600 - FGWHRU - AL Gulf Coast SMR H2 Project - Lurgi - Air Liquide - La Porte, Texas,
USA
Nameplates
1. Nameplates for the steam and blow down drum.
BIH explain that it is not longer possible to further revise the TEI Struthers documentation. SI
Units are to be used. Duel units are to be maintained in kpag and barg.
Tosco Agree to generate a drawing of the nameplates themselves and incorporate ABS’s latest
comment.
BIH ACTION: To confirm the requirement for RT-1 for the U stamp plate?
3. ASME VIII div 1 crossovers and desuperheater pup piece will NOT be U stamped, however
ABS inspection level will include all that is required by ASME VIII div 1.
PWHT
5. Coil 03A. ABS outline that the superheater coil to manifold welds fall within ASME sec1 PW-39
c) meaning that PWHT is required.
TORSCO ACTION: Torsco to submit PWHT procedure and complete PWHT
6. Coil 03B.
BIH/ABS ACTION: Further investigation into the code is required to see if PWHT is applicable
In accordance with PW-39, PWHT is required unless exempted by the notes in Table PW-39.
Therfore, I would like to request Torsco QC to look at every weld joint ( including fillet welds) for
exemption. If there is no exemption, pls consider that PWHT is required See below which is
copied from ASME Section I.in yellow
PW-39.1 Before applying the detailed requirements
and exemptions in these paragraphs, satisfactory weld procedure
qualifications of the procedures to be used shall be
performed in accordance with all the essential variables of
Section IX including conditions of postweld heat treatment
or lack of postweld heat treatment and including other
restrictions listed below. Except as otherwise specifically
provided in PFT-29, PMB-9, PW-40.2, PW-40.3, and in
the notes within Table PW-39, all welded pressure parts
of power boilers shall be given a postweld heat treatment
at a temperature not less than that specified in Table PW-
39.1. The materials in Table PW-39 are listed in accordance
with the materials P-Number grouping of QW-420 of Section
IX. PW-39.1 Before applying the detailed requirements
and exemptions in these paragraphs, satisfactory weld procedure
qualifications of the procedures to be used shall be
performed in accordance with all the essential variables of
Section IX including conditions of postweld heat treatment
or lack of postweld heat treatment and including other
restrictions listed below. Except as otherwise specifically
provided in PFT-29, PMB-9, PW-40.2, PW-40.3, and in
the notes within Table PW-39, all welded pressure parts
of power boilers shall be given a postweld heat treatment
at a temperature not less than that specified in Table PW-
39.1. The materials in Table PW-39 are listed in accordance
with the materials P-Number grouping of QW-420 of Section
IX.
ABS ACTION: To send the definition of circumferential butt welds from ASME IX to BIH
Definitions
FROM – ASME IX
QW/QB-492