Professional Documents
Culture Documents
Rotary Bored Piling: / J.M. Piling Co. Limited
Rotary Bored Piling: / J.M. Piling Co. Limited
Limited
METHOD STATEMENT
ISSUE CONTROL
This document remains the property of the Murphy Group. The holder shall be responsible for complying with the
instructions that accompany revisions.
The Design Manager or his / her nominee shall only issue revisions. Amendments shall be identified by the revision
number and a vertical line in the margin.
SIGN
05 Subcontractor(s), TBC
CONTENTS
B. Risk Assessments
E. Lift Plan
I. COSHH Assessments
[Control of Substances Hazardous to Health]
J. Insurances
M. ISO 9001:2008
[Quality Management System Certificate]
ISO 14001:2004
[Environmental Management System Certificate]
BS OHSAS 18001:2007
[Occupational Health & Safety Management System Certificate]
N. CHAS Certificate
[Contractors Health and Safety]
A 5m exclusion zone will be maintained around the Piling Rig in operation, and piles
recently cast will be covered with a metal grate.
3.5. Access
Access routes onto and off site will be as agreed with the Principal Contractor. The
Rotary Bored Piling Rig will be transported to site on a low loader capable of
carrying the Rig. The Rig will track itself off the low loader and will not be lifted off
by means of a crane. If necessary, a wide enough ramp will be constructed to
provide a safe access onto site for the Rig and timber boards/spreader plates placed
to protect any existing surfaced areas and kerbs, c/o the Principal Contractor.
Mc Aleer & Rushe will carry out the setting out in accordance with the latest Pile
layout drawings received.
4.0 Resources
4.1. Materials
• Concrete – UKAS certified
• Reinforcing Steel – CARES certified
• COSHH as per assessments in Appendix I
4.2. Plant
The following equipment items are envisaged to be used for Piling operations:
Item Quantity
All plant and equipment will be certified and maintained to PUWER 98 and where
applicable, LOLER 98.
Manpower Quantity
4.3. Labour
5.0 Methodology
This method statement explains in depth the rotary bored piling technique.
To overcome these potential risks, the following safety features will be implemented
to ensure a safe method of working: -
GENERAL Piles will be constructed with a diesel powered track mounted Rotary
Piling Rig.
ACCESS Access to the Piling area will be as provided by Mc Aleer & Rushe.
Access ramps between working areas to be no greater than 1:10
gradient.
LIGHTING Task lighting as fitted to plant will be provided and maintained by JMP.
General/safety lighting for the access and working area will be
provided by Mc Aleer & Rushe if necessary.
RIG
Mobilisation - The Rig will be mobilised on the signed off Pile mat area. The
Pile equipment will be a diesel powered track mounted Rotary Piling Rig.
Before erecting the mast, the tracks of the machine will be extended to full
width to provide full stability. The hydraulic Piling Rig is self-erecting and the
mast, during mobilisation, is lifted from the travelling horizontal position to the
vertical working through a series of rams positioned on the mast and Rig
body.
Equipment and Material Delivery - All construction traffic including the Piling
Rig, delivery vehicles and concrete wagons will access the site works using
the designated Works Access’s only. On arrival to site all equipment and
material deliveries will report to the person in charge prior to off loading. All
deliveries will transit through the site with a Banksman present at all times.
No keys are to be left in unmanned machines.
WORKING PLATFORM
Piling Platforms:
The piling platform designed by Consulting Engineers is based on the BRE Load
cases for the Soilmec piling rig. The platform will be installed by Telford Homes as
per the specification designed. The working platform certificate (WPC) will be signed
off by the relevant parties – designer and McAleer & Rushe. The working platform
certificate shall be issued in conjunction with a Form C. A copy of the completed
‘working platform certificate’ shall be kept on site. The piling platform shall extend 2m
beyond the working area.
Testing of the working platform will include plate bearing tests on each piling
platform. Inspection of the piling matt will be carried out regularly by McAleer &
Rushe any anomalies in the piling matt will be addressed immediately by McAleer &
Rushe. There will be no excavation of the piling platform where the piling rig is
working until the piling rig is finished piling on that platform.
Any unsupported pile shafts – where the pile cut off levels are low – will be correctly
backfilled following the completion of pile construction so there is no hole left open at
the end of each day.
Platforms for tracked plant: good practice guide to the design, installation,
maintenance and repair of ground-supported working platforms – BRE 2004).
any works on site and the Working Platform Regular Inspection Log is to be
maintained by the Principal Contractor in accordance FPS/WPC/4 Guidance
on Working Platforms for Tracked Plant 3.1-3.3. This is the responsibility of
Mc Aleer & Rushe.
Temporary Works Design for the working platform should in accordance with
the approved Forms of F002 & F003 submitted to Network Rail.
PILING SEQUENCE
The Piling sequence will be generally as per agreed with Mc Aleer & Rushe.
The piles will be constructed in such a manner that no damage will be caused
to piles previously constructed i.e. cracking, clashing or disturbing.
PARTY WALL
Mc Aleer & Rushe to have in place a procedure for Piling works adjacent to
Party Walls.
PILE BORING
The position of each Pile will be set out by Mc Aleer & Rushe and referenced
with the Pile number prior to drilling. Whilst the mast of the Rig is in a vertical
position the tip of the boring tool will be lowered and manoeuvred to be
directly into the centre of the relevant Pile location pin.
Prior to the commencement of drilling, the mast will be checked for verticality
in both orientations by reference to a spirit level.
Based on the Soil Investigation Report, casing may be used. If used, the
boring tool will pre-drill to permit the temporary casing to be placed as
necessary. The casing will be lifted by the Piling Rig and inserted into the
bore to achieve a seal by the operation of the Rig. The bore will be extended
by the Piling Rigs auger down to the required depth in accordance with the
relevant drawing and Pile schedule.
During boring, the boring tool is extracted and spoil deposited adjacent to the
bore. At regular intervals during boring, spoil arisings built up adjacent to the
bore will be cleared by the attendance excavator. This will be removed at a
later date by Mc Aleer & Rushe to a designated stockpile.
Mc Aleer & Rushe to appoint a 360° excavator for handling waste materials
and Pile arisings.
Once the correct depth has been reached this will be checked by tape and
recorded on the Pile record sheet.
CONCRETING
Concrete of specified mix 35N DC-4 S3 shall be used to construct the Piles.
The concrete will be delivered in ready mix trucks using the designated
access routes and will be routed through the site to the Pile head position with
a Banksman in attendance at all times.
Prior to concreting, a JMP employee will inspect the concrete ticket, ensuring
the concrete is of the correct specification.
REINFORCEMENT
The reinforcement will be delivered in straight lengths of reinforcement bar
and helical links and placed in a designated area as agreed with Mc Aleer &
Rushe site management team. All reinforcement will be kept off the ground.
This steel fixing station will have ‘tressels’ where the reinforcement will be
placed as the cages are fixed by the competent steel fixers. The steel fixers
will be working under the supervision of JMP and will have the relevant
training cards, and will be briefed on this JMP document with sign-off of same.
The Banksman will ensure that the reinforcement is placed on the ‘stands’ or
‘tressels’ in a safe manner so the steel fixer can commence cage fabrication.
The steel fixer will fix the cages as per the design schedule. The Piling
foreman will inspect the cages after fabrication.
The cages will be lifted via the attendant excavator and lifting apparatus to a
storage area agreed with Mc Aleer & Rushe with a slinger / banksman
present. All lifting equipment including chains, slings etc will be fully certified.
The lifting procedure will be in accordance with the Lifting Plan.
Piles with tension reinforcement will be placed using the main winch of the
Piling Rig. The Pile cages will be placed on the Piling mat (laid out). The
‘hanging wire’ will be fixed to the cage and the shackle attached to the safety
bar. The cage will be lifted into the cased Pile. The safety bar will sit or rest on
the casing, ensuring there is no personnel coming into contact with the
placement of the cage. Should the bar require repositioning there are two
safety handles on either end of the safety bar away from the hanging wire and
cage. The safety cage will be fully certified and tested.
The Piling Rig or attendant excavator will lift the cage from the horizontal to the
vertical, slew around and lower the cage into the Pile bore (refer to image
below)
Shackle, connected to
two legged chains
Safety handles
When Piling operations have been completed the process shall be repeated
at the next Pile position. No Piles will be left open hole, and an exclusion
zone must be maintained around recently cast Piles for safety reasons.
Once the Piles have been trimmed to cut-off level, integrity testing may be
undertaken.
Throughout the Pile construction process, the appropriate construction and
inspection records and activities will be maintained in accordance with the
Safety Management System, Works Procedures and the Specification
5.4. Reinforcement
As detailed in JMP Pile design calculations.
Holliday Concrete Testing Ltd will perform the testing of concrete cubes and hold
UKAS testing accreditation.
Pile Integrity Testing - All Piles will be integrity tested after completion. No
Pile integrity testing shall take place under 5 days from the time of cast, and
may only be performed after the Pile has been satisfactorily trimmed for
testing purposes. The trimming is required to remove surface latency from
the Pile and should result in minimum damage to the piles.
The work will proceed generally in accordance with Mc Aleer & Rushe Programme.
6.0 Quality
6.1. Safety Management System
The works shall be carried out compliant with the Safety Management System
(SMS). The SMS is a documented set of policies, and procedures which when
implemented satisfactorily will enhance safety performance thus leading to higher
efficiency and fewer accidents. The Safety Management System describes how the
Group Safety Structure works and is therefore a key to the success of the business.
The Safety Management System (SMS) is certified to the Occupational Health and
Safety Management System Specification OHSAS 18001:2007, which has been
developed to be compatible with ISO 9001:2008 Quality, and ISO 14001:2004
Environmental management system standards, in order to facilitate the integration of
Safety, Quality and Environmental management systems.
Parts of the Murphy Group Safety System also include Environmental and/or Quality
Management System requirements, and are therefore already ‘integrated’.
The Murphy Group is fully committed to supporting Industry and Client led Health,
Safety and Welfare programmes wherever they are established. The Group Safety
Management System will wherever possible, reflect those Health, Safety and
Welfare programmes.
The Board of Directors give their full support to the Safety Management System
(SMS) as it regards the Health and Safety of all people employed by the Group and
anybody else who may be affected by our activities, as being of paramount
importance. The SMS is defined in full in:
MOH0002-MAN-00001 Group Safety Manual
Any non-conforming items identified during the contract period shall be addressed
as appropriate by non-conformance reports. Where corrective actions are
necessary, the Piling Project Manager shall be notified to ensure timely completion
of the contract stages to the agreed schedule.
6.3. Induction
All labour will attend a Site Induction prior to work on the project. JMP will also hold
internal inductions prior to work commencing. When particular methods of working
6.5. PPE
Correct types of Murphy branded PPE for all Murphy site employees shall be
provided and worn as required, they include:
• Hard hats, mandatory
• Hi-visibility vests, mandatory
• Safety Footwear, mandatory
• Safety Glasses, mandatory
• Gloves, mandatory/appropriate to the task
• Hearing protection
• Any other PPE deemed applicable to the works
When changing auger teeth, inserting auger, pins into auger head & saw cutting
heavy duty glasses will be worn. The operatives will have all of this PPE provided for
them by JM Piling and each operative will be responsible for their own particular
PPE.
Additional items of PPE may be required for specific operations. Those items will be
identified and a briefing given as required. All PPE will to be fit for purpose.
Correct issue and use of PPE for steel fixers is the responsibility of the sub-
contracted company but will be monitored by JMP.
6.6. Records
A copy of this Method Statement will be retained on site for inspection and will be
briefed to all site personnel, by the Piling Project Manager or Site Foreman.
64 to 66 York Way,
Islington
London
N1 9AG
7.0 Environment
• Skips, water bowser and licensed carriers will be provided by Mc Aleer & Rushe.
• Piling operations should take place only within specified working hours
• Hazardous waste, such as oil contaminated materials, used spill kits etc. shall be
disposed of by a licensed carrier
• Concrete trucks will be washed out into a plastic lined concrete washout area which
will be replaced as required or emptied when 75% full by Mc Aleer & Rushe.
The location of these concrete washout areas will be advised at a later date
APPENDICES
a. Risk Assessments
Change in Depth of made The piles will not obtain the designed Exploratory investigation undertaken, any change in the strata to
ground ground, sand & capacity. that of the site investigation recorded and reported to the Design
conditions gravel, clay, London 25 Manager immediately. JMP / Main 5
Clay extends further Contractor
across the site then Works to stop until the change in design has been resolved.
proven in the site
investigation.
Design Differential Differential settlement of pile causing the Design the piles to be end bearing into the same strata and a
Approach settlement due to the piles all act differentially when loaded minimum depth penetration into the end bearing strata.
piles bearing into 25 JMP 5
varying or different
bands of strata.
Design Pile Design not an Piles not sufficiently designed to support the As part of the design use an accurate design line to represent
Approach accurate required loads. the Site Investigation testing results.
representation of the 25 JMP 5
site investigation
results.
Piling The piles installed Piles not falling within the ground beam / The main contractor’s consultants to identify piles that could
Tolerances raking or out of pile cap causing a redesign. potential be out of position but still within tolerance, particularly
position but still 6 piles with low cut-off levels. Main 4
within the SPREW With contiguous or secant wall piles the Contractor
piling tolerances. piles can ‘rake’ into or out of the basement Piling Tolerances are in accordance with the ICE specification for
comprising the retaining wall thickness or piling and embedded retaining walls, second edition (B1.8
reducing the size of the basement. Installation tolerances – Table B1.4 Standard installation
tolerances).
Reinforcement Piles reinforcement Inadequate reinforcement projection (less Ensure the reinforcement is installed at the correct levels,
Projection projection & fixing than 40 x D, bar diameter). providing the minimum anchorage.
the cage 9 JMP / Main 2
reinforcement into The reinforcement bar diameter larger than The main contractor’s consultants to identify piles that could Contractor
the beam or slab. 16mm diameter, resulting in the ground potential be affected by large reinforcement bars projecting into
worker unable to ‘bend’ or ‘fix’ the the slab or ground beam.
reinforcement into the beam or slab.
CONSTRUCTION
Piling Matt Inadequate design, The piling rig to overturn or collapse. Ensure the piling platform is designed to the correct BRE Load
construction or Cases and the Load Cases are exact loadings of the piling rig.
maintenance of the 25 JMP / Main 5
piling platform. Ensure the installation or construction of the piling platform is in Contractor
accordance with the piling platform specification.
Compiled By: Patrick Gilhooley Date: Reviewed By: Kieran Herbert Date:
18/06/15
Signature (s): 18/06/2015
Signature (s):
Note: All employees are to be informed of control measures prior to work commencing.
Piling Design - Risk Assessment
Severity of Hazard
Catastrophic
Moderate
Trivial
Minor
Major
1 2 3 4 5
Likelihood of Occurrence
Extremely Remote – unlikely to occur 1 1 2 2 4 5
Remote – small chance that it will occur 2 2 4 6 8 10
Possible – chance that it may occur 3 3 6 9 12 15
Reasonable Probable – probably will occur 4 4 8 12 16 20
Almost Certain – likely to occur immediately or 5 5 10 15 20 25
soon
SITE WELFARE
Site Cabins -Cabin condition -Inhaling harmful gasses causing sickness -Facilities provided must be clean and appropriate for use
-Live power to the -Being electrocuted by live electricity -Cabins must be in well-kept conditions and be inspected
Cabin possibly causing injury or death regularly
-Accessories in -Sustaining Cuts/Lacerations due to sharp -All electrical appliances must be PAT tested before use.
Cabin edges. 10 -All services to cabins must be properly installed and inspected 5
Main Contractor
-Weils disease C/O Main Contractor to ensure no accidents occur.
/JMP
-All site welfare to be locked over night to ensure nothing gets
tampered with when site is unoccupied
-Main Contractor to provide site welfare.
-Ensure hands are washed before eating and keep all cuts
covered up to reduce the chance contracting weils disease.
ENVIRONMENT
Refueling / -Gas/Oil/Fuel -potential run-off of harmful chemicals used -Ensure the use of drip trays under all plant and materials that
Greasing / in refueling and maintenance of the piling rig could develop a drip/leaks of harmful materials e.g. Fuel bowser,
Storage of and equipment affecting the surrounding Agitator, Pump etc.
harmful ground -make sure field bowsers are visually inspected DAILY to identify
materials -chemicals running into watercourses any leaks or damage that could cause a leak.
resulting in water course pollution. 16 -Ensure all materials are kept as far away from standing water/ 4
JMP
-Leaking fuel bowsers/ COSHH stores flood water/ rivers as possible to reduce risk of contamination.
resulting in harmful pollution -Spill Kits must be in near vicinity to equipment that has the
potential to cause a hazardous spill.
-COSHH assessments must be consulted and the crew briefed
before the task is undertaken
COSHH assessments will outline the PPE required for the task.
General / Pile -Noise -Noise of machinery can cause serious -Hearing protection must be worn when in the specified vicinity of
Boring -Working hours damage to hearing the rigs (specified by noise assessments) JMP / Main
-noise in a sensitive community can cause 9 -Working hours to be agreed with site Management Contractor 2
disruption among local neighbors.
RIGGING UP / DE-RIGGING
Piling Risk Assessment
Erecting the -Machinery -Failure of the piling rig or its components -The Piling Rig must be erected as stated in the manufacturers
Piling Rig resulting in serious injuries or death manual by competent persons
-getting trapped in moving parts causing -An experienced and CPCS qualified piling rig operative will be
serious injury the only person permitted to operate the Piling rig.
-12 monthly Thorough inspection certificates must be checked to
20 ensure the test is in date. 5
JMP
-The Rig pre-start checklist and daily/weekly checklist must be
filled out and up to date
-Any previous defects in the rig to be amended before
commencement of work.
-CPCS banksman must be present at all times
Working at -Falling from height -when erecting the rig, the piling operative -Safety harnesses must be used when working at height and
height could fall from height and cause serious attached to a sturdy place.
injury and endanger others around them -A restraint lanyard must be used to restrict the piling operative
16 coming to close to the edge of the rig JMP 8
-Harnesses must be thoroughly inspected and checked prior to
use
-Harnesses must be of correct fit
Working from -Working from height -Risk of falling from height causing Death or -MEWP must be tested every 6 months
MEWP -Falling objects serious injury -Before use, test certificates and checks shall be carried out
-Toppling of Plant -Dropping objects onto people below MEWP recorded daily inspection/prior to use inspection
-Failure of MEWP causing serious injury -All handrails shall be locked into place.-
-MEWP toppling causing serious 25 -If any damage to MEWP do not use and contact supplier 5
injury/Death and damage to plant and -MEWP only to be used on firm level ground (piling mat area)
nearby structures -Harness to be used with fall restrain lanyard.
-Failure of MEWP causing toppling of plant, -Harness to be used at all times and attached to the dedicated
potentially crushing or trapping personnel harness point.
-If MEWP fails when a person is stuck at height emergency
services should be called for rescue
-Competent person only to operate MEWP
- In case of MEWP failing whist carrying personnel. Somebody
must be deemed competed to lower MEWP from the controls at
ground level. If unable to do so 999 must be called to ask for fire
and rescue.
Replacing -splinters of metal -Tungsten may fracture when struck and -all changes to auger teeth/pins to be carried out using the
Teeth and coming off Augers seriously injure personnel. following equipment; High impact eye protection, copper
inserting Pins and teeth hammers,
JMP
into Auger 16 -all PPE must be worn correctly 4
Heads
BORING OF PILES
Operation of -Improper operation -Improper operation of the piling Rig could -Ensure all personnel operating the piling rig are CPCS qualified
Rig of Piling Rig cause serious damage to equipment and and deemed competent
-moving rig serious injury or death to personnel -Banksman to be clearly visible to Rig operative at all times
unsupervised -Failure of the Piling Rig causing Damage to 25 -Piling rig to be Operated in conjunction with the operator manual JMP 5
property or serious injury/Death -Banksman to be the only person to signal the movement of the
-Crushing or making contact with people Rig
working around Rig
Piling Risk Assessment
Open Bores -Deep excavations -Falling down an open or recently concreted -All recently bored and concreted piles are to be covered with
-Open bores pile could cause serious injury or death. grates
-Machinery toppling over after driving over 25 -Personnel not involved with piling should be segregated from 5
JMP
an open bore the piling mat area.
- Machine drivers shall back fill the open bore with hardcore to
make them safe at the end of every day
General -Uncontrolled -Injury to the public -The site will have hoarding extending the full length of the
Piling/Boring personnel -Serious damage to nearby affected area or, other methods of segregating plant from the
-Working near equipment/structures 12 public 6
pathways -Other tradesmen - Main Contractor to have splash guards in place if there is a Main Contractor
-Public highways significant risk of falling debris to nearby buildings/pathways.
-Safe systems of work to be identified in the method statement if
working next to busy roads.
CONCRETING AND REINFORCING PILES
Lifting -Lifting of cages -Piling operatives and/or uncontrolled -Operatives must refer to the lift plan before any lifts take place
reinforcement -Proximity of nearby personnel under slung loads -If the lift cannot be carried out in accordance with the lift plan
cage buildings -failure of lifting gear causing serious injury the AP must be contacted
-uncontrolled or death -Piling rig only to lift reinforcement cages
personnel -Failure of piling rig Causing serious injury -All other lifts to be carried out by attendant excavator and HIAB Main Contractor 5
-Slinging of the load or death 20 -See Method Statement for lifting tension reinforcement. / JMP
-Improper use of lifting gear causing loads
to fall
-Damage to nearby equipment and
structures
Pouring and -Concrete burns -If concrete comes into contact with skin it -Consult method statement and COSHH assessments for
pumping -Failure of can cause serious injuries working with concrete to get correct PPE.
concrete Pump/Hoses -If a concrete pipe were to burst it would -Concrete pump shall be checked for the inspection records and
cause serious damage to property, and test certificates
could cause serious injury to personnel -Concrete hoses and fittings should be visually inspected daily to
16 check for any slices or damage to the outside JMP 8
-Concrete hoses to be double bagged.
- The concrete pump shall be segregated from any persons not
dealing with the concreting works
-Vehicles shall not drive over concrete hoses
GENERAL
Welding / -Welding equipment -Welding equipment is extremely hot and -CITB and coded welder only
cutting -Hot works can cause serious burns -Correct PPE must be Worn (Fireproof overalls/welding mask)
-Abrasive wheels -Areas of rig being worked on can also along with mandatory PPE requirements outlined in method
become very hot and cause serious Burns statement.
-Due to the nature of the work a Fire could 20 -When carrying out cutting or welding works are must be 5
be caused resulting in serious injury or segregated and screened off.
death -Correct fire extinguisher to be kept in the near vicinity at all JMP
-Mounting of abrasive wheels by untrained times
persons causing wheel to detach -gas and oxygen to be stored separately
-Wheel guards being damaged or removed -Trained operatives only to use Abrasive wheels
causing serious injury -Ensure equipment is properly maintained and fit for purpose
-Ensure correct type of blades are being used for the job
-Ensure people around you are aware of areas being worked on
Piling Risk Assessment
Refueling / -Hazardous -Spillages can cause Serious burns / -Refer and comply with COSHH assessments provided in
Cleaning / Materials sickness / Headaches / breathing problems method statement, assessment to be briefed to all by foreman.
Lubricating / -Spillages(refer to environmental) 12 -Wear correct PPE as identified in the COSHH assessment JMP 6
-Fire -Fire can cause serious injuries or death to -Ensure correct fire extinguishers are supplied and in good
General -General personnel and damage working condition. If unsure of correct type for task, ask site
Housekeeping equipment/structures inside and outside of management.
site 20 -Ensure fire extinguishers are in date and fit for purpose. 8
JMP
-Slips trips and fall can occur if work areas -Ensure all work areas are tidied throughout the day and at the
are left untidy. end of every day
-Areas left untidy can also encourage fire -Ensure all rubbish is placed in correct bins at the end of every
day
General -Security of -Unauthorized use of Piling equipment -Tools must be stored away properly when not in use and while
equipment and plant -tools left unattended could be picked up on lunch/tea breaks
and used by unauthorized personnel -Ensure tools are not left anywhere where public can pick them
8 up JMP 4
-Use cable mats where cables cross paths
-Piling rig to be left Locked when not in use
-No keys to be left in the Piling rig at anytime
Steel fixing -Untidy work area -An untidy area can cause slips trips and -The work area should be cleared of obstructions and trip
-Manual Handling falls resulting in serious injury hazards
-Sharp edges -Lifting heavy loads can cause injuries -Collect excessive tying wire
-Cuts and lacerations can be obtained from 16 -Steel fixing tressels should be laid on firm level ground. JMP 5
shard or protruding steel -Stack reinforcement in agreed lay down areas.
-Use barriers to segregate from other works
-Use mechanical aids to lift steel bundles and heavy cages
Setting out -Plant movement -plant movement in the vicinity could -Ensure yourself and your EDM are in clear view and out of the
-Untidy work areas seriously injure or cause a fatality route of moving plant.
-Spray markers -Slips trips and falls could occur if area is -Make plant operators aware that you are working in the area 5
-Hammering in pins untidy 20 -Keep work area tidy at all times JMP
-Fumes released from spray paint could -Refer to COSHH for working with spray paint
cause headaches and sickness -Ensure Lump hammer is in good condition and that the head is
secured.
Compiled By: Patrick Gilhooley Date Reviewed by: Kieran Herbert Date:
18/06/15 18/06/2015
Signature
Signature(s)
Piling Risk Assessment
NOTE:
Should any new scenarios arise that are not covered in this risk assessment, site management should be contacted
immediately and the task not be carried out until a specific risk assessment has been completed, issued and understood.
Refer to Method Statement for mandatory PPE requirements on ALL J.M.Piling jobs.
capable of causing
doctors or hospital
first aid treatment
imminent danger
or severe injury
Catastrophic –
attendance
wide scale
1 2 3 4 5
Likelihood of Occurrence
Extremely Remote – unlikely to occur 1 1 2 2 4 5
Remote – small chance that it will occur in time 2 2 4 6 8 10
Possible – chance that it may occur 3 3 6 9 12 15
Reasonable Probable – probably will occur in 4 4 8 12 16 20
time
Almost Certain – likely to occur immediately or 5 5 10 15 20 25
soon
J.M. Piling Co. Limited
J.M. Piling Co. Limited Daily Report No.
Main Contractor: Job Name Total Piles This Sheet
Location/Block Reference: Machine Total Piles To Date
Schedule Rev: Foreman Concrete Mix: N/ DC‐
Concrete cubes taken from pile
number:
Digger in assist
Yes: No: SIGNED FOR BY J.M. PILING Co. LTD:
If 'no' give reason:
SIGNED FOR BY PRINCIPLE CONTRACTOR:
POH0001/FOR/00005/Rev03
J.M. Piling Co. Limited
R-312/200
and representative offices as:
SOILMEC S.p.A.
Ground Engineering Equipment
5819, via Dismano
47023 Cesena (FC) - Italy
tel. +39-0547-319111
fax +39-0547-318548
http:// www.soilmec.it
e-mail: soilmec@soilmec.it
R-312/200
and representative offices as:
SOILMEC S.p.A.
Ground Engineering Equipment
5819, via Dismano
47023 Cesena (FC) - Italy
tel. +39-0547-319111
fax +39-0547-318548
http:// www.soilmec.it
e-mail: soilmec@soilmec.it
A new model After the success of the R-312 HD Soilmec introduces the new model R-312/200 performing:
- bored piles with dry drilling or bentonite mud
- continuous flight auger piles (CFA)
The main features of the R-312/200 are the following: 2 - Turret c/w CUMMINS 6BTA55.9-C200
6000
- new powerful rotary diesel engine and sound proofed canopy,
- high speed drilling mounted on a 360° slew ring
6000
- easy transport: it can be transported with rotary and kelly bar installed 5
3 - Winch assembly
- compliance with the machine laws for safety standards
- total reduction of rig up time, about 20 minutes from arrival to the job site 4 - Parallelogram system allowing
- easy to use and handle working radius adjustment always
- low operating costs maintaining the mast in vertical position.
- wide range of accessories (depthmeter, inclinometer, air conditioning, free fall winch) C/w electronic device for automatic stop ø 750
21742
intermediate element 11.9 m long and
8646
Large diameter bored pile
a top element 3.5 m long. The max torque 750
10490
can be applied all over the mast length
24900
17784
Max pile diameter mm 1500
1932
Max pile depth m 48 (with 5x11 kelly bar) 6 - Sheave cathead 7
16228
16600
13500
130
13000
Max drilling speed rpm 42 hydraulic cylinder
890
Spin off speed rpm 153 8 - Rotary head with 3 drilling speeds and
10500
5250
Main winch nominal line pull kN 133 one high spin off speed. The max torque
3198
Power BHP 200 @ 2200 rpm 9 - Telescopic kelly bar with guide to
Crowd system kN 123.7 / 101.8 mast available with friction or mechanical
4500
2550
Operating weight tons 35 locking type
2553
Transport weight (c/w kelly bar) tons 34
2256
344
The nominal values are referred to 100% total efficiency. 395 750
8
1267
940
885
795
520
Continuous Flight Auger (CFA)
4510 3710
500
450
EXTENDED TRACK WIDTH 3700 mm 3500 3500
3500 3500 (MIN. 3000) 3621 SHOE WIDTH 600 mm
Max pile diameter mm 750 (3000+3500)
(3000÷3500) 3950
MIN. 2750 MAX. 3950
3666
707 600
1870
1509
12090 12119 WEIGHT: 1000 kg
elements length depth weight height elements length depth weight height
no m m tonn m no m m tonn m 1474
3277
3426
4x 7,5 25,0 2,9 5,0 4x 9,0 34,0 3,3 5,0
2540
2540
2500
1652
1652
1652
1649
4x 9,0 32,0 3,3 5,0 4x 11,0 38,0 3,9 4,6
1279
952
795
852
885
952
4x 11,0 39,0 3,9 4,6 5x 10,5 46,5 8,5 8,3 1199 1397
WEIGHT: 33000 kg
5x 9,0 40,0 4,3 5,0 5x 11,5 51,5 9,0 8,3 1199
1360 3254
1986
5x 11,0 48,0 5,1 4,6 5x 13,5 62,0 10,3 6,76 3269 4510 4311
3269 4510 4340
The main features of the R-312/200 are the following: 2 - Turret c/w CUMMINS 6BTA55.9-C200
6000
- new powerful rotary diesel engine and sound proofed canopy,
- high speed drilling mounted on a 360° slew ring
6000
- easy transport: it can be transported with rotary and kelly bar installed 5
3 - Winch assembly
- compliance with the machine laws for safety standards
- total reduction of rig up time, about 20 minutes from arrival to the job site 4 - Parallelogram system allowing
- easy to use and handle working radius adjustment always
- low operating costs maintaining the mast in vertical position.
- wide range of accessories (depthmeter, inclinometer, air conditioning, free fall winch) C/w electronic device for automatic stop ø 750
21742
intermediate element 11.9 m long and
8646
Large diameter bored pile
a top element 3.5 m long. The max torque 750
10490
can be applied all over the mast length
24900
17784
Max pile diameter mm 1500
1932
Max pile depth m 48 (with 5x11 kelly bar) 6 - Sheave cathead 7
16228
16600
13500
130
13000
Max drilling speed rpm 42 hydraulic cylinder
890
Spin off speed rpm 153 8 - Rotary head with 3 drilling speeds and
10500
5250
Main winch nominal line pull kN 133 one high spin off speed. The max torque
3198
Power BHP 200 @ 2200 rpm 9 - Telescopic kelly bar with guide to
Crowd system kN 123.7 / 101.8 mast available with friction or mechanical
4500
2550
Operating weight tons 35 locking type
2553
Transport weight (c/w kelly bar) tons 34
2256
344
The nominal values are referred to 100% total efficiency. 395 750
8
1267
940
885
795
520
Continuous Flight Auger (CFA)
4510 3710
500
450
EXTENDED TRACK WIDTH 3700 mm 3500 3500
3500 3500 (MIN. 3000) 3621 SHOE WIDTH 600 mm
Max pile diameter mm 750 (3000+3500)
(3000÷3500) 3950
MIN. 2750 MAX. 3950
3666
707 600
1870
1509
12090 12119 WEIGHT: 1000 kg
elements length depth weight height elements length depth weight height
no m m tonn m no m m tonn m 1474
3277
3426
4x 7,5 25,0 2,9 5,0 4x 9,0 34,0 3,3 5,0
2540
2540
2500
1652
1652
1652
1649
4x 9,0 32,0 3,3 5,0 4x 11,0 38,0 3,9 4,6
1279
952
795
852
885
952
4x 11,0 39,0 3,9 4,6 5x 10,5 46,5 8,5 8,3 1199 1397
WEIGHT: 33000 kg
5x 9,0 40,0 4,3 5,0 5x 11,5 51,5 9,0 8,3 1199
1360 3254
1986
5x 11,0 48,0 5,1 4,6 5x 13,5 62,0 10,3 6,76 3269 4510 4311
3269 4510 4340
The main features of the R-312/200 are the following: 2 - Turret c/w CUMMINS 6BTA55.9-C200
6000
- new powerful rotary diesel engine and sound proofed canopy,
- high speed drilling mounted on a 360° slew ring
6000
- easy transport: it can be transported with rotary and kelly bar installed 5
3 - Winch assembly
- compliance with the machine laws for safety standards
- total reduction of rig up time, about 20 minutes from arrival to the job site 4 - Parallelogram system allowing
- easy to use and handle working radius adjustment always
- low operating costs maintaining the mast in vertical position.
- wide range of accessories (depthmeter, inclinometer, air conditioning, free fall winch) C/w electronic device for automatic stop ø 750
21742
intermediate element 11.9 m long and
8646
Large diameter bored pile
a top element 3.5 m long. The max torque 750
10490
can be applied all over the mast length
24900
17784
Max pile diameter mm 1500
1932
Max pile depth m 48 (with 5x11 kelly bar) 6 - Sheave cathead 7
16228
16600
13500
130
13000
Max drilling speed rpm 42 hydraulic cylinder
890
Spin off speed rpm 153 8 - Rotary head with 3 drilling speeds and
10500
5250
Main winch nominal line pull kN 133 one high spin off speed. The max torque
3198
Power BHP 200 @ 2200 rpm 9 - Telescopic kelly bar with guide to
Crowd system kN 123.7 / 101.8 mast available with friction or mechanical
4500
2550
Operating weight tons 35 locking type
2553
Transport weight (c/w kelly bar) tons 34
2256
344
The nominal values are referred to 100% total efficiency. 395 750
8
1267
940
885
795
520
Continuous Flight Auger (CFA)
4510 3710
500
450
EXTENDED TRACK WIDTH 3700 mm 3500 3500
3500 3500 (MIN. 3000) 3621 SHOE WIDTH 600 mm
Max pile diameter mm 750 (3000+3500)
(3000÷3500) 3950
MIN. 2750 MAX. 3950
3666
707 600
1870
1509
12090 12119 WEIGHT: 1000 kg
elements length depth weight height elements length depth weight height
no m m tonn m no m m tonn m 1474
3277
3426
4x 7,5 25,0 2,9 5,0 4x 9,0 34,0 3,3 5,0
2540
2540
2500
1652
1652
1652
1649
4x 9,0 32,0 3,3 5,0 4x 11,0 38,0 3,9 4,6
1279
952
795
852
885
952
4x 11,0 39,0 3,9 4,6 5x 10,5 46,5 8,5 8,3 1199 1397
WEIGHT: 33000 kg
5x 9,0 40,0 4,3 5,0 5x 11,5 51,5 9,0 8,3 1199
1360 3254
1986
5x 11,0 48,0 5,1 4,6 5x 13,5 62,0 10,3 6,76 3269 4510 4311
3269 4510 4340
R-312/200
and representative offices as:
SOILMEC S.p.A.
Ground Engineering Equipment
5819, via Dismano
47023 Cesena (FC) - Italy
tel. +39-0547-319111
fax +39-0547-318548
http:// www.soilmec.it
e-mail: soilmec@soilmec.it
R-312/200
and representative offices as:
SOILMEC S.p.A.
Ground Engineering Equipment
5819, via Dismano
47023 Cesena (FC) - Italy
tel. +39-0547-319111
fax +39-0547-318548
http:// www.soilmec.it
e-mail: soilmec@soilmec.it
d. Lift Plan
Project Name
Equipment to be used on
Soilmec SF50 CFA Piling Rig
site.
BRE Load Case 1:
qlk = 167kPa, L1 = 2.24m,
W1 = 0.7 m
Maximum plant loading
BRE Load Case 2:
q2k = 277kPa, L2 = 1.27m,
W2 = 0.7 m.
(Note: BR470 ’Working Platforms for Tracked Plant: Good practice guide to the design, installation, maintenance and repair
of ground-supported platforms’ is available from IHS BRE Press – Tel 01344 328 038)
Designer Organisation
The working platform will be REGULARLY INSPECTED, MAINTAINED, MODIFIED, REPAIRED, and
REINSTATED to the as-designed condition after any excavation or damage, throughout the period
when the equipment is on the site. A completed copy of this certificate signed by an authorised
person from the Principal Contractor shall be given to each user of the working platform prior to
commencement of any works on site.
Organisation Signature
The HSE has worked closely with the FPS to develop this initiative and supports the principle of reducing
accidents by the certification of properly designed, prepared and maintained working platforms