Monthly Project Status Report Overall Status: On Track

Project Name: RESTORATION OF SAN PABLO CATHEDRAL BELFRY

July 1, 2017

Status Code Legend


 On Track: Project is on schedule  High Risk: At risk, with a high risk of going off track
 At Risk: Milestones missed but date intact  Off Track: Date will be missed if action not taken

The project is ON TRACK  The experiment on Jabon Y Alumbre has commenced and is now under observation
the week of 6/1/2017 -  Fabrication of sample baluster for Belfry’s Roof Deck.
6/30/2017, due to the  Plastering (Initial Coating) of walls, columns, details, and arched window openings on
following: 2nd, 3rd, and 4th Level of the Belfry.
 Study of Jabon Y Alumbre (waterproofing application on roof)

Issues:  The cross’ support/base is in need of repair/rebuild.


 The cross itself is in need of repair, also, the parish wants the wind vane to rotate again.
 Rainy season. *works moved to the interior*
 New design and/or system for the bells.

Milestones  Done with Documentation


accomplished the week  Done Plastering (Initial Coating) on 2nd Level of the Belfry.
of 6/1/2017 - 6/30/2017:  Removed belfry’s cross and dismantled the base of the cross.

Milestones planned this  Electrical Plan (Prepared by an Electrical Engineer)


week, but not achieved  New System for Bells
with variance:

Milestones planned for  Experiment: Jabon Y Alumbre


next week:  Plastering: 3rd Level of the Belfry
 Fabrication (approved) of Balusters

Revellin de Recoletos, Victoria Street Phone: (02) 527-6623 e-mail: info@escuelataller.org.ph 1


Intramuros 1200, Manila City, Philippines Telefax: (02) 525-1986 www.escuelataller.org.ph
Areas/questions for [Please See Submitted Phase I: Documentation Report]
discussion:

Last week’s issues Materials and Procedures for the Application of Jabon Y Alumbre.
forwarded to this week:

Ongoing Works Photo Documentation

Image 1. Fabrication of Balusters (Sample Only). Image 2. Removal of cross above the tower.

Revellin de Recoletos, Victoria Street Phone: (02) 527-6623 e-mail: info@escuelataller.org.ph 2


Intramuros 1200, Manila City, Philippines Telefax: (02) 525-1986 www.escuelataller.org.ph
Image 3. Documentation of Cross. Image 4. Documentation of Cross.

Image 5. Chipping works. Image 6. Chipping works. Image 7. Chipping works.

Revellin de Recoletos, Victoria Street Phone: (02) 527-6623 e-mail: info@escuelataller.org.ph 3


Intramuros 1200, Manila City, Philippines Telefax: (02) 525-1986 www.escuelataller.org.ph
Image 8. Sample documentation works. Image 9. Sample Documentation Works.
Image 5. Chipping works. Image 6. Chipping works.

Image 10. Sample documentation works. Image 11. Sample documentation works.

Revellin de Recoletos, Victoria Street Phone: (02) 527-6623 e-mail: info@escuelataller.org.ph 4


Intramuros 1200, Manila City, Philippines Telefax: (02) 525-1986 www.escuelataller.org.ph
Image 12. Belfry with scaffolding set-up and safety nets. Image 13. Rear view of the Belfry.

Prepared by: Noted by:

Ar. Sarah Jane S. Pahimnayan Ar. Jeffrey D. Cobilla


Junior Project Officer Head, Academics & Workshop and Technical Team

End of Report

Revellin de Recoletos, Victoria Street Phone: (02) 527-6623 e-mail: info@escuelataller.org.ph 5


Intramuros 1200, Manila City, Philippines Telefax: (02) 525-1986 www.escuelataller.org.ph

You might also like