Week 4
Time
# Date Work Summary / Daily Activity Taken
1 14/03/2021 -start install the slab for Rs wall by nehemiah - install panel of rs wall 8 hour/s
2 15/03/2021 - continue install panel and slab for Rs wall - superstructure work at blok admin 8 hour/s
3 16/03/2021 - continue install Rs wall - put sand river before start install the tendant - and compact the sand to make sure it compact 8 hour/s
4 17/03/2021 - cidb rush to site for checking ( morning ) - continue install panel and slab Rs wall 8 hour/s
5 18/03/2021 -continue install panel and slab for Rs wall - superstructure work at blok admin 8 hour/s
6 20/03/2021 -Rs wall - cut the geotextile and put it at Rs wall slab ( under slab ) - put in sand river and compact - calculate the bed for rumah 8 hour/s
kongsi
Work Summary / Daily Activity : RS wall work such as panel and slab installation
Instruction for Supervisor
Please confirm the student activity report on the related Week 4 before making evaluation and comments. Tick (√) on the appropriate checkbox :
Date :
Comments :