BAHAGIAN 5.

0 : KOS SEWA LOJI DAN PERALATAN


Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak
Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan,
Selangor dan Johor
Kawasan Timur - Pahang, Terengganu dan Kelantan

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN


Item Description
UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT
(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

1 Backhoe hour 60.56 50.00 - 100.00 62.08 50.00 - 80.00 61.32 50.00 - 100.00

2 Dragline
RB 19 hour 72.50 50.00 - 100.00 83.73 80.00 - 123.00 78.12 50.00 - 123.00
RB 22 hour 80.31 65.00 - 100.00 92.43 90.00 - 131.00 86.37 65.00 - 131.00
RB 30 hour 92.94 70.00 - 110.00 101.53 100.00 - 157.00 97.24 70.00 - 157.00

3 Excavator
Up to 0.5 m3 hour 75.88 65.00 - 100.00 88.85 60.00 - 150.00 82.37 60.00 -150.00
3 3
0.5 m to 1.0 m hour 87.44 69.00 - 125.00 112.03 71.00 - 187.50 99.74 69.00 - 187.50
Over 1.0 m3 hour 101.56 75.00 - 175.00 132.69 81.00 - 187.50 117.13 75.00 - 187.50

4 Excavator houdralic operated


Up to 0.5 m3 hour 78.75 60.00 - 100.00 96.50 60.00 - 190.00 87.63 60.00 -190.00
0.5 m3 to 1.0 m3 hour 90.00 70.00 - 125.00 119.44 70.00 - 195.00 104.72 70.00 -195.00
Over 1.0 m3 hour 103.94 80.00 - 175.00 139.88 80.00 - 210.00 121.91 80.00 - 210.00

5 Face Showel
Model 920 hour 82.69 60.00 - 100.00 98.31 50.00 - 170.00 90.50 50.00 - 170.00
Model 950 hour 92.50 70.00 - 125.00 116.23 90.00 - 175.00 104.37 70.00 - 175.00
Model 966 hour 105.31 80.00 - 175.00 136.39 90.00 - 180.00 120.85 80.00 - 180.00

6 Back Pusher hour 61.88 45.00 - 95.00 56.80 50.00 - 75.00 59.34 45.00 - 95.00

7 Vibrating Roller 15 tonne hour 78.59 45.00 - 105.00 104.07 80.00 - 150.00 91.33 45.00 - 150.00

8 Compressor hour 76.53 35.00 - 125.00 53.94 35.00 - 112.50 65.24 35.00 - 125.00

9 Bulldozer
Model D4 hour 80.94 60.00 - 100.00 88.00 60.00 - 116.00 84.47 60.00 - 116.00
Model D6 hour 93.71 70.00 - 110.00 99.94 70.00 - 140.00 96.83 70.00 - 140.00
Model D8 hour 110.65 60.00 - 140.00 119.48 70.00 - 173.00 115.07 60.00 - 173.00

89
BAHAGIAN 5.0 : KOS SEWA LOJI DAN PERALATAN
Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak
Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan,
Selangor dan Johor
Kawasan Timur - Pahang, Terengganu dan Kelantan

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN


Item Description
UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT
(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

10 Tractor hour 74.64 50.00 - 150.00 98.57 50.00 - 150.00 86.61 50.00 - 150.00

11 Mobile Crane
3 tonne hour 62.31 45.00 - 80.00 65.66 45.00 - 100.00 63.99 45.00 - 100.00
16 tonne hour 72.41 55.00 - 106.00 80.37 60.00 - 125.00 76.39 55.00 - 125.00
25 tonne hour 88.50 65.00 - 113.00 96.64 80.00 - 140.00 92.57 65.00 - 140.00
35tonne hour 101.60 70.00 - 150.00 117.80 90.00 - 180.00 109.70 70.00 - 180.00
40 tonne hour 129.63 75.00 - 200.00 145.32 95.00 - 250.00 137.48 75.00 - 250.00

12 Motor Grader hour 76.00 60.00 - 100.00 106.50 80.00 - 140.00 91.25 60.00 - 140.00

13 Dumper
3
Up to 0.5 m hour 63.12 30.00 - 80.00 74.33 50.00 - 125.00 68.73 30.00 - 125.00
0.5 m to 3.5 m3
3
hour 67.00 45.00 - 86.00 84.95 62.50 - 120.00 75.98 45.00 - 120.00

14 Steel Roller
8 tonne hour 63.65 30.00 - 100.00 101.13 65.00 - 150.00 82.39 30.00 - 150.00
12 tonne hour 75.00 40.00 - 120.00 120.53 80.00 - 200.00 97.77 40.00 - 200.00

15 Low Loader hour 86.80 70.00 - 100.00 190.04 50.00 - 380.00 138.42 50.00 - 380.00

16 Lorry
6 tonne hour 59.71 35.00 - 80.00 60.62 40.00 - 80.00 60.17 35.00 - 80.00
8 tonne hour 69.29 50.00 - 85.00 78.22 60.00 - 100.00 73.76 50.00 - 100.00
10 tonne hour 79.06 60.00 - 100.00 96.81 75.00 - 150.00 87.94 60.00 - 150.00

17 Tipper without road tax


6 tonne hour 56.47 30.00 - 80.00 49.61 30.00 - 70.00 53.04 30.00 - 80.00
10 tonne hour 71.47 50.00 - 120.00 69.91 38.00 - 120.00 70.69 38.00 - 120.00

18 Tipper with road tax


6 tonne hour 65.88 40.00 - 100.00 66.75 40.00 - 80.00 66.32 40.00 - 100.00
10 tonne hour 82.35 65.00 - 130.00 91.50 70.00 - 150.00 86.93 65.00 - 150.00

90
BAHAGIAN 5.0 : KOS SEWA LOJI DAN PERALATAN
Kawasan Utara - Perlis, Kedah, Pulau Pinang dan Perak
Kawasan Tengah - Wilayah Persekutuan Kuala Lumpur, Melaka, Negeri Sembilan,
Selangor dan Johor
Kawasan Timur - Pahang, Terengganu dan Kelantan

KAWASAN UTARA KAWASAN TENGAH KAWASAN TIMUR KESELURUHAN


Item Description
UNIT PURATA JULAT PURATA JULAT PURATA JULAT PURATA JULAT
(RM) (RM) (RM) (RM) (RM) (RM) (RM) (RM)

19 Concrete Mixer
Concrete Mixer 7/5 hour 38.53 10.00 - 95.00 37.53 10.00 - 80.00 38.03 10.00 - 95.00
Concrete Mixer 10/7 hour 45.88 10.00 - 100.00 50.39 10.00 - 100.00 48.14 10.00 - 100.00
Concrete Mixer 14/10 hour 56.59 15.00 - 110.00 64.61 15.00 - 120.00 60.60 15.00 - 120.00
Concrete Mixer 21/14 hour 69.94 15.00 - 125.00 79.78 15.00 - 150.00 74.86 15.00 - 150.00

20 Water Pump
3'' Diameter hour 46.88 10.00 - 90.00 34.15 20.00 - 70.00 40.52 10.00 - 90.00
6'' Diameter hour 61.18 10.00 - 100.00 45.47 25.00 - 75.00 53.33 10.00 - 100.00
8" Diameter hour 74.59 10.00 - 150.00 59.94 30.00 - 100.00 67.27 10.00 -150.00

21 Welding and cutting set complete


Oxy - acetylene hour 52.94 20.00 - 90.00 86.68 40.00 - 200.00 69.81 20.00 - 200.00
Electric hour 46.33 15.00 - 100.00 91.36 50.00 - 200.00 68.85 15.00 - 200.00

Drilling machine complete with all necessary


22 hour 69.08 30.00 - 100.00 219.89 150.00 - 500.00 144.49 30.00 - 500.00
equipment