
Wed Thu
Roof 20 days 10/11/23 100% RM 40,000.00 152 hrs
11/2/23
Wed Tue
Roof Beam 6 days 100% RM 5,000.00 48 hrs
10/11/23 10/17/23
Wed Fri
Roof Truss 8 days 100% RM 15,000.00 64 hrs
10/18/23 10/27/23
Sun Thu
Roof Installation 5 days 100% RM 20,000.00 40 hrs
10/29/23 11/2/23
Mechanical and Sun Tue
15 days 100% RM 60,000.00 128 hrs
Electrical Works 11/5/23 11/21/23
Sun Tue
Plumbing 5 days 100% RM 18,000.00 40 hrs
11/5/23 11/21/23
Thu Tue
Electrical 5 days 100% RM 20,000.00 40 hrs
11/9/23 11/14/23
Fire Protection Wed Fri
3 days 100% RM 10,000.00 24 hrs
Installation 11/15/23 11/17/23
Sun Tue
HVAC System 3 days 100% RM 12,000.00 24 hrs
11/19/23 11/21/23
Wed Sun
Finishes 331 days 11/22/23 100% RM 186,000.00 432 hrs
12/29/24
Wed Sun
Plastering 10 days 11/22/23 100% RM 40,000.00 80 hrs
12/3/23
Mon Thu
Floor Screeding 10 days 100% RM 35,000.00 80 hrs
12/4/23 12/14/23
Sun Fri
Ceiling 6 days 100% RM 30,000.00 48 hrs
12/17/23 12/22/23
Sun Sun
Tiling 15 days 12/24/23 100% RM 30,000.00 120 hrs
1/14/24
Door and Window Sun Thu
5 days 100% RM 36,000.00 40 hrs
Installation 1/14/24 1/18/24
Thu Sun
Painting 17 days 100% RM 15,000.00 64 hrs
1/18/24 12/29/24
Sun Mon
External Works 168 days 100% RM 65,000.00 128 hrs
7/23/23 2/12/24
Wed Fri
Ramp and Apron 3 days 100% RM 15,000.00 24 hrs
1/31/24 2/2/24
Sun Thu
Drainage 5 days 100% RM 10,000.00 40 hrs
7/23/23 7/27/23
Sun Tue
Access Road 3 days 100% RM 15,000.00 24 hrs
2/4/24 2/6/24
Wed Mon
Landscape 5 days 100% RM 25,000.00 40 hrs
2/7/24 2/12/24
Testing and Tue Sun
4 days 100% RM18,000.00 16 hrs
Commissioning 2/13/24 2/18/24

26
Tue Sun
RI Inspection 4 days 100% RM18,000.00 16 hrs
2/13/24 2/16/24
Certificate of
Statutory Sun Sun
0 days 100% RM0.00 176 hrs
Completion 2/18/24 2/18/24
(CSC)
Sun Sun
Project Finish 0 days 100% RM0.00 48 hrs
2/18/24 2/18/24
Project Sun Sun
0 days 100% RM0.00 48 hrs
Handover 2/18/24 2/18/24

27
Table

Week Cumulative Cost Percentage Works Week Cumulative Cost Percentage Works Week Cumulative Cost Percentage Works Week Cumulative Cost Percentage Works
1 RM 1,775.15 1% 34 RM 493,345.73 54% 67 RM 1,384,699.32 100% 100 RM 1,394,733.11 100%
2 RM 3,550.30 2% 35 RM 513,396.45 55% 68 RM 1,385,003.38 100% 101 RM 1,395,037.16 100%
3 RM 5,325.44 3% 36 RM 538,875.74 57% 69 RM 1,385,307.43 100% 102 RM 1,395,341.22 100%
4 RM 7,213.02 4% 37 RM 557,021.70 59% 70 RM 1,385,611.49 100% 103 RM 1,395,645.27 100%
5 RM 8,988.17 5% 38 RM 582,130.18 61% 71 RM 1,385,915.54 100% 104 RM 1,395,949.32 100%
6 RM 10,763.31 6% 39 RM 594,313.61 62% 72 RM 1,386,219.59 100% 105 RM 1,396,000.00 100%
7 RM 12,538.46 7% 40 RM 632,755.42 65% 73 RM 1,386,523.65 100%
8 RM 15,313.61 8% 41 RM 664,863.91 66% 74 RM 1,386,827.70 100%
9 RM 17,088.76 9% 42 RM 681,639.05 68% 75 RM 1,387,131.76 100%
10 RM 56,863.91 10% 43 RM 704,414.20 70% 76 RM 1,387,435.81 100%
11 RM 64,639.05 10% 44 RM 746,189.35 72% 77 RM 1,387,739.86 100%
12 RM 74,118.34 11% 45 RM 799,964.50 74% 78 RM 1,388,043.92 100%
13 RM 86,893.49 12% 46 RM 845,739.64 76% 79 RM 1,388,347.97 100%
14 RM 97,335.31 13% 47 RM 896,514.79 78% 80 RM 1,388,652.03 100%
15 RM 106,443.79 14% 48 RM 946,289.94 80% 81 RM 1,388,956.08 100%
16 RM 115,923.08 16% 49 RM 991,065.09 82% 82 RM 1,389,260.14 100%
17 RM 163,167.11 19% 50 RM 1,027,840.24 83% 83 RM 1,389,564.19 100%
18 RM 164,411.15 19% 51 RM 1,089,615.38 85% 84 RM 1,389,868.24 100%
19 RM 170,406.24 21% 52 RM 1,109,741.73 87% 85 RM 1,390,172.30 100%
20 RM 177,122.58 23% 53 RM 1,128,868.08 88% 86 RM 1,390,476.35 100%
21 RM 186,182.19 26% 54 RM 1,151,819.70 90% 87 RM 1,390,780.41 100%
22 RM 194,241.79 29% 55 RM 1,232,975.61 93% 88 RM 1,391,084.46 100%
23 RM 200,958.13 31% 56 RM 1,246,304.81 96% 89 RM 1,391,388.51 100%
24 RM 210,385.48 33% 57 RM 1,278,384.02 97% 90 RM 1,391,692.57 100%
25 RM 229,851.53 35% 58 RM 1,340,463.22 99% 91 RM 1,391,996.62 100%
26 RM 248,095.57 37% 59 RM 1,380,542.42 100% 92 RM 1,392,300.68 100%
27 RM 271,294.96 39% 60 RM 1,382,621.62 100% 93 RM 1,392,604.73 100%
28 RM 324,827.69 41% 61 RM 1,382,925.68 100% 94 RM 1,392,908.78 100%
29 RM 359,041.42 42% 62 RM 1,383,229.73 100% 95 RM 1,393,212.84 100%
30 RM 392,483.23 46% 63 RM 1,383,533.78 100% 96 RM 1,393,516.89 100%
31 RM 415,591.72 48% 64 RM 1,383,837.84 100% 97 RM 1,393,820.95 100%
32 RM 436,866.86 50% 65 RM 1,384,141.89 100% 98 RM 1,394,125.00 100%
33 RM 451,142.01 52% 66 RM 1,384,445.95 100% 99 RM 1,394,429.05 100%
Physical & Financial S-Curve Graph

Physical & Financial S-Curve


RM1,600,000.00 120%

RM1,400,000.00
100%

RM1,200,000.00

80%
RM1,000,000.00

percentage
cost

RM800,000.00 60%

RM600,000.00
40%

RM400,000.00

20%
RM200,000.00

RM- 0%
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100 103
weeks

cumulative cost cumulative percent done


Financial S-Curve Graph

Financial S-Curve
RM1,600,000.00

RM1,400,000.00

RM1,200,000.00

RM1,000,000.00
cost

RM800,000.00

RM600,000.00

RM400,000.00

RM200,000.00

RM-
1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 97 100 103
weeks

cumulative cost
5.0 DISCUSSION

Microsoft is a prolific creator of PC software for engineering student and also been use as life
working civil engineering especially project manager. The most well-known operating
system is Windows. For many years, Microsoft Project has been the most popular project
management software. This is primarily due to project managers and team members'
familiarity with other Microsoft products, rather than because Microsoft Project is the best
option. Microsoft Project is another tool for project planning, scheduling, and competent and
well-organized project management. It displays a series of events and estimates how long the
construction will take to complete. Furthermore, the Microsoft Project helps us to track the
progress of our planned tasks. In a normal workflow, the Work Breakdown Structure (WBS)
sits between the functional specification and the project plan. Each job is defined in depth in
a functional specification, which also contains design and development criteria. The work
breakdown structure (WBS) gives a high-level overview of the project. The functional
specification details the aims and objectives. The application's behaviour of the work
breakdown structure (WBS) is frequently used to create Gantt charts for projects. According
to the timeline, this project will take 590 days to complete beginning on 1 January 2023 until
29 December 2024. In this timeline, we started with planning and preliminary works. In
preliminaries work we got site cleaning, site investigation, retaining system, excavation and
monthly report and progress photograph. We also break the permanent work we into two
phase which is building work phase 1 and building work phase 2. In this phase we focus on
the sub structure and super structure. In sub structure, we do the piling, pile cap and stump. In
super structure, we started do on the ground floor, first floor and second floor. In this
progress we do the formwork installation, rebar installation, column, beam and slab and more.
Then proceed with beam and slab ,brick walls and roof stages. Then, continue with
mechanical and electrical work such as plumbing, electrical, fire protection and more. After
that, we continue the progress with finishes work and continue with the external works such
as ramp and apron, drainage, access road and landscape. Lastly, after the building work finish,
we proceed with the RI inspection and Certificate of Statutory Completion (CSC).

31
6.0 CONCLUSION
Finally, the report includes all important construction information, such as the deadline, the
progress that must be monitored for each work activity, and the total construction cost. All
the holidays linked with the completion of the project have been considered. Throughout the
project's implementation, weather variables were also considered. By presenting the start and
end dates for each activity, the use of Microsoft Project to produce Gantt charts aids in the
smoothing of the construction process. In a nutshell, it assists in avoiding project delays and
keeping everything on track. The report also includes an S-curve for physical and financial
data, which is useful for tracking the actual and real-time cumulative data of project parts. In
a nutshell, it assists in avoiding project delays and keeping everything on track. The report
also includes an S-curve for physical and financial data, which is useful for tracking the
actual and real-time cumulative data of project parts. It also assists in identifying problems
and determining whether any changes are necessary to get back on track.

32
REFERENCES

1. Najmi, H. S., (2011, May 15). Project Management for Construction Projects. An-
Najah National University Faculty of Graduate Studies. Retrieved from
https://scholar.najah.edu/sites/default/files/all- -
thesis/project_management_for_construction_projects.pdf/ on 15 December 2022.
2. Foley, M. J., (2014, September 19). What's new for business users in Microsoft's
Office '16'? Retrieved from https://www.zdnet.com/article/whats-new-for-business
users-in-microsofts-office-16/ on 15 December 2022.
3. Carl S. Chatfield, Timothy D. Johnson (2016) Microsoft Project 2016 Step by Step:
MS Project 2016 Step. Retrieved from
https://books.google.com.my/books?id=iRPuCwAAQBAJ&printsec=frontcover&redi
r_esc=y#v=onepage&q&f=false/ on 16 December 2022.
4. Abhishek sharma and k.k. pathak.(2015),”Manpower Planning, Scheduling and
Tracking of a Construction ProjectUsing Microsoft Project Software’-National
Institute of Technical Teachers Training and Research, Vol. 3,No. 2,pp. 161–169.
5. Devikamalam and J. Jane Helena. (2013) “Resource Scheduling Of Construction
Projects Using GeneticAlgorithm” -International Journal of Advanced Engineering
Technology Vol. 5 Issue 4
6. A.A.Lakade and A.K.Gupta’ (2013) ,“A Project Management Approach Using Erp
and Primavera in ConstructionIndustry” OSR Journal of Mechanical and Civil
Engineering (IOSR-JMCE), PP: 21-24.
8.0 Minutes of Meeting

Meeting Date : 13 December 2022 ( 2.00pm - 3.00 pm )


Attendance : 1) Muhammad Hasiq bin Md Anis (AF190033)
2) Nur Izzati binti Mohd Basri (AF190181)
3) Muhammad Haiqal Rafiq bin Rosli (AF190027)
4) Muhammad Aliff Iman bin Shamsudin (AF190161)
5) Mohamad Rasyid bin Rosly (AF190073)
Topic : Discussion of Microsoft Project

No. Activities Action


1. Understand the project Find a suitable solution to solve the
instruction. project requirement.
2. Workload has been divided Ensure each group member has their own
among each member. task and needs to be done accordingly.
3. Set a dateline for the project Follow the dateline that has been set up
submission. and compile all the task for submission.
Prove of Meeting :

Prepared by: Date:


15 December 2022
Rasyid
….………………………………………
Mohamad Rasyid bin Rosly (AF190073)
5"X3" RIDGE TILE
RIDGE PLATE
4"x2" RUSTRUTS
2"x2" RAFTER
6.3R @ 6"
ASBESTOS SHEET
4"x3" WALL PLATE
9"x1" VALANCE BOARD

4Y 16MM MAIN
BARS

12mm

PRONT ELEVATION SECTION


9"THICK BRICK WALL

1/2" THICK PLASTER.


1/2" THICK D.P.C.

3"TICK 1:3:6 CONCRETE

R.R. MASONARY.

SCHEDULE OF DOOR AN WINDOWS


1:2:4 CONCRETE

D-3 TOI AND D-3 F


BATH F

X W-1 X X W-2 BED ROOM X


DINING
LIVING
ROOM D-2 D-2 BED ROOM
AREA
W-1 KITCHEN W-1 DETAIL OF FOUNDATION.
D-1 D-2
W-2

W-2 W-2
DINING ROOM W-1

GROUND FLOOR PLAN FIRST FLOOR PLAN