Professional Documents
Culture Documents
No. URAIAN
( Rp )
VI DIBULATKAN 500.000.000,00
A. PROFESIONAL STAFF
1 Supervision Engineer Orang 1,00 7,00 26.662.500,00 186.637.500,00
2 Quantity /Quality Engineer Orang 1,00 5,00 24.885.000,00 124.425.000,00
Laporan Pengawasan :
1 Laporan RMK Eks 1,00 5,00 84.000,00 420.000,00
2 Laporan Pendahuluan Eks 1,00 5,00 150.000,00 750.000,00
3 Laporan Mingguan dan Bulanan Eks 7,00 5,00 150.000,00 5.250.000,00
4 Laporan Akhir Eks 1,00 5,00 350.000,00 1.750.000,00
5 Hardisk Bh 1,00 1.000.000,00 1.000.000,00
TOTAL BIAYA REPRODUKSI LAPORAN 9.170.000,00