Professional Documents
Culture Documents
Engineering Department
EXHIBIT A.
NO CRITICAL PATH.
EXHIBIT B.
RECURRING CONTRACTOR PERFORMANCE PROBLEMS NO CRITICAL PURCHASE PLAN.
NO CONSTRUCTION PLAN.
Some of the specific problems owners experience
are: networks with too much detail, networks with
poor logic, lack of early identification of critical-
. SLIGRTING OF UX;ISTIC PROBLEMS.
ity, hazy construction planning, and minimal sense
of urgency in purchasing critical material. In too
many instances engineering progress is measured by
manhours expended, instead of by useful work per- . NO/POOR SDBCONTRACT PLAN.
325
EXHIBIT C. COMMUNICATION - A VITAL AND NEGLECTED FACTOR
ENGINEERING MANPOWER CONTROL.
Too often schedules, especially logic networks,
This necessary early control is to ensure appear to be a mass of arrows, lines and circles.
that the contractor has sufficient manpower At first sight, engineering and construction mana-
available and planned to meet current and future gers throw up their hands in horror and resort to
requirements. The evaluation should cover the barcharts which they have maintained for just such
contractor's total workload, past experience with a situation. When this happens, both owner and
scope increases, available manpower, possible means contractor lose; sometimes for the specific project,
of effectively augmenting manpower, allowances for and always in the long run. Schedule engineers
lost time, holidays and vacations, and so forth. need to be reminded, regularly and forcibly,
that "their" schedule is not the end product. The
successful completion of the project is the end
product.
EXHIBIT E.
THE SCHEDULE ENGINEER.
EXHIBIT D.
In a recent national three-day seminar on
On very large projects in remote locations,
material logistics are a major problem. planning and scheduling, a survey of attending
It is
essential that material tonnage histograms be contractors showed that approximately 10% of their
schedule personnel fulfilled the requirements listed
prepared and evaluated against the capacity of
proposed transport and unloading facilities. It in Exhibit E. Large, complex projects require
is more than embarrassing to find the daily tonnage capable and experienced schedule engineers. Too
often, detailed and sophisticated shceduling systems
capacity of a shipping harbour is a tenth of that
required to handle peak-month shipments. have proven ineffective due to the lack of exper-
ience of the schedule engineers. As owners' re-
presentatives, it appears to us that in many cases
the contractor's career structure does not place
sufficient weight on the position of schedule
engineer. We have observed young capable schedule
engineers moving into interesting, supervisory
responsibility within the engineering, project
and construction departments. That's fine, but we
also need to see such people moving into respected
and responsible positions in scheduling.
326
of a project with a preliminary, generalized over- criticality is often fould for the procurement of
all critical path schedule, detailed operational long delivery equipment and materials.
requirements, and a lean-but-adequate owners task
force to monitor the contractor's operations. The Construction subcontracts are a major consider-
responsibility of the owners task force is to define ation, and the "Subcontract Preparation Schedule"
the owner's interests and see that they are preserved can be effective in letting and controlling sub-
throughout the project. Detailed planning, sched- contracts in a businesslike, orderly fashion, with
uling and control are the contractor's responsibility, due regard to their criticality.
and it is his responsibility to see that they are
efficient operations, effectively utilized. The key elements of engineering progress are
usually found in civil design, and in production
This is an equal partnership operation. of piping isometrics. Curves showing the cubic
yards of concrete which have been defined by
drawing issue, and the piping which has been defined
SENIOR SCHEDULE ENGINEER Exhibit E by isometrics issued, all against a time scale,
can be effective in monitoring engineering progress.
QUALIFICATIONS
Construction status reporting can be improved
by relating progress to quantified bi-weekly work
programs.
. EDUCATION - BATCHELOR DECREE OR EQUIVALENT.
Effective construction subcontract control
requires appropriate contractual provisions author-
. 5 YEARS OR MORE IN RELATED INDUSTRY WORK. izing monitoring of progress and performance.
. BE PREPARED TO TRAVEL.
EXHIBIT F.
MODIFICATIONS TO THE TYPICAL CONTRACTOR SYSTEM.
It cannot be emphasized too strongly that Owner and contractor must structure their
collection and analysis of historical schedule and task force organizations to harmonize. The better
cost data on an integrated basis is essential for the coordination and communication of owner and
effective project control of both schedules and contractor personnel in this joint task force
costs. Integration of scheduling with cost control operation, the greater the prospect for successful
functions throughout project performance is vital project execution.
for efficient operation.
Systems and procedures do not build projects.
A significant feature of a successful schedule People do.
monitoring operation is the relationship between
contractor and owner personnel. As seen from the
flow chart, one item of the initial execution phase
of a capital project is "screening and qualifying"
contractors prior to contract award. During this
activity, owner scheduling requirements can be
clearly explained, and performance commitments
obtained from the contractors being screened.
EXHIBIT J.
PROJECT MASTER SCHEDULE - U. S. A.
328
EXHIBIT L.
OVERALL BREAKDOWN - MEDIUM SIZED PROJECTS
EXHIBIT K.
OVERALL BREAKDOWN - LARGE PROJECTS.
EXHIBIT N.
CONSTRUCTION SUBCONTRACT CONTROL.
330