Professional Documents
Culture Documents
Current Practice and Way Forward”, 18-19 January, 2019, New Delhi
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 1
Presentation Outline
• Introduction
• Literature Review
• Short Paneled Concrete Pavement (SPCP)
• Construction of SPCP
• Test Sections 1 and 2
• Lessons Learnt
• Future Research Directions
• Selected References
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 2
Introduction
Extended
ExtendedBase
Base Membrane
Membrane
PQC,M40
PQC, M40
DLC, M10
A 3.5 m
Plan view
4.5 m
B
Elevation
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 3
JPCP: Performance based design
Sun
T2>T1
Typical thickness 250 to 290
Top Down Cracking mm
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 4
Short Paneled Concrete Pavements (SPCP):
An Alternative Option?
!?
Cost
SPCP ≃ Bituminous
Thickness
Performance
• Durable
• No Wild Cracking
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 5
Short Paneled Concrete Pavements (SPCP)
• SPCP: Similar to JPCP but short panel size (0.5 x 0.5
m to 2.0 x 2.0 m) and reduced thickness (load and
thermal stresses)
• Use of PQC- on strong foundation (CTSB and DLC)
• Contraction joints @ 0.5 to 2.0 m length; with/ without
any reinforcement (Dowel /Tie bars) and with/ without
joint sealing
• Likely to have more compressive stresses on
foundation
• Materials and Cost saving
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 6
SPCP vs JPCP
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 7
Design variables for SPCP
Design traffic
Number of lanes
Size of the panel (concrete slabs)
Thickness of the panel
Interfacial bond between PQC and DLC
Type of base layer
Lateral wheel wander
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 8
Effect of Joint Spacing
Joints : Timely joint spacing and cutting
(1/3rd depth- 3 to 5 mm width)
Short Paneled Concrete Pavement (SPCP) Jointed Plain Concrete Pavement (JPCP)
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 9
SPCP Construction
PQC
DLC
CTGSB
Subgrade
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 10
SPCP Construction: Test section 1, NH-2
384 m long, NH-02, Panagarh Bypass, West Bengal (Sept., 2016)
Panel Size, Thickness,
Interface b/w Panel and DLC Chainage, km Length, m
Sq.m mm
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 11
Test Section 1, NH-2
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 12
Saw cutting window
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 13
SPCP: Joint saw cutting
First level
3m
Plan view of SPCP
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 14
SPCP: Joint saw cutting
Second level 3m
1m
Plan view of SPCP
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 15
SPCP: Joint saw cutting
Primary cut Secondary cut
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 16
Finished Pavement, NH-2
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 17
SPCP Construction: Test section 2, NH-33
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 18
SPCP Construction
Joint Cutting:
Initial: 3 x 3 m
Final: 1 x 1 m
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 19
Plan view of SPCP
SPCP: Finished Stage
Dowels/Ties
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 20
SPCP: Load Distribution
PQC
DLC
5m
Root cause for sympathetical cracking
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 22
SPCP
Important Issue: Mismatch in DLC and PQC joints (2 x 2 m)
2m
PQC
DLC
5m
Root cause for sympathetical cracking
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 23
SPCP
Important Issue: Matching DLC and PQC joints (1.5 x 1.5 m)
1.5 m
PQC
DLC
5m Safe from sympathetical cracking
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 24
Lessons Learnt
Mechanized paving found to be effective from construction time
and surface finish.
Few construction joints. Considerable reinforcement can be
avoided and hence cost saving.
Material saving. In other words, sustainability and cost saving.
Timely saw cutting is important.
Width of narrow contraction joints is about 3-5 mm.
Two stage joint cutting system found to be effective
Joints in DLC and PQC should overlap.
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 25
Future Research Directions
Seasonal variation of Load Transfer Efficiency (LTE) in short
slabs.
Effect of slab geometry on LTE.
Effect of different base layers on structural performance.
Establishment of relationship between LTE and crack width
opening.
Performance of SPCP with various interfacial bond conditions
between PQC and DLC.
Distress mapping of in-service pavement.
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 26
Structural Evaluation
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 27
Selected References
• Raoufi, K., Radlinska, A., Nantung, T., & Weiss, J. (2008). Methodology for
determining the timing of saw cutting in concrete pavements. Transportation Research
Record, 2081(1), 110-117.
• Zollinger, D. G., Tang, T., & Xin, D. (1994). Sawcut depth considerations for jointed
concrete pavement based on fracture mechanics analysis. Transportation Research
Record, (1449).
• Roesler, J. R., Cervantes, V. G., & Amirkhanian, A. N. (2012). Accelerated
performance testing of concrete pavement with short slabs. International Journal of
Pavement Engineering, 13(6), 494-507.
• AASHTO (1993). “Guide for Design of Pavement Structures.” American Association
of State Highway and Transportation Officials.
• IRC: 58 (2015). “Guidelines for the Design of Plain Jointed Rigid Pavements for
Highways”. The Indian Roads Congress, New Delhi.
• Salsilli, R., Wahr, C., Delgadillo, R., Huerta, J., & Sepúlveda, P. (2015). Field
performance of concrete pavements with short slabs and design procedure calibrated
for Chilean conditions. International Journal of Pavement Engineering, 16(4), 363-
379.
• Ministry of Road Transport and Highways (MoRTH) (2013). “Specifications for Road
and Bridge works”, fifth revision, The Indian Roads Congress, New Delhi
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 28
Acknowledgements
Thank you…
K Sridhar Reddy Construction and Rehabilitation of Rigid Pavement-Current Practice and Way Forward 1/24/2019 29