0-1 Mobilization

1-2 Minor Bridge


2-3 Road work
3-4 Misc Works
4-5Drainage and protection work (Road)
1-6 flyover foundation including abutment & Protection
6-7 Superstructure including pier
7-8 Finishing works

2 3 4

4 Months 3 Months 4 Months

0 1 6 7
2 Months 6 Months 6 Months
5

3 Months 3 Months

8
4 Months