Project Charter Doc Number XX

Version XX

Revision History

Name Date Reason For Changes Version

Charter No: 01

Project Telecom Tower


Created By Aqua Group Date 24-12-2020
Phone 051-5165653 Email aqua5050@gmail.com

Project Description Team Aqua with its crew, performing general construction activities with an
emphasis on tower system installation, maintenance, and inspection of support
structures used in the provision of essential telecommunication systems,
including personal wireless communications, public safety communications,
utility networks, and broadcasting in the F.8 Sector Islamabad. It includes new
advanced 4G technology for 1500 residence and approximately 9000 persons.
Project Charter Doc Number XX
Version XX

Deliverables or Key
Milestones Event or Deliverable Target Date Responsibility
Procurement 24 Dec to 24 Jan Waseem + Maska
Team safety training 24 Feb to 24 May Aqua Group
Team technical training 25 May to 24 Aqua Group
June
Raw Material (handling and
storage)
Construction start date
Site on air date – The date when
the technology system is
operational and carrying traffic
Construction complete date
Installation of Safety features in
telecom towers (tower aviation
lamps at the crown, lifelines
etc., painting)

Construction of shelters for


Indoor installations, technical
facilities construction and
interior design, connection and
installation of power generation
set up

Installation and connection of


FTTA (optical fibers to
antenna)

Maintenance

Inception and closing


Project Cost 17,450,000
Projection (budget)
Stakeholders Sir Salman Tasneem Ghanni
Project Charter Doc Number XX
Version XX

Resources HR Resources:

Fiza Mushtaq
Sonia Hanif
Maska Khan
Waseem Abbas Mujahid

Other resources:

Raw material
Storage place
…….
……
……
…..

Project Technical risk


Consideration Employees safety risk
(Issues/Risks Operational risk
Time for completion of the scope
Stakeholder requirement
Performance standards and construction quality
Technology installation standards

Project Budget
17,900,000

(450,000 + 500000 )?????? Explain what these figure meant

Approvals