Section 09-0235A
Advice
Under some operating conditions, the hydraulics system may experience instability
of hydraulic pressures. In addition to the pressures fluctuating at the implement
valve stack, the attaching implement hoses may pulsate. An update has been
released to resolve this issue.
To resolve this issue, three things have been changed:
1. Load sense and pump reference hoses have been changed from a dash 4 to a
dash 6 hose size.
2. An orifice has been added to the load sense line.
3. An update to the implement valve software.
Parts Involved
AGCO Limited
Registered Office: Abbey Park Stoneleigh Kenilworth England CV8 2TQ
Telephone: 024 76694400 Fax: 024 7652495 Registered No. 509133 England www.challengerag.com
Challenger is a worldwide brand of AGCO.
Page 2 of 4 CHALL 45/09
Action
534421D1
CH100-4336
CH7S-1912
534407D1
AG135975
Figure 1
The new hose routing is the same as old hose routing. The three clips in Figure 1
need to be replaced due to the larger diameter of the hoses. However, the
connecting fittings to the hose will be the same, except part number AG135975
positioned at the bottom of the implement valve stack.
Page 3 of 4 CHALL 45/09
Warranty Information
Type of warranty: rectification program
Campaign number: RP6366
Causal part number: 534407D1
Labour rate code: generic
Defect code: 95-modification
Failure description RP6366 service bulletin CHALL 45/09
Labour allowance: 5.0 hours
Parts disposition: scrap
All claims to be submitted by 31 October 2010
Additional Information
Warranty claims must indicate the cost of parts identified as required on this
bulletin and allowable labour. Any additional warranty work must be submitted on a
separate claim.
This program must be completed 100%. Dealer Certification will be affected if the
rework is not 100% complete by the completion date.
Travel Allowance
Claim one (1) additional hour of labour for travel on warranty registered retailed
machines only.
Page 4 of 4 CHALL 45/09
Appendix A
Yours faithfully
Tom Robinson
Manager Technical Support —
Challenger
This bulletin is for technical information only and does not constitute authority for
warranty claims.
Bulletin source TR
© 2009 AGCO Corporation