You are on page 1of 3

Job Safety Analysis (JSA)

Document Control #: FO-JSA-09 Revision Date: 17/07/2017


Task: Filling, gauging and hydrostatic testing Issuer: Ghaith YOUNSI

Description Hazard Control


 Marking the work area,
 warning signs to be clearly displayed,
 Tool box talk will be given to the worker at site prior to
start the work
 Permit of work signed and completed by the HSSE
- Damage of pipe officer ,
Pipe filling
- Personal injury  Study of the ground (if wet, stability ...) before the start
of the operation.
 Persons not involved in this operation will be cleared
from work area,
 Only competent persons will be included in this
operation .
 Check fluid test before start of operation ,
Soil pollution,  Tool box talk will be given to the worker at site prior to
Testing fluid start the work
Personal injury .
 Wear appropriate PPE,
Use pressure pump Pump in pression  warning signs related to this operation to be clearly
displayed ,
 Existence of an instruction related to the risks of the
work to the work near the pressure pumps ,
 Parsonal training ,
 Persons not involved in this operation will be cleared

Job Safety Analysis FO-JSA-01 Issue 1.0


from work area,
 Sensibilization of personal related to the risks of
working near the pressure pump,
 First aid kit will be avaliaible ,
 A first-aid worker must be available to staff.

 The HSE supervisor must check the certificates and


status of all the measures instrument ,
 Disposal of Defective Measurement Instruments,
Utilisation des instruments de Instruments des mesures non  Personal training,
mesures conformes  Permit of work signed and completed by the HSSE
officer ,
 Workers must also learn reduce their muscle tension
during their work and work in a good position .

Job Safety Analysis FO-JSA-01 Issue 1.0


Name of present Signature

Approved by:

Job Safety Analysis FO-JSA-01 Issue 1.0