Document Control #: FO-JSA-010 Revision Date: 17/07/2017
Task: De-watering, drying Issuer: Ghaith YOUNSI
Description Hazard Control
Marking of the working area at least 1 meter from the edge of the trench, Safety signs will be displayed for this operation, Tool box talk will be given by the HSSE supervisor to the worker at site, Permit to work signed and completed by the HSSE supervisor concerned parties Persons not involved in this operation will be cleared Only competent persons will be involved in this - Treated Water and air Treated Water removal operationOnly authorized persons will be in the work pressure area, Fix and prepare where to drain the pipe linePrepare a drain pit to contain the testing water Wear appropriate PPE, Check the compressor and hose connection, Reduce compressor noise as much as possible.Use ear plugs where noise exist (Air compressor) The HSSE supervisor shall ensure the display of sign ‘prohibited accesses to the work area’. Marking of the working area at least 1 meter from the edge of the trench, Drying - Pressure Foam Pig Safety signs will be displayed for this operation Permit to work signed and completed by the HSSE Job Safety Analysis FO-JSA-01 Issue 1.0 supervisor, Persons not involved in this operation will be cleared Only competent persons will be involved in this operation, Wear appropriate PPE, Verification of the conditions of use of PPE and their adaptation to this operation (gloves, safety shoes and helmet)