You are on page 1of 29

IRC International Seminar on “Construction and Rehabilitation of Rigid Pavement-

Current Practice and Way Forward”, 18-19 January, 2019, New Delhi

Methodology adopted for Construction of


Short Paneled Concrete Pavements
(SPCP) on High Volume Roads
Authors:
K Sridhar Reddy
Prof. M. Amaranatha Reddy
Dr. Nilanjan Mitra
Prof. K Sudhakar Reddy
Presenter:
K Sridhar Reddy

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 1
Presentation Outline
• Introduction
• Literature Review
• Short Paneled Concrete Pavement (SPCP)
• Construction of SPCP
• Test Sections 1 and 2
• Lessons Learnt
• Future Research Directions
• Selected References
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 2
Introduction
Extended
ExtendedBase
Base Membrane
Membrane
PQC,M40
PQC, M40

DLC, M10

GSB, Drainage Layer Current practice


Subgrade (Natural Soil/Prepared Fill)

A Typical Concrete Pavement System

A 3.5 m

Plan view
4.5 m

B
Elevation

Jointed Plain Concrete Pavement (JPCP)


Dowel Relief cut of h/3

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 3
JPCP: Performance based design
Sun

Specifications and Guidelines-


IRC:58-2015 - JPCP

T1>T2 Salient Features:

Fatigue Damage Analysis by Miner’s


Bottom Up Cracking Approach:
Cumulative Fatigue Damage BUC
+
Cumulative Fatigue Damage TDC
=
Cumulative Fatigue Damage Total < 1, Safe

T2>T1
Typical thickness 250 to 290
Top Down Cracking mm

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 4
Short Paneled Concrete Pavements (SPCP):
An Alternative Option?

!?

Cost
SPCP ≃ Bituminous
Thickness
Performance
• Durable
• No Wild Cracking

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 5
Short Paneled Concrete Pavements (SPCP)
• SPCP: Similar to JPCP but short panel size (0.5 x 0.5
m to 2.0 x 2.0 m) and reduced thickness (load and
thermal stresses)
• Use of PQC- on strong foundation (CTSB and DLC)
• Contraction joints @ 0.5 to 2.0 m length; with/ without
any reinforcement (Dowel /Tie bars) and with/ without
joint sealing
• Likely to have more compressive stresses on
foundation
• Materials and Cost saving
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 6
SPCP vs JPCP

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 7
Design variables for SPCP

Design traffic
Number of lanes
Size of the panel (concrete slabs)
Thickness of the panel
Interfacial bond between PQC and DLC
Type of base layer
Lateral wheel wander

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 8
Effect of Joint Spacing
 Joints : Timely joint spacing and cutting
(1/3rd depth- 3 to 5 mm width)

 Load Transfer: Aggregate interlock across closely spaced joints

1.0 m 1.0 m 1.0 m 4.5 m

Short Paneled Concrete Pavement (SPCP) Jointed Plain Concrete Pavement (JPCP)

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 9
SPCP Construction

PQC
DLC
CTGSB
Subgrade

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 10
SPCP Construction: Test section 1, NH-2
384 m long, NH-02, Panagarh Bypass, West Bengal (Sept., 2016)
Panel Size, Thickness,
Interface b/w Panel and DLC Chainage, km Length, m
Sq.m mm

Nonwoven Geotextile 519+316 to 519+450 134


1x1 180 Emulsion of RS-I 519+450 to 519+550 100
Bonded 519+550 to 519+700 150

PQC, M40, 180 mm

DLC, M10, 150 mm

CTSB, 2.5%, 150 mm

Subgrade, CBR>10%, 500 mm

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 11
Test Section 1, NH-2

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 12
Saw cutting window

Courtesy: Raoufi et al., TRR, 2008

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 13
SPCP: Joint saw cutting
First level
3m
Plan view of SPCP

Short Paneled Concrete Pavement (SPCP)

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 14
SPCP: Joint saw cutting
Second level 3m
1m
Plan view of SPCP

Short Paneled Concrete Pavement (SPCP)

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 15
SPCP: Joint saw cutting
Primary cut Secondary cut

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 16
Finished Pavement, NH-2

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 17
SPCP Construction: Test section 2, NH-33

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 18
SPCP Construction

Joint Cutting:
Initial: 3 x 3 m
Final: 1 x 1 m

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 19
Plan view of SPCP
SPCP: Finished Stage

Short Paneled Concrete Pavement (SPCP)


Profile

No. of relief cuts or No Dowels

Dowels/Ties
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 20
SPCP: Load Distribution

Wheel Load Distribution on Short Paneled Concrete Pavement (SPCP), NH-2


K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 21
SPCP
Important Issue: Mismatch in DLC and PQC joints (1 x 1 m)
1m

PQC
DLC
5m
Root cause for sympathetical cracking

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 22
SPCP
Important Issue: Mismatch in DLC and PQC joints (2 x 2 m)
2m

PQC
DLC
5m
Root cause for sympathetical cracking

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 23
SPCP
Important Issue: Matching DLC and PQC joints (1.5 x 1.5 m)
1.5 m

PQC
DLC
5m Safe from sympathetical cracking

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 24
Lessons Learnt
 Mechanized paving found to be effective from construction time
and surface finish.
 Few construction joints. Considerable reinforcement can be
avoided and hence cost saving.
 Material saving. In other words, sustainability and cost saving.
 Timely saw cutting is important.
 Width of narrow contraction joints is about 3-5 mm.
 Two stage joint cutting system found to be effective
 Joints in DLC and PQC should overlap.

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 25
Future Research Directions
 Seasonal variation of Load Transfer Efficiency (LTE) in short
slabs.
 Effect of slab geometry on LTE.
 Effect of different base layers on structural performance.
 Establishment of relationship between LTE and crack width
opening.
 Performance of SPCP with various interfacial bond conditions
between PQC and DLC.
 Distress mapping of in-service pavement.

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 26
Structural Evaluation

Critical Loading Positions: 𝑑𝑢𝑙


• LTE at joints, % = x 100
• Interior 𝑑𝑙
• Edge • Seasonal variation, variation of geometry on LTE
• Corner • Degree of bonding

K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 27
Selected References
• Raoufi, K., Radlinska, A., Nantung, T., & Weiss, J. (2008). Methodology for
determining the timing of saw cutting in concrete pavements. Transportation Research
Record, 2081(1), 110-117.
• Zollinger, D. G., Tang, T., & Xin, D. (1994). Sawcut depth considerations for jointed
concrete pavement based on fracture mechanics analysis. Transportation Research
Record, (1449).
• Roesler, J. R., Cervantes, V. G., & Amirkhanian, A. N. (2012). Accelerated
performance testing of concrete pavement with short slabs. International Journal of
Pavement Engineering, 13(6), 494-507.
• AASHTO (1993). “Guide for Design of Pavement Structures.” American Association
of State Highway and Transportation Officials.
• IRC: 58 (2015). “Guidelines for the Design of Plain Jointed Rigid Pavements for
Highways”. The Indian Roads Congress, New Delhi.
• Salsilli, R., Wahr, C., Delgadillo, R., Huerta, J., & Sepúlveda, P. (2015). Field
performance of concrete pavements with short slabs and design procedure calibrated
for Chilean conditions. International Journal of Pavement Engineering, 16(4), 363-
379.
• Ministry of Road Transport and Highways (MoRTH) (2013). “Specifications for Road
and Bridge works”, fifth revision, The Indian Roads Congress, New Delhi
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 28
Acknowledgements

• National Highway Authority of India (NHAI), Govt. of


India for sponsoring the research entitled “Field
Investigations of Paneled Concrete Pavements (FPC)”,.
• Late Prof. B B Pandey, Advisor, SRIC, IIT Kharagpur
• IL&FS Transportation Networks Limited (ITNL), Barwa-
Adda Expressways Ltd (NH-2).
• Dilip Buildcon Ltd., Bhopal, India (NH-33).

Thank you…
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 29

You might also like