Professional Documents
Culture Documents
Chapter 3 Precast Concrete Frame With Moment Connection PDF
Chapter 3 Precast Concrete Frame With Moment Connection PDF
Precast
column
Concrete
footing
• Most popular connection used in Malaysia is the
grouted sleeve, as it is the most economical.
• Construction method:
>> High tensile steel starter bars are left protruding
from the foundation. After that, a precast column
with vertical sleeves at the end is inserted into the
starter bars. The sleeves are then filled in with grout
to provide a monolithic connection.
• This connection type is considered rigid and has the
ability to provide moment resistance at the
connection between column end to footing.
4.0 Floor system
• The floor system in a precast framed structure consists of horizontal
components of beams, slabs and connections.
• In this layout, precast concrete
components such as precast
beams are spanning in the
longitudinal direction of the
building and supported by
precast columns; whereas the
precast slabs are spanning in the
transverse direction and
supported by the precast beams.
Resistance to
vertical shear
Lattice truss
(a)
(b)
• The complete floor system uses a combination of precast
concrete planks, steel mesh and cast insitu concrete
topping. The use of cast in-situ concrete topping with top
steel mesh, effectively ties all the loose precast planks
together provides a monolithic slab with enhance stiffness
and rigidity.
• In terms of spanning performance, precast planks are
suitable for short spanning structures in the range of 2m to
5m. Hence, this floor system is suitably employed in
residential dwellings where planks with spans of less than
5m are sufficient.
5.0 Structural integrity
• A precast concrete structure is said to have the structural integrity if it is able
to withstand localised damage or failure of one component without causing
progressive collapse to the neighbouring components.
• This may be achieved by tying the loose precast components together using
steel ties.
• The ties in between the components have the ability to transfer loads to un-
failed members through alternate load paths.
1 1
section 1 - 1
Cut
Perimeter
floor tie
(Tie No. 3)
Transfer of lateral
loads to lateral stability
system through floor
diaphragm action.
• For untopped precast slabs, the rigid floor diaphragm of the precast
floors can be achieved by connecting the precast slabs by means of
welding, or tying.
• Figure below shows the tying method, using steel bars, to tie ends of
untopped precast slabs.
• The monolithic aspect of untopped precast slabs can be enhanced
further by enclosing the untopped precast slabs with a boundary
(peripheral) tension tie (see Ties No.4 and No.5).
For topped precast slabs, the rigid diaphragm can be achieved by having
reinforced structural topping consisting of cast insitu concrete with steel
mesh.
8.0 Lateral stability system
The unbraced frame is designed to carry both vertical and lateral loads.
Under the action of vertical Under the action of lateral loads Under the action of both
loads, the frame response is (see Figure (b)), the frame sways vertical and gravity loads, the
shown in Figure (a) in which and the lateral stability of the bending action of beams and
the degree of bending in the overall unbraced frame relies on columns that provides
beams and columns resistance to both the vertical
depends on the stiffness and the degree of bending in the
beams and columns that and lateral loads is shown in
strength of beam-to-column
connections. eventually relies on the strength Figure (c) and Figure (d).
and stiffness of beam-to-column
connections.
Response of moment frame due to: (a). gravity load only (b). lateral load only
(c). gravity and lateral loads