...., .. W;th the approval of the Competent Authority, it has ~n decided that
henceforth Contingency Charges for all NH related works will be levied @1% of the
CivH Cost component of instead of existing Z.8%. This shall apply to all estirnat~
\-"/hether original or revised.
3. This change in the contingency charges will be effective from the date of issue of
tim letter. Projects which- already been cleared by SFC/EFC/PIB wilt not be effected by
t his decision.
\f'~\
...,,___
-----
(Umrav Meena)
Under Secretary to the Government of India
Copy to :
DG(RoJds)/Chnirman, NHAI /The Managing Director, NHfJXl/ All ADGs/ AU JSs/ All
Cfs/Chairman NHLML/All Regioral Officer:;.