Professional Documents
Culture Documents
Power Flow Study and Contingency Status of WSCC 9 Bus Test System Using MATLAB
Power Flow Study and Contingency Status of WSCC 9 Bus Test System Using MATLAB
Abstract—Power flow study is the initial step which provides II. POWER SYSTEM ANALYSIS TOOLBOX (PSAT)
voltage magnitudes, phase angles, active and reactive power flows
at respective buses under normal operating conditions. It helps in
analyzing the current state of the power system and effective The Power System Analysis Toolbox (PSAT) which is an
alternative options for expanding the existing system in order to open source Matlab toolbox used in simulation and analysis of
meet with the increasing load demand. Contingency Analysis is small and medium sized electric power system.
also a major part of study for reliable and planned operation of
power system. It is very significant function in modern Energy PSAT has following tools to analyze the network:
Management Systems. The objective of contingency analysis is to
give operator the information about the static security. There are
several factors which may lead to the contingency in power
system, for example line outage, transformer outage, generator 1. Power flow [Newton Raphson, (BX, XB) Fast Decoupled
outage and overloads resulting the extreme situations such as methods]
voltage collapse, over loads in other branches and/or sudden 2. Optimal power flow
system voltage rise or drop. Contingency analysis is used to 3. Continuation power flow
calculate parameters violations. In this paper, maximum loading
4. Small signal stability analysis and
parameter is calculated and contingency status of Western
System Coordinating Council 3 Machine, 9 Bus test system is 5. Time domain simulation as well as several static and
done using PSAT toolbox in MATLAB. dynamic models, including non-conventional loads,
synchronous and asynchronous machines, regulators and facts.
Index Terms— Contingency Ranking, Continuation Power
Flow (CPF), PSAT, Maximum Loading Parameter (Ȝ) PSAT is also provided with a complete set of user-friendly
graphical interfaces and a Simulink-based editor of one-line
network diagrams.
I. INTRODUCTION
Voltage instability happens in a power system due to its III. DETERMINATION OF CONTINGENCY STATUS WITH
stressed condition. Voltage instability leads to voltage collapse REFERRED TO BUS
which leads to total blackout to the whole system. Forecasting System under examination is WSCC 3 machine, 9 Bus test
of voltage collapse is significant in power system planning and system with 100 MVA base shown in Fig.1. It consists of 3
operation because it is one of the main reason of voltage two winding transformers connected at bus no. 1, 2 and
instability which can be avoided by proper analyzing the 3.Three generators connected at bus no. 1, 2 and3, six constant
contingencies. Line outage contingencies are ranked in order impedance transmission lines with 100 MVA base and 3 PV
to identify the line which highly affects voltage stability of the loads connected at bus no. 5, 6 and 8.Bus no. 1 is the swing
system when there is an outage occurs in that particular line, it bus.
could be recognized and instant protection is provided to the
system. The contingency ranking process can be conducted by Step 1: Make the single line diagram of the test system.
computing the maximum loading parameter of each line for a
particular line outage. The contingency which is ranked Step 2: Input the data for each and every component of the test
highest implies that it contributes to system instability. system as required.
Step 4: Solve the Power Flow using Newton Raphson for the
test system without any contingency.
G1 72 28 1.04
G2 163 5 1.025
G3 85 -11 1.025
Voltage ratio
X MVA
T1 0.0576 77 16.5/230 KV
T3 0.0586 86 13.8/230 KV
6 90 30 1
8 100 35 1
339
2015 International Conference on Recent Developments in Control, Automation and Power Engineering (RDCAPE)
340
2015 International Conference on Recent Developments in Control, Automation and Power Engineering (RDCAPE)
TABLE VI: Power Flow using Newton Raphson Method having trapezoidal
rule as Integration Method with transmission line outage TABLE VIII: Contingency ranking for WSCC 9 bus system
Transmi
ssion
line Severity Maximum Loading
Pgen Qgen Pload Qload Ploss Qloss Bus
from order parameter (Ȝ)
(pu) (pu) (pu) (pu) (pu) (pu)
bus no. x
to bus
no. y
1 4 TO 5 0.89151
4-5 3.1745 2.3942 2.9691 0.74362 0.20546 1.6505
2 5 TO 7 1.1053
4 6 TO 9 1.1841
7-8 3.4298 2.209 3.2735 0.8654 0.15632 1.3436
5 8 TO 9 1.4823
Voltage at Bus1
Maximum Loading (pu) 1.04 1.04 1.04 1.04 1.04 1.04
S.No. Bus
Parameter (Ȝ)
Voltage at Bus2
(pu) 1.025 1.025 1.025 1.025 1.025 1.025
Voltage at Bus8
Table VII shows the values of Maximum Loading Parameter (pu) 0.96923 0.95 0.997 0.984 0.983 0.876
(Ȝ) after outage of single transmission line one by
one.Maximum loading parameter is found using Continuation Voltage at Bus9
Power flow. (pu) 1.001 0.949 1.007 1.012 1.012 0.894
341
2015 International Conference on Recent Developments in Control, Automation and Power Engineering (RDCAPE)
V. CONCLUSION
Contingency Analysis is one of the important aspects in
current scenario of energy management system. It helps the
operator to determine the most critical element in the system .
which must be identified in order to avoid further
discrepancies resulting in system blackout. In this paper power
flow is done to find line power losses and bus voltages of
remaining system and CPF is performed finding maximum
loading factor. Contingency analysis is done here for outage of
transmission lines. Lines are removed one by one taking other
lines with original values. Buses are arranged with respect to
the maximum loading parameter and it is found that
transmission line connected between bus 4 and 5 has least
loading parameter while transmission line connected between
4 and 6 has highest loading parameter. Consequently
transmission line connected between bus no. 4 and 6 should be
highly protected to avoid voltage instability. This increases the
reliability and efficiency of the interconnected system which is
required.
References
[1] Namami Krishna Sharma, Sudhir P. Phulambrikar, Manish Prajapati,
Ankita Sharma, “Contingency Ranking and Analysis using Power
System Analysis Toolbox (PSAT)”,IISTE [Online],Vol.4(6), pp. 59-63,
2013. Available: http://www.iiste.org
[2] Bhakti Nitve, Rajani Naik, “Steady state analysis of IEEE-6 Bus System
Using PSAT power toolbox”, IJESIT, Vol.3, pp 197-203, May 2014.
[3] W.-K. Chen, “Linear Networks and Systems. Belmont”, CA:
Wadsworth, pp. 123–135, 1993.
[4] Ismail Musirin, Titik Khawa and Abdul Rahnia, “Fast Automatic
Contingency Analysis and Ranking Technique for Power System
Security Assessment”, SCOReD, Putrajaya, Malaysia, pp.231-236.
2003.
[5] Mostafa Alinezhad and Mehrdad Ahmadi Kamarposhti,”Static Voltage
Stability Assessment Considering the Power System Contingencies
using Continuation Power Flow Method” World Academy of Science,
Engineering and Technology, Vol:3, pp.628-634, Feb. 2009.
[6] M. A. Kamarposhti, H. Lesani, “Contingencies Ranking for Voltage
Stability Analysis using Continuation Power Flow Method”, Elektronika
irelektrotechnika, Vol:3, pp.73,76, 2010.
[7] Ahmadi Kamarposhti M., Alinezhad M. ,”Effects of FACTS Controllers
on Maximum Loading Point to Study Static Voltage Collapse
Phenomena”,23rd International Power System Conference (PSC 2008),
pp.1-11,Tehran, 2008.
[8] Poshtan M., Rastgoufard P., Singh B,” Contingency Ranking for
Voltage Stability Analysis of Large-Scale Power Systems”, Proceeding
of IEEE PES Power System Conference and Exposition,pp. 1595-
1602,2004.
[9] Majid Poshtan, Parviz Rastgoufard, and Brij Singh, “Contingency
Ranking for Voltage Stability Analysis of Large-Scale Power Systems”
, Proceeding of IEEE /PES Power System Conference and Exposition,
pp. 1595-1602, Oct. 2004.
[10] Prabha kundur,”Power System voltage stability and Control”, McGraw-
Hill.
[11] Carson W. Taylor, “Power System voltage stability and Control”,
McGraw-Hill, Inc.1993.
[12] An Open Source Power System Analysis Toolbox, Federico Milano,
Member, IEEE.
342