ABSTRACT OF COST

ANNEXURE - lI
Name of work :- Improvement of NH- 202 Junction to Khuilungtang, Dungrei, Hungpung road 0 - 2.26 km. (SH :- Providing granular sub base of shingle
from 0.00 - 2.26 km WBM & PC surface from 0 - 1.46 km)

Sl. No. Sub-head & Items of work Quantity Rate Unit Amount Remark
1 2 3 4 5 6 7
Rate
1 Preparing sub-grade by excavating earth upto 22.5 cm deep, dressing to camber and based on
8475.00 Rs. 32.90 Rs. 2,78,828.00
consolidating with road roller including disposal of surplus earth within 50m. MSR'2017
2 Providing laying & compacting granular base/sub-base according to lines, grades& cross-
sections by using naturally occurring sand gravel/conforming to IRC Grade 2 of M.O.S.T.
specification free from organic or other deleterious constituents compact by rolling with power
roller of 8 to10 tonnes capacity in layers not exceeding 150 mm (spread thickness)including
1271.25 Rs. 1,660.28 m3 Rs. 21,10,631.00 - do -
rolling of the road surface to proper level & grade 30 cm width edging on both sides etc.
complete as directed by the Engineer-in-charge. ( i/c carriage charge of all materials)
3 Providing and laying one layer W.B.M. 7.5 cm consolidated thickness using 1 cum of stone
aggregate conforming to IRC Grades per 10 sqm of road surface & 0.23cum of binder materials
of approved quantity per 10 sqm of road surface including consolidating of the same, rolling of
the surface to camber, superelevation & grade by using template straight edges & spirit level in
layers not exceeding 100 mm to 130 mm thick (spread thickness), dry & wet rolling with 8 to10
tonne roller including earth edging 30 cm width on both sides & applying binding materials as
specified i/c carriage charge of all materials
i) I.R.C. Grade -II 410.63 Rs. 3,775.04 m3 Rs. 15,50,126.00 - do -
ii) I.R.C. Grade -III 410.63 Rs. 3,856.26 m3 Rs. 15,83,477.00
4 2cm consolidated thick single coat pre-mix carpet surfacing with 0.27 cum stone chipping
12.5mm sizes 0.18cum and 10mm size 0.09 cum mix with 14.6 kg. of binder per 10sqm of road
surface & rolling complete i/c. a seal coat IRC type "B" with 0.06 cum of stone chipping 6.3mm
niminal size and 6.8kg of bitumen 80/100 per 10sqm of road surfaces i/c P/A evenly a
priming/tack coat with bitumen (80/100) @ 10kg/10sqm & Preparing surface by bursing with wire
5475.00 Rs. 384.60 m3 Rs. 21,05,685.00 - do -
brushes for ramming caked mud etc. sweeping with brooms and finally fanning the cleared
surface with gunny bags to removed all loose dirt etc. and providing & applying evenly a priming
tack/coat with Bitumen (80/100) @ 10 Kg./10Sqm.
Rs. 76,28,747.00

Assistant Engineer Executive Engineer,


Ukhrul HQ. Sub-Division, PWD, Manipur. Ukhrul Division, P.W.D. Manipur.