1. What is Johnson’s most pressing problem? Why?


2. What can Johnson do to help her team launch the new product within the six-week
timeframe? Be specific?
3. Assume Johnson will select a new team to launch another Web-based product after this
product is complete. What do you recommend she do differently next time? Explain.
Ellen Johnson had just completed her first month as manager for a successful company that
provides a variety of Web-based services and solutions. Last week, she was informed that she
would be the new leader of a team that included 10 individuals. To her surprise, not only were
these team members diverse in terms of their functional training and expertise, but they also
represented a variety of cultural backgrounds and only three were located in her office building.
She quickly learned that 7 of the 10 individuals actually worked from their home countries, which
included Japan, China, Mexico, Australia, Germany, Colombia, and Egypt. Up until this point,
this “virtual team” collaborated on projects by using a variety of communication tools, including
instant e-mail messaging, telephone calls, videoconferencing, document sharing, and
occasional meetings at headquarters. After reviewing some of the past meeting notes and
communication transcripts among the group members, Johnson realized that many of the team
members had very different communication styles and levels of proficiency in English.
The team’s new assignment was an important one. The 10 members needed to develop and
roll out a new product within the next six weeks. This was in direct response to a new product
just launched by a major competitor. To complicate matters, a six-week product development
cycle was unheard of; until this point, the company’s turnaround time for a new product offering
was approximately three months. The company had no choice. If they did not counter the
competitive threat immediately, then the company risked losing some key customers and
market share. Johnson researched the past performance of her newly inherited virtual team.
Although the overall quality of past decisions was quite high, the team seemed to take several
months to make those decisions. This was a potential problem for Johnson. Time was no longer
a luxury. She had to figure out a way to encourage the team to move faster without
compromising quality. Through a combination of analyzing past team meeting notes and
transcripts and speaking one-on-one with team members, she started to accumulate some facts
that might be useful in solving the decision-making speed issue.
First, Johnson discovered that the Japanese and Chinese team members did not participate
much in the videoconferences or telephone conference calls; rather, they preferred written
communication in the form of faxes and e-mail. In contrast, the Australian and Mexican team
members seemed to thrive on telephone calls and face-to-face meetings. Second, there
appeared to be some infighting among the three members of the group who were domiciled at
headquarters. Most of the past arguments seemed to be about the group’s mission.
Each had a very different idea in mind in terms of what the group needed to accomplish. The
comments in written communications didn’t get personal, but there were definitely heated
debates about what objectives the group should be focusing on. The third potential obstacle to
faster decision making had to do with the sporadic use of face-to-face meetings. To her
surprise,

Reach out to freelance2040@yahoo.com for enquiry.


Johnson discovered that such meetings rarely occurred and that there was no attempt to bring
the group together when it was first formed last year. Johnson expected that the team would
have met and perhaps engaged in some team-building exercises to build trust and rapport
among team members. This was not the case. In addition, the team did not receive any form of
decision-making or group conflict resolution training.
Johnson sat back in her office and thought about the problem at hand. She needed her team to
develop and launch a new product within six weeks. To produce a high-quality product, each of
the 10 virtual team members had to contribute their knowledge and effort in a cooperative and
timely manner.