ABCI/SITE/NHIDCL/NH-54/PKG-4/2020-21/ 110 Date: 02-05-2020

The General Manager (P)


National Highways and Infrastructure Development Corporation Limted
PMU-Lunglei
Mizoram – 796701

Kind Attn: Mr. Pradeep Gairola

Sub: “Widening and up-gradation to 2-lane with paved shoulder configuration and geometric
improvements from km 166.00 to km 208.00 (Package-4) on Aizawl-Tuipang section of NH-54
in the State of Mizoram on EPC mode with JICA loan assistance” – Reg. Shifting of Utilities

Ref: i) NHIDCL Letter no NHIDCL/BO-Aizawl/2019-20/204 dated 09.10.2019


ii) Our letter no. ABCI/KOL/NHIDCL/NH54/PKG-4/2019-20/920 dated 14.10.2019
iii) NHIDCL Letter no NHIDCL/BO-Aizawl/2019-20/221 dated 23.10.2019
iv) Our letter no. ABCI/KOL/NHIDCL/NH54/PKG-4/2019-20/1078 dated 18.11.2019
v) Our letter no. ABCI/SITE/AE/NH-54/PKG-4/2019-20/ 05 dated 18.11.2019(P&E Dept.)
vi) Memo no NHIDCL/BO-Aizawl/2019-20/356 dated 03.01.2020
vii) Our letter no. ABCI/KOL/NHIDCL/NH54/PKG-4/2019-20/1735 dated 27.02.2020
viii) NHIDCL Letter no NHIDCL/PMU-Lunglei /2019-20/13 dated 02.03.2020
ix) Our letter no. ABCI/KOL/NHIDCL/NH54/PKG-4/2019-20/1772 dated 04.03.2020
x) AE’s Letter no. Rodic-Tpf/Mizoram-Jica/Pkg-3/4/5/Aizawl-Tuipang/2020/304 dated 13.03.2020
xi) NHIDCL Letter no NHIDCL/PMU-Lunglei /Tech/Pkg-4/02 dated 21.03.2020
xii) NHIDCL Letter no 202/NHIDCL/PMU-Lunglei /NH-54/Wk/Pkg-4/02 dated 22.03.2020(Received
on 22.04.2020)
xiii) NHIDCL Letter no 202/NHIDCL/PMU-Lunglei /NH-54/Wk/Pkg-4/11 dated 01.05.2020

Dear Sir,

We are in receipt of your letter dated 01.05.2020 regarding the subject matter; consequently we wish to
humbly submit as under.

1. It has been communicated to the Contractor only on 21.03.2020 that the Contractor is to deposit
money as per the NHIDCL-HO approved estimate to Public Health Engineering Department and
Power & Electricity Department for shifting of the respective utilities for the instant project which
will be reimbursed by NHIDCL to the Contractor on production of invoice.

2. Accordingly it was requested by the Contractor to execute a tripartite supplementary agreement


between the Authority, Contractor and the utility owning department who will shift the affecting
utilities and make the project road free from all the obstructing utilities prior to deposit the
sanctioned sum to the utility owning agencies.

3. However due to outbreak of pandemic coronavirus and subsequent restrictions and lockdown the
further necessary action could not be proceeded with the respective departments for the reasons
beyond the control of the Contractor.
4. The NHIDCL authority has further requested to the Contractor vide letter under reference (xiii) to
deposit the sanctioned sum to the utility owning agencies.

5. It is therefore once again requested to kindly provide us the draft supplementary agreement for
tripartite arrangement between the NHIDCL Authority, Contractor and the respective utility owning
department stating all the terms and conditions therein, so that the same can be executed at the
earliest enabling the Contractor to deposit the requisite sum to the utility owning department for
shifting of utilities.

Thanking you and assuring you of our best services always.

Yours faithfully,
For ABCI Infrastructures Pvt. Ltd.

Authorized Signatory
Prafulla Borgohain
Senior General Manager

Copy for kind information to:-

Copy for kind information and necessary action to:-


1. The Executive Director (P), NHIDCL, RO,Aizawl
2. The Deputy General Manager (P), NHIDCL, Lunglei, Mizoram
3. NHIDCL Site Office (Pkg 4) Lunglei, Mizoram
4. Sri Saksham Tyagi, Site Representative of NHIDCL, Lunglei.