CHECKLIST Page : 1 of 1
Prep. : ASH, BKT, PKS, RK
Familiarisation with Cargo Handling Appr. : CMS
Equipment and Deck Machinery Date : 30.06.2016 Rev: 01
9as appropriate
• Has the operation of the following equipment been studied and fully understood?
− Cargo Pumps including trips and locations, starting and stopping procedure
− Inert Gas/N2 Plant System and venting arrangements, pressure censor (if fitted)
− Ballast pump electrical/steam operated including starting and stopping
− Auto Unloading System
− Cargo eductors
− Ballast eductors
− Cargo and ballast lines, IG lines on deck and pump room (as applicable)
− Cargo valve system operation (remote and local)
− Cargo stripper pump
− Ballast exchange system (including sediment removal system if fitted) & precautions
− Tank cleaning pump oil discharge and monitoring equipment
− Fixed gas detection system (pump room and ballast tanks)
− IG and O2 recorder
− Cargo Tank Gauging System
− Ballast Tank Gauging System
− Draft Gauging System
− Portable ullaging and sampling equipments
− O2 analyser, HC detector (Explosimeter and Tankscope), H2S detector
− Load Computer
− Hydraulically operated valves (including deck stand) and hand pump
− Anti pollution equipment
− Anchoring of cargo lines, expansion bellow and reaction pads
− Cargo tank high level and high-high level alarm
− Cargo heating system, if fitted
− ODMCS
− Pump room bilge alarm
− Hypermist detection system, if fitted
− Operation of framo pumps and portable framo pumps
− Inerting and purging of double hull spaces
− VEC and VOC system
• Are you familiar with mooring arrangement of the vessel?
• Are you familiar with operation of following deck machinery?
− Windlass and winches
− Hose handling crane and provision crane
− Gangways and pilot assist ladder
− Air operated pumps for oil containment
− Capstan
Name of Officer.....................................................