Republic of the Philippines

Northwest Samar State University


Rueda St., Calbayog City 6710
Website: http//www.nwssu.edu.ph
Email: main@nwssu.edu.ph
Telefax: (055) 2093657
ISO 9001:2015
Certified
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 4


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 15,581,240.90
Project Duration : February 3 - November 30, 2023 (300 Calendar Days)
Date : December 15, 2023
MORNING WEATHER: Fine
ACTIVITIES
CE-1. Installation of tiles at to laundry area (right side)
2. Fabrication of metal door for garbage chute.
3. Application of tile grout at floor tiles at hallway.
4. Installation wooden door at selected room.
5. Carving of door jamb in preparation for door installation.
6. Arranging of cabinets to bedrooms.
7. Replacement of one (1) floor tile at restaurant/canteen area.
EE- 1. Installation of single luminaire reflector at hallway
2. Installation of single luminaire reflector at porch area.

AFTERNOON WEATHER: Partly Rainy


ACTIVITIES
CE-1. Installation of tiles at to laundry area (right side)
2. Fabrication of metal door for garbage chute.
3. Application of tile grout at floor tiles at hallway.
4. Installation wooden door at selected room.
5. Carving of door jamb in preparation for door installation.
6. Arranging of cabinets to bedrooms.
7. Replacement of one (1) floor tile at restaurant/canteen area.
EE- 1. Installation of single luminaire reflector at hallway
2. Installation of single luminaire reflector at porch area.

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : _____ TIMELINESS : _____ 3 - Good
1
FOREMAN : _____
5
QUALITY : _____ 2 - Poor
1
WORKERS : _____ 4
EFFECIENCY : _____ 1- Very Poor
16 3
Prepared by:

ENGR. DARWIN Z. TAN BRYAN C. VALENCIANO


Site Inspector - Civil Works Site Inspector - Architectural Works

ENGR. JOHN DALE E. YABAO ENGR. MARIEL JANE A. FUENTIBLANCA


Site Inspector - Mechanical Works Site Inspector - Electronics Works

Noted: Approved:

ENGR. LEO D. NICOLASORA ENGR. MARLON D. SOBREVIGA


IPMC Overall Team Leader IPMC - Chairman
Republic of the Philippines
Northwest Samar State University
Rueda St., Calbayog City 6710
Website: http//www.nwssu.edu.ph
Email: main@nwssu.edu.ph
Telefax: (055) 2093657
ISO 9001:2015
Certified
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 4


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 15,581,240.90
Project Duration : February 3 - November 30, 2023 (300 Calendar Days)
Date :

MORNING WEATHER:
ACTIVITIES

AFTERNOON WEATHER:
ACTIVITIES

REMARKS
-

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : _____ TIMELINESS : _____ 3 - Good
FOREMAN : _____ QUALITY : _____ 2 - Poor
WORKERS : _____ EFFECIENCY : _____ 1- Very Poor

Prepared by:

ENGR. DARWIN Z. TAN BRYAN C. VALENCIANO


Site Inspector - Civil Works Site Inspector - Architectural Works

ENGR. JOHN DALE E. YABAO ENGR. MARIEL JANE A. FUENTIBLANCA


Site Inspector - Mechanical Works Site Inspector - Electronics Works

Noted: Approved:

ENGR. LEO D. NICOLASORA ENGR. MARLON D. SOBREVIGA


IPMC Overall Team Leader IPMC - Chairman
Republic of the Philippines
Northwest Samar State University
Rueda St., Calbayog City 6710
Website: http//www.nwssu.edu.ph
Email: main@nwssu.edu.ph
Telefax: (055) 2093657
ISO 9001:2015
Certified
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 4


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 15,581,240.90
Project Duration : February 3 - November 30, 2023 (300 Calendar Days)
Date : December 13, 2023
MORNING WEATHER: Partly Rainy
ACTIVITIES
CE-1. Fabrication of door (D-4)
2. Painting of storage underneath the laundry sink and door.
3. Installation of garbage chute door (D-9)
4. Application of putty on wooden door.
5. Application of skim coat on garbage shaft
6. Installation of door in toilet (Restaurant/Canteen)
7. Injection of concrete to "kapak" tiles.
EE- 8. Installation of downlight in storage and toilet.

AFTERNOON WEATHER: Partly Rainy


ACTIVITIES
CE-1. Fabrication of door (D-4)
2. Painting of storage underneath the laundry sink and door.
3. Installation of garbage chute door (D-9)
4. Application of putty on wooden door.
5. Application of skim coat on garbage shaft
6. Installation of door in toilet (Restaurant/Canteen)
7. Injection of concrete to "kapak" tiles.
EE- 8. Installation of downlight in storage and toilet.

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : 1 TIMELINESS : 5 3 - Good
FOREMAN : 1 QUALITY : 4 2 - Poor
WORKERS : 16 EFFECIENCY : 3 1- Very Poor

Prepared by:

ENGR. DARWIN Z. TAN BRYAN C. VALENCIANO


Site Inspector - Civil Works Site Inspector - Architectural Works

ENGR. JOHN DALE E. YABAO ENGR. MARIEL JANE A. FUENTIBLANCA


Site Inspector - Mechanical Works Site Inspector - Electronics Works

Noted: Approved:

ENGR. LEO D. NICOLASORA ENGR. MARLON D. SOBREVIGA


IPMC Overall Team Leader IPMC - Chairman
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 4


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 15,581,240.90
Project Duration : February 3 - November 30, 2023 (300 Calendar Days)
New Completion Date: December 3, 2023
Date : December 15, 2023 (Friday)

MORNING WEATHER: Partly Rainy


ACTIVITIES
EE1.Chipping for DP-1R at right side area.
CE1. Repainting of selected walls at canteen area.
2. Painting of walls at genset room (semi-gloss)

AFTERNOON WEATHER: Partly Rainy


ACTIVITIES
EE1.Chipping for DP-1R at right side area.
CE1. Repainting of selected walls at canteen area.
2. Painting of walls at genset room (semi-gloss)

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : 0 TIMELINESS : 5 3 - Good
FOREMAN : 1 QUALITY : 3 2 - Poor
WORKERS : EFFECIENCY : 1- Very Poor
2 3

Prepared by:

ENGR. DARWIN Z. TAN BRYAN C. VALENCIANO


Site Inspector - Civil Works Site Inspector - Architectural Works

ENGR. JOHN DALE E. YABAO ENGR. MARIEL JANE A. FUENTIBLANCA


Site Inspector - Mechanical Works Site Inspector - Electronics Works

Noted: Approved:

ENGR. LEO D. NICOLASORA ENGR. MARLON D. SOBREVIGA


IPMC Overall Team Leader IPMC - Chairman
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 5


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 2,193,219.32
Project Duration : November 7, 2023 - March 6, 2024 (120 Calendar Days)
Date : December 15, 2023 (Friday)
MORNING WEATHER: Partly Rainy
ACTIVITIES
No works

AFTERNOON WEATHER: Partly Rainy


ACTIVITIES
CE1. Installation of 4" plumbing pipe to excavated deep well.

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : 0 TIMELINESS : 5 3 - Good
FOREMAN : 1 QUALITY : 4 2 - Poor
WORKERS : EFFECIENCY : 3 1- Very Poor
1

Prepared by: Noted:

ENGR. DARWIN Z. TAN ENGR. LEO D. NICOLASORA


Site Inspector - Civil Works IPMC Overall Team Leader

Approved:

ENGR. MARLON D. SOBREVIGA


IPMC - Chairman
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 4


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 15,581,240.90
Project Duration : February 3 - November 30, 2023 (300 Calendar Days)
New Completion Date: December 3, 2023
Date :

MORNING WEATHER:
ACTIVITIES

AFTERNOON WEATHER:
ACTIVITIES

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : TIMELINESS : 3 - Good
FOREMAN : QUALITY : 2 - Poor
WORKERS : EFFECIENCY : 1- Very Poor

Prepared by:

ENGR. DARWIN Z. TAN BRYAN C. VALENCIANO


Site Inspector - Civil Works Site Inspector - Architectural Works

ENGR. JOHN DALE E. YABAO ENGR. MARIEL JANE A. FUENTIBLANCA


Site Inspector - Mechanical Works Site Inspector - Electronics Works

Noted: Approved:

ENGR. LEO D. NICOLASORA ENGR. MARLON D. SOBREVIGA


IPMC Overall Team Leader IPMC - Chairman
DAILY PROGRESS REPORT

Poject title : CONSTRUCTION OF THREE STUDENTS' DORMITORY - PHASE 5


Location : NwSSU Main Campus, Calbayog City
Contract Cost : Php 2,193,219.32
Project Duration : November 7, 2023 - March 6, 2024 (120 Calendar Days)
Date :

MORNING WEATHER:
ACTIVITIES

AFTERNOON WEATHER:
ACTIVITIES

REMARKS

MANPOWER: PERFORMANCE RATING: Rating Value:


5 - Excellent
4 - Very Good
SITE ENGINEER : TIMELINESS : 3 - Good
FOREMAN : QUALITY : 2 - Poor
WORKERS : EFFECIENCY : 1- Very Poor

Prepared by: Noted:

ENGR. DARWIN Z. TAN ENGR. LEO D. NICOLASORA


Site Inspector - Civil Works IPMC Overall Team Leader

Approved:

ENGR. MARLON D. SOBREVIGA


IPMC - Chairman