METHOD STATEMENT
1.0 INTRODUCTION
2.0 PURPOSE
Consultant : Meinhardt
2. PURPOSE
The purpose of this construction method is to provide guidance on the required works
to construct the buildings and external works of Penilsula Yangon Project in order to
achieve the require quality, safety and timely completion as per schedule. A full investigation
by a Qualified Project Engineer and Planning Engineer will be required prior to any works
commencing on construction works. This proposed construction method document noted
above should be read in conjunction the reference contract documents, drawings and
specification. Any discrepancies between this information and current conditions on site
should be reported to the Employer immediately.
This method of statement is prepared to ensure that construction of buildings for the
project shall comply on plans specifications and all relevant standard and code requirements
in the execution of different work activities to be performed in the construction of buildings
and other relevant structure associated with the project in general. In addition this will serve
3.1.1 Material
3.1.2 Preparation
- Task launch meeting will be held by Engineer in charge of the works with all the staff
concerned by this activity to explain and remind for the Method Statement (MS),
Inspection & Testing Plan (ITP),Safety.
- Fire Water Pipe, Foam Pipe and fitting for external and internal are bought to the site
and inspected by authorized person by BYMA ENGINEER.
3.2.1 Material
3.2.2 Preparation
- Task launch meeting will be held by Engineer in charge of the works with all the staff
concerned by this activity to explain and remind for the Method Statement (MS),
Inspection & Testing Plan (ITP), Safety.
- Main Fire Alarm Panel, Sub-Fire Alarm Panel, FR Cable and Fixture for external and
internal are bought to the site and inspected by authorized person by BYMA
ENGINEER.
- After finishing the checking and cleaning conduit well, the cable can be pulled in conduit to
respective point.
- The alarm bell, Horns, Strobe Light and Manual call install at specified mounted level
according to the shop drawing and respective site engineer.
- The Main Fire Alarm Panel have one loop for alarm bell, horns, strobe light, manual
call points, Heat detector, smoke detector, beam detector. The Sub-alarm panel have
two number and each panel have one loop for alarm bell, horns, strobe light, manual
call points, heat detector, smoke detector, beam detector. The installation of FAP is
specified according to the shop drawing.
Safety harness and lanyards must be worn by all personal who work at a place from which
they are liable to fall into water or at a height of more than 2 meters.
5.2 Grinding
A daily meeting will be given to you prior to the beginning of each work days. These
meetings are designed to keep your updated on current events and plans. They will tell you of
hazardous areas where extra care is required. The correct way to do a task to prevent injury to yourself
or others will be explained clearly to you.
7.2.1 Type of initiating devices used in this project and their test methods are as follows:
- Smoke Detector- Apply SOLO Aerosol in the smoke detector chamber until red LED glows
steady.
- Heat Detector- Switch on and place the heat run covering the detector until the LED glows
steady.
- Manual Call Point- Open the manual call point using simplex key.
- Sprinkler Flow Switch- Open the test drain valve until fire alarm control panel receives
FIRE signal. (Sprinkler supplier coordination required).
7.2.3 Function test of devices shall be carried out loop by loop as follows:
- Verify all interfaces are functioning in case of activation of corresponding initiating devices.
- Test shall be carried out in the sequence of loop by loop. It will be tested by activating any
detector or break glass in the loop and verify the following effects are taken place.
- It will be tested by activating one device in the building also, one manual call point will be
operated in each floor. The testing will be done as follows:
- PA System: Fire and Ensure that all speakers are working.
- Fire Fighting: Create Fire and ensure that the signal is going to the panel.
After successful testing of entire system a historical log shall be generated and printed for
review and comments for inspectors.
The system has a walk test feature which allows a signal person to test the devices. Walk test
enable will show as a trouble warning in the system and will be cleared after successful exit of walk
test. Walk test events also will be recorded in Main fire alarm panel. System will reset itself after
every device test.
After the successful commissioning the results will be recorded on the testing and
commissioning sheets attached with the documents.
TOOLS
- Welding Machine
- Thread Machine
- Cutting Machine
- Holing Machine
- Stand Drill
- Grinder
- Hole Saw
- Painting Machine
- Measure Tape
- Line Marker
- Accessories
- Insulation tester
- Digital Multi Meter
- Detector Tester
- G.I Bender
- Cable puller
- Wire Cutter
- Tester
- Screw driver
- Hacksaw blades
- Measuring tape
- Line marker
- Accessories
- Safety induction for all workers, staff supervisors, labor related to this work by MINDAMA
Safety officer.
- Task launch meeting for all workers working on this task and direct supervisors by BYMA
Engineer in charge.