July 1, 2017
The project is ON TRACK The experiment on Jabon Y Alumbre has commenced and is now under observation
the week of 6/1/2017 - Fabrication of sample baluster for Belfry’s Roof Deck.
6/30/2017, due to the Plastering (Initial Coating) of walls, columns, details, and arched window openings on
following: 2nd, 3rd, and 4th Level of the Belfry.
Study of Jabon Y Alumbre (waterproofing application on roof)
Last week’s issues Materials and Procedures for the Application of Jabon Y Alumbre.
forwarded to this week:
Image 1. Fabrication of Balusters (Sample Only). Image 2. Removal of cross above the tower.
Image 10. Sample documentation works. Image 11. Sample documentation works.
End of Report