Professional Documents
Culture Documents
Chapter 4
Rigid Pavement
Presented By:
Assoc. Prof. Dr. Mohamad Yusri Aman
1
12/17/2020
Surface Course
2
12/17/2020
Rigid Pavement
• The rigid pavement are associated
with rigidity or flexural strength or
slab action.
• The load is distributed over a wide
area of subgrade soil.
• Rigid pavement is laid in slabs with
steel reinforcement
The first concrete pavement was built
in Bellefontaine, Ohio in 1893.
In 2001 there was about 95,000 km
was constructed in United States.
3
12/17/2020
4
12/17/2020
Strength of the road is less dependent Strength of the road is highly dependent on the
on the strength of the sub grade strength of the sub grade
Rolling of the surfacing in not needed Rolling of the surfacing is needed
Road cannot be used until 14 days of Road can be used for traffic within 24 hours
curing
Force of friction is less Deformation in the sub
Force of friction is high grade is not transferred to the upper layers.
No Damage by Oils and Greases
Damaged by Oils and Certain Chemicals
Components/Terminology
5
12/17/2020
JPCP JRCP
Jointed Plain Concrete Jointed Reinforced
Pavement Concrete Pavement
CRCP
Continuously Reinforced
Concrete Pavement
1. no steel reinforcement
2. uses contraction joints to control
cracks
3. transverse joints are spaced in
order to prevent joint-cracks due to
temperature and moisture stresses
6
12/17/2020
Plain concrete pavement
4.2 m max
5 m max
No dowels – must have short slabs + lean concrete sub‐base
7
12/17/2020
Aggregate Interlock
Aggregate Interlock
8
12/17/2020
Looking at a plain concrete pavement
Joints
Along – 4.2m
Across – 4.3m
Widened truck
lane
* All joints sealed with
silicone since mid‐1980s
9
12/17/2020
Jointed reinforced pavement
(JRCP)
– Reinforcement (0.1 – 0.2%)
– 30-100’ Joint Spacing
– 6-10” Slabs
– Construction joints w/ dowels
– Granular or stabilized subbase
– Problems
– Load transfer failure
– Large tensile stresses
– Environmental damage at joints
10
12/17/2020
11
12/17/2020
Jointed reinforced pavement
mesh reinforcement
8 - 15 m typ.
To limit joint opening prefers 8m max
12
12/17/2020
Continuously reinforced concrete
(CRCP)
• Reinforcement (0.5-0.7%)
• 7-9” Slab
• Granular or stabilized subbase
• Cracks spaced 3-8 ft
• Problems
– Punchouts
• Keys for success
– Drainage
– Materials
– Reinforcing design
13
12/17/2020
Continuously reinforced concrete (CRCP)
bar reinforcement
1 - 2.5 m typ.
Looking at a CRC pavement
Cracks initially about 5m, then later 1‐ 2.5m
Still need joints along pavement
14
12/17/2020
15
12/17/2020
Construction Joints
Construction Joints
16
12/17/2020
17
12/17/2020
Avoiding conflicts
• Continuity of joint lines
• Acute angles
• Isolation joints
Continuity of joints
avoid mismatched joints
18
12/17/2020
300-500 mm
Steel design
19
12/17/2020
• Reinforcing steel
– Keep cracks tight, carry tension due to friction
• Tie bars
– Tie lanes or lane/shoulder together
• Dowel bars
– Load transfer
Dowel Bar
20
12/17/2020
21
12/17/2020
22
12/17/2020
23
12/17/2020
24
12/17/2020
• To each other
• Surface
• Road centreline
25
12/17/2020
26
12/17/2020
Both “acceptable”
27
12/17/2020
28
12/17/2020
Tie bar
29
12/17/2020
30
12/17/2020
Reinforcing steel
Temperature Reinforcement
• Only to keep cracks tight
• Calculate amount of steel by balancing forces
– Account for slab size, friction, allowable stress in steel
hfL
As
2 fs
Where: As = required area of steel (in2) / foot of pavement width
h = slab thickness, in
f = coefficient of resistance (1.5)
L = length of slab (ft)
fs = allowable stress in steel (lb/in2)
31
12/17/2020
32
12/17/2020
JRCP
Design assumes a crack will occur
mesh reinforcement
8 - 15 m typ.
Jointed pavements
33
12/17/2020
34
12/17/2020
35
12/17/2020
Reinforcement location
36
12/17/2020
Structural value ?
37
12/17/2020
Reinforcement support
• Need to support reinforcement in design location
• Crew will have to walk over it
• Regular grid of bar chairs approx 1m
Balance between :
• Cost of reinforcement
• Minimise wastage of cut reinforcement
• Cost of dowels at joints
• Unpredictability of joint movement and sealant
performance for long slabs
38
12/17/2020
Suggested about 9m
• Will probably not develop more than one crack.
• Uses 1.5 sheets of standard fabric with overlap
• Joint movement/sealant performance still
reasonable
• Joint sealant groove still only about 8mm – not
noticeable to traffic
Continuously reinforced concrete (CRCP)
bar reinforcement
1 - 2.5 m typ.
39
12/17/2020
mdyusri@uthm.edu.my 79
40