You are on page 1of 10

Proceedings of Bridge Engineering 2 Conference 2008

23 April 2008, University of Bath, Bath, UK

A CRITICAL ANALYSIS OF THE DONGHAI BRIDGE, SHANGHAI,


CHINA
Ci Song1
1
University of Bath

Abstract: This paper provides a critical analysis of the Donghai Bridge which includes aesthetics, loading,
structure, construction, durability, vandalism, future changes and improvements. It gives the idea how to look a
bridge from an aesthetic view and also how a bridge is actually built. Especially for a crossing-sea project, the
special construction methods are designed due to harsh site conditions and limited construction period.

Keywords: crossing-sea project, cable-stayed bridge, prefabrication

1 Background information
Donghai bridge is located at north of Hangzhou Bay
in East Sea of China. It can also be called as the East Sea
Bridge. By being one of the three collaboration works,
part of Shanghai international shipping center, Donghai
Bridge is the connection in Yangtze Delta vest area (i.e.
Shanghai City, Jiangsu Province and Zhejiang Province).
It services for the overland transport of containers of
Yangshan Deep Water Port of International Shipping
Center and it offers water supply, electricity supply and
communications, etc. The Yangshan Deep Water Port is
China’s first free-trade port upon its completion in 2010.
The Donghai Bridge starts from the Luchao Port in Figure 1: Location of Donghai Bridge
Shanghai and goes across north area of Hangzhou Bay,
and finally, reaches the small Yangshan Island in Zhejiang In March 2001, the deep water port project in
Province. The location of site is shown in Fig 1. Donghai Shanghai is formally agreed by the nation. After one year,
Bridge is the first truly offshore bridge in china’s bridge in March 2002, the State Council examined and passed
history and it is also the longest cross-sea bridge in the the feasibility research on the first phase of this project.
world. The total cost of project is about 11.8 billion CNY The construction commenced in June 2002 and continued
(1.64 billion USD). for three and half years. In Dec 2005, Donghai Bridge
The overall length of Donghai Bridge is 32.5km and was completed together with the deep water port (Phase I)
width of the bridge is 31.5m. It is designed to be a and opened to traffic. Ref. [1] Innovative anti-corrosion
motorway bridge which carries 6 lanes of traffic. This technique is used to prevent the marine corrosion in
includes 3.7km onshore section (Luchao Port, Shanghai), Donghai Bridge. So the bridge is designed to stand for
25.3km offshore section (between Luchao Port and Big 100 years.
Tortoise Island) and 3.5km sea embankment including
another cable stayed bridge – Kezhushan Bridge (between
Big Tortoise Island and Kezhushan Island). The 2 Aesthetics of the Bridge
Kezhushan Bridge is not analyzed in this paper. The aesthetics of bridges plays a very important role
in the overall success of building a bridge. Fritz
Leonhardt, the most famous bridge engineer of the 20th
E-mail: cs283@bath.ac.uk
century, defined ten aspects of aesthetics of bridges, because different thickness of deck is used for the
which are used to analyze the aesthetic design of Donghai auxiliary navigation span which is shown in Fig 3. This
Bridge. can be covered by varying the box girder section
thickness internally, but it is very inefficient and huge
waste of materials.
2.1 Fulfillment of Function
The structure of Donghai Bridge is very simple and
clearly shown to the public. The main span of the bridge
is a cable-stayed bridge with double pylons. The deck is
held by groups of cables connecting to two pylons. Two
inverse Y- shaped massive pylons give confidence in
stability of the bridge. Cable-stayed bridges are very often
chosen for large span crossing-sea projects due to its
simple construction and clearly fulfillment of functions.
Simplicity leads to the successful design of function of
Donghai Bridge.

2.2 Proportions
Proportions have significant effect on designing
Figure 3: Various thickness of deck at auxiliary
bridges. All balances between masses and voids, depths
navigation spans
and spans need to be achieved. As shown in Fig 2,
Donghai Bridge displays excellent proportions across the
sea. The masses and voids are perfectly balanced. The 2.4 Refinements
height of pylons also matches the maximum span. The
There are only two piers at each support across the
thickness of deck is just correct to the breath of piers.
width of deck so that no views of opaque barrier will
Everything are balanced and perfectly fit to each other. All
appear from oblique angles. Not much more refinements
these balances give an impressive aesthetic view of the
have been done to create the aesthetics of Donghai Bridge.
bridge.
For the improvement of the refinements to the bridge,
tapering piers can be used rather than a straight one.

2.5 Integration into the Environment


As shown in Fig 2, Donghai Bridge is a cable-stayed
bridge which gives a wonderful pleased view across a
wide span of water. Donghai Bridge has a great success in
integrating its own structure into the surrounding features
and environment.

Figure 2: Proportions of bridge 2.6 Surface Texture


Surface texture is very important in bridges, but often
2.3 Order ignored. Ref. [2] Same as all other concrete bridges, the
surface texture of Donghai Bridge is a matt finish. Rough
Some cable-stayed bridges may have potentially ugly finishing is very often used in piers, but in this case, most
view from oblique angles due to the crisscrossing of structural elements are prefabricated and have much finer
cables. This problem only happens when two or three finishing than cast in-situ. Therefore, a significant
planes of cables were designed to support the structure. In aesthetic appeal has been added to Donghai Bridge by its
order to prevent the crisscross cables, Donghai Bridge is smooth finishing.
designed to have only one plane of cables. But the
single-plane system reduces the torsional strength of the
structure. So the deck needs to be substantially stiffened 2.7 Colour and Character
to take the additional torsion and this result very deep Black cables have been used in Donghai Bridge to
deck which is inefficient. To overcome this problem, an accentuate the certain cables in day times. Because all
inverse Y-shaped tower is used instead of just one vertical cables of bridge are in black, so they disappear at night.
pylon. The top of the inverse Y-frame is made vertical and Only the deck and two pylons are high-lighted with blue
all cables attached along this part of the pylon with a fan artificial lighting at night. Contributing with two lines of
configuration. The fan configuration of cables gives most lamp lighting, the bridge is just like a dragon floating on
efficient effect to the structure. Therefore, this system the sea when looking from far away.
gives maximum benefit for a single plane of cables while
unpleasant oblique views avoided.
For a good ordered bridge, there should be non-stops
or an unbroken line as eyes moving through the entire
length of bridge. The Donghai Bridge fails in this field
E-mail: cs283@bath.ac.uk
γ fL = 1.15 (ULS – combination 1)
γ f 3 = 1.10 (ULS – combination 1)
The dead load of deck = Wd. γ fL . γ f 3 =497.4 kN/m

3.2 Superimposed Load


The superimposed load is mainly the road fill. The
fill for Donghai Bridge is asphalt. Assume the thickness
Figure 4: Night scene of bridge of the asphalt is 100mm. The unit weight of asphalt is
2300kg/m³.
The weight of road Wr = 2300×9.81×0.1×30
2.9 Complexity = 67.7kN/m
The main reason for designing a cable-stayed bridge γ fL = 1.75 (ULS – combination 1)
is because simple construction can be carried out over a
relatively long span. There is not much complexity in the γ f 3 = 1.10 (ULS – combination 1)
Donghai Bridge. The most complex section is the main The superimposed load = Wr. γ fL . γ f 3 =130.3 kN/m
navigation span which has two inverse Y-shaped pylons
with stays cables attached at top.
3.3 HA Traffic Live Load
2.10 Incorporation of Nature Carriageway = 14.25m wide
Deck Span = 160m
From bird’s eye view, Donghai Bridge is curved in an
Design for a meter width of deck:
S shape. This shape incorporate better into the nature
Number of notional lanes = 4
rather than a straight line shape for a structure built on
Notional land width = 15.75/4 = 3.94m
water. It is clearly shown in Fig 5. The colour of East Sea
From Table 13 BS5400:
in China appears brown instead of blue. It has much better
W = 13.6 kN/m (per notional lane)
effect as dark gray appearance of bridge fitting into
Knife Edge Load (KEL) = 120 kN (per notional lane)
natural colour of deep water.
For a meter of width of deck:
W = 13.6/3.94 = 3.45 kN/m
KEL = 120/3.94 = 30.46 kN
γ fL = 1.50 (ULS – combination 1)
Design HA Loading for a meter width of deck:
W = 1.50 × 3.45 = 5.175 kN/m
KEL = 1.50 × 30.46 = 45.69 kN
Maximum mid span bending moment with KEL at
mid span = M ult
M ult = (5.175 × 160 2 )/8 + (45.69 × 160)/4
= 18387.6 kNm
γ f 3 = 1.10 for ULS concrete bridge
Figure 5: Bird’s eye view of Donghai Bridge
M ult = 1.10 × 18387.6 = 20226.36 kNm

3 Loading 3.4 HB Traffic Live Load


All loadings in this conference paper are calculated Nominal load per axle = 45 units × 10kN = 450kN
according to BS5400. The maximum bending moment will be achieved by
using the shortest HB vehicle. i.e. with 6m spacing.
The maximum moment for a simply supported span
3.1 Dead Load occurs under the inner axle when the vehicle is positioned
The cross-section of main navigation section – cable such that the mid span bisects the distance between the
stayed bridge is composite box section which is too centriod of the load and the nearest axle. With a 160m
complicated for consideration. The other type of span and the 6m HB vehicle with equal axle loads, the
cross-section, concrete twin box sections are used to inner axle is placed at 1.5m from the mid span. Fig 6
define the dead load.
Assume the cross-section area of concrete twin box
sections is 16.7m². The unit weight of reinforced concrete
is 2400kg/m³.
The weight of deck Wd = 2400×9.81×16.7=393.2
kN/m
Figure 6: HB loading
E-mail: cs283@bath.ac.uk
RL = 450(73.7+75.5+81.5+83.8)/160 = 884.5 kN Another more important action by wind is uplift of a
RR = 4 × 450 – 884.5 = 915.5kN vertical downward force. This nominal force is calculated
Moment at X = 884.5 × 81.5 – 450 × 1.8 as Eq. (4) Ref. [2]
= 71276.75 kNm
The HB vehicle occupies one lane with HA load in Pv = qA3C L (4)
the adjacent lane. Assume that the HB load is carried by a
notional lane width of deck.
Hence the moment per meter width of deck The dynamic pressure, q is same as calculated before.
2
= 71276.75/3.94 = 18090.55 kNm The plan area A 3 =11025 m . Because the cross-section
γ fL = 1.30 (ULS – combination 1) of deck is a twin box-section, the lift coefficient C L =0.75
Design HB moment for a meter width of deck:
is taken. Calculate Pt from Eq. (4), gives that
M ult = 1.30 × 18090.55 = 23517.72 kNm
Pt =13339kN.

3.5 Wind Load


3.6 Temperature Effects
The wind load is analysis by other standards which is
quite different from British Standards. But in this Temperature effects are an important consideration
conference paper, all the loadings are defined according to during bridge design. The simple approach is used here to
BS5400. consider the temperature fluctuations of Donghai Bridge.
The overall length of Donghai Bridge is 32.5km and
The maximum wind gust, v c , which would strike
has a mixing of concrete and composite decks. There are
the bridge is given in equation 1 as quite lot expansions joints have been put in different
positions of bridge. Assume the maximum distance
vc = vK 1 S1 S 2 (1) between two expansion joints is 140m and the entire
bridge cross section increases in temperature by 25℃.
Assume the mean hourly wind speed is 35m/s and the The distance of bridge will move longitudinally at the
Donghai Bridge is 15m above the ground and horizontal expansion joints is calculated using Eq. (5)
wind loaded length is 340m, so that the gust factor S 2 is
e = ∆Τ.l .α (5)
found from table as 1.37 and the funneling factor S1 is
1.00 generally. Ref. [2] v c is calculated by Eq. (1) The coefficient of thermal expansion for steel and
-6
concrete is a= 12 × 10 /℃. The applied length l =100m.
which v c =51.3 m/s
The total extension e = 30mm and 15mm for each
The horizontal wind load acting at the centriod of the expansion joint to move in longitudinally.
part of the bridge under consideration is given by equation If the expansion joints are clogged, some
(2) as longitudinal compressive stress is which will be built up
and the stress can be calculated using Eq. (6)
Pt = qA1C D (2)
σ = ∆Τ.α.E (6)
2
Where q=0.613 vc (3)
Steel will expand more than concrete under same
increased temperature. So use the Young’s Modulus for
Using the value of v c from Eq. (1) and calculate q, steel to calculate the stress. The Young’s Modulus for
which is the dynamic wind pressure from Eq. (3), then steel E = 200,000 N/mm². σ =60N/mm²
q=1.61kN/ m 2 . The solid horizontal projected area
2
A1 =1400 m . C D is the drag coefficient which is read 4 Design of Structures

from graph by calculated b/d value. Ref. [2] C D =1.2 for The bridge is designed in S-shape from the plan view
with the minimum radius 2500m. This is not only due to
the deck.
the aesthetic appeal, but also for the construction
Other elements such as parapets and piers must also
requirements of highway bridge. Firstly, too long straight
be considered according to wind load. The wind load
section will cause drivers’ visual fatigue and increase the
results for 350m span are shown in Table 1 below:
accidents. Secondly, the central axis of each section
should perpendicular to the direction of rising tide and
Table 1: Pt values of different elements of bridge falling tide. This method not only reduces water influence
2 2 to the bridge, but also helps safe navigation for ships
q(kN/ m ) A1 ( m ) CD Pt (kN)
when passing the Donghai Bridge.
Deck 1.61 1400 1.2 2705
Piers 1.61 6×60 1.2 696
4.1 Main Navigation Section
Parapets 1.61 350×0.3 1.2 203
The width of the beam is 33m and the depth is 4m. It
is a single box with three chambers. The Main span is
E-mail: cs283@bath.ac.uk
420m. Large span induced huge moment and shear on the box-sections. The depth of deck is much thicker at
deck. If using concrete box-section, the thickness of supports than where else. The thickness of deck varies
flanges and webs will be much larger than other spans to along the span with the minimum thickness at mid-span
take the moment and shear. Therefore, the weight of each and maximum at supports. Stiffer section attracts bending
box-section will be extremely massive and cannot be moment. So the deck on the support is built thicker to
lifted by crane boat. Even concrete box-section can be resist the bending moment. All concrete box-sections are
stiffened by adding steel inside the camber, but still not prestressed by internal prestressing.
very efficient and economic. Steel box sections are chosen
to use instead of concrete. The problem of steel box
4.4 Main Navigation Span – Cable -stayed Bridge
sections is buckling and this may lead to collapse. In order
to overcome this problem, the top flange is stiffened by
casting a concrete slab on the top. This forms a
concrete-steel composite box section. The top concrete
flange is treated as a continuous slab and webs carry the
shear. The bottom flange is in compression in hogging
regions. Other steel plates are also stiffened by adding
steel profile and bracings inside. As shown in Fig. 7, all
steel plates are surprising thin and lightweight.

Figure 9: Inverse Y-shaped double pylons with stay


cables in fan configuration
Figure 7: Cross-section of composite box girder of main
navigation section
There are several reasons to choose a cable-stayed
bridge rather than suspension bridge crossing a wide span.
4.2 Offshore Non-navigation Section Cable-stayed bridges display a more direct load-path from
deck to pylon through the stay cables. Ref. [2] The
The precast continuous beam with the span of 60m or
construction method of cable-stayed bridges is easy and
70m is used for offshore non-navigation section. Instead
each cable is relatively thin and replaceable. The main
of single box section, two identical box sections with one
element of this bridge is the double pylons with single
chamber are selected. The cross-section of box girder is
plane of cables. Two inverse Y-shaped pylons are selected
shown in Fig. 8. All box sections have same thickness
with many closely-spaced stays attach to the top vertical
along entire span. Concrete box sections are prefabricated
part of pylons as shown in Fig. 9. The height of pylon is
in segments in island near the site. Each section is
148m. The most efficient configuration – fan system is
‘mate-cast’, so that the previous segment becomes part of
used without any ugly oblique views resulting. This form
the formwork for the next one. Ref. [2] Box section
of structure not only has the aesthetic benefit, but also has
segments are then transferred to the site and all
the advantage that torsional stiffness is added to the
prestressed by internal prestressing to hold all segments
bridge by creating a triangular ‘closed’ section. The
back in positions. Extra deflectors are also added to the
height of pylon is 148m. Cable stay is high strength
box section for external prestressing in advance. They are
Pre-fabricated parallel wire strand (PPWS). PPWS is
not used until any deviation occurs during construction or
fabricated by high strength galvanized wire which is
in future services.
totally paralleled with a section of hexagon or other shape.
Ref. [4] The wire bundle is wrapped with high strength
polyurethane tape and fixed sockets at both ends of cable.
The standard distance of cables on the pylon is 2m and
8mon the beam. The elevation of main navigation section
– cable-stayed bridge is shown in Fig. 10.

Figure 8: Cross-section of offshore non-navigation


section

4.3 Auxiliary Navigation Section


There are 3 auxiliary navigation bridges with main
span of 120m, 140m, and 160m respectively. Two Figure 10: Elevation of main cable-stayed bridge
identical single box sections with single chamber are also
chosen for these sections. Three auxiliary navigation
sections are actually built as a cantilever bridge with 4.5 Expansion Joints and Bearings
E-mail: cs283@bath.ac.uk
Because the deck of cable-stayed bridge mostly made large scale of the bridge. Because it serves for the
of steel, so as the temperature increasing, the deck of main Yangshan Deep Water Port, so it needs to be completed
span will expand largely. So expansion joints are put in together with the first phase of Little Yang-shan Port.
the middle of span to allow any horizontal movements up By considering the short construction period and
to 140mm. The normal service life for expansion joints is overall length of Donghai Bridge, travelling formwork
longer than 20 years. Ref. [1] method is used in construction of onshore section. For the
Both steel hinge (rocker) bearings and rubber pot offshore section which is about 98% of the Donghai
bearings are used in Donghai Bridge at different positions. Bridge, neither travelling formwork method nor
The steel hinge bearing acts as a pin connection and no incremental launching method is applicable due to its
horizontal movement is allowed but it can rotate. The inefficiency and different offshore conditions. So precast
rubber pot bearing is the most popular used one, which is concrete construction is much more preferred with
slightly cheaper than others. launching and balanced cantilever construction methods.
At four navigation sections, spans of deck are very large
and launching girder method is uneconomic since
5 Construction
building temporary supports in deep water is very
expansive. So only balanced cantilever method is applied.
5.1 Complex Construction Conditions When construction goes to the area near the bank of
island where water is very shallow and full of submerged
Donghai Bridge is located in site which has
rocks, the floating cranes cannot reach there, so those
subtropical oceanic monsoon climate. It is on the south
sections are constructed by travelling formwork method
edge of north subtropical zone and east-asia monsoon
or incremental launching method.
region. Mainly wind is North wind and east-south wind
throughout whole year. Strongly influenced by the
monsoon, the site has clearly four seasons; cold in winter 5.2 Soil Conditions and Foundations
and hot in summer. The annual average temperature is
There are 12 layers of different soils in the site of
15.3-16.1°C and annual average rainfall is 1053.9mm.Ref.
Donghai Bridge. Soils have been defined up to seven
[3]
layers from top to bottom as shown in Table 3.
The tidal type of sea area belongs to shallow tide with
irregular and half day characteristics. Two rising tides and
Table 3: 7 layers of soil from top to bottom Ref. [3]
two falling tides happen each day with distinct aspects of
back and forth tide. Ref [1] Compres
Layer Colour Soil type
-sibility
Table 2: Characters of tide in east sea of Shanghai 1 Grey Mud High Loose
Ref. [3] Yellow
2 Sandy silt Medium Medium
Little Yangshan to grey
Luchao Port Muddy silty
Station 3 Grey High Loose
Station clay
(08/1997-12/200
(1978-1994) 4 Grey Silty clay High Loose
1)
Average sea Loose to
0.23 0.18 Medium
level (m) 5(1) Grey Clay medium
to high
Average high loose
1.86 1.52 Grey- Medium
tide level (m) 5(41) Sandy clay Medium
Average low green loose
-1.34 -1.23 Medium
tide level (m) Grey-gr
Maximum level 5(42) Silty clay Medium dense to
5.14 5.03 een
difference (m) dense
Average level Dark
3.20 2.75 6 green to Silty clay Medium Medium
difference (m)
Average yellow
5 hours 5 hours Medium
duration of 7(11) Yellow Sandy silt Medium
26minutes 51minutes dense
rising tide
Average Medium
6 hours Medium
duration of 7 hours 7(12) Yellow Silty sand dense to
34minutes to low
falling tide dense
Grey-
Medium
According to Table 2, the bridge construction is yellow Silty fine Medium
7(2) dense to
hugely influenced by typhoon, wave, tide, cold-air and to sand to low
dense
other bad conditions. According to the capacities of yellow
equipments have been used in reducing effect of wind and Interbedded
current, the average workable days is less than 180days silty clay Medium
7(2t) Grey Medium
per year over three hand half years total construction and sandy loose
period. Therefore, another critical issue need to consider silt
is the limited construction period. The construction period
of Dong Hai Bridge is only 42 months comparing to the
E-mail: cs283@bath.ac.uk
As shown in Table 3, the soil condition of site is quite forward and construction continuous. Main installation
bad, so that pile foundation is chosen for the bridge. Layer process of cable-stayed bridge is shown in Fig. 12.
7(12) and Layer 7(2) both have low impressibility and are
formed by good quality dense sands. They are also stably
distributed along the whole site. The depth and thickness
of the soil is also ideal for the pile foundation, so layer 7
is chosen to carry the bearing capacity the pile foundation
5.2.1 GPS systems
Driving piles into the sea bed is very largely
influenced by the currents and waves. It is very difficult
for driving ships to get to the exact positions. There are
not as many monitoring points can be set out as on land.
Therefore, the normal onshore surveying methods are not
very applicable and not accurate enough for the
construction. According to the offshore pile driving
technology, new innovative GPS-RTK technique is used
in this project, known as “The Offshore GPS Pile Driving
Position System”. This system can monitor the position of
ship and accurate any errors from calculations. By the Figure 12: Erection process of cable-stayed bridge
monitoring of GPS system, the high accuracy is achieved
and the problem is solved.
5.2.2 Pile caps
The outer shell of pile caps are also prefabricated in
island. Each shell is transported to the site and erected to
the pile groups as shown in Fig. 11. Once finished
connecting to piles, the reinforcement is left for the pier,
and the top of pile cap is covered in-situ with concrete.

Figure 13: Balanced cantilever construction for


cable-stayed bridge

5.3.1 Composite deck


The main navigation span of bridge deck is
constructed using precast concrete topped steel composite
box sections. The profile of box-section is single box with
triple chambers which is shown in Fig 6. The top flange
Figure 11: Erection of pile cap of box-section is stiffened with prestressed concrete and
bottom flange and web are steel. Each box-section is
prefabricated in large scale prefabricate site on island,
then transported to the construction site and craned and
5.3 Main Navigation Section – Cable Stayed Bridge erected into place. All casting work should be done in
Tow inverse Y-shaped tower is casted in-situ in the prefabricate site, including assembling and welding steel
site. After completed the main tower and auxiliary piers, box section, casting in-situ concrete top flange to the steel
one temporary support is installed at each side of tower structure, etc. After all prefabrication steps have been
along bridge axis to support the first several segments of done, the box-sections are moved to storage to stay for 90
precast box sections above. The first five segments are days before using.
lifted into position by floating boat crane and erected and Process of balanced cantilever construction for the
connected on the two temporary supports. Another deck:
segment is lifted into position and first cable is installed 1. Precast box section is transported to site by ship
from tower to the deck. After this, the mobile crane is and lift up into position by crane.
assembled on the deck and used for further lifting work. 2. Adjust space between last segment. As in position,
The construction is done by balanced cantilever method. start connecting two segments and also fill in an epoxy
As the construction reaches the auxiliary pier, the resin to the joint to further aid smooth connecting.
temporary supports are removed from pylon and side 3. Add the tendons for prestressing and cast in-situ
temporary support is added to the auxiliary pier. One 10m wide concrete top slab.
segment is erected to the top of auxiliary pier first and 4. When strength concrete is over 90%, pull back the
then connected to the deck from pylon. Another stay cable tendons to prestress the segment.
is added to hold the deck. Then the mobile crane moves 5. Move crane forward

E-mail: cs283@bath.ac.uk
6. Install stays from tower to the segment to pull the The span of offshore non-navigation section is either
deck up in position. 60m or 70m. All the segments are prefabricated on the
7. Crane lift next segment on and repeat all the steps prefabricate site on island and transport to the wharf each
from step 1 as a whole section by the way of transverse moving and
longitudinal moving. All the piers and girders are
transported to the site by boats.
The 60m box girders are lift to the position and
erected using crane boat and “Hercules” (2500 tonnes
capacity). The 70m box girders are lift to the position and
erected using crane boat and “Little Swan” (3000 tonnes
capacity), shown in Fig. 16 .
Each box section is first lift to the top of pier and
supported by temporary supports. All connection works
are done in-situ on the temporary supports. After all
segments connected to each other, the deck is converted
into a continuous beam.

Figure 14: Composite box girder lift by mobile crane

As two spans meet about to meet together, the key


segment is prefabricated specially that the steel section is
slightly longer. Because steel deck cannot cast in-situ, so
the closure of the span becomes tricky. One side of key
segment is connected as usual by bolting to the pervious
one. At the other side, use the temporary connection plate
to adjust the position. Once it is in the correct position, a
permanent plate is replaced and closure finished.

5.4 Onshore Section


Section near the Luchao Port selects 50m span Figure 16: 70m box girder is lift by “Little Swan”
continuous box girder. It is constructed in-situ using
travelling formwork method.
5.6 Auxiliary Navigation Section
50m span continuous box girder is also selected for
the section near bank of Big Tortoise Island. Because the The other three auxiliary navigation channels are
crane boat cannot work in shallow water, so that constructed using different methods. The span of
incremental launching method is used for this section. auxiliary navigation section is 120m, 140m and 160m
respectively.
The pier is precast to box section of enforcement
5.5 Offshore Non-navigation Section
concrete thin wall. The first box girder segment is cast
in-situ on the top of each pier by formwork. All other
segments are also cast in-situ using balanced cantilever
construction which is shown in Fig. 17. The deck is built
outwards in both directions from a pier by mobile
carriages and suspended formwork. The thickness of deck
varies along the span. As the concreting continuous and
the deck tapers, the arrangement of formwork adapted to
get smaller dimensions.

Figure 15: Erection of piers

There are two piers at each support. All the piers for
non-navigation section are precast on island and
transported to site. Each pier is lift to the top of pile cap
and connected to the foundations as shown is Fig. 15. Figure 17: Cast in-situ using balanced cantilever
construction
E-mail: cs283@bath.ac.uk
6 Durability 7 Protection from vandalism
Donghai Bridge is located at wretch marine
environment. In order to make sure the bridge can stand 7.1 Anti-collision system
for 100 years, a serial of completely, economical and
In order to protect the bridge from vandalism by
reasonable anticorrosion system is drafted and applied to
boats and ships, both of VTS (Vessel Traffic
the construction of the bridge. Each element of bridge has
Administrative System) and safety protection system are
its own strategy and corresponding system due to the
applied.
variation of structures, materials and environments.
Some independent anti-collision piers are arranged at
All the technological requirements are drafted as well.
both sides of main navigation channel around tower bases.
E.g. raw materials of high performance concrete, ratios of
The light collision can be absorbed and resisted directly
mixture, production processes, construction methods, etc.
by the anti-collision piers. But for the heavy collisions,
So the site construction can all be guided by these
anti-collision piers are not strong enough, so that the pier
standards.
foundation together with other anti-collision facilities will
restrict the impact.
6.1 Anticorrosion Strategies for Different Elements: According to the navigation standard, boats shapes,
collision forces and anti-collision facilities, for the
6.1.1 PHC (Prestressed High Strength Concrete) piles auxiliary navigation channel, a special orange colour
High performance concrete + steel reinforcement protective box is adopted. The pile cap of each pier is
protection layer + FRP (Fiber Reinforced Plastics) wrapped by the orange protective box. There are lots little
wrapping reinforcement + filling core reinforcement
holes on the protective box which can absorb and reduce
method
the impact. This system is very economic because no
6.1.2 Steel piles
extra protective piers are required.
Sacrificial anodes protection method (replacement
every 35 years) + heavy-duty anticorrosive coating
protection (1000µm, life-time 10 years) + filling core
reinforcement method + predicted steel piles corrosion
amount (7mm). Ref. [3]
Temporary anode pieces are installed during
construction and they are left on it (life-time≥2 years).
6.1.3 Drilling piles
Concrete with mineral admixture + steel protective
canister + steel reinforcement protection layer
6.1.4 Pile caps, piers and girders
High performance concrete + steel reinforcement
protection layer
The surfaces of piers in splash zone are coated by
waterproof painting.
6.1.5 Stay Cables Figure 18: Orange protective box
All the cables are made by galvanized steel wires
which are coated by a layer of zinc to prevent corrosion. 7.2 Anti-collision Parapets
Hot extrusion HDPE (High Density Polyethylene) cable
jacket is wrapped to each cable and sealed to prevent Donghai Bridge services for the ports. High standard
storm water logging. requirements for safety are very important and must be
6.1.6 Bearings achieved. Special researches have been done to the
Triple anti-corrosion methods are used on bearing: anti-collision system of parapets. The anti-collision
weathering steel (including 09CuPCrNiA, 15CrCuMn and parapets are designed for standard containers which have
ZG20Mn) + metal coating + heavy-duty anticorrosive a weight up to 55 tones. Designed maximum colliding
painting. Ref. [3] speed is 60km/h and colliding angle is 15 degree. After
6.1.7 Expansion joints and handrails several tests and comparisons, the steel-concrete
Expansion joints and handrails are protected by hot composite material is selected for parapets.
dip galvanizing anticorrosive method.
8 Future Changes and Improvements:
6.2 Exposed Testing Station: There are 4 navigation channels in Donghai Bridge.
The reason for setting the exposed testing station is to One is located in the main navigation section. It is for
monitor the actual effects of anticorrosive systems in 5000DWT vessel and the clearance is 300x40m. It is a
Donghai Bridge. It also provides important basis and single channel with double directions. One is for
testing results for future maintenances of bridge. On the 1000DWT vessel and the clearance is 100x25m (double
other hand, the exposed testing station collects data of channels single direction);And Two are for 500DWT
offshore anticorrosive technique used in Donghai Bridge vessel, the clearance is 56x17.5m (double channels single
and accumulates experiences for the future applications direction), located near the Luchao harbor and little
with improvements. The exposed testing station is built at Wugui Island. Ref [1]
north-west of Big Tortoise Island. Considering the overall length of Donghai Bridge is
32.5km, 4 navigation channels may not enough for the
E-mail: cs283@bath.ac.uk
future. One of the solutions is that one more cable-stayed
bridge is added to the route of bridge on the Luchao Port
side. But this will make the structure very complex
because another cable-stayed bridge, Kezhushan Bridge,
which is connect to the Donghai Bridge already. The
maximum span of Kezhushan Bridge is 332m and it
connects the end of Donghai Bridge to the Yangshan Deep
Water Port. In fact, Kezhushan Bridge does not have any
navigation requirements, so it is quite a waste to having a
long span cable-stayed bridge there.

9 Summery
For a bridge have overall length 32.5km, the Donghai
Bridge is excellently designed and dramatically
constructed in three and half years. It also gives
impressive aesthetic feeling while the philosophy of
simplicity applies.

References
[1] http://dorim.mokpo.ac.kr/~kwerc/data_file/Symposiu
m/session2/Zeng-Huan%20Zhang.pdf
[2] Ibell, T., c. 1997. Bridge Engineering 1 lecture notes,
University of Bath
[3] Deep Water Port and Donghai Bridge Project
http://co.163.com/neteaseivp/forum/dirSearch.jsp
[4] http://en.spccc.com/website/searchProductSingle.acti
on?proId=8080808016c1e8130116c1f670ed0002
[5] Lin, Yuanpei. Shanghai Lupu Bridge and Donghai
Bridge

E-mail: cs283@bath.ac.uk

You might also like