BPM 305 (TMA01) – PROJECT SCHEDULING AND CONTROL (MOHAMED ALI B1210887)

technical institutes
technical institutes and general hospitals.
hospitals. This record and testi
testimony
mony intends to
formulate consistency of classification and identification of functional areas so
that end users, quantity surveyors and architects can liaise and coordinate their 
prerequisites and resolution on a common or level platform.

 As such, a massive and extensive database or directory of buildings initially


analysed to be converted into functional area costs. It is complicated and time
consuming as elemental cost analysis is needed with reference to the tender 
sum before segregating or subdividing between the various functional spaces.
The functional area for each function are aggregated or multiplied with the
functional area rates and summed or totalled.

(b) Work out the estimated cost of a hospital using each of the methods.

(i) Unit Method.


Functional units: 2000 number of beds
Cost per bed: $60,000 based on updated data

Total estimated cost = $60,000 x 2000 = $120,000,000

(ii) Superficial Method. 

Page 11 of 22