Spec No.

Unit Rate For 2013-2014 2014-2015 2015-2016

Morth Section-3100 One Square Meter of RE Item Rate


Wall Facia 3583
Labour rate 1000

RATE ANALYSIS OF ITEMS


Description Unit Quantity Rate Rs Cost Rs
1. Labour cost
Labour for casting & erection of panels,
per sqm for
Leveling pad, coping beam, Filter media 1 1000 1000
wall facia
etc completed
Total Labour
2. Material

Providing design and knitted & PVC coated polyester per sqm for 1 908 908
geogrid-techgrid, with accessories (Geotexile EPDM pad wall facia
& connector) and supervison for Reinforeced soil wall of
heigth 6 meters to 8 meters

Providing concrete panel of size 200mm(wide) x per sqm for


wall facia 1 1050 1050
1600mm(height) x 180mm (thickness) from M35
concrete as per the drawing & design of panel including
supply of mould for panel casting

Providing leveling pad (PCC-M15) below the reinforced per sqm for 1 50 50
soil wall of size 0.35m(wide) x 0.2m(thick) wall facia

Providing copping beam (RCC-M25) at top of the


reinforced soil wall of size 0.18m(wide), 0.25m varying, per sqm for 1 50 50
with 8mm dia ties @150mm c/c (concrete 0.18cum, wall facia
Reinforcement 1.6Kg/sqm

Providing filter media, 600mm thick of 20mm down per sqm for
aggregate behind the RS Wall for drainage, as per 1
wall facia
specification
Total Material 2058
3.Machine 175
4. Total lead 150
5. Total of 2 to 4 2383
1. Scaffolding
2.Sundries 1% 23.83
3.Water Charges 1% 23.83
Total 2430.66

Overhead charges & conctractor profit 10% 243.066


Abstract Rate 2673.726
Total Rate 3673.726