This Job Safety Analysis document outlines the hazards and safety controls for filling, gauging, and hydrostatic testing of pipes. It identifies hazards such as damage to pipes, personal injury, soil pollution, and risks associated with the use of pressure pumps and measurement instruments. The safety controls include marking work areas, using warning signs, conducting toolbox talks, requiring permits of work, using proper PPE, clearing non-essential personnel, training workers, and having first aid available. The document aims to minimize risks and ensure safety during the tasks.
This Job Safety Analysis document outlines the hazards and safety controls for filling, gauging, and hydrostatic testing of pipes. It identifies hazards such as damage to pipes, personal injury, soil pollution, and risks associated with the use of pressure pumps and measurement instruments. The safety controls include marking work areas, using warning signs, conducting toolbox talks, requiring permits of work, using proper PPE, clearing non-essential personnel, training workers, and having first aid available. The document aims to minimize risks and ensure safety during the tasks.
This Job Safety Analysis document outlines the hazards and safety controls for filling, gauging, and hydrostatic testing of pipes. It identifies hazards such as damage to pipes, personal injury, soil pollution, and risks associated with the use of pressure pumps and measurement instruments. The safety controls include marking work areas, using warning signs, conducting toolbox talks, requiring permits of work, using proper PPE, clearing non-essential personnel, training workers, and having first aid available. The document aims to minimize risks and ensure safety during the tasks.
Document Control #: FO-JSA-09 Revision Date: 17/07/2017
Task: Filling, gauging and hydrostatic testing Issuer: Ghaith YOUNSI
Description Hazard Control
Marking the work area, warning signs to be clearly displayed, Tool box talk will be given to the worker at site prior to start the work Permit of work signed and completed by the HSSE - Damage of pipe officer , Pipe filling - Personal injury Study of the ground (if wet, stability ...) before the start of the operation. Persons not involved in this operation will be cleared from work area, Only competent persons will be included in this operation . Check fluid test before start of operation , Soil pollution, Tool box talk will be given to the worker at site prior to Testing fluid start the work Personal injury . Wear appropriate PPE, Use pressure pump Pump in pression warning signs related to this operation to be clearly displayed , Existence of an instruction related to the risks of the work to the work near the pressure pumps , Parsonal training , Persons not involved in this operation will be cleared
Job Safety Analysis FO-JSA-01 Issue 1.0
from work area, Sensibilization of personal related to the risks of working near the pressure pump, First aid kit will be avaliaible , A first-aid worker must be available to staff.
The HSE supervisor must check the certificates and
status of all the measures instrument , Disposal of Defective Measurement Instruments, Utilisation des instruments de Instruments des mesures non Personal training, mesures conformes Permit of work signed and completed by the HSSE officer , Workers must also learn reduce their muscle tension during their work and work in a good position .