DATE: 25-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 25-08-20 25-08-20 ment Closure
(m) (m)
KABITIRTHA
DICD100H/1 0.00 0.00 0.00 0.00 0.00 202 211.40 - - DRILL RIG STANDBY AT CAMP
KDR 750(02) 0.00 0.00 0.00 0.00 0.00 484 588.40 - - DRILL RIG STANDBY AT CAMP
DY CRFM 50 0.00 0.00 0.00 0.00 0.00 70 210 235.45 - - HYD. HOSE LEAKAGE FROM CRAWLER MOTOR
Sub Total - 0.00 70.00
BADAM
Dy-120/02 MABD-33/P-07 740 640 683 22.00 21.00 43.00 246 334 418.15 1/17/2019 - NQ DRILLING; COAL AND SANDSTONE FM.
Dy 100H/03 0 0 0 0.00 0.00 0.00 311 0.00 - - MACHINE STANDBY AT CAMP
Sub Total - 43.00 246.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 40 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 81 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 5 81 54.5 - - RIG B/D; REAPIRING IN PROGRESS
Sub Total - 0.00 5.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 645 0.00 - -
CULTIVATION WORK HAS STARTED

Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 323 0 - - RIG SHIFTED TO POINT; WAITING FOR BH APPROVAL
DRILLING UNDER PROGRESS; NO WORK DONE IN 2ND SHIFT DUE TO HEAVY
DY50CR/05 LHR -29 375 314.00 321.00 7.00 0.00 7.00 38 323 321 8/5/2020 - RAINFALL AND FAST CURRENT IN ADJACENT STREAM

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 161 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 7.00 38.00
JSW Jajang
B.H. 08/20
KDR 750/03 PBH-JJC/41/20 15.20 22.40 3.20 4.00 7.20 45 242 63.15 8/20/2020 - HQ DRILLING; BHJ FM.; 100% W/LOSS

B.H. 05/20
DYNA 50CR/07 PBH -JJC/03/20 79.70 84.50 3.70 1.10 4.80 68 242 103.8 8/5/2020 - BHJ HQ DRILLING

KDR 750/01 B.H. 03/20 33.45 35.75 2.30 0.00 2.30 30 242 34.65 7/31/2020 - HQ DRILLING; BHQ FM; RIG B/D (MAIN SHAFT ADAPTER BROKEN)
PBH-JJC/20/20
B.H. 04/20
DYNA 50CR/01 52.45 55.70 3.25 0.00 3.25 36 242 55.7 8/2/2020 - HQ DRILLING IN BHJ; 100% W/LOSS IN HOLE; RIG B/D (GEARBOX PROBLEM)
PBH-JJC/14/20
B.H. 07/20
Dyna 50H/01 50.80 55.90 3.40 1.70 5.10 86 242 55.9 8/18/2020 - HQ DRILLING; BHJ FM.
PBH- JJC/76/20

Dyna 50CR/08 B.H. 06/20 25.85 28.30 2.10 0.35 2.45 100 157 28.3 8/10/2020 - HQ DRILLING IN BHJ; 50 % W/LOSS IN BH
PBH-JJC/80/20
Sub Total - 25.10 365.00
PICHRI
LY-44/01 P-24/MAPH04 425 16.50 30.00 6.00 7.50 13.50 40 323 285 8/24/2020 - HW LINER 6 M TO 22.5 M RIH; HQ DRILLING
ALL DRILLING ACCESSORIES BEING SHIFTED TO CAMP YARD; SEARCHING FOR
CDR-1000 P-14/MAPH02 850 464.50 464.50 0.00 0.00 0.00 323 464.5 8/4/2020 8/24/2020 NEXT POINT
DI-08 P-16/MAPH03 650 315.95 354.95 21.00 18.00 39.00 170 403 354.95 8/11/2020 - NQ DRILLING IN PROGRESS
Sub Total - 52.50 210.00
GSI MAHUDA
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 25-08-20 25-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-22/ 270° / HOLE CLOSED; SURVEY DONE; MACHINR SET AT NEW POINT; ALL
UCD 60-1 160 144.25 160.95 0.00 0.00 16.70 16.70 542 470.35 8/20/2020 8/25/2020
-50° SUPPORTING DONE
KMA-24/S400/-
UCD 60-1 125 0.00 0.00 0.00 0.00 0.00 8/25/2020
60°
REMOVED CAHIN PULLEY ANAD DERRICK; ANGLE SET AT NEW POINT;
UCD 60-2 KMA-21/ +20°/N400/90°85 0.00 22.25 0.00 0.00 22.25 22.25 587 562.9 8/25/2020
DRILLING
Sub Total - 16.70 0.00
AGUCHA UG
DSP 14
UDD-330 SBH No.- 148.00 148.00 0.00 0.00 0.00 0 0 - - 14 M CASING LOWERED
Reaming'
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- NQ DRILLING; THEN RIG B/D; GEAR SHAFT LOCK BROKEN; PART DESPATCHED
DIMP-175 76.5 mm'
241.05 242.65 1.60 0.00 1.60 0 102.9 6/22/2020 -
FROM DELHI
Sub Total - 1.60 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1103.40 1109.20 2.70 3.10 5.8 210.4 6/19/2020 - B/D DUE TO MAIN WINCH PROBLEM; REPAIRED AND DRILLING STARTED
Q)'
Sub Total - 5.80 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 25-08-20 25-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 200 68 7/23/2020 - REAMING IN PROGRESS;RIG PORTION SIDE B/D

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - MANPOWER TRANSFERRED TO MALKERA PROJECT SITE
Borehole

Krishna rig
Jamadoba BH No. 01 23.00 49.15 26.15 0.00 150 49.15 8/18/2020 - SUPPORT AND CASING SET; REAMING STARTED

Sub Total - 0.00 350.00


NGRI KOYNA

DYNA 350 KBH-10-R 1500 1240.40 1240.40 0.00 0.00 0.00 75.4 1/22/2020 - RIG OFF; WORKERS ENGAGED IN CHECKING RODS AND CORE BOX PACKING

Sub Total - 0.00 0.00


DATE: 24-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 24-08-20 24-08-20 ment Closure
(m) (m)
KABITIRTHA
DICD100H/1 0.00 0.00 0.00 0.00 0.00 194 211.40 - - DRILL RIG STANDBY AT CAMP
KDR 750(02) 0.00 0.00 0.00 0.00 0.00 465 588.40 - - DRILL RIG STANDBY AT CAMP
DY CRFM 50 0.00 0.00 0.00 0.00 0.00 201 235.45 - - DRILL RIG STANDBY AT CAMP
Sub Total - 0.00 0.00
BADAM
Dy-120/02 MABD-33/P-07 740 612 640 16.00 12.00 28.00 238 323 375.15 1/17/2019 - NQ DRILLING; SHALE AND COAL FM.
Dy 100H/03 0 0 0 0.00 0.00 0.00 297 0.00 - - MACHINE STANDBY AT CAMP
Sub Total - 28.00 238.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 39 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 77 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 5 77 54.5 - - RIG B/D DURING SHIFTING; REAPIRING IN PROGRESS
Sub Total - 0.00 5.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 619 0.00 - -
CULTIVATION WORK HAS STARTED

Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 10 310 0 - - RIG SHIFTED TO POINT; WAITING FOR BH APPROVAL

DY50CR/05 LHR -29 375 302.00 314.00 9.00 3.00 12.00 40 310 314 8/5/2020 - DRILLING UNDER PROGRESS; PROGRESS POOR DUE TO HEAVY RAINFALL

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 155 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 12.00 50.00
JSW Jajang
B.H. 08/20
KDR 750/03 PBH-JJC/41/20 12.60 15.20 1.60 1.00 2.60 60 232 55.95 8/20/2020 - HQ DRILLING; BHJ FM.; 100% W/LOSS

B.H. 05/20
DYNA 50CR/07 PBH -JJC/03/20 74.20 79.70 3.50 2.00 5.50 60 232 99 8/5/2020 - CASING RETRIEVED; BHJ HQ DRILLING

KDR 750/01 B.H. 03/20 31.65 33.45 0.80 1.00 1.80 45 232 32.35 7/31/2020 - HQ DRILLING; BHQ FM;
PBH-JJC/20/20
B.H. 04/20
DYNA 50CR/01 48.65 52.45 2.40 1.40 3.80 75 232 52.45 8/2/2020 - HQ DRILLING IN BHJ; 100% W/LOSS IN HOLE
PBH-JJC/14/20
B.H. 07/20
Dyna 50H/01 45.40 50.80 3.00 2.40 5.40 90 232 50.8 8/18/2020 - HQ DRILLING; BHJ FM.
PBH- JJC/76/20

Dyna 50CR/08 B.H. 06/20 23.95 25.85 1.20 0.70 1.90 180 148 25.85 8/10/2020 - HQ DRILLING IN BHJ; 50 % W/LOSS IN BH
PBH-JJC/80/20
Sub Total - 21.00 510.00
PICHRI
LY-44/01 P-24/MAPH04 425 0.00 16.50 6.00 10.50 16.50 40 310 271.5 8/24/2020 - RIG SETTING DONE; DRILLING STARTED; HW LINER 6 M RIH
GPL DONE; BH CLOSED; ALL HW LINER RETRIEVED; NQ/HQ DISMATLING IN
CDR-1000 P-14/MAPH02 850 464.50 464.50 0.00 0.00 0.00 20 310 464.5 8/4/2020 8/24/2020 PROGRESS

HW LINER RIH; HQ DRILLING; PARTIAL W/LOSS IN HOLE; POOR PROGRESS


DI-08 P-16/MAPH03 650 296.45 315.95 0.00 19.50 19.50 100 387 315.95 8/11/2020 -
DUE TO FRACTURED FM.; HQ COMPLETE P/O FOR HQ CASING PURPOSE
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 24-08-20 24-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
Sub Total - 36.00 160.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-22/ 270° / DRILLING IN PROGRESS; H/L FOR BIT CHOPPING AND BROKEN WIRELINE;
UCD 60-1 -50° 125 136.20 144.25 0.00 4.90 3.15 8.05 497 453.65 8/20/2020 ONE SHIFT WEEKLY OFF
UCD 60-2 KMA-21/ +20°/N400/90°85 0.00 0.00 0.00 0.00 0.00 0.00 565 540.65 8/20/2020 ONE SHIFT OFF DUE TO UNAVAILABILITY OF GATE PASS; RIG B/D
Sub Total - 8.05 0.00
AGUCHA UG
DSP 14 50 M CASING LOWERED; CASING MANUALLY SHIFTED FROM DSP-13 TO
UDD-330 SBH No.- 148.00 148.00 0.00 0.00 0.00 0 0 - - WORKING SITE
Reaming'
Sub Total - 0.00 0.00
AGUCHA SUR PF
NQ WITH FLEXIBLE BARREL LOWERED TO REAM MOTOR PATH; NQ P/O;
Surface to -180-
DIMP-175 76.5 mm' 237.15 239.65 2.50 0.00 2.50 0 99.9 6/22/2020 - SURVEY DONE; NQ ROD WITH O/S REAMER LOWERED THEN DRILLING
STARTED.
Sub Total - 2.50 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1103.40 1103.40 0.00 0.00 0 204.6 6/19/2020 - B/D DUE TO MAIN WINCH PROBLEM
Q)'
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 24-08-20 24-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 250 68 7/23/2020 - BH CLEANED; REAMING STARTED

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - MANPOWER TRANSFERRED TO MALKERA PROJECT SITE
Borehole

Krishna rig
Jamadoba BH No. 01 6.00 23.00 17.00 0.00 150 23 8/18/2020 - 8" PILOT BH PUNCTURED 16A SEAM

Sub Total - 0.00 400.00


NGRI KOYNA
BH WASHED; NQ RODS P/O ALL ALONG WITH ANGLE MEASUREMENTS AT
DYNA 350 KBH-10-R 1500 1240.40 1240.40 0.00 0.00 0.00 70 75.4 1/22/2020 -
EQUAL INTERVALS OF 6 M
Sub Total - 0.00 70.00
DATE: 24-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 24-08-20 24-08-20 ment Closure
(m) (m)
KABITIRTHA
DICD100H/1 0.00 0.00 0.00 0.00 0.00 185 211.40 - - DRILL RIG STANDBY AT CAMP
KDR 750(02) 0.00 0.00 0.00 0.00 0.00 445 588.40 - - DRILL RIG STANDBY AT CAMP
DY CRFM 50 0.00 0.00 0.00 0.00 0.00 193 235.45 - - DRILL RIG STANDBY AT CAMP
Sub Total - 0.00 0.00
BADAM
Dy-120/02 MABD-33/P-07 740 590 612 10.00 12.00 22.00 130 311 347.15 1/17/2019 - HQ DRILLING; SHEAR ZONE, FRACTURED SHALE FM.
LY-44/01 0 0 0 0.00 0.00 0.00 111 272.80 - - MACHINE SHIFTED TO RD 20 SITE CAMP
Dy 100H/03 0 0 0 0.00 0.00 0.00 282 0.00 - - MACHINE STANDBY AT CAMP
Sub Total - 22.00 130.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 37 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 74 0 - - ROAD MAKING UNDER PROGRESS FOR RIG SHIFTING
RIG BEING SHIFTED TO NEXT POINT; SHIFTING SLOW DUE TO HEAVY
LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 5 74 54.5 - -
RAINFALL
Sub Total - 0.00 5.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 594 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 80 297 0 - - RIG SHIFTED TO POINT
DRILLING IN PROGRESS; PROGRESS POOR DUE TO JAMMING TENDENCY IN
DY50CR/05 LHR -29 375 288.00 302.00 5.00 9.00 14.00 84 297 302 8/5/2020 -
HOLE

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 148 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 14.00 164.00
JSW Jajang
B.H. 08/20
KDR 750/03 10.80 12.60 0.80 1.00 1.80 35 223 53.35 8/20/2020 - HQ DRILLING; BHJ FM.
PBH-JJC/41/20
B.H. 05/20
DYNA 50CR/07 74.20 74.20 0.00 0.00 0.00 35 223 93.5 8/5/2020 - FISHING IN PROGRESS; TRYING TO RETRIVE CASING
PBH -JJC/03/20
B.H. 03/20
KDR 750/01 30.85 31.65 0.30 0.50 0.80 30 223 30.55 7/31/2020 - HQ DRILLING; BHQ FM;
PBH-JJC/20/20
B.H. 04/20
DYNA 50CR/01 45.75 48.65 1.05 1.85 2.90 75 223 48.65 8/2/2020 - HQ DRILLING IN BHJ; 100% W/LOOS IN HOLE
PBH-JJC/14/20
B.H. 07/20
Dyna 50H/01 45.10 45.40 0.00 0.30 0.30 20 223 45.4 8/18/2020 - RIG B/D IN 1ST SHIFT; HQ DRILLING IN 2ND SHIFT; BHJ FM.
PBH- JJC/76/20
B.H. 06/20
Dyna 50CR/08 23.20 23.95 0.35 0.45 0.80 85 139 23.95 8/10/2020 - HQ DRILLING IN BHJ
PBH-JJC/80/20
Sub Total - 6.60 280.00
PICHRI
LY-44/01 P-24/MAPH04 425 0.00 0.00 0.00 0.00 0.00 297 255 - - LAND NEGOTIATION SUCCESSFUL; RIG FOUNDATION DONE
CDR-1000 P-14/MAPH02 850 464.50 464.50 0.00 0.00 0.00 297 464.5 8/4/2020 - GPL DONE FROM 325 M UPTO 464.50 M
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 24-08-20 24-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

HW LINER RIH; HQ DRILLING; PARTIAL W/LOSS IN HOLE; POOR PROGRESS


DI-08 P-16/MAPH03 650 269.25 296.45 16.80 10.40 27.20 150 371 296.45 8/11/2020 - DUE TO FRACTURED FM.; HQ COMPLETE P/O FOR HQ CASING PURPOSE

Sub Total - 27.20 150.00


GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-22/ 270° /
UCD 60-1 125 109.50 136.20 0.00 14.85 11.85 26.70 474 445.6 8/20/2020 DRILLING IN PROGRESS; ONE SHIFT WEEKLY OFF
-50°
UCD 60-2 KMA-21/ +20°/N400/90°85 0.00 0.00 0.00 0.00 0.00 0.00 565 540.65 WEEKLY OFF
Sub Total - 26.70 0.00
AGUCHA UG
DSP 14
UDD-330 SBH No.- 148.00 148.00 0.00 0.00 0.00 0 0 - - WEEKLY OFF
Reaming'
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm'
224.75 237.15 6.00 6.40 12.40 0 97.4 6/22/2020 - MDD IN PROGRESS
Sub Total - 12.40 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1103.40 1103.40 0.00 0.00 0 204.6 6/19/2020 - B/D DUE TO MAIN WINCH PROBLEM
Q)'
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 24-08-20 24-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 200.00 68 7/23/2020 - WEEKLY OFF

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0.00 7 7/17/2020 - WEEKLY OFF
Borehole

Krishna rig
BH No. 01 6.00 6.00 0.00 0.00 40.00 6 8/18/2020 - WEEKLY OFF
Jamadoba

Sub Total - 0.00 240.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1230.55 1240.40 9.85 0.00 9.85 105 75.4 1/22/2020 - NQ DRILLING IN PROGRESS
Sub Total - 9.85 105.00
DATE: 18-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 18-08-20 18-08-20 ment Closure
(m) (m)
KABITIRTHA
DICD100H/1 0.00 0.00 0.00 0.00 0.00 145 211.40 - - DRILL RIG STANDBY AT CAMP

KDR 750(02) MRKB 91/SP-4(C) 660 642.30 658.00 15.70 0.00 15.70 131 348 588.40 7/30/2020 8/18/2020 BH CLOSED; PROJECT COMPLETED; ALL RODS P/O AND DISMANTLED

DY CRFM 50 0.00 0.00 0.00 0.00 0.00 151 235.45 - - ALL HQ RODS AND EMPTY CORE BOXES SHIFTED TO BASE CAMP
Sub Total - 15.70 131.00
BADAM
Dy-120/02 MABD-33/P-07 740 406 428 10.00 12.00 22.00 170 255 163.15 1/17/2019 - HQ DRILLING; SANDSTONE, SHALE TO FRACTURED SHALE FM.

LY-44/01 MABD-92 /P-81 770 734 754 12.00 8.00 20.00 115 87 261.80 NQ DRILLING; SANDSTONE AND SHALE TO FRACTURED SHALE FM.
7/6/2020 -
LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - RIG SHIFTED FROM SUKULKHAPIA CAMP TO DIL CAMP
Dy 100H/03 0 0 0 0.00 0.00 0.00 210 0.00 - - MACHINE STANDBY AT CAMP
Sub Total - 42.00 285.00
KURMITAR
REPAIRING COMPLETED AND READY TO SHIFT; NO APPROACHABLE ROADS;
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 29 0 - - INFORMED OMC OFFICIALS AND SOUGHT HELP; INCESSANT RAINFALL FOR
LAST 5 DAYS SO ROAD MAKING NOT POSSIBLE
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 58 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
DRY DRILLING CONTINUES; CORE BOXES SHIFTED FROM DRILLING SITE TO
LY-38/01 KIOM/72/47 9.50 18.00 8.50 0.00 8.50 15 58 48 8/14/2020 -
MINES
Sub Total - 8.50 15.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 465 0.00 - - AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 232 0 - - RIG REPAIRED; WAITING FOR HYD. OIL
DRILLING; 228 M NQ HOISTED AS INNER TUBE JAMMED IN BARREL AND
DY50CR/05 LHR -29 375 204.00 228.00 12.00 12.00 24.00 101 232 228 8/5/2020 -
BOULDER JAMMED AT BIT MOUTH

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 116 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 24.00 101.00
JSW Jajang
KDR 750/03 B.H. 01/20 69.00 69.00 0.00 0.00 0.00 5 174 40.75 7/25/2020 8/16/2020 WIATING FOR NEXT POINT
DYNA 50CR/07 B.H. 05/20 71.20 72.30 1.00 0.10 1.10 45 174 91.6 8/5/2020 - HQ DRILLING; BHJ FM; 100%W/LOSS IN HOLE
KDR 750/01 B.H. 03/20 25.80 26.20 0.30 0.10 0.40 35 174 25.1 7/31/2020 - HQ DRILLING; BHQ FM;
DYNA 50CR/01 B.H. 04/20 35.50 37.00 1.40 0.10 1.50 65 174 37 8/2/2020 - HQ DRILLING IN BHQ; 100% W/LOOS IN HOLE
Dyna 50H/01 B.H. 07/20 0.00 2.00 2.00 0.00 2.00 40 174 2 8/18/2020 - HQ DRILLING IN PROGRESS
Dyna 50CR/08 B.H. 06/20 19.00 20.30 0.50 0.80 1.30 100 96 20.3 8/10/2020 - HQ DRILLING IN BHJ
Sub Total - 6.30 290.00
PICHRI
LY-44/01 P-6 260 255.00 255.00 0.00 0.00 0.00 232 255 8/3/2020 - WAITING FOR CMPDI GEOLOGIST'S DECISION TO CLOSE HOLE
CDR-1000 P-14 850 338.50 363.50 10.50 14.50 25.00 160 232 363.5 8/4/2020 - NQ RIH COMPLETE; DRILLING; HARD FM.
DI-08 P-16 650 142.95 180.65 23.20 14.50 37.70 150 290 180.65 8/11/2020 - DRILLING; 100% W/LOSS; POOR PROGRESS DUE TO FRACTURED FM.
Sub Total - 62.70 310.00
GSI MAHUDA
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 18-08-20 18-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-18/ 270° / DRILLING IN PROGRESS; 1 TIME H/L; INNER TUBE, WATER SWIVEL,
UCD 60-1 125 74.05 102.70 0.00 14.40 14.25 28.65 361 289.8 8/13/2020
-34° ROTATION HEAD GREASING

UCD 60-2 KMA-20/+8°/N400 85 24.20 39.45 0.00 6.05 9.20 15.25 452 403.65 8/17/2020 DRILLING IN PROGRESS; ALL MANPOWER WORKING IN SURFACE CORE SHED
Sub Total - 28.65 0.00
AGUCHA UG
DSP 14
12.5" DRILLING SUCCESSFULLY COMPLETE TO BOTTOM; 10 NOS. CASING
UDD-330 SBH No.- 148.00 148.00 0.00 0.00 0.00 0 0 - -
SHIFTED FROM SURFACE TO UG
Reaming'
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- P/O HQ ROD AND SURVEY DONE; NQ LOWERED AND 6 M DRILLING DONE;
DIMP-175 76.5 mm'
442.10 442.10 0.00 0.00 0.00 0 54.25 6/22/2020 -
NQ P/O AND MOTOR LOWERED UPTO BOTTOM
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1103.40 1103.40 0.00 0.00 0 204.6 6/19/2020 - B/D DUE TO MAIN WINCH PROBLEM
Q)'
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 18-08-20 18-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 200.00 68 7/23/2020 - 29 M 12" REAMING DONE; V - CUTTING WORK UNDER PROGRESS

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0.00 7 7/17/2020 - MAN POWER TRANSFERRED TO MALKERA CORE DRILLING PROJECT
Borehole

Krishna rig 12" DRILLING IN PROGRESS; RIG LEVELLING DONE AND CHECKED BY TSL
Jamadoba BH No. 01 0.00 4.00 4.00 0.00 40.00 4 8/18/2020 - SURVEYOR

Sub Total - 0.00 240.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1215.00 1226.20 11.20 0.00 11.20 168 61.2 1/22/2020 - NQ DRILLING; PROGRESS HAMPERED DUE TO VERY HEAVY RAINFALL
Sub Total - 11.20 168.00
DATE: 17-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 17-08-20 17-08-20 ment Closure
(m) (m)
KABITIRTHA
DICD100H/1 0.00 0.00 0.00 0.00 0.00 137 211.40 - - DRILL RIG STANDBY AT CAMP

KDR 750(02) MRKB 91/SP-4(C) 660 617.30 642.30 14.00 11.00 25.00 151 329 572.70 7/30/2020 - NQ DRILLING; FRACTURED COAL FM.

LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - - RIG AND MATERIAL LOADED ON TRUCK;
DY CRFM 50 0.00 0.00 0.00 0.00 0.00 143 235.45 7/16/2020 8/13/2020 ALL NQ RODS SHIFTED TO BASE CAMP
Sub Total - 25.00 151.00
BADAM
Redrill &
Dy-120/02 MABD-33/P-07 740 391.75 406 0.00 14.25 14.25 161 195 0.00 1/17/2019 SHIFTED FROM HARLI CAMP TO MABD33/P07A; HQ DRILLING IN PROGRESS
Prog

LY-44/01 MABD-92 /P-81 700 712 734 12.00 10.00 22.00 130 82 241.80 7/6/2020 - NQ DRILLING; SANDSTONE AND SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy 100H/03 0 0 0 0.00 0.00 0.00 46 244 141.15 - - RIG B/D; RIG SHIFTED FROM POINT TO SUKULKHAPIA CAMP
Sub Total - 36.25 337.00
KURMITAR
REPAIRING COMPLETED AND READY TO SHIFT; NO APPROACHABLE ROADS;
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 27 0 - -
INFORMED OMC OFFICIALS AND SOUGHT HELP
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 55 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
DRY DRILLING CONTINUES; CORE BOXES SHIFTED FROM DRILLING SITE TO
LY-38/01 KIOM/72/47 4.00 9.50 5.50 0.00 5.50 15 55 39.5 8/14/2020 - MINES
Sub Total - 5.50 15.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED

Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 439 0.00 - - RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 219 0 - - RIG REPAIRING IN PROGRESS
WATER SWIVEL REPAIRED; DRILLING; DUE TO RIVER BED WATER ENTERED
DY50CR/05 LHR -29 375 192.00 204.00 6.00 6.00 12.00 55 219 204 8/5/2020 - HOLE; H/L 20 PAIR RODS FOR BIT CHANGING

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 110 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 12.00 55.00
JSW Jajang
KDR 750/03 B.H. 01/20 69.00 69.00 0.00 0.00 0.00 10 165 40.75 7/25/2020 8/16/2020 BH CLOSED; ALL CASING AND DRILL STRING HOISTED
DYNA 50CR/07 B.H. 05/20 69.30 71.20 1.20 0.70 1.90 45 165 90.5 8/5/2020 - HQ DRILLING; BHJ FM; 100%W/LOSS IN HOLE
KDR 750/01 B.H. 03/20 24.90 25.80 0.30 0.60 0.90 30 165 24.7 7/31/2020 - HQ DRILLING; BHQ FM;
DYNA 50CR/01 B.H. 04/20 34.30 35.50 0.35 0.85 1.20 60 165 35.5 8/2/2020 - HQ DRILLING IN BHQ; 100% W/LOOS IN HOLE
Dyna 50H/01 0.00 0.00 0.00 0.00 0.00 165 0 - - SHIFTED TO NEW BH POINT; RIG B/D

Dyna 50CR/08 B.H. 06/20 18.50 19.00 0.50 0.00 0.50 30 87 19 8/10/2020 - HQ DRILLING IN BHJ; NO WATER IN PIT SO NO PROGRESS IN 2ND SHIFT
Sub Total - 4.50 175.00
PICHRI

LY-44/01 P-6 260 244.50 255.00 10.50 0.00 10.50 20 219 255 8/3/2020 - NQ DRILLING; TARGET DEPTH ACHIEVED; WAITING FOR CMPDI DECISION

CDR-1000 P-14 850 325.00 338.50 0.00 13.50 13.50 115 219 338.5 8/4/2020 - NQ RIH COMPLETE; DRILLING; HARD FM.
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 17-08-20 17-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
DI-08 P-16 650 99.45 142.95 23.20 20.30 43.50 80 274 142.95 8/11/2020 - DRILLING; 100% W/LOSS; POOR PROGRESS DUE TO FRACTURED FM.
Sub Total - 67.50 215.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD

UCD 60-1 KMA-18/ 270° / 125 42.30 74.05 0.00 16.90 14.85 31.75 339 261.15 8/13/2020 - DRILLING IN PROGRESS
-34°
BH CLOSED; SURVEY DONE; ALL RODS HOISTED & SUPPORT DISMANTLED;
UCD 60-2 KMA-19/ 0°/N400/90° 85 79.65 81.50 0.00 1.85 0.00 1.85 429 388.4 8/14/2020 8/17/2020
NEW POINT SET; DRILLING
UCD 60-2 KMA-20/+8°/N400 85 0.00 24.20 0.00 4.05 20.15 8/17/2020
Sub Total - 31.75 0.00
AGUCHA UG
DSP 14
12.5" DRILLING; B SHIFT: WAIT FOR DIESEL; NO PROGRESS AS DIESEL
UDD-330 SBH No.- 148.00 148.00 0.00 0.00 0.00 0 0 7/21/2020 -
BROWSER NOT ARRIVED; H/L, BIT AND HAMMER CHECKED
Reaming'
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm'
442.10 442.10 0.00 0.00 0.00 0 54.25 6/22/2020 - HOLE WASHED FROM 180 M TO 194 M; WOC
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1103.40 1103.40 0.00 0.00 0 204.6 6/19/2020 - B/D DUE TO MAIN WINCH PROBLEM
Q)'
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 17-08-20 17-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
TOP DRIVE ROPE PULLEY SHAFT BROKEN; V- CUTTING IN PROGRESS; WORK
Sparr Rig BH No. 01 192.00 0.00 0.00 0.00 0.00 0.00 68 7/23/2020 - OVER RIG BEING SHIFTED FROM SIJUA COLLIERY TO BHELATAND NEW SAND
BUNKER

LY-38
Upward BH No. 01 43.00 0.00 0.00 0.00 0.00 0.00 7 7/17/2020 - MAN POWER TRANSFERRED TO MALKERA CORE DRILLING PROJECT
Borehole

Krishna rig
Jamadoba BH No. 01 0.00 0.00 0.00 0.00 10.00 0 RIG SET AT BH POINT

Sub Total - 0.00 10.00


NGRI KOYNA
BARREL AND STRING CLEANED AND 192 PAIRS NQ WITH GAUGING
DYNA 350 KBH-10-R 1500 1215.00 1215.00 0.00 0.00 0.00 140 50 1/22/2020 -
LOWERED; WORK HAMPERED DUE TO VERY HEAVY RAINFALL
Sub Total - 0.00 140.00
DATE: 11-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 11-08-20 11-08-20 ment Closure
(m) (m)
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 823.00 823.00 0.00 0.00 0.00 36 89 211.40 7/8/2020 - BH CLOSED; GPL COMPLETE; EMPTY CORE BOXES SHIFTED TO CAMP

KDR 750(02) MRKB 91/SP-4(C) 660 465.00 504.15 20.45 18.70 39.15 172 213 434.55 7/30/2020 - NQ DRILLING; SHALE

LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - - RIG STANDBY AT BASE CAMP
MRKB 90 (SP08) NQ DRILLING; SHALE AND COAL FM.; COMPLETE ROD P/O AS CORE DROPPED
DY CRFM 50 660 594.95 610.65 6.70 9.00 15.70 130 92 201.10 7/16/2020 -
(C) IN BARREL
Sub Total - 54.85 338.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 172 124 0.00 1/17/2019 Redrill HQ REDRILLING; SHEAR ZONE AND SANDSTONE FM.
RIG SHIFTED FROM SUKULKHAPIA CAMP TO RD20 SITE CAMP WITH GPS,
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - -
PUMP AND DG SET

LY-44/01 MABD-92 /P-81 400 613 624 6.00 5.00 11.00 90 53 131.80 7/6/2020 - NQ DRILLING; SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


NQ DRILLING; BH WASHED; SANDSTONE FM.; TARGET DEPTH ACHIEVED;
Dy-120/02 MABD-44/P-72 850 827.75 841.4 7.00 6.65 13.65 220 160 122.40 4/25/2019 -
DRILLING STOPPED
Sub Total - 24.65 482.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 18 0 - - REPAIRING COMPLETED AND READY TO SHIFT
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 35 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
LY-38/01 KIOM/71/48 14.00 14.00 0.00 0.00 0.00 35 30 8/8/2020 8/11/2020 BH CLOSED; CORE BOXES SHIFTED TO MAIN CAMP
Sub Total - 0.00 0.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 284 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 142 0 - - RIG REPAIRING IN PROGRESS
HQ LOWERED WITH SHOE BIT; REAMING; NQ ROD PAIR MADE; NQ DRILLING;
DY50CR/05 LHR -29 375 102.00 132.00 15.00 15.00 30.00 133 142 132 8/5/2020 -
PROGRESS HAMPERED DUE TO HEAVY RAIN

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 71 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 30.00 133.00
JSW Jajang
HQ DRILLING; FRACTURED FM.; WORK STOPPED IN 2ND SHIFT DUE TO
KDR 750/03 B.H. 01/20 61.80 61.80 0.00 0.00 0.00 106 33.55 7/25/2020 -
UNAVAILABILITY OF WATER IN PIT
DYNA 50CR/07 B.H. 05/20 42.90 44.80 0.00 1.90 1.90 25 106 64.1 8/5/2020 - HQ DRILLING IN HARD MASSIVE ORE
KDR 750/01 B.H. 03/20 21.05 21.05 0.00 0.00 0.00 106 19.95 7/31/2020 - NO WORK DONE AS WATER SWIVEL TURNED OFF

DYNA 50CR/01 B.H. 04/20 29.75 29.75 0.00 0.00 0.00 106 29.75 8/2/2020 - HQ DRILLING IN BHQ; NO WATER IN PIT SO NO WORK DONE IN 2ND SHIFT

Dyna 50H/01 0.00 0.00 0.00 0.00 0.00 106 0 - - SHIFTING TO NEW BH POINT
Dyna 50CR/08 B.H. 06/20 1.50 6.00 4.50 0.00 4.50 35 35 6 8/10/2020 - HQ DRILLING IN BHQ
Sub Total - 6.40 60.00
PICHRI
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 11-08-20 11-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

NQ DRILLING; SANDSTONE AND SHALE FM.; WORK STOPPED DUE TO LOCAL


LY-44/01 P-6 260 187.20 202.00 11.80 3.00 14.80 40 202 187.2 8/3/2020 - ISSUES
CDR-1000 P-14 850 244.50 282.00 18.50 19.00 37.50 170 282 244.5 8/4/2020 - DRILLING; PARTIAL W/LOSS; SANDSTONE AND SHALE FM.
SITE PREPARATION AND RIG SETTING COMPLETE; DRILLING; 6M HW LINER
DI-08 P-16 650 0.00 12.85 12.85 0.00 12.85 45 12.85 0 8/12/2020 -
LOWERED
Sub Total - 65.15 255.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-16/ 270° / DRILLING; H/L FOR BIT CHANGE; HARD FM.; BIT CHOPPING AND LOWERING;
UCD 60-1 +10° 125 92.70 106.75 0.00 6.50 7.55 14.05 226 176.55 8/7/2020 - ALL RODS HOISTING
LEFT HAND ROD, GEAR BOX SHIFTED FROM SURFACE TO N400MRL; H/L FOR
UCD 60-2 KMA-17/ 90°/+40° 85 49.60 64.75 0.00 9.20 5.95 15.15 271 256.9 8/5/2020 - BIT CHOPPING; HARD FM.
Sub Total - 14.05 0.00
AGUCHA UG
DSP 14 WAITING TO SHIFT ACCESSORIES BUT LOADER NOT AVAILABLE; MACHINE
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - SHIFTED TO DSP-14; 1" CONNECTION FOR DRILLING WATER NEEDED;
Reaming WAITING FOR MACHINE AND COMPRESSOR SHIFTING PLAN
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- MOTOR P/O DUE TO HARD FM.; NQ LOWERED WITH FLEXIBLE BARREL AND
DIMP-175 76.5 mm'
441.05 441.25 0.20 0.00 0.20 0 53.2 6/22/2020 -
MOTOR PATH REAMING FOM 307 M TO 424 M
Sub Total - 0.20 0.00
TDMA ZAWAR
DD20ZWE272(N DRILLING IN PROGRESS; PROGRESS POOR AS TRIPPING DUE TO STUCK TUBE
KDR-1200/02 950 1080.00 1089.00 2.90 6.10 9 200 190.2 6/19/2020 -
Q) IN BARREL
Sub Total - 9.00 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 11-08-20 11-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD

HYD. HOSE PIPE BROKEN 2 TIMES; HOLE PACKED WITH CUTTING; HOLE
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 0 68 7/23/2020 - NEEDS TO BE WASHED BY SMALL RR BIT THEN REAMING JOB WILL START

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - NO ACTIVITY DUE TO WATER LOGGING AT SITE
Borehole

Krishna rig
Jamadoba BH No. 01 0.00 0.00 0.00 0.00 0.00 0 WAITING FOR REQUIRED MATERIALS

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1193.00 1193.00 0.00 0.00 0.00 124 28.1 1/22/2020 - 125 PAIR NQ RODS WITH NQ BARREL AND BIT LOWERED
Sub Total - 0.00 124.00
DATE: 11-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 11-08-20 11-08-20 ment Closure
(m) (m)
KABITIRTHA
BH CLOSED; CENTRIFUGAL W/S PUMP AND COAL CORE BOXES SHIFTED TO
DICD100H/1 MRKB 89/SP-7(C) 820 823.00 823.00 0.00 0.00 0.00 36 89 211.40 7/8/2020 - CAMP; 40 RODS SHIFTED TO KDR RIG AND 20 RODS SHIFTED TO DY CRFM
RIG

KDR 750(02) MRKB 91/SP-4(C) 660 465.00 504.15 20.45 18.70 39.15 172 213 434.55 7/30/2020 - NQ DRILLING; SHALE AND COAL FM.

LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - - RIG STANDBY AT BASE CAMP
MRKB 90 (SP08) 594.95 M ROD R/I AFTER BIT CHANGING; BH WASHED; DRILLING; SHALE AND
DY CRFM 50 (C) 660 594.95 610.65 6.70 9.00 15.70 130 92 201.10 7/16/2020 - FRACTURED COAL FM.
Sub Total - 54.85 338.00
BADAM
HQ REDRILLING; SHEAR ZONE AND SANDSTONE FM., FRACTURED SHALE; BH
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 172 124 0.00 1/17/2019 Redrill
WASHED
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 613 624 6.00 5.00 11.00 90 53 131.80 7/6/2020 - NQ DRILLING; SANDSTONE AND SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy-120/02 MABD-44/P-72 850 827.75 841.4 7.00 6.65 13.65 220 160 122.40 4/25/2019 - NQ DRILLING; FRACTURED COAL, SHALE AND SANDSTONE FM.
Sub Total - 24.65 482.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 18 0 - - REPAIRING COMPLETED AND READY TO SHIFT
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 35 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
LY-38/01 KIOM/71/48 14.00 14.00 0.00 0.00 0.00 35 30 8/8/2020 8/11/2020 BH CLOSED; CORE BOXES SHIFTED TO MAIN CAMP
Sub Total - 0.00 0.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 284 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 142 0 - - RIG REPAIRING IN PROGRESS
DY50CR/05 LHR -29 375 102.00 132.00 15.00 15.00 30.00 133 142 132 8/5/2020 - DRILLING IN PROGRESS

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 71 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 30.00 133.00
JSW Jajang
KDR 750/03 B.H. 01/20 61.80 61.80 0.00 0.00 0.00 106 33.55 7/25/2020 - NO WORK DONE DUE TO UNAVAILABILITY OF BIT
HQ DRILLING IN 2ND SHIFT ONLY; WORK STOPPED DUE TO UNAVILABILTY OF
DYNA 50CR/07 B.H. 05/20 42.90 44.80 0.00 1.90 1.90 25 106 64.1 8/5/2020 -
BIT IN 1ST SHIFT
KDR 750/01 B.H. 03/20 21.05 21.05 0.00 0.00 0.00 106 19.95 7/31/2020 - NO WORK DONE DUE TO UNAVAILABILITY OF BIT
DYNA 50CR/01 B.H. 04/20 29.75 29.75 0.00 0.00 0.00 106 29.75 8/2/2020 - NO WORK DONE DUE TO UNAVAILABILITY OF BIT
Dyna 50H/01 0.00 0.00 0.00 0.00 0.00 106 0 - - RIG B/D ( SELF STARTER USED IN DY:50CR/07)
Dyna 50CR/08 B.H. 06/20 1.50 6.00 4.50 0.00 4.50 35 35 6 8/10/2020 - HQ DRILLING; NO DRILLING IN 2ND SHIFT DUE TO LIGHTING PROBLEM
Sub Total - 6.40 60.00
PICHRI
NQ DRILLING; SANDSTONE FM., SHALE; CORE SLIPPED IN BARREL; P/O AND
LY-44/01 P-6 260 187.20 202.00 11.80 3.00 14.80 40 202 187.2 8/3/2020 -
RIH; DRILLING RECOMMENCED
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 11-08-20 11-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
CDR-1000 P-14 850 244.50 282.00 18.50 19.00 37.50 170 282 244.5 8/4/2020 - DRILLING; PARTIAL W/LOSS; SANDSTONE AND SHALE FM.
SITE PREPARATION AND RIG SETTING COMPLETE; DRILLING; 6M HW LINER
DI-08 P-16 650 0.00 12.85 12.85 0.00 12.85 45 12.85 0 8/12/2020 -
LOWERED
Sub Total - 65.15 255.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-16/ 270° / DRILLING; H/L FOR BIT CHANGE; HARD FM.; BIT CHOPPING AND LOWERING;
UCD 60-1 +10° 125 92.70 106.75 0.00 6.50 7.55 14.05 226 176.55 8/7/2020 - ALL RODS HOISTING
LEFT HAND ROD, GEAR BOX SHIFTED FROM SURFACE TO N400MRL; H/L FOR
UCD 60-2 KMA-17/ 90°/+40° 85 49.60 64.75 0.00 9.20 5.95 15.15 271 256.9 8/5/2020 - BIT CHOPPING; HARD FM.
Sub Total - 14.05 0.00
AGUCHA UG
DSP 14 WAITING TO SHIFT ACCESSORIES BUT LOADER NOT AVAILABLE; MACHINE
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - SHIFTED TO DSP-14; 1" CONNECTION FOR DRILLING WATER NEEDED;
Reaming WAITING FOR MACHINE AND COMPRESSOR SHIFTING PLAN
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- MOTOR P/O DUE TO HARD FM.; NQ LOWERED WITH FLEXIBLE BARREL AND
DIMP-175 76.5 mm'
441.05 441.25 0.20 0.00 0.20 0 53.2 6/22/2020 -
MOTOR PATH REAMING FOM 307 M TO 424 M
Sub Total - 0.20 0.00
TDMA ZAWAR
DD20ZWE272(N DRILLING IN PROGRESS; PROGRESS POOR AS TRIPPING DUE TO STUCK TUBE
KDR-1200/02 950 1080.00 1089.00 2.90 6.10 9 200 190.2 6/19/2020 -
Q) IN BARREL
Sub Total - 9.00 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 11-08-20 11-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD

HYD. HOSE PIPE BROKEN 2 TIMES; HOLE PACKED WITH CUTTING; HOLE
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 0 68 7/23/2020 - NEEDS TO BE WASHED BY SMALL RR BIT THEN REAMING JOB WILL START

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - NO ACTIVITY DUE TO WATER LOGGING AT SITE
Borehole

Krishna rig
Jamadoba BH No. 01 0.00 0.00 0.00 0.00 0.00 0 WAITING FOR REQUIRED MATERIALS

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1193.00 1193.00 0.00 0.00 0.00 124 28.1 1/22/2020 - 125 PAIR NQ RODS WITH NQ BARREL AND BIT LOWERED
Sub Total - 0.00 124.00
DATE: 10-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 10-08-20 10-08-20 ment Closure
(m) (m)
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 801.60 823.00 16.70 4.70 21.40 156 81 211.40 7/8/2020 - DRILLING; DRILLING STOPPED BY GEOLOGIST; BH WASHED

KDR 750(02) MRKB 91/SP-4(C) 660 431.70 465.00 15.90 17.40 33.30 144 194 395.40 7/30/2020 - NQ DRILLING; SHALE AND SANDY SHALE FM.

RIG STANDBY AT BASE CAMP; WAITING FOR TRANSPORTING VEHICLE AND


LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - - HYDRA
MRKB 90 (SP08) TRIED TO EXTEND BH BUT UNSUCCESSFUL DUE TO HIGH TORQUE; P/O
DY CRFM 50 (C) 660 583.45 594.95 11.50 0.00 11.50 75 84 185.40 7/16/2020 - 594.95 M ROD DUE TO BIT DAMAGE; WAITING FOR DECISION
Sub Total - 66.20 375.00
BADAM
HQ REDRILLING; JAMMING TENDENCY; SHEAR ZONE AND SANDSTONE FM.;
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 138 113 0.00 1/17/2019 Redrill
BH WASHED
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 588 613 12.00 13.00 25.00 140 48 120.80 7/6/2020 - NQ DRILLING; SANDSTONE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy-120/02 MABD-44/P-72 850 816.4 827.75 7.00 4.35 11.35 221 145 108.75 4/25/2019 - NQ DRILLING; FRACTURED COAL FM.
Sub Total - 36.35 499.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 16 0 - - RIG UNDER REPAIRING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 32 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
LY-38/01 KIOM/71/48 7.50 14.00 6.50 0.00 6.50 10 32 30 8/8/2020 - DRY DRILLING CONTINUES
Sub Total - 6.50 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 258 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 129 0 - - RIG B/D
MOBIL FILTER, DIESEL FILTER AND COOLANT FILTER CHANGED; MOBIL TOP
DY50CR/05 LHR -29 375 90.00 102.00 9.00 3.00 12.00 48 129 102 8/5/2020 -
UP 15 L; DRILLING

LY-44 GLT-07 400 266.50 266.50 0.00 0.00 0.00 65 75.3 7/6/2020 - WORK STOPPED AS GALOTE SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 12.00 48.00
JSW Jajang
HQ DRILLING IN BHJ; DRILLING STOPPED DUE TO WATER SHORTAGE AS
KDR 750/03 B.H. 01/20 61.00 61.80 0.80 0.00 0.80 25 97 33.55 7/25/2020 -
TANKER B/D
HQ DRILLING IN PROGRESS; DRILLING STOPPED DUE TO WATER SHORTAGE
DYNA 50CR/07 B.H. 05/20 34.30 42.90 4.90 3.70 8.60 60 97 62.2 8/5/2020 -
AS TANKER B/D
KDR 750/01 B.H. 03/20 20.80 21.05 0.25 0.00 0.25 20 97 19.95 7/31/2020 - HQ DRILLING; BHJ FM.; NO WORK IN 2ND SHIFT AS NO WATER IN PIT
DYNA 50CR/01 B.H. 04/20 29.40 29.75 0.35 0.00 0.35 30 97 29.75 8/2/2020 - HQ DRILLING; BHQ FM.; SHORTAGE OF WATER DUE TO TANKER B/D
Dyna 50H/01 0.00 0.00 0.00 0.00 0.00 97 0 - - RIG B/D ( SELF STARTER USED IN DY:50CR/07)

Dyna 50CR/08 B.H. 06/20 0.00 1.50 1.50 0.00 1.50 25 26 1.5 8/10/2020 - HQ DRILLING; NO DRILLING IN 2ND SHIFT DUE TO SHORTAGE OF WATER
Sub Total - 11.50 160.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 10-08-20 10-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
PICHRI
LY-44/01 P-6 260 160.00 187.20 15.00 12.20 27.20 45 129 187.2 8/3/2020 - NQ DRILLING; SANDSTONE FM., COAL AND SHALE
CDR-1000 P-14 850 207.00 244.50 19.50 18.00 37.50 175 129 244.5 8/4/2020 - DRILLING; PARTIAL W/LOSS; SANDSTONE FM.

DI-08 P-16 650 0.00 0.00 0.00 0.00 0.00 161 0 - - NEGOTIATION WITH LAND OWNER SUCCESSFUL; ARRANGEMENT FOR
FOUNDATION WORK; JACK AND MAST UP
Sub Total - 64.70 220.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-16/ 270° /
UCD 60-1 125 69.95 92.70 0.00 12.70 10.05 22.75 203 162.55 8/7/2020 - DRILLING; 3 TIMES H/L FOR BIT CHOPPING; HARD FM.; ALL RODS HOISTING
+10°
UCD 60-2 KMA-17/ 90°/+40° 85 34.60 49.60 0.00 0.00 15.00 15.00 248 241.75 8/5/2020 - 2 TIME H/L FOR BIT CHOPPING
Sub Total - 22.75 0.00
AGUCHA UG
DSP 14
PUMP SHIFTED; SITE CLEANING DONE; 1" CONNECTION FOR DRILLING
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - WATER NEEDED; WAITING FOR MACHINE AND COMPRESSOR SHIFTING PLAN
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm'
437.10 441.05 1.65 2.30 3.95 0 53.2 6/22/2020 - MOTOR LOWERED UPTO BOTTOM AND MDD STARTED
Sub Total - 3.95 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 1200 1055.40 1080.00 10.20 14.40 24.6 400 181.2 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 24.60 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 10-08-20 10-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
HOLE PACKED WITH CUTTING; HOLE NEEDS TO BE WASHED BY SMALL RR BIT
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 0 68 7/23/2020 - THEN REAMING JOB WILL START

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - NO ACTIVITY DUE TO WATER LOGGING AT SITE
Borehole

Krishna rig
Jamadoba BH No. 01 0.00 0.00 0.00 0.00 0.00 0 WAITING FOR REQUIRED MATERIALS

Sub Total - 0.00 0.00


NGRI KOYNA
CASING REACHED BOTTOM AT 1193 M; 13 M CAVING FROM 1144 M TO
DYNA 350 KBH-10-R 1500 1193.00 1193.00 0.00 0.00 0.00 110 28.1 1/22/2020 -
1157 M OBSERVED; BH WASHED
Sub Total - 0.00 110.00
DATE: 09-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 09-08-20 09-08-20 ment Closure
(m) (m)
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 793.30 801.60 0.00 8.30 8.30 60 73 190.00 7/8/2020 - RIG UNDER REPAIR; DRILLING; SHALE AND COAL FM.; 72 M RODS P/O

KDR 750(02) MRKB 91/SP-4(C) 660 406.20 431.70 13.20 12.30 25.50 93 174 362.10 7/30/2020 - NQ DRILLING; SHALE AND SANDSTONE FM.; 72 M ROD P/O

RIG STANDBY AT BASE CAMP; WAITING FOR TRANSPORTING VEHICLE AND


LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - - HYDRA
MRKB 90 (SP08)
DY CRFM 50 (C) 660 567.05 583.45 9.00 7.40 16.40 76 75 173.90 7/16/2020 - NQ DRILLING; SHALE AND COAL FM.; 72 M ROD P/O
Sub Total - 50.20 229.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 104 102 0.00 1/17/2019 Redrill HQ REDRILLING; FRACTURED SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 574.5 588 7.00 6.50 13.50 90 44 95.80 7/6/2020 - NQ DRILLING; COAL AND SANDSTONE AND SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

Dy-120/02 MABD-44/P-72 850 808.9 816.4 4.50 3.00 7.50 170 116 89.90 4/25/2019 - WIRELINE ROPE CHANGED; DRILLING; FRACTURED COAL FM., SHEAR ZONE
Sub Total - 21.00 364.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 15 0 - - RIG UNDER REPAIRING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 29 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
DRY DRILLING CONTINUES; CORE BOXES SHIFTED FROM DRILLING SITE TO
LY-38/01 KIOM/71/48 5.50 7.50 2.00 0.00 2.00 5 29 23.5 - - HILL TOP AREA
Sub Total - 2.00 5.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 232 0.00 - - AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 116 0 - - RIG B/D
DY50CR/05 LHR -29 375 79.00 90.00 0.00 11.00 11.00 124 116 90 8/5/2020 - HW LINER PLACED FROM27 M TO 72.50 M; DRILLING
DRILLING IN PROGRESS; 10 PAIR RODS HOISTED; WORK STOPPED AS GALOTE
LY-44 GLT-07 400 262.00 266.50 4.50 0.00 4.50 15 58 75.3 7/6/2020 - SITE SEALED BY H.P. GOVT DUE TO COVID ALERT
Sub Total - 15.50 139.00
JSW Jajang
KDR 750/03 B.H. 01/20 58.50 61.00 2.50 0.00 2.50 35 87 32.75 7/25/2020 - HQ DRILLING IN BHJ; DRILLING STOPPED DUE TO DRILL STRING JAM

DYNA 50CR/07 B.H. 05/20 28.00 34.30 5.90 0.40 6.30 55 87 53.6 8/5/2020 - HQ DRILLING IN PROGRESS; DRILLING STOPPED DUE TO WATER SHORTAGE

KDR 750/01 B.H. 03/20 19.10 20.80 0.90 0.80 1.70 45 87 19.7 7/31/2020 - HQ DRILLING; BHJ FM.
DYNA 50CR/01 B.H. 04/20 28.25 29.40 1.00 0.15 1.15 65 87 29.4 8/2/2020 - HQ DRILLING; BHJ FM.
Dyna 50H/01 0.00 0.00 0.00 0.00 0.00 87 0 - - RIG B/D ( SELF STARTER USED IN DY:50CR/07)
Dyna 50CR/08 0.00 0.00 0.00 0.00 0.00 17 0 - - SHIFTED TO NEW BH POINT
Sub Total - 11.65 200.00
PICHRI
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 09-08-20 09-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

HQ DRILLING; SANDSTONE FM.; P/O AND NQ R/I; NQ DRILLING; SANDSTONE


LY-44/01 P-6 260 146.00 160.00 4.80 9.20 14.00 40 116 160 8/3/2020 - FM., COAL AND SHALE
CDR-1000 P-14 850 177.00 207.00 15.00 15.00 30.00 105 116 207 8/4/2020 - DRILLING; PARTIAL W/LOSS; SANDSTONE FM.
DI-08 P-16 650 0.00 0.00 0.00 0.00 0.00 145 0 - - LAND OWNER'S OBJECTION TO DO WORK
Sub Total - 44.00 145.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-16/ 270° /
UCD 60-1 125 69.95 69.95 0.00 0.00 0.00 0.00 181 139.8 8/7/2020 - WEEKLY OFF AND NO GATE PASS FOR ONE SHIFT
+10°
UCD 60-2 KMA-17/ 90°/+40° 85 0.00 34.60 19.30 0.00 15.30 34.60 226 226.75 8/5/2020 - BACK SUPPORT DONE; 1 TIME H/L
Sub Total - 0.00 0.00
AGUCHA UG
DSP 14
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - WEEKLY OFF
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm'
437.10 437.10 0.00 0.00 0.00 0 49.25 6/22/2020 - WEEKLY OFF
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1049.00 1055.40 6.40 0.00 6.4 200 150.2 6/19/2020 - 6.40 M DRILLED; RIG B/D DUE TO HYD. HOSE DAMAGE
Q)
Sub Total - 6.40 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 09-08-20 09-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 0 68 7/23/2020 - WEEKLY OFF

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - WEEKLY OFF
Borehole

Krishna rig
BH No. 01 0.00 0.00 0.00 0.00 0.00 0 WEEKLY OFF
Jamadoba

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1193.00 1193.00 0.00 0.00 0.00 120 28.1 1/22/2020 - RIH HQ PIPES WITH SHOE BIT FOR CASING UPTO 1140 M
Sub Total - 0.00 120.00
DATE: 08-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 08-08-20 08-08-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 MACHINE AND MATERIALS STANDBY AT PATRATU CAMP
Sub Total - 0.00 30.00
KABITIRTHA
NQ DRILLING; FRACTURED COAL FM.; O WORK DONE IN 2ND SHIFT DUE TO
DICD100H/1 MRKB 89/SP-7(C) 820 779.80 793.30 13.50 0.00 13.50 72 65 181.70 7/8/2020 -
RIG B/D (SELF STARTER NOT WORKING PROPERLY)

KDR 750(02) MRKB 91/SP-4(C) 660 358.50 406.20 24.50 23.20 47.70 169 155 336.60 7/30/2020 - NQ DRILLING; SHALE AND SANDSTONE FM.

RIG STANDBY AT BASE CAMP; WAITING FOR TRANSPORTING VEHICLE AND


LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - -
HYDRA
MRKB 90 (SP08)
DY CRFM 50 660 535.25 567.05 18.30 13.50 31.80 115 67 157.50 7/16/2020 - NQ DRILLING; SHALE , SANDSTONE AND COAL FM.
(C)
Sub Total - 93.00 356.00
PICHRI
HQ DRILLING; SANDSTONE FM., COAL, SHALE; PROGRESS HAMPERED DUE
LY-44/01 P-6 260 120.50 146.00 12.00 13.50 25.50 45 103 146 8/3/2020 -
TO LOCAL ISSUES
DRILLING; PARTIAL W/LOSS; SANDSTONE FM.; PROGRESS HAMPERED DUE
CDR-1000 P-14 850 138.00 177.00 21.00 18.00 39.00 165 103 177 8/4/2020 - TO LOCAL ISSUES
DI-08 P-16 650 0.00 0.00 0.00 0.00 0.00 129 0 - - LAND OWNER'S OBJECTION TO DO WORK
Sub Total - 64.50 210.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 92 90 0.00 1/17/2019 Redrill HQ REDRILLING; AMC PUMP B/D; FRACTURED SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 559.5 574.5 8.00 7.00 15.00 95 39 82.30 7/6/2020 - NQ DRILLING; COAL AND SANDSTONE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


NQ DRILLING; SANDSTONE, SHALE AND FRACTURED COAL FM.; WIRELINE
Dy-120/02 MABD-44/P-72 850 795.75 808.9 9.00 4.15 13.15 229 116 89.90 4/25/2019 - ROPE BROKEN; 206 M NQ ROD H/L
Sub Total - 28.15 416.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 103 0 - - RIG B/D
DY50CR/05 LHR -29 375 61.00 79.00 13.00 5.00 18.00 66 103 79 8/5/2020 - DRILLING IN PROGRESS
LY-44 GLT-07 400 254.00 262.00 5.00 3.00 8.00 45 52 70.8 7/6/2020 - DRILLING IN PROGRESS
Sub Total - 26.00 111.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 13 0 - - RIG UNDER REPAIRING
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 26 0 - - AT LOADING POINT & SHORTAGE OF MANPOWER
LY-38/01 KIOM/71/48 0.00 5.50 5.50 0.00 5.50 10 26 21.5 7/31/2020 - DRY DRILLING CONTINUES
Sub Total - 5.50 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 206 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 08-08-20 08-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-16/ 270° / ALL RODS GREASED; H/L FOR BIT CHOPPING; DRILLING; HARD FM.; ALL RODS
UCD 60-1 125 30.15 69.95 21.25 8.70 9.85 39.80 181 139.8 8/7/2020 -
+10° HOISTING
UCD 60-2 KMA-15/+31°/N400 85 76.75 77.75 0.00 0.00 1.00 1.00 203 192.15 8/5/2020 - INNER TUBE RELEASED FROM BARREL; NEW ANGLE SET AT 40°
Sub Total - 39.80 0.00
AGUCHA UG
DSP 14 WITING FOR NEXT PLAN FOR REAMING; BOTH SITES UNDER PREPARATION;
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - DSP-14 - PUMP UNDER SHIFTING; NORTH 105 CV - WAITING FOR BOTTOM
Reaming DEVELOPMENT
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm
436.10 437.10 1.00 0.00 1.00 0 49.25 6/22/2020 - NQ REAMING; BH SURVEY DONE; DRILLING STARTED
Sub Total - 1.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 1023.00 1049.00 12.00 14.00 26 400 150.2 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 26.00 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 08-08-20 08-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 0 68 7/23/2020 - CLEANING WORK DONE ON UG

LY-38
Upward BH No. 01 43.00 43.00 0.00 0.00 0.00 0 7 7/17/2020 - HOISTING DONE
Borehole

Krishna rig
Jamadoba BH No. 01 0.00 0.00 0.00 0.00 0.00 0 SITE PREPARATION WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA

R/I UPTO BOTTOM BUT OBSERVED BH COLLAPSED UPTO 1144 M; TRIED TO


CLEAN WITH ROTATION AND CHOPPING BUT FAILED; DECISION MADE TO
DYNA 350 KBH-10-R 1500 1193.00 1193.00 0.00 0.00 0.00 107 28.1 1/22/2020 -
TRY WITH HQ ROD SHOE BIT WITH HQ CASING; P/O UPTO SURFACE;
REMOVED BARREL AND BIT; ENAGED ONE HQ PIPE WITH IMP. ROD SHOE BIT

Sub Total - 0.00 107.00


DATE: 06-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 06-08-20 06-08-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 MACHINE STANDBY AT PATRATU CAMP
Sub Total - 0.00 30.00
KABITIRTHA
WIRELINE ROPE SHIFTED FROM CAMP AND FITTED; DRILLING; SHALE FM.;
DICD100H/1 MRKB 89/SP-7(C) 820 732.90 757.20 12.00 12.30 24.30 202 48 145.60 7/8/2020 -
318 M ROD P/O AS WIRELINE ROPE DISMANTLED FROM JOINT

KDR 750(02) MRKB 91/SP-4(C) 660 269.30 312.70 22.90 20.50 43.40 150 116 243.10 7/30/2020 - NQ DRILLING; SHALE FM.

ALL MATERIALS SHIFTED TO BASE CAMP; GEAR BOX AND HOUSING FITTING
LY 44/01 0.00 0.00 0.00 0.00 0.00 0 0.00 - -
COMPLETE
MRKB 90 (SP08) NQ DRILLING; HARD SHALE FM; DRILLING NOT EXTENDED DUE TO DRILLING
DY CRFM 50 660 504.35 510.15 5.60 0.20 5.80 83 50 100.60 7/16/2020 -
(C) DIFFICULTY AND ENGINE TROUBLE
Sub Total - 73.50 435.00
PICHRI
LY-44/01 P-6 260 67.50 94.50 13.50 13.50 27.00 60 77 94.5 8/3/2020 - HQ DRILLING; SANDSTONE FM AND COAL
CDR-1000 P-14 850 65.00 101.50 19.00 17.50 36.50 170 77 101.5 8/4/2020 - DRILLING; 60% W/LOSS; SANDSTONE FM.
WORK HAMPERED DUE TO HEAVY RAIN (FARMING LAND); WAITING FOR
DI-08 P-16 650 0.00 0.00 0.00 0.00 0.00 97 0 - -
IRON PLATE
Sub Total - 63.50 230.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 173 68 0.00 1/17/2019 Redrill HQ REDRILLING; FRACTURED SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 535.5 546.5 6.00 5.00 11.00 90 29 54.30 7/6/2020 - NQ DRILLING; SHEAR ZONE, FRACTURED COAL FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy-120/02 MABD-44/P-72 850 773 783 4.20 5.80 10.00 170 87 64.00 4/25/2019 - NQ DRILLING; FRACTURED COAL FM.
Sub Total - 21.00 433.00
HAMIRPUR

RIG SHIFTING STARTED BUT THEN RIG B/D; REPAIRING UNSUCCESSFUL; HW


DY50CR/04 0.00 0.00 0.00 0.00 77 0 - - LINER AND HQ RODS SHIFTED FROM FARSI SITE TO LOHARKAR NALA SITE

6 M PX CASING AND 9 M HW LINER PLACED; DRILLING STARTED; 27 M HQ


DY50CR/05 LHR -29 375 3.00 27.00 9.00 15.00 24.00 90 77 27 8/5/2020 -
AD 18 M HW LINER REVIVED
FUEL PUMP INJECTOR REPAIRED; PROGRESS SUFFERED DUE TO FUEL PUMP
LY-44 GLT-07 400 226.50 235.50 0.00 9.00 9.00 20 39 44.3 7/6/2020 -
INJECTOR PROBLEM AND ENGINE HEATING
Sub Total - 33.00 110.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 0 - - RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 19 0 - - AT LOADING POINT
RIG BEING SHIFTED TO NEXT POINT; ROD AND OTHER ACCESSORIES SHIFTED
LY-38/01 KIOM/70/49 21.50 21.50 0.00 0.00 0.00 19 16 7/31/2020 -
AND SITE PREPARATION DONE.
Sub Total - 0.00 0.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 155 0.00 - - AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 06-08-20 06-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA11/ 270° /
UCD 60-1 125 104.45 122.95 0.00 6.15 12.35 18.50 135 69.85 7/28/2020 8/6/2020 H/L FOR BIT CHOPPING; HARD FM; BH CLOSED; ALL RODS HOISTED
+4°
3 M BARREL, MAST SUPPORT, TOOL BOX, CORE BOX SHIFTED FROM
UCD 60-2 KMA-15/+31°/N400 85 17.00 51.90 17.10 14.70 3.10 34.90 158 166.3 8/5/2020 -
SURFACE TO N400; H/L FOR 3 M BARREL SETTING; HARD FM.
Sub Total - 18.50 0.00
AGUCHA UG
DSP 14 COMPRESSOR SHIFTED TO SURFACE AND UNDER REPAIRING; DSP-14- PUMP
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - DIRECTION CHANGING IN PROGRESS
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm 413.25 426.65 6.45 7.00 13.45 0 38.7 6/22/2020 - MDD IN PROGRESS; HARD FM.
Sub Total - 13.45 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 Q) 950 982.50 996.00 13.50 0.00 13.5 400 97.2 6/19/2020 - DRILLING IN PROGRESS; TRIPPING DUE TO BIT CHANGE
Sub Total - 13.50 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 06-08-20 06-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 20 68 7/23/2020 - ROD HOISTING COMPLETED

LY-38
Upward BH No. 01 38.00 43.00 5.00 0.00 5.00 0 7 7/17/2020 - BH PUNCTURED
Borehole

Sub Total - 5.00 20.00


NGRI KOYNA

HQ DRILLING RESUMED WITH HIGH TORQUE AND JAMMING TENDENCY;


DYNA 350 KBH-10-R 1500 1185.80 1191.10 5.30 0.00 5.30 167 26.1 1/22/2020 - PROGRESS HAMPERED DUE TO VERY HEAVY RAIN AND STORMY WINDS; ONE
MORE BROKEN JOINT IN WIRELINE ROPE FOUND AND FIXED

Sub Total - 5.30 167.00


DATE: 05-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 05-08-20 05-08-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 MACINE STANDBY AT PATRATU CAMP
Sub Total - 0.00 30.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 701.80 732.90 13.50 17.60 31.10 170 40 121.30 7/8/2020 - NQ DRILLING; SHALE FM

NQ ROD R/I UPTO 229.6 M; BH WASHED; DRILLING RECOMMENCED; SHALE


KDR 750(02) MRKB 91/SP-4(C) 660 229.60 269.30 17.70 22.00 39.70 136 97 199.70 7/30/2020 -
FM.

LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 0 0.00 6/9/2020 7/20/2020 RIG SHIFTED TO BASE CAMP

MRKB 90 (SP08)
DY CRFM 50 660 482.35 504.35 9.00 13.00 22.00 133 42 94.80 7/16/2020 - NQ DRILLING; HARD SHALE TO SHALE AND SANDSTONE FM
(C)
Sub Total - 92.80 439.00
PICHRI
LY-44/01 P-6 260 40.50 67.50 14.00 13.00 27.00 40 65 67.5 8/3/2020 - HQ DRILLING; SANDSTONE FM AND COAL
CDR-1000 P-14 850 30.00 65.00 18.00 17.00 35.00 135 65 65 8/4/2020 - DRILLING; 60% W/LOSS AT 47.50 M DEPTH
P-16 650 0.00 0.00 0.00 0.00 WORK HAMPERED DUE TO HEAVY RAIN (FARMING LAND); WAITING FOR
DI-08 0.00 81 0 - -
IRON PLATE
Sub Total - 62.00 175.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 162 56 0.00 1/17/2019 Redrill HQ REDRILLING; FRACTURED SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP
JAMMING TENDENCY DURING DRILLING; BH WASHED 2 TIMES; DRILLING;
LY-44/01 MABD-92 /P-81 400 530.5 535.5 2.00 3.00 5.00 80 24 43.30 7/6/2020 - SHEAR ZONE
LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP
773 M NQ ROD P/O AS WIRELINE ROPE BROKEN; NQ LOWERED AND BH
Dy-120/02 MABD-44/P-72 850 768.5 773 4.50 0.00 4.50 139 73 54.00 4/25/2019 -
WASHED; SHALE AND COAL
Sub Total - 9.50 381.00
HAMIRPUR

RIG SHIFTING STARTED BUT THEN RIG B/D; REPAIRING UNSUCCESSFUL; HW


DY50CR/04 0.00 0.00 0.00 0.00 65 0 - -
LINER AND HQ RODS SHIFTED FROM FARSI SITE TO LOHARKAR NALA SITE

DY50CR/05 LHR -29 375 0.00 3.00 3.00 0.00 3.00 40 65 3 8/5/2020 - RIG SET; SITE PREPARATION DONE; DRILLING STARTED; 3 M PX CASING
DONE
LY-44 GLT-07 400 226.50 226.50 0.00 0.00 0.00 10 32 35.3 7/6/2020 - 8 M DRILLED THEN FUEL PUMP B/D; REPAIRING UNSUCCESSFUL
Sub Total - 3.00 50.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 8 0 - - RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 16 0 - - AT LOADING POINT
LY-38/01 KIOM/70/49 21.50 21.50 0.00 0.00 0.00 10 16 16 7/31/2020 - RIG BEING SHIFTED TO NEXT POINT
Sub Total - 0.00 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 129 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 05-08-20 05-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA11/ 270° /
UCD 60-1 125 80.40 104.45 0.00 7.15 10.35 17.50 113 57.9 7/28/2020 - H/L FOR BIT CHOPPING; HARD FM.
+4°
KMA-14/
UCD 60-2 85 80.40 85.85 5.45 0.00 0.00 5.45 135 131.4 8/2/2020 - BH CLOSED; SURVEY DONE; SUPPORT DISMANTLED; NEW HOLE STARTED
+21°/90°
UCD 60-2 KMA-15/+31°/N400 85 0.00 17.00 17.00 0.00 0.00 17.00
Sub Total - 22.95 0.00
AGUCHA UG
DSP 14
WAITING FOR COMPRESSOR SHIFTING PLAN, BUT VOLVO NOT AVAILABLE
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 -
FOR SHIFTING; DE WATERING PUMP DIRECTION CHANGING IN PROGRESS
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 76.5 mm
403.10 413.25 6.00 4.15 10.15 0 25.3 6/22/2020 - NQ DRILLING DONE; NQ P/O AND MOTOR LOWERED THEN MDD STARTED
Sub Total - 10.15 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 963.00 982.50 12.00 7.50 19.5 200 83.7 6/19/2020 - DRILLING IN PROGRESS; RODS P/O FOR BIT CHANGE
Q)
Sub Total - 19.50 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 05-08-20 05-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 192.00 192.00 0.00 0.00 0.00 20 68 7/23/2020 - PILOT BH PUNCTURED IN DESIRED LOCATION

LY-38
Upward BH No. 01 36.00 38.00 2.00 0.00 2.00 0 2 7/17/2020 - MACHINE MAINTENANCE
Borehole

Sub Total - 2.00 20.00


NGRI KOYNA
LOWERED HQ UPTO 1140 M AFTER GAUGING WITH 76 MM GAUGE; HEAVY
DYNA 350 KBH-10-R 1500 1185.00 1185.00 0.00 0.00 0.00 73 20.8 1/22/2020 -
RAIN AND CYCLONIC WINDS HAMPERED WORK
Sub Total - 0.00 73.00
DATE: 03-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 03-08-20 03-08-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 LAND OWNER STOPPED SHIFTING FOR CROP COMPENSATION
Sub Total - 0.00 30.00
KABITIRTHA
NQ DRILLING; COAL FM; CORE DROPPED; 656.70 M ROD P/O AND R/I; BH
DICD100H/1 MRKB 89/SP-7(C) 820 655.40 669.80 1.30 13.10 14.40 144 24 58.20 7/8/2020 -
WASHED DRILLING

KDR 750(02) MRKB 91/SP-4(C) 660 145.00 191.40 23.20 23.20 46.40 136 58 121.80 7/30/2020 - 72 M ROD R/I; BH WASHED; HQ DRILLING; SHALE FM.

RIG SHIFTING NOT POSSIBLE DUE TO INSUFFICIENT MANPOWER AND


LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 0 0.00 6/9/2020 7/20/2020
MUDDY ROAD CONDITION
MRKB 90 (SP08)
DY CRFM 50 660 439.65 460.15 11.50 9.00 20.50 180 25 50.60 7/16/2020 - R/I 72 M ROD; BH WASHED; NQ DRILLING; HARD SHALE FM
(C)
Sub Total - 81.30 460.00
PICHRI
P-6 260 0.00 11.00 4.50 6.50 DERRICK SET, AMC PUMP REPAIRING, CENTRIFUGAL PUMP INSTALLED;
LY-44/01 11.00 50 39 11 8/3/2020 -
DRILLING IN PROGRESS
CDR-1000 P-14 850 0.00 0.00 0.00 0.00 0.00 39 0 - - SITE PREPARATION DONE; RIG SET AT POINT
DI-08 P-16 650 0.00 0.00 0.00 0.00 0.00 48 0 - - RIG SHIFTING TO BH POINT
Sub Total - 11.00 50.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 162 34 0.00 1/17/2019 Redrill HQ REDRILLING; SHALE , SANDSTONE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 498.7 519.5 9.80 11.00 20.80 110 15 27.30 7/6/2020 - NQ DRILLING; HARD SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy 50 - CR/08 0 0 0 0.00 0.00 0.00 10 0.00 - - MACHINE STANDBY AT CAMP
5 M DRILLED THEN WIRELINE ROPE BROKE AT 420 M; NQ H/L; DRILLING;
Dy-120/02 MABD-44/P-72 850 734.1 747.6 5.00 8.50 13.50 204 44 28.60 4/25/2019 - SHALE AND FRACTURED COAL FM.
Sub Total - 34.30 476.00
HAMIRPUR

RIG SHIFTING STARTED BUT THEN RIG B/D; REPAIRING UNSUCCESSFUL; HW


DY50CR/04 0.00 0.00 0.00 0.00 39 0 - - LINER AND HQ RODS SHIFTING FROM FARSI SITE TO LOHARKAR NALA SITE

DY50CR/05 GLT- 0.00 0.00 0.00 0.00 0.00 39 0 7/10/2020 7/31/2020 WAITING FOR HOLE POINT
LY-44 GLT-07 400 201.50 211.50 3.00 7.00 10.00 35 19 28.3 7/6/2020 - 8 M DRILLED THEN FUEL PUMP B/D; REPAIRING UNSUCCESSFUL
Sub Total - 10.00 35.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 5 0 - - RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 0 - - AT LOADING POINT
LY-38/01 KIOM/70/49 13.00 21.50 8.50 0.00 8.50 10 10 16 7/31/2020 - DRY DRILLING CONTINUES; CORE BOX SHIFTING
Sub Total - 8.50 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 77 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 03-08-20 03-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA11/ 270° / DRILLING; VERY HARD FM.; 4 TIMES H/L; FAN SHIFTING FROM N400 TO S400;
UCD 60-1 125 59.10 66.05 0.00 0.00 6.95 6.95 68 12.95 7/28/2020 -
+4° OLD GEAR BOX SHIFTING FROM S400 TO SURFACE

UCD 60-2 KMA-14/ 85 47.50 61.75 0.00 0.00 14.25 14.25 68 90.3 8/2/2020 - MUCKING FROM 11 AM TO 2.45 PM; HARD FM.; VENTILATION FAN
+21°/90° TRANSPORT N400 TO S400 BY LHD
Sub Total - 21.20 0.00
AGUCHA UG
DSP 14 HAMMER WASHED; CHANGED COMPRESSOR AIR FILTER; OIL COOLER BODY
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - LEAKAGE FROM BOTTOM FOUND; NEED WELDING WORK; COMPRESSOR
Reaming SHIFTING PLAN RECEIVED
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- NQ RODS LOWERED FORBOTOOM SURVEY; BEARING CORRECTION NEEDED;
DIMP-175 96 mm 397.10 399.95 2.85 0.00 2.85 0 12 6/22/2020 - NQ P/O AND MOTOR LOWERED; MDD STARTED
Sub Total - 2.85 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 Q) 950 908.60 936.00 12.40 15.00 27.4 200 37.2 6/19/2020 - DRILLING IN PROGRESS
Sub Total - 27.40 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 03-08-20 03-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 180.00 190.00 10.00 0.00 10.00 100 66 7/23/2020 - RIG PULLEY SHAFT BROKEN

LY-38
Upward BH No. 01 36.00 36.00 0.00 0.00 0.00 0 7/17/2020 - DRAIN MAKING DONE
Borehole

Sub Total - 10.00 100.00


NGRI KOYNA
P/O REMAINING HQ STRING FULL OF MUD; 3 M CORE RECOVERED;
DYNA 350 KBH-10-R 1500 1185.80 1185.80 0.00 0.00 0.00 94 20.8 1/22/2020 - COMPLETE WIRELINE ROPE REMOVED, SELECTED ND REMOVED DAMAGED
PARTS THEN REJOINED THE SAME WITH SOME OLD ROPE
Sub Total - 0.00 94.00
DATE: 02-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 02-08-20 02-08-20 ment Closure
(m) (m)
PATRATU
PLATE AND WOODEN BEAMS SHIFTED MANUALLY TO CAMP SITE; LAND
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 OWNER NOT ALLOWING TO SHIFT RIG AND ASKING FOR RS. 45000 LAND
COMPENSATION
Sub Total - 0.00 30.00
KABITIRTHA
NQ DRILLING; SHALE FM; CORE DROPPED; TRIED TO RELEASE BUT
DICD100H/1 MRKB 89/SP-7(C) 820 636.95 655.40 10.45 8.00 18.45 120 16 43.80 7/8/2020 -
UNSUCCESSFUL; 36 M ROD P/O

KDR 750(02) MRKB 91/SP-4(C) 660 116.00 145.00 14.50 14.50 29.00 92 39 75.40 7/30/2020 - HQ DRILLING; SHALE FM; 72 M ROD P/O

RIG SHIFTING NOT POSSIBLE DUE TO INSUFFICIENT MANPOWER AND


LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 0 0.00 6/9/2020 7/20/2020
MUDDY ROAD CONDITION
MRKB 90 (SP08)
DY CRFM 50 660 426.65 439.65 8.00 5.00 13.00 70 17 30.10 7/16/2020 - NQ DRILLING; HARD SHALE FM; P/O 72 M ROD
(C)
Sub Total - 60.45 282.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 0.00 127 23 0.00 1/17/2019 Redrill HQ REDRILLING; SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 492.2 498.7 3.00 3.50 0.00 6.50 60 10 6.50 7/6/2020 - NQ DRILLING; HARD SHALE FM.

LY-44/03 0 0 0 0.00 0.00 0.00 0 0.00 - - MACHINE STANDBY AT CAMP


Dy 50 - CR/08 0 0 0 0.00 0.00 0.00 6 0.00 - - MACHINE STANDBY AT CAMP
Dy-120/02 MABD-44/P-72 850 729.1 734.1 0.00 5.00 5.00 68 29 15.10 4/25/2019 - GEAR BOX SEAL AND GEAR OIL CHANGED; NQ DRILLING; SHALE FM.
Sub Total - 11.50 255.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 26 0 - - NEW HOLE POINT AT LOHARKAR NALA
DY50CR/05 GLT- 0.00 0.00 0.00 0.00 0.00 26 0 7/10/2020 7/31/2020 WAITING FOR HOLE POINT
LY-44 GLT-07 400 201.50 211.50 3.00 7.00 10.00 35 13 20.3 7/6/2020 - SPINDLE REPAIRED; DRILLING IN PROGRESS
Sub Total - 10.00 35.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 3 0 - - RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 6 0 - - AT LOADING POINT
LY-38/01 KIOM/70/49 11.00 13.00 2.00 0.00 2.00 5 6 7.5 7/31/2020 - DRY DRILLING CONTINUES; CORE BOX SHIFTING
Sub Total - 2.00 5.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 52 0.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA11/ 270° /
UCD 60-1 +4° 125 59.10 59.10 0.00 0.00 0.00 0.00 45 6 7/28/2020 - WEEKLY OFF
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 02-08-20 02-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

KMA-14/
UCD 60-2 +21°/90° 85 0.00 47.50 27.10 20.40 0.00 47.50 45 76.05 8/2/2020 - MAST SUPPORT DONE; BACK SUPPORT DONE; DRILLING STARTED; HARD FM.
Sub Total - 47.50 0.00
AGUCHA UG
DSP 14
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 0 7/21/2020 - WEEKLY OFF
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm
397.10 397.10 0.00 0.00 0.00 0 9.15 6/22/2020 - WEEKLY OFF
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N FISHING DONE; MAIN WINCH ROPE DAMAGED, REPLACED AND DRILLING
KDR-1200/02 950 905.00 908.60 0.00 3.60 3.6 400 9.8 6/19/2020 -
Q) STARTED
Sub Total - 3.60 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 02-08-20 02-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 180.00 180.00 0.00 0.00 0.00 180 56 7/23/2020 - DRILLING IN PROGRESS

LY-38
Upward BH No. 01 36.00 36.00 0.00 0.00 0.00 0 7/17/2020 - BLASTING DONE FOR DRAIN MAKING
Borehole

Sub Total - 0.00 180.00


NGRI KOYNA
7.50 M DRILLED THEN WATER PRESSURE GOT BLOCKED; TRIED TO RELEASE
DYNA 350 KBH-10-R 1500 1178.30 1185.80 7.50 0.00 7.50 130 20.8 1/22/2020 - BUT UNSUCCESSFUL; WIRELINE GOT BROKEN; 100 PAIRS P/O WITH MUD IN
STRING
Sub Total - 7.50 130.00
DATE: 01-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 01-08-20 01-08-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 MACHINE AND PLATE SHIFTED FROM SITE TO NEARBY ROAD
Sub Total - 0.00 30.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 611.60 636.95 10.35 15.00 25.35 192 650.00 653.00 7/8/2020 - WIRELINE ROPE JOINED; NQ DRILLING; FRACTURED SHALE FM.

KDR 750(02) MRKB 91/SP-4(C) 660 69.60 116.00 23.20 23.20 46.40 107 650.00 921.20 7/30/2020 - HQ DRILLING; SHALE FM.

RIG SHIFTING NOT POSSIBLE DUE TO INSUFFICIENT MANPOWER AND


LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 300.00 281.40 6/9/2020 7/20/2020
MUDDY ROAD CONDITION
MRKB 90 (SP08) NQ DRILLING; HARD SHALE FM.; 412.65 M ROD P/O AND R/I AFTER BIT
DY CRFM 50 660 409.55 426.65 3.10 14.00 17.10 130 400.00 409.55 7/16/2020 -
(C) CHANGE
Sub Total - 88.85 429.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 138 400.00 482.80 1/17/2019 Redrill HQ REDRILLING; SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 200.00 130.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 492.2 492.2 0.00 0.00 0.00 350.00 492.20 7/6/2020 - DERRICK SET AGAIN; UNABLE TO DRILL DUE TO HEAVY RAINFALL

LY-44/03 0 0 0 0.00 0.00 0.00 500.00 359.00 - - MACHINE STANDBY AT CAMP


Dy 50 - CR/08 MABD-79/P-83 610 610 610 0.00 0.00 0.00 36 150.00 156.00 3/16/2020 - RIG AND MATERIALS SHIFTING TO CAMP
Dy-120/02 MABD-44/P-72 850 719 729.1 7.10 3.00 10.10 94 300.00 192.10 4/25/2019 - NQ DRILLING; FRACTURED COAL, SHALE, SHEAR ZONE FM.
Sub Total - 10.10 268.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 26 0 - - WAITING FOR HOLE POINT
DY50CR/05 GLT-08 400 471.00 471.00 0.00 0.00 0.00 14 26 0 7/10/2020 7/31/2020 ALL CASING P/O; WAITING FOR POINT

LY-44 GLT-07 400 191.20 201.50 4.30 6.00 10.30 50 13 20.3 7/6/2020 - 191.20 M P/O DUE TO BIT DAMAGE; BIT CHANGED: DRILLING IN PROGRESS
Sub Total - 10.30 64.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 28.3 - - RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 50.00 27 - - AT LOADING POINT
LY-38/01 KIOM/70/49 5.50 11.00 5.50 0.00 5.50 10 5.50 7/31/2020 - DRY DRILLING CONTINUES
Sub Total - 5.50 10.00
SOMAVARAM

DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
CULTIVATION WORK HAS STARTED
RIG IDLE AND SHIFTED TO CAMP AS CURRENTLY NO BH POINTS AVAILABLE
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 500.02 472.00 - -
AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA11/ 270° / 6 M DRILLED; HARD FM.; 3 TIMES H/L FOR BIT CHOPPING; HYD PIPE
UCD 60-1 125 53.10 59.10 0.00 0.00 6.00 6.00 600 532.55 7/28/2020 -
+4° DAMAGED; RIG B/D; MAN POWER SHORTAGE DUE TO EID.
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 01-08-20 01-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

KMA-13/N400/
UCD 60-2 +9°/90° 85 52.85 81.40 17.65 4.85 6.05 28.55 7/31/2020 8/1/2020 BH CLOSED; HOISTED ALL RODS; SURVEY DONE
Sub Total - 34.55 0.00
AGUCHA UG
DSP 14
CONCRETE PAD AND MOUNT PREPARED FOR DEWATERING PUMP; 24 H
UDD-330 SBH No.- 0.00 0.00 0.00 0.00 0.00 0 200 181.5 7/21/2020 - WAIT FOR FIXING OF CONCRETE
Reaming
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- MDD DONE; MDD P/O AND NQ LOWERED WITH FLEXIBLE BARREL UPTO 256
DIMP-175 96 mm
387.95 397.10 7.15 2.00 9.15 0 500 327.95 6/22/2020 -
M; LOWERING IN PROGRESS
Sub Total - 9.15 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 898.80 905.00 6.20 6.20 12.4 200 625 643.8 6/19/2020 - CORING; ROD SLIPPED FROM 658 M; FISHING IN PROGRESS
Q)
Sub Total - 12.40 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 01-08-20 01-08-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 124.00 180.00 56.00 0.00 56.00 260 124 7/23/2020 - DRILLING IN PROGRESS

LY-38
Upward BH No. 01 36.00 36.00 0.00 0.00 0.00 0 36 7/17/2020 - WAITING FOR BLASTING
Borehole

Sub Total - 56.00 260.00


NGRI KOYNA
DRILLING; AT TIME OF DRILLING, SOMETIMES, VERY HIGH TORQUE AND
DYNA 350 KBH-10-R 1500 1165.00 1178.30 13.30 0.00 13.30 123 500 310.4 1/22/2020 -
JAMMING TENDENCY WAS OBSERVED
Sub Total - 13.30 123.00
DATE: 31-07-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 31-07-20 31-07-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 200.00 190.5 5/22/2020 7/16/2020 SHIFTING UNDER PROGRESS
Sub Total - 0.00 30.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 586.90 611.60 13.70 11.00 24.70 207 650.00 653.00 7/8/2020 - NQ DRILLING; FRACTURED SHALE FM.

KDR 750(02) MRKB 91/SP-4(C) 660 23.00 69.60 23.40 23.20 46.60 114 650.00 921.20 7/30/2020 - HQ DRILLING; SHALE FM.

RIG SHIFTING NOT POSSIBLE DUE TO INSUFFICIENT MANPOWER AND


LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 300.00 281.40 6/9/2020 7/20/2020
MUDDY ROAD CONDITION
MRKB 90 (SP08)
DY CRFM 50 660 382.55 409.55 13.50 13.50 27.00 136 400.00 409.55 7/16/2020 - NQ DRILLING; HARD SHALE FM.
(C)
Sub Total - 98.30 457.00
BADAM
Dy 100H/03 MABD-33/P-07 740 391.75 391.75 0.00 0.00 0.00 173 400.00 482.80 1/17/2019 Redrill HQ REDRILLING; SHALE FM.
DI-17/01 0 0 0 0.00 0.00 0.00 200.00 130.00 - - MACHINE STANDBY AT CAMP

LY-44/01 MABD-92 /P-81 400 492.2 492.2 0.00 0.00 0.00 350.00 492.20 7/6/2020 - GROUTING NOT SET, SO DRILLING NOT STARTED

LY-44/03 0 0 0 0.00 0.00 0.00 500.00 359.00 - - MACHINE STANDBY AT CAMP

Dy 50 - CR/08 MABD-79/P-83 610 610 610 0.00 0.00 0.00 79 150.00 156.00 3/16/2020 - BH CLOSED BY CMPDI GEOLOGIST; HQ ROD AND HW LINER P/O COMPLETE

Dy-120/02 MABD-44/P-72 850 694.3 719 9.70 15.00 24.70 221 300.00 192.10 4/25/2019 - NQ DRILLING; FRACTURED COAL, SHALE, SNADSTONE , SHALEY COAL FM.
Sub Total - 24.70 473.00
HAMIRPUR

DY50CR/04 0.00 0.00 0.00 0.00 400.00 0 - - DISCUSSION BETWEEN FROEST R/O AND AMD OFFICIAL UNSUCCESSFUL

DY50CR/05 GLT-08 400 464.00 471.00 7.00 0.00 7.00 84 400.00 471 7/10/2020 7/31/2020 7 M DRILLED THEN BH WASHED AND GPL COMPLETED AND BH CLOSED

LY-44 GLT-07 400 177.50 191.20 11.00 2.70 13.70 55 300.00 191.2 7/6/2020 - DRILLING IN PROGRESS; 191.20 M P/O DUE TO BIT DAMAGE
Sub Total - 20.70 139.00
KURMITAR
VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 28.3 RIG B/D
LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 50.00 27 AT LOADING POINT
KIOM/70/49 0.00 5.50 5.50 0.00
LY-38/01 5.50 10 5.50 SHIFTING AND OTHER RELATED WORKS DONE; DRY DRILLING CONTINUES
Sub Total - 5.50 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
RIG AND MATERIALS SHIFTED TO CAMP AS CURRENTLY NO BH POINTS
Dy50CR/10 SP- 0.00 0.00 0.00 0.00 0.00 500.02 472.00 - -
AVAILABLE AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 31-07-20 31-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
HZL KAYAD
KMA11/ 270° /
UCD 60-1 125 32.25 53.10 0.00 9.40 11.45 20.85 600 532.55 7/28/2020 - DRILLING IN PROGRESS; HARD FM.
+4°
KMA-
UCD 60-2 85 81.75 85.60 3.85 0.00 0.00 3.85 600 571.65 7/29/2020 7/31/2020 BH CLOSED AND SURVEY DONE
12/N400/0°
KMA-13/N400/ NEW ANGLE SET; MAST SUPPORT DONE; DRILLING STARTED; CORE BOXES
UCD 60-2 85 0.00 52.85 12.00 20.80 20.05 52.85 7/31/2020 -
+9°/90° SHIFTED FROM DRIVE TO CROSS CUT; HARD FM.
Sub Total - 77.55 0.00
AGUCHA UG
CV -105
ASKED TO START DSP-14, OLD HOLE REAMING; SITE VISITED AND CHECKED
UDD-330 SBH No.- 57 Size 90.50 90.50 0.00 0.00 0.00 0 200 181.5 7/21/2020 - AND PLAN TO CHANGE PUMP DIRECTION DONE
-8"
Sub Total - 0.00 0.00
AGUCHA SUR PF

Surface to -180- 6 M DRILLED; ALL NQ ROD AND HQ CASING HOISTED; MOTOR LOWERED
DIMP-175 96 mm
381.95 387.95 6.00 0.00 6.00 0 500 327.95 6/22/2020 - UPTO 212M; GRL SET AND MOTOR LOWERED TO BOTTOM WITH MARKING;
NO MOTOR DRILLING DONE AS RMC MAN DID NOT SUPPLY DRILLING WATER

Sub Total - 6.00 0.00


TDMA ZAWAR
DD20ZWE272(N CANTILEVER MOUNTING BOLT FIXED AND LEAKAGE ARRESTED FROM HYD.
KDR-1200/02 Q) 950 894.10 898.80 4.70 0.00 4.7 400 625 643.8 6/19/2020 - PUMP FITTINGS; TRIPPING DUE TO BIT CHANGE
Sub Total - 4.70 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 31-07-20 31-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 71.50 124.00 52.50 0.00 52.50 180 124 7/23/2020 - DRILLING IN PROGRESS

LY-38
Upward BH No. 01 36.00 36.00 0.00 0.00 0.00 36 7/17/2020 - WAITING FRO BLASTING DUE TO DRAIN CUTTING WORK
Borehole

Sub Total - 52.50 180.00


NGRI KOYNA

DRILLING; DURING LAST RUN, WIRELINE ROPE BROKEN FROM 240 M,; P/O
DYNA 350 KBH-10-R 1500 1151.50 1165.00 13.50 0.00 13.50 120 500 310.4 1/22/2020 - 40 PAIRS AND JOINED THE SAME; AT TIME OF DRILLING, SOMETIMES, VERY
HIGH TORQUE AND JAMMING TENDENCY WAS OBSERVED

Sub Total - 13.50 120.00


DATE: 01-08-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 27-07-20 27-07-20 ment Closure
(m) (m)
PATRATU
TRIED TO RELEASE RIG THROUGH CULTIVATED LAND BUT UNABLE DUE TO
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 30 167.74 190.5 5/22/2020 7/16/2020 HEAVY RAIN
Sub Total - 0.00 30.00
KABITIRTHA

MRKB 89/SP-7(C) RH GEAR BOX REACHED SITE BUT NO WORK DONE AS DRILLER GOING ON
DICD100H/1 820 504.65 504.65 0.00 0.00 0.00 566.13 546.05 7/8/2020 - LEAVE

MRKB 88/SP-5(C) WIRELINE ROPE CHANGED AND NEW ROPE ADDED; NQ DRILLING; SHALE,
KDR 750(02) 690 686.40 706.90 10.10 10.40 20.50 121 566.13 820.50 7/7/2020 - COAL TO FRACTURED COAL FM.

LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 8 435.48 281.40 6/9/2020 7/20/2020 DERRICK DISMANTLED AND OTHER MATERIAL SHIFTED TO BASE CAMP; RH
GEAR BOX SHIFTED TO BH SITE
MRKB 90 (SP08)
DY CRFM 50 (C) 660 270.40 303.00 15.60 17.00 32.60 155 459.00 303.00 7/16/2020 - NQ DRILLING; HARD SHALE FM.
Sub Total - 53.10 284.00
BADAM

RIG 3 100H/03 MABD-33/P-07 391.75 391.75 0.00 0.00 0.00 46 348.39 482.80 1/17/2019 Redrill MACHINE SHIFTED TO P 07 ND MATERIALS SHIFTED TO SUKULKHAPIA CAMP

RIG 4 DI-17/01 0 0 0 0.00 0.00 0.00 174.19 130.00 - - MACHINE STANDBY AT CAMP

Rig 1 LY-44/01 MABD-92 /P-81 400 428.7 459 15.30 15.00 30.30 126 303.33 459.00 7/6/2020 - NQ DRILLING; SANDSTONE AND SHALE FM.

Rig 5 LY-44/03 0 0 0 0.00 0.00 0.00 435.48 359.00 - - MACHINE STANDBY AT CAMP
497 M BQ P/O; NQ REAMING FROM 493 TO 497 M; BQ LOWERED; BH
Rig 6 50 - CR/08 MABD-79/P-83 600 497 500 0.00 3.00 3.00 90 130.65 46.00 3/16/2020 - CAVING AND WASHED AND DRILLING RECOMMENCED; SHEAR ZONE AND
SANDSTONE FM.
Rig 7 Dy-120/02 MABD-44/P-72 850 571.4 600.1 15.20 13.50 177 260.00 73.20 4/25/2019 - NQ DRILLING; SHALE FM.
Sub Total - 33.30 439.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 350.00 0 - - WAITING FOR HOLE POINT
DY50CR/05 GLT-08 400 400.00 405.00 0.00 5.00 5.00 36 350.00 405 7/10/2020 - AMD DECISION TO EXTEND 25 M; DRILLING IN PROGRESS
LY-44 GLT-07 400 123.00 129.00 6.00 0.00 6.00 20 264.00 129 7/6/2020 - DRILLING IN PROGRESS
Sub Total - 11.00 56.00
SOMAVARAM

DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
CULTIVATION WORK HAS STARTED
RIG AND MATERIALS SHIFTED TO CAMP AS CURRENTLY NO BH POINTS
Dy50CR/10 SP-08 250 188.50 188.50 0.00 0.00 0.00 241.94 472.00 7/21/2020 7/25/2020
AVAILABLE AT SITE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-
HOISTING ALL RODS AND LOWERING 15 M WITH REAMING; BH CLOSED;
UCD 60-1 08/S400/270°/+1 125 118.60 126.05 0.00 1.30 6.15 7.45 541.88 479.45 7/18/2020 -
7° SUPPORT DISMANTLED; CORE BOXES SHIFTED TO POCKET
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 27-07-20 27-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

KMA-
UCD 60-2 10/N400/0°/90° 85 49.80 82.80 0.00 16.55 16.45 33.00 542.84 430.2 7/24/2020 - DRILLING IN PROGRESS

Sub Total - 40.45 0.00


AGUCHA UG
CV -105
UDD-330 SBH No.- 57 Size 90.50 90.50 0.00 0.00 0.00 0 174.18 181.5 7/21/2020 - WAITING FOR DEVELOPMENT AT -205
-8"
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm 227.45 265.15 20.30 17.40 37.70 0 435.48 205.15 6/22/2020 - HQ DRILLING; MAIN PUMP HYD. PIPE LEAKAGE SEEN; REPAIRED
Sub Total - 37.70 0.00
TDMA ZAWAR

KDR-1200/02 DD20ZWE272(N 950 753.10 783.10 15.00 15.00 30 400 544.35 528.1 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 30.00 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 27-07-20 27-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 8.00 8.00 0.00 0.00 0.00 40 8 7/23/2020 - TRIED TO LOWER 10' CASING BUT RAINFALL FROM 1 PM TO 4 PM

LY-38
Upward BH No. 01 25.00 25.00 0.00 0.00 0.00 45 25 7/17/2020 - ROD H/L FOR SWISH VALVE SETTING
Borehole

Sub Total - 0.00 85.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1147.00 1147.00 0.00 0.00 0.00 0 435.48 292.4 1/22/2020 - RIG B/D
Sub Total - 0.00 0.00
DATE: 26-07-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 16-07-20 16-07-20 ment Closure
(m) (m)
PATRATU

160FT ROAD MAKING BY JCB THROUGH CULTIVATED LAND AND PAIR ROD
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 167.74 190.5 5/22/2020 7/16/2020
CASING DISMANTLED AND SHIFTED FROM DRILLING SITE TO ROAD SIDE

Sub Total - 0.00 0.00


KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 504.65 504.65 0.00 0.00 0.00 0.00 545.16 546.05 7/8/2020 - RIG IDLE AS RH GEAR BOX UNDER REPAIR IN MAPL W/S

KDR 750(02) MRKB 88/SP-5(C) 690 660.10 686.40 9.00 8.70 8.60 26.30 141 545.16 800.00 7/7/2020 - NQ DRILLING; COAL, SHALE AND SANDSTONE FM.

LY 44/01 MRKB 86/SP-3(C) 660 624.00 624.00 0.00 0.00 0.00 0.00 419.35 281.40 6/9/2020 - RIG IDLE AS NO LOCAL HELPERS AVAILABLE AT SITE

MRKB 90 (SP08)
DY CRFM 50 660 260.40 270.40 1.00 9.00 0.00 10.00 65 432.00 270.40 7/16/2020 - NQ DRILLING; HARD SHLE FM; 261 M ROD P/O FOR BIT CHANGE THEN R/I;
(C)
Sub Total - 36.30 141.00
BADAM
RIG 3 100H/03 0 0 0 0.00 0.00 0.00 58 335.48 482.80 - - MACHINE UNDER SHIFTING TO SUKULKHPIA CAMP
RIG 4 DI-17/01 0 0 0 0.00 0.00 0.00 167.74 130.00 - - MACHINE STANDBY AT CAMP

Rig 1 LY-44/01 MABD-92 /P-81 400 416 428.7 6.70 6.00 12.70 68 291.67 428.70 7/6/2020 - NQ DRILLING; SHALE FM.

Rig 5 LY-44/03 0 0 0 0.00 0.00 0.00 419.35 359.00 - - MACHINE STANDBY AT CAMP

Rig 6 50 - CR/08 MABD-79/P-83 600 493 497 2.00 2.00 4.00 72 125.81 43.00 3/16/2020 - BQ DRILLING; BH CAVING AND WASHED; SHEAR ZONE AND SANDSTONE FM.

Rig 7 Dy-120/02 MABD-44/P-72 850 541 571.4 15.40 15.00 136 250.00 44.50 4/25/2019 - NQ DRILLING; SHALE TO SANDY SHALE FM.
Sub Total - 16.70 334.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 333.33 0 - - WAITING FOR HOLE POINT
DY50CR/05 GLT-08 400 397.00 400.00 3.00 0.00 3.00 29 333.33 400 7/10/2020 - TARGET DEPTH ACHIEVED; DRILLING STOPPED BY AMD OFFICIAL
LY-44 GLT-07 400 115.00 123.00 8.00 0.00 8.00 25 252.00 123 7/6/2020 - DRILLING IN PROGRESS
Sub Total - 11.00 54.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Dy50CR/10 SP-08 250 188.50 188.50 0.00 0.00 0.00 20 241.94 472.00 7/21/2020 7/25/2020 GPL DONE; RETRIEVED ALL RODS AND CASINGS FROM HOLE
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 20.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA-
FUMES PRESENT DUE TO N400 BLASTING SO CREW WENT TO S400 FOR
UCD 60-1 08/S400/270°/+1 125 92.10 118.60 12.35 0.00 14.15 26.50 522.53 472 7/18/2020 -
7° DRILLING; HARD FM.
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 16-07-20 16-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

KMA-
UCD 60-2 10/N400/0°/90° 85 49.80 49.80 0.00 0.00 0.00 0.00 514.27 397.2 7/24/2020 - WEEK OFF

Sub Total - 26.50 0.00


AGUCHA UG
CV -105
UDD-330 SBH No.- 57 Size 82.00 90.50 0.00 8.50 8.50 0 103.23 82 7/21/2020 - 8" DRILLING;ALL RODS HOISTED; WAITING FOR DEVELOPMENT AT -205
-8"
Sub Total - 8.50 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm 227.45 227.45 0.00 0.00 0.00 0 419.35 167.45 6/22/2020 - WEEKLY OFF
Sub Total - 0.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 950 707.00 753.10 21.70 24.40 46.1 200 524.19 498.1 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 46.10 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 16-07-20 16-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
Sparr Rig BH No. 01 8.00 8.00 0.00 0.00 0.00 8 7/23/2020 - WEEKLY OFF

LY-38
Upward BH No. 01 25.00 25.00 0.00 0.00 0.00 25 7/17/2020 - WEEKLY OFF
Borehole

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1147.00 1147.00 0.00 0.00 0.00 0 419.35 292.4 1/22/2020 - RIG B/D
Sub Total - 0.00 0.00
DATE: 16-07-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 16-07-20 16-07-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 103.23 190.5 5/22/2020 7/16/2020 GPL DONE UPTO 942 M; BH CLOSED
Sub Total - 0.00 0.00
KHARKHAREE
LY-44 MAKH-29-P-18 300 288.00 288.00 0.00 0.00 0.00 129.03 262.50 6/30/2020 7/12/2020 GUARD DUTY
KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 RIG SHIFTED TO MAIN CAMP
KDR 750/03 MAKH-28-P-16 440 441.00 441.00 0.00 0.00 0.00 40 227.10 366.00 6/29/2020 7/12/2020 RIG SHIFTED TO MAIN CAMP
Di - 8 MAKH-27-P-27 690 637.50 637.50 0.00 0.00 0.00 50 258.06 403.30 6/25/2020 7/12/2020 RIG SHIFTED TO MAIN CAMP
Sub Total - 0.00 130.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 269.05 304.85 15.00 20.80 35.80 192 335.48 346.25 7/8/2020 - HYD. FOOT CLAM REPAIRED; NQ DRILLING; SHALE TO HARD SHALE FM

KDR 750(02) MRKB 88/SP-5(C) 690 347.50 391.70 22.20 22.00 44.20 144 335.48 505.30 7/7/2020 - NQ DRILLING; HARD SHALE TO SHALE AND SANDSTONE FM.

PUMP REPAIRING, WIRELINE PULLEY CHANGED; NQ DRILLING; SHALE AND


LY 44/01 MRKB 86/SP-3(C) 660 574.20 585.20 6.50 4.50 11.00 71 258.06 242.60 6/9/2020 - FRACTURED COAL FM.
MRKB 90 (SP08)
DY CRFM 50 (C) 660 0.00 20.00 20.00 0.00 20.00 45 162.00 20.00 7/16/2020 - HQ DRILLING; 12 M HW LINER LOWERED IN HOLE; SHALE FM.
Sub Total - 111.00 407.00
BADAM
NQ ROD HOISTED AND CHANGED THEN LOWERED; NQ DRILLING; SHALE,
RIG 3 100H/03 MABD-77/P-76 900 904 913.4 0.00 9.40 9.40 161 206.45 415.00 3/2/2020 - SANDSTONE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 422 437 8.00 7.00 15.00 104 103.23 96.00 6/16/2020 - NQ DRILLING; LOOSE SAND FM.

Rig 1 LY-44/01 MABD-92 /P-81 400 207.5 238 15.00 15.50 30.50 122 175.00 238.00 7/6/2020 - HQ DRILLING; SHALE FM.

Rig 2 LY-44/02 0 0 0 0.00 0.00 0.00 232.26 142.00 6/17/2020 7/10/2020 MACHINE STANDBY AT CAMP
TARGET DEPTH ACHIEVED, MACHINE STOPPED BY GEOLOGIST; SANDSTONE
Rig 5 LY-44/03 MABD-91 /P-55 400 376.5 380.5 4.00 0.00 4.00 30 258.06 359.00 6/30/2020 -
AND METAMORPHIC FM.
Rig 6 50 - CR/08 MABD-79/P-83 600 471 485.7 2.50 12.20 14.70 159 77.42 31.70 3/16/2020 Redrill NQ DRILLING IN PROGRESS; SHALE FM.
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 212 150.00 0.00 4/25/2019 Redrill HQ NONCORING REDRILLING; SAND FM.
Sub Total - 73.60 788.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 166.67 0 - - WAITING FOR HOLE POINT
DY50CR/05 GLT-08 400 90.00 128.00 18.00 20.00 38.00 120 166.67 128 7/10/2020 - DRILLING IN PROGRESS
LY-44 GLT-07 400 50.50 59.50 9.00 0.00 9.00 25 132.00 59.5 7/6/2020 - DRILLING IN PROGRESS
Sub Total - 47.00 145.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 16-07-20 16-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 28.3 - - SHIFTING TOWARDS CAMP

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 16.13 27 - - SHIFTING TOWARDS CAMP

Rig 6 - Dyna -
KIOM/00/00 0.00 0.00 0.00 0.00 0.00 32.26 91.2 - - RIG REPAIRED; TO GO TO JSW JAJANG SITE; MOBILISATION DATE 18-07-2020
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10.00 0 - - OFF
Sub Total - 0.00 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
NEGOTIATION WITH OWNER OF NPP-01 IN PROCESS; OWNER DENYING, BUT
Dy50CR/10 NPP-25 350 160.00 160.00 0.00 0.00 0.00 241.94 283.50 7/10/2020 7/14/2020 TRYING TO CONVINCE HIM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA06 / 270° /
UCD 60-1 125 46.50 88.85 14.90 15.35 12.10 42.35 329.03 317.3 7/12/2020 - DRILLING; HARD FM;
-14°
FOOT CLAMP TRANSPORTED FROM SURFACE TO UG, BUT SAME PROBLEM
UCD 60-2 KMA07/ +28° 85 36.05 36.05 0.00 0.00 0.00 0.00 200.00 201.4 7/15/2020 - AS BEFORE; FOOT CLAMP MAINTENACE DONE AND FITTED; MACHINE MADE
READY FOR DRILLING
Sub Total - 42.35 0.00
AGUCHA UG
Location - North
UDD-330 105 CV SBH No. 73.00 82.00 0.00 9.00 9.00 0 103.23 82 7/2/2020 - 8" DRILLING;MAIN FEED HYD. HOSE LEAKAGE; NOT ABLE TO P/O
56
Sub Total - 9.00 0.00
AGUCHA SUR PF
Surface to -180- 3 M NQ DRILLING THEN NQ ROD AND HQ CASING HOISTED; NQ LOWERED
DIMP-175 96 mm
156.75 159.75 0.00 3.00 3.00 0 258.06 99.75 6/22/2020 -
FOR MULTI SHOT SURVEY THEN P/O
Sub Total - 3.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 16-07-20 16-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

DD20ZWE272(N
KDR-1200/02 Q) 950 516.10 544.30 12.00 16.20 28.2 400 322.58 289.3 6/19/2020 - DRILLING IN PROGRESS
Sub Total - 28.20 400.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 16-07-20 16-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SIJUA COLLIERY WORK

BH 01 0.00 STARTER SHIFTING FROM UG LANDING TO SITE

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1063.10 1081.10 18.00 0.00 18.00 140 258.06 226.5 1/22/2020 - HQ DRILLING CONTINUES
Sub Total - 18.00 140.00
DATE: 15-07-20

Starting Target Progress Date of


Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth HSD Commence SITE UPDATES REMARKS
(m) (m) Depth (m) I II III total 15-07-20 15-07-20 ment Closure
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 942.50 942.50 0.00 0.00 0.00 250 96.77 190.5 5/22/2020 - WAITING FOR GPL
Sub Total - 0.00 250.00
KHARKHAREE
LY-44 MAKH-29-P-18 300 288.00 288.00 0.00 0.00 0.00 0.00 262.50 232.50 6/30/2020 7/12/2020 RIG SHIFTING NOT POSSIBLE DUE TO HEAVY RAIN

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 0.00 0.60 0.60 6/5/2020 7/1/2020 ALL MATERIALS SHIFTED TO MAIN CAMP

KDR 750/03 MAKH-28-P-16 440 441.00 441.00 0.00 0.00 0.00 0.00 366.00 322.00 6/29/2020 7/12/2020 ALL MATERIALS SHIFTED TO MAIN CAMP
Di - 8 MAKH-27-P-27 690 637.50 637.50 0.00 0.00 0.00 0 241.94 403.30 6/25/2020 7/12/2020 ALL MATERIALS SHIFTED TO MAIN CAMP
Sub Total - 0.00 0.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 236.70 269.05 13.70 18.65 32.35 212 314.52 310.45 7/8/2020 - MAST SUPPORTING STAND FITTED AND MUD MIXING UNIT SET; NQ
DRILLING; HARD SHALE FM

KDR 750(02) MRKB 88/SP-5(C) 690 300.30 347.50 23.10 24.10 47.20 158 314.52 461.10 7/7/2020 - NQ DRILLING; HARD SHALE TO SHALE AND SANDSTONE FM.

LY 44/01 MRKB 86/SP-3(C) 660 555.70 574.20 7.00 11.50 18.50 104 241.94 231.60 6/9/2020 - NQ DRILLING; SHALE AND SANDSTONE FM.

DY CRFM 50 MRKB 90 (SP08) 660 0.00 0.00 0.00 0.00 0.00 25 135.00 0.00 - - RIG SHIFTED TO POINT; SITE PREPARATION COMPLETE BUT DRILLING NOT
(C) DONE AS DRILLER ENGAGED IN SHIFTING DUTY
Sub Total - 98.05 474.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 881.3 904 14.00 8.70 22.70 173 193.55 405.60 3/2/2020 - NQ DRILLING; SAND AND SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 422 422 0.00 0.00 0.00 30 96.77 81.00 6/16/2020 - NQ DRILLING; LOOSE SANDSTONE FM.

Rig 1 LY-44/01 MABD-92 /P-81 400 177.5 207.5 15.00 15.00 30.00 130 163.33 207.50 7/6/2020 - HQ DRILLING; SHALE TO FRACTURED SHALE FM.

MACHINE AND ALL MATERIALS SHIFTED TO SUKULKHPIA CAMP AND ON


Rig 2 LY-44/02 0 0 0 0.00 0.00 0.00 217.74 142.00 6/17/2020 7/10/2020 STANDBY

Rig 5 LY-44/03 MABD-91 /P-55 400 348.5 376.5 14.00 14.00 28.00 105 241.94 355.00 6/30/2020 - NQ DRILLING; SHALE TO FRACTURED SHALE AND SANDSTONE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 166 72.58 17.00 3/16/2020 Redrill REDRILLING; 356.70 M HQ CASING AND NQ ROD LOWERED AND DRILLING
STARTED
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 177 140.00 0.00 4/25/2019 Redrill HQ NONCORING REDRILLING; SAND FM.
Sub Total - 80.70 781.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 150.00 0 - - WAITING FOR HOLE POINT
DRILLING IN PROGRESS; PROGRESS SLOW DUE TO BOULDER AND SAND FM.
DY50CR/05 GLT-08 400 63.00 90.00 8.00 19.00 27.00 84 150.00 90 7/10/2020 -
AND REPAIRING OF RIG

LY-44 GLT-07 400 39.50 50.50 11.00 0.00 11.00 25 120.00 50.5 7/6/2020 - DRILLING IN PROGRESS; PROGRESS SLOW DUE TO BOULDER AND SAND FM.
Sub Total - 38.00 109.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0
BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 15-07-20 15-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 28.3 - - SHIFTING TOWARDS CAMP

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 16.13 27 - - SHIFTING TOWARDS CAMP

Rig 6 - Dyna - RIG UNDER REPAIR; TO GO TO JSW JAJANG SITE; MOBILISATION DATE 18-07-
KIOM/00/00 0.00 0.00 0.00 0.00 0.00 32.26 91.2 - -
50H 2020

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10.00 0 - - OFF
Sub Total - 0.00 10.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
GPL DONE AND BH CLOSED; RETRIEVED AND P/O ALL HQ AND HW CASINGS;
Dy50CR/10 NPP-25 350 160.00 160.00 0.00 0.00 0.00 283.50 7/10/2020 7/14/2020 NEGOTIATION WITH OWNER OF NPP-01 IN PROCESS; OWNER DENYING, BUT
TRYING TO CONVINCE HIM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD

UCD 60-1 KMA06 / 270° / 125 13.15 46.50 0.00 16.30 17.05 33.35 309.68 274.95 7/12/2020 - DRILLING; HARD FM; ONE SHIFT OFF DUE TO JOB TRAINING
-14°
BH CLOSED; NEW HOLE SET AT +24°, HARD FM; RIG B/D, FOOT CLAMP SEAL
UCD 60-2 KMA07/ +28° 85 0.00 36.05 0.00 17.05 19.00 36.05 171.43 201.4 7/15/2020 - BROKEN SO BROUGHT TO SURFACE FOR MAINTENANCE
Sub Total - 69.40 0.00
AGUCHA UG
Location - North
8" DRILLING; DIESEL NOT RECEIVED DUE TO BROWSER B/D AND VERY POOR
UDD-330 105 CV SBH No. 61.00 73.00 0.00 12.00 12.00 0 96.77 73 7/2/2020 - FACE VENTILATION; ALL RODS P/O AND SURVEY DONE
56
Sub Total - 12.00 0.00
AGUCHA SUR PF
HQ LOWERED AND CEMENT CUTTING FROM 120 M TO 153.75 M; HQ P/O,
Surface to -180-
DIMP-175 96 mm
153.75 156.75 0.00 3.00 3.00 0 241.94 96.75 6/22/2020 - BARREL REMOVED AND HQ RODS LOWERED AS CASING; NQ RODS LOWERED
AND DRILLING STARTED
Sub Total - 3.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 15-07-20 15-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)

DD20ZWE272(N
KDR-1200/02 Q) 20 486.10 516.10 12.00 18.00 30 200 261.1 6/19/2020 - DRILLING IN PROGRESS
Sub Total - 30.00 200.00
Target Progress
Starting Date of
Rig Type T.D. Closing SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth (m) I II III total HSD 15-07-20 15-07-20 Commence Closure SITE UPDATES REMARKS
(m) ment
(m) (m)
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SIJUA COLLIERY WORK

BH 01 0.00 STARTER SHIFTING FROM BASTACOLLA TO UG LANDING

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 1046.60 1063.10 16.50 0.00 16.50 180 241.94 208.5 1/22/2020 - HQ DRILLING CONTINUES
Sub Total - 16.50 180.00
DATE: 12-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 12-07-20 12-07-20 ment Closure
(m) (m)
PATRATU
NQ DRILLING CONTINUES THROUGH FRACTURED COAL AND SANDSTONE
Dy(175/3) BH - 05 1000 879.00 891.00 7.00 5.00 12.00 250 64.52 139 5/22/2020 - FM.; BH WASHED; FREQUENT BLOCKAGE ENCOUNTERED
Sub Total - 12.00 250.00
KHARKHAREE
DRILLING IN PROGRESS; BH CLOSED BY GEOLOGIST; COMPLETE NQ ROD
LY-44 MAKH-29-P-18 300 233.50 258.00 13.50 11.00 24.50 90 80.65 232.50 6/30/2020 7/12/2020 WITH BARREL P/O

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 FISHING CONTINUES

KDR 750/03 MAKH-28-P-16 440 376.50 397.00 12.00 8.50 20.50 150 141.94 322.00 6/29/2020 7/12/2020 BH CLOSED; WAITING FOR GPL
BH CLOSED BY GEOLOGIST; COAL CORE EXCISION AND SHIFTED TO
Di - 8 MAKH-27-P-27 690 573.00 610.00 19.00 18.00 37.00 185 161.29 375.80 6/25/2020 7/12/2020 BASTACOLLA CAMP; ALL NQ RODS WITH BARREL P/O; HQ CASING JAMMED,
TRIED TO RELEASE BUT UNSUCCESSFUL
Sub Total - 82.00 465.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 58.05 113.40 29.25 26.10 55.35 164 209.68 154.80 7/8/2020 - HQ DRILLING; SHALE FM.; PROGRESS HINDERED DUE TO HEAVY RAINFALL

HQ DRILLING; SHALE FM.; HQ RODS P/O; HQ DRILLING COMPLETE;


KDR 750(02) MRKB 88/SP-5(C) 660 112.60 159.30 23.40 23.30 46.70 109 209.68 272.90 7/7/2020 -
PROGRESS HINDERED DUE TO HEAVY RAINFALL
SUMP PIT CLEANED; WATER REFILLED AND MUD MIXING; WIRELINE ROPE
LY 44/01 MRKB 86/SP-3(C) 660 499.00 519.10 9.10 11.00 20.10 89 161.29 176.50 6/9/2020 - FITTED; NQ DRILLING; HARD SHALE FM.; PROGRESS HINDERED DUE TO
HEAVY RAINFALL
DY:50 CR CRAWLER CHAIN DISMANTLED AND SHIFTED TO MAINDHEMO W/S
Sub Total - 122.15 362.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 738.9 771.3 15.90 16.50 32.40 206 129.03 272.90 3/2/2020 - NQ DRILLING; SHALE, COAL FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 358 376 8.00 10.00 18.00 138 64.52 35.00 6/16/2020 - NQ DRILLING; SHEAR ZONE AND SHALE FM.

HQ DRILLING; SHALE TO FRACTURED SHALE FM.; CHAIN SPROCKET AND


Rig 1 LY-44/01 MABD-92 /P-81 400 83.2 102.2 10.00 9.00 19.00 116 105.00 102.20 7/6/2020 - CHAIN DAMAGED, AFTER REPAIRING MACHINE STARTED
Rig 2 LY-44/02 MABD-90/P-90 400 359.5 359.5 0.00 0.00 0.00 40 145.16 142.00 6/17/2020 7/10/2020 MATERIALS BEING SHIFTED TO CAMP

Rig 5 LY-44/03 MABD-91 /P-55 400 232 257 15.00 10.00 25.00 95 161.29 235.50 6/30/2020 - NQ DRILLING; SHALE AND SANDSTONE FM.

HQ NONCORING REDRILLING; 45 PAIR HQ RODS BROKEN; HQ ROD P/O AND


Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 158 48.39 17.00 3/16/2020 Redrill
HQ TAPE LOWERED AND CONNECTED; AGAIN HQ ROD P/O; SHEAR ZONE FM.

Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 68 90.00 0.00 4/25/2019 Redrill BH CAVING AND WASHED; HQ NONCORING REDRILLING; SAND FM.
Sub Total - 94.40 821.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 66.67 0 - - DISCUSSION WITH PVT. LAND OWNER FOR BH POINT UNSUCCESSFUL
DY50CR/05 GLT-08 0.00 14.00 14.00 0.00 14.00 40 66.67 14 7/10/2020 - DRILLING IN PROGRESS
LY-44 GLT-7 13.50 18.50 5.00 0.00 5.00 25 60.00 18.5 7/6/2020 - HW LINER REAMING; DRILLING IN PROGRESS
Sub Total - 19.00 65.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0
BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 12-07-20 12-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 18.00 28.30 10.30 0.00 10.30 28.3 7/7/2020 7/10/2020 SHIFTING

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 16.13 0 - - SHIFTING FOR LAST POINT

Rig 6 - Dyna -
KIOM/68/38 11.00 29.40 18.40 0.00 18.40 50 32.26 91.2 7/9/2020 7/10/2020 CHASSIS CRANK B/D
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 28.70 50.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Dy50CR/10 NPP-25 350 0.00 77.00 51.00 26.00 77.00 161.29 200.50 7/10/2020 - DRILLING IN PROGRESS
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 77.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA03 / 270° /
UCD 60-1 -24° 125 71.50 94.50 0.00 12.95 10.05 23.00 212.90 192.9 7/7/2020 - WEEKLY OFF

BH CLOSED; HOISTING DONE; REMOVED ALL SUPPORT; ANGLE SET IN NEW


UCD 60-2 KMA04 / +10° 85 0.00 47.00 10.20 27.00 9.80 47.00 28.57 47 7/10/2020 7/12/2020 HOLE; LEVELLING DONE
Sub Total - 70.00 0.00
AGUCHA UG
Location - North
UDD-330 105 CV SBH No. 16.00 34.00 9.00 9.00 18.00 0 64.52 34 7/2/2020 - WEEKLY OFF
56
Sub Total - 18.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm
121.50 132.00 10.50 0.00 10.50 0 161.29 72 6/22/2020 - WEEKLY OFF
Sub Total - 10.50 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 20 354.10 381.10 11.80 15.20 27 200 126.1 6/19/2020 - DRILLING IN PROGRESS; TRIPPING DUE TO BIT CHANGE
Q)
Sub Total - 27.00 200.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 12-07-20 12-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SIJUA COLLIERY WORK

BH 01 0.00 PARTIAL MACHINE ASSEMBLY DONE

Sub Total - 0.00 0.00


NGRI KOYNA
DYNA 350 KBH-10-R 1500 983.60 983.60 0.00 0.00 0.00 248 161.29 129 1/22/2020 - HQ DRILLING CONTINUES
Sub Total - 0.00 248.00
DATE: 11-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 10-07-20 10-07-20 ment Closure
(m) (m)
PATRATU

NQ DRILLING CONTINUES THROUGH FRACTURED COAL AND SHALE FMBH


Dy(175/3) BH - 05 1000 879.00 891.00 7.00 5.00 12.00 250 64.52 139 5/22/2020 -
WASHED; NQ DRILLING CONTINUES THROUGH SANDSTONE FM.

Sub Total - 12.00 250.00


KHARKHAREE
LY-44 MAKH-29-P-18 300 233.50 258.00 13.50 11.00 24.50 90 80.65 232.50 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 36 M HQ CASING RETRIEVED BY UNSCREWING; TOTAL 57 M RETRIEVED

KDR 750/03 MAKH-28-P-16 440 376.50 397.00 12.00 8.50 20.50 150 141.94 322.00 6/29/2020 - DRILLING IN PROGRESS; BIT CHANGED AFTER COMPLETE ROD P/O; DRILLING
IN PROGRESS
Di - 8 MAKH-27-P-27 690 573.00 610.00 19.00 18.00 37.00 185 161.29 375.80 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 82.00 465.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 58.05 113.40 29.25 26.10 55.35 164 209.68 154.80 7/8/2020 - HQ DRILLING; SHALE FM.

KDR 750(02) MRKB 88/SP-5(C) 660 112.60 159.30 23.40 23.30 46.70 109 209.68 272.90 7/7/2020 - HQ DRILLING; SHALE FM.

NQ DRILLING; SHALE, SANDSTONE AND COAL FM.; NO WORK DONE AFTER 4


LY 44/01 MRKB 86/SP-3(C) 660 499.00 519.10 9.10 11.00 20.10 89 161.29 176.50 6/9/2020 - AM DUE TO SHORTAGE OF WIRELINE ROPE
RIG UNLOADED; RIG B/D; BOLT OF CRAWLER SPROCKET DISMANTLED AND
DY:50 CR
LOST ON THE WAY; DRILL MATERIALS SHIFTED TO SITE
Sub Total - 122.15 362.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 738.9 771.3 15.90 16.50 32.40 206 129.03 272.90 3/2/2020 - NQ DRILLING; SHALE, SANDSTONE, COAL FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 358 376 8.00 10.00 18.00 138 64.52 35.00 6/16/2020 - NQ DRILLING; COALAND SNADSTONE FM.

HQ DRILLING; SHALE TO FRACTURED SHALE FM.; PROG. POOR DUE TO


Rig 1 LY-44/01 MABD-92 /P-81 400 83.2 102.2 10.00 9.00 19.00 116 105.00 102.20 7/6/2020 -
HEAVY RAIN
Rig 2 LY-44/02 MABD-90/P-90 400 359.5 359.5 0.00 0.00 0.00 40 145.16 142.00 6/17/2020 7/10/2020 HW LINER P/O & MACHINE SHIFTED TO LOADING POINT

Rig 5 LY-44/03 MABD-91 /P-55 400 232 257 15.00 10.00 25.00 95 161.29 235.50 6/30/2020 - NQ DRILLING; COAL AND SANDSTONE FM.

HQ NONCORING REDRILLING; HQ ROD P/O AND LOWERED AFTER


Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 158 48.39 17.00 3/16/2020 Redrill
CHANGING BIT( USING CORING BIT); SHALE AND SAND FM.

Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 68 90.00 0.00 4/25/2019 Redrill BH CAVING AND WASHED; HQ NONCORING REDRILLING; SHALE, SAND FM.
Sub Total - 94.40 821.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 66.67 0 - - DISCUSSION WITH PVT. LAND OWNER FOR BH POINT UNSUCCESSFUL
PX REAMING UPTO 11.70 M; HW LINER P/O UPTO 14 M AND BIT CHANGED;
DY50CR/05 GLT-08 0.00 14.00 14.00 0.00 14.00 40 66.67 14 7/10/2020 - R/I AND BH WASHED; DRILLING
LY-44 GLT-7 13.50 18.50 5.00 0.00 5.00 25 60.00 18.5 7/6/2020 - HW LINER REAMING; DRILLING IN PROGRESS
Sub Total - 19.00 65.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0
BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 10-07-20 10-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 18.00 28.30 10.30 0.00 10.30 28.3 7/7/2020 7/10/2020 SHIFTING

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 16.13 0 - - MATERIALS BEING SHIFTED

Rig 6 - Dyna -
KIOM/68/38 11.00 29.40 18.40 0.00 18.40 50 32.26 91.2 7/9/2020 7/10/2020 SHIFTING
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 28.70 50.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Dy50CR/10 NPP-25 350 0.00 77.00 51.00 26.00 77.00 161.29 200.50 7/10/2020 - DRILLING IN PROGRESS
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 77.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA03 / 270° /
UCD 60-1 -24° 125 71.50 94.50 0.00 12.95 10.05 23.00 212.90 192.9 7/7/2020 - DRILLING; HARD FM.; H/L 2 TIMES

UCD 60-2 KMA04 / +10° 85 0.00 47.00 10.20 27.00 9.80 47.00 28.57 47 7/10/2020 - DRILLING IN PROGRESS; HARD FM.; 2 TIMES H/L
Sub Total - 70.00 0.00
AGUCHA UG
Location - North
UDD-330 105 CV SBH No. 16.00 34.00 9.00 9.00 18.00 0 64.52 34 7/2/2020 - DRILLING; ROD GUIDE DAMAGED, NEW GUIDE SHIFT FROM SURFACE
56
Sub Total - 18.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm 121.50 132.00 10.50 0.00 10.50 0 161.29 72 6/22/2020 - HQ DRILLING; 50% W/LOSS IN BH
Sub Total - 10.50 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 20 354.10 381.10 11.80 15.20 27 200 126.1 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 27.00 200.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 10-07-20 10-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SIJUA COLLIERY WORK

BH 01 0.00 PARTIAL MACHINE ASSEMBLY DONE

Sub Total - 0.00 0.00


NGRI KOYNA
REMOVED COMPLETE ROPE OF WIRELINE WINCH; INTERCHANGE SMALL
DYNA 350 KBH-10-R 1500 983.60 983.60 0.00 0.00 0.00 248 161.29 129 1/22/2020 - JOINTS WITH LONG ROPE TO REDUCE NUMBER OF JOINTS; DRILLING
RESUMED
Sub Total - 0.00 248.00
DATE: 10-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 10-07-20 10-07-20 ment Closure
(m) (m)
PATRATU
NQ DRILLING CONTINUES THROUGH FRACTURED COAL AND HARD SHALE FM
Dy(175/3) BH - 05 1000 879.00 891.00 7.00 5.00 12.00 250 64.52 139 5/22/2020 - WITH FREQUENT BLOCKAGE
Sub Total - 12.00 250.00
KHARKHAREE
CDR-1000 0.00 0.00 0.00 0.00 0.00 40 48.39 109.65 - - RIG SHIFTED TO BASTACOLLA CAMP
LY-44 MAKH-29-P-18 300 233.50 258.00 13.50 11.00 24.50 90 80.65 232.50 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 21 M HQ CASING RETRIEVED BY UNSCREWING

KDR 750/03 MAKH-28-P-16 440 376.50 397.00 12.00 8.50 20.50 150 141.94 322.00 6/29/2020 - DRILLING IN PROGRESS; PROGRESS POOR DUE TO HIGHLY BROKEN FM.

Di - 8 MAKH-27-P-27 690 573.00 610.00 19.00 18.00 37.00 185 161.29 375.80 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 82.00 505.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 58.05 113.40 29.25 26.10 55.35 164 209.68 154.80 7/8/2020 - 58.05 M ROD P/O AND BIT CHANGED THEN R/I; HQ DRILLING; SHALE FM.

KDR 750(02) MRKB 88/SP-5(C) 660 112.60 159.30 23.40 23.30 46.70 109 209.68 272.90 7/7/2020 - HQ DRILLING; SHALE FM.

LY 44/01 MRKB 86/SP-3(C) 660 499.00 519.10 9.10 11.00 20.10 89 161.29 176.50 6/9/2020 - NQ DRILLING; SHALE FM.
Sub Total - 122.15 362.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 738.9 771.3 15.90 16.50 32.40 206 129.03 272.90 3/2/2020 - NQ DRILLING; HARD SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 358 376 8.00 10.00 18.00 138 64.52 35.00 6/16/2020 - NQ DRILLING; COAL

HQ DRILLING; SHALE TO FRACTURED SHALE FM.; PROG. POOR DUE TO


Rig 1 LY-44/01 MABD-92 /P-81 400 83.2 102.2 10.00 9.00 19.00 116 105.00 102.20 7/6/2020 -
HEAVY RAIN
Rig 2 LY-44/02 MABD-90/P-90 400 359.5 359.5 0.00 0.00 0.00 40 145.16 142.00 6/17/2020 7/10/2020 BH CLOSED BY CMPDI

Rig 5 LY-44/03 MABD-91 /P-55 400 232 257 15.00 10.00 25.00 95 161.29 235.50 6/30/2020 - NQ DRILLING; SHALE TO HARD SHALE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 158 48.39 17.00 3/16/2020 Redrill HQ NONCORING REDRILLING; SHALE AND SAND FM.
BH CAVING AND WASHED; 27/8 ROD LOWERED UPTO 96.90 M BUT CUTTING
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 68 90.00 0.00 4/25/2019 Redrill NOT WASHED PROPERLY AND EXPERIENCED CONTINUOUS BLOCKAGE AND
TORQUE SO ROD CHANGED TO HQ; SHALE, SAND FM.
Sub Total - 94.40 821.00
HAMIRPUR
DY50CR/04 0.00 0.00 0.00 0.00 66.67 0 - - DISCUSSION WITH PVT. LAND OWNER FOR BH POINT UNSUCCESSFUL
DY50CR/05 GLT-08 0.00 14.00 14.00 0.00 14.00 40 66.67 14 7/10/2020 - RIG SET AND WATER ARRANGEMENTS DONE; DRILLING
LY-44 GLT-7 13.50 18.50 5.00 0.00 5.00 25 60.00 18.5 7/6/2020 - HW LINER REAMING; DRILLING IN PROGRESS
Sub Total - 19.00 65.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0 BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 10-07-20 10-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 18.00 28.30 10.30 0.00 10.30 28.3 7/7/2020 7/10/2020 BH CLOSED

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 16.13 0 - - MATERIALS BEING SHIFTED

Rig 6 - Dyna -
KIOM/68/38 11.00 29.40 18.40 0.00 18.40 50 32.26 91.2 7/9/2020 7/10/2020 BH CLOSED
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 28.70 50.00
SOMAVARAM
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - CULTIVATION WORK HAS STARTED
Dy50CR/10 NPP-25 350 0.00 77.00 51.00 26.00 77.00 161.29 200.50 7/10/2020 - DRILLING IN PROGRESS
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
LAND OWNERS NOT AGREEING TO GIVE LAND FOR DRILLING AS
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
CULTIVATION WORK HAS STARTED
Sub Total - 77.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA03 / 270° /
UCD 60-1 -24° 125 71.50 94.50 0.00 12.95 10.05 23.00 212.90 192.9 7/7/2020 - DRILLING; HARD FM.; H/L 2 TIMES

SITE SETUP DONE; MAST SUPPORT DONE; 2 TIMES H/L FOR BIT CHANGE;
UCD 60-2 KMA04 / +10° 85 0.00 47.00 10.20 27.00 9.80 47.00 28.57 47 7/10/2020 - DRILLING IN PROGRESS
Sub Total - 70.00 0.00
AGUCHA UG
Location - North
UDD-330 105 CV SBH No. 16.00 34.00 9.00 9.00 18.00 0 64.52 34 7/2/2020 - DRILLING; ALL RODS P/O AND SURVEY DONE
56
Sub Total - 18.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm
121.50 132.00 10.50 0.00 10.50 0 161.29 72 6/22/2020 - 10 M CEMENT CUTTING; 100% W/ RETURN; HQ DRILLING IN PROGRESS
Sub Total - 10.50 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 20 354.10 381.10 11.80 15.20 27 200 126.1 6/19/2020 - DRILLING IN PROGRESS
Q)
Sub Total - 27.00 200.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 10-07-20 10-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SIJUA COLLIERY WORK

BH 01 0.00 PARTIAL MACHINE ASSEMBLY DONE

Sub Total - 0.00 0.00


NGRI KOYNA
INNER TUBE REMOVED FROM BARREL; MATER COUPLING DAMAGED AND
REPLACED; ONE HQ ROD CRACKED VERTICALLY; R/I 128 PAIRS HQ PIPES
DYNA 350 KBH-10-R 1500 983.60 983.60 0.00 0.00 0.00 248 161.29 129 1/22/2020 - WITH BARREL; R/I 30 PAIRS HQ STRINGS; DUE TO HEAVY RAINFALL AND
FOGGY CONDITION, NIGHT WOK WAS NOT POSSIBLE
Sub Total - 0.00 248.00
DATE: 09-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 09-07-20 09-07-20 ment Closure
(m) (m)
PATRATU

P/O, P/D CPMPLETED; BH WASHED DUE TO CAVING; NQ DRILLING THROUGH


Dy(175/3) BH - 05 1000 877.00 879.00 0.00 2.00 2.00 240 58.06 127 5/22/2020 -
FRACTURED FM. WITH FREQUENT BLOCKAGE AN JAMMING TENDENCY

Sub Total - 2.00 240.00


KHARKHAREE
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 43.55 109.65 6/12/2020 7/4/2020 GUARD DUTY ONLY
LY-44 MAKH-29-P-18 300 207.00 233.50 13.50 13.00 26.50 85 72.58 208.00 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 HQ CASING JAMMED; FISHING UNDERWAY

KDR 750/03 MAKH-28-P-16 440 348.50 376.50 13.00 15.00 28.00 155 127.74 301.50 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 538.00 573.00 18.00 17.00 35.00 180 145.16 338.80 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 89.50 460.00
KABITIRTHA
HQ DRILLING IN PROGRESS; PROGRESS HAMPERED DUE TO VERY HARD AND
DICD100H/1 MRKB 89/SP-7(C) 820 23.60 58.05 24.45 10.00 34.45 176 188.71 99.45 7/8/2020 -
FRACTURED SHALE FM.

KDR 750(02) MRKB 88/SP-5(C) 660 65.50 112.60 23.80 23.30 47.10 102 188.71 226.20 7/7/2020 - HQ DRILLING IN PROGRESS; SHALE FM.

DOUBLE PULLEY ARRANGEMENT DONE; NQ DRILLING; NQ DRILL ROD AND


LY 44/01 MRKB 86/SP-3(C) 660 484.60 499.00 5.40 9.00 14.40 45 145.16 156.40 6/9/2020 - EMPTY CORE BOXES SHIFTED FROM MRKB 85 TO MRKB 89; WORK STOPPED
DUE TO HEAVY RAIN
Sub Total - 95.95 323.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 712.9 738.9 15.00 11.00 26.00 162 116.13 240.50 3/2/2020 - NQ DRILLING IN PROGRESS;SANDSTONE AND SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 347 358 5.00 6.00 11.00 98 58.06 17.00 6/16/2020 - NQ DRILLING; SHEAR ZONE AND COAL FM.

HQ DRILLING; PROGRESS LOW DUE TO HEAVY RAIN; SHALE TO FRACTURED


Rig 1 LY-44/01 MABD-92 /P-81 400 65.3 83.2 7.60 10.30 17.90 109 93.33 83.20 7/6/2020 - SHALE FM.
3 M DRILLED AND BH WASHED; TARGET DEPTH ACHIEVED, DRILLING
Rig 2 LY-44/02 MABD-90/P-90 400 356.5 359.5 3.00 0.00 3.00 25 130.65 142.00 6/17/2020 - STOPPED BY GEOLOGIST; METAMORPHIC FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 206 232 13.00 13.00 26.00 95 145.16 210.50 6/30/2020 - NQ DRILLING IN PROGRESS; SHALE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 130 43.55 17.00 3/16/2020 Redrill NON CORING HQ REDRILLING; SAND, SHALE FM.
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 69 80.00 0.00 4/25/2019 Redrill 96.90 M HQ REAMING AND HW LINER LOWERED; SHALE FM.
Sub Total - 83.90 619.00
HAMIRPUR
HW LINER REAMING DONE UPTO 7 M; RIG B/D (HYD. MOTOR CHAIN
LY-44 GLT-7 10.50 13.50 3.00 0.00 3.00 15 48.00 13.5 7/6/2020
BROKEN); CHAIN CHANGED; DRILLING UNDER PROGRESS

DY50CR/04 0.00 0.00 0.00 0.00 50.00 0 DISCUSSION WITH PVT. LAND OWNER FOR NEW BH POINT UNSUCCESSFUL

DY50CR/05 0.00 0.00 0.00 0.00 0.00 50.00 0 RIG AND DRILLING MATERIALS SHIFTED AND SITE PREPARATION COMPLETE

Sub Total - 3.00 15.00


GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0
BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 09-07-20 09-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 8.00 18.00 10.00 0.00 10.00 18 7/7/2020 - DRILLING IN PROGRESS

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 14.52 0 - - MATERIALS UNDER SHIFTING

Rig 6 - Dyna -
KIOM/68/38 0.00 11.00 11.00 0.00 11.00 45 29.03 72.8 7/4/2020 7/8/2020 RIG SHIFTED TO NEW POINT AND DRILLING STARTED
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 21.00 45.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - AGREE TO GIVE THEIR LAND FOR DRILLING
Dy50CR/10 NPP-25 0.00 0.00 0.00 0.00 0.00 145.16 123.50 - - RIG AND ALL MATERIALS SHIFTED TO NPP-25; RIG SETUP DONE
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
AGREE TO GIVE THEIR LAND FOR DRILLING
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
AGREE TO GIVE THEIR LAND FOR DRILLING
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA03 / 270° /
UCD 60-1 -24° 125 34.85 71.50 16.05 11.75 8.85 36.65 193.55 169.9 7/7/2020 - 19 RUNS DRILLED; 1 HR POWERCUT; 1 TIME H/L; BIT CHANGED; HARD FM.

ELECTRICAL CONNECTIONS DONE; WATER PIPELINE CONNECTION DONE;


UCD 60-2 0.00 0.00 0.00 0.00 0.00 0.00 0 - - MACHINE SET AT 10° ANGLE; CABLE SHIFTED FROM CAMP TO MINE; CABLE
JOINED AND HUNG; CONNECTION DONE; MACHINE TESTED OK

Sub Total - 36.65 0.00


AGUCHA UG
Location - North
AIR HOSE CONNECTED AND DRILLING STARTED; PROGRESS LOW DUE TO
UDD-330 105 CV SBH No. 3.50 16.00 6.50 6.00 12.50 0 58.06 16 7/2/2020 - COMPRESSOR OVERHEATING
56
Sub Total - 12.50 0.00
AGUCHA SUR PF

Surface to -180- 10 M CEMENT CUTTING; 100% W/RETURN; HQ DRILLING STARTED BUT


DIMP-175 96 mm
119.00 121.50 2.50 0.00 2.50 0 145.16 61.5 6/22/2020 - AGAIN 100% W/LOSS AT 121.50 M DEPTH; TAKING TORQUE SO ALL RODS
P/O AND BOTTOM 5 M CEMENTED
Sub Total - 2.50 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 09-07-20 09-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)

DD20ZWE272(N 16 M DRILLING DONE; R/I OS BARREL, FRACTURED GROUND SO SHORT


KDR-1200/02 Q) 20 338.10 354.10 11.50 4.50 16 350 99.1 6/19/2020 - RUNS TAKEN; CORING; TRIPPING DUE TO BIT CHANGE
Sub Total - 16.00 350.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 09-07-20 09-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
TSL DHANBAD
MANPOWER ENGAGED IN SHIFTING DRILLING ACCESSORIES FROM
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0
BHELATAND OLD SITE TO BASTACOLLA

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA

HQ DRILLING DONE, THEN OBSERVED PUMP BLOCKAGE; TRIED TO RELEASE


BUT FAILED AND WIRELINE ROPE BROKE; WIRELINE ROPE REJOINED; TRIED
DYNA 350 KBH-10-R 1500 967.10 983.60 16.50 0.00 16.50 248 145.16 129 1/22/2020 - TO RETRIEVE INNER TUBE BUT UNSUCCESSFUL; COMPLETE HQ STRINGS P/O
AND OBSERVED THAT BARREL AND INNER TUBE STUCK IN CRITICAL
SITUATION; TRYING TO RELEASE

Sub Total - 16.50 248.00


DATE: 08-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 08-07-20 08-07-20 ment Closure
(m) (m)
PATRATU
BH WASHED 2 TIMES DUE TO CAVING; NQ DRILLING CONTINUES THROUGH
Dy(175/3) BH - 05 1000 870.00 877.00 6.00 1.00 7.00 160 51.61 125 5/22/2020 - FRACTURED FM. WITH FREQUENT BLOCKAGE
Sub Total - 7.00 160.00
KHARKHAREE
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 38.71 109.65 6/12/2020 7/4/2020 GUARD DUTY ONLY
LY-44 MAKH-29-P-18 300 184.50 207.00 11.00 11.50 22.50 85 64.52 181.50 6/30/2020 - DRILLING IN PROGRESS
FISHING SUCCESSFUL; NQ RELEASED FROM 311 M AND P/O; HQ CASING
KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 55 0.00 0.60 6/5/2020 7/1/2020 JAMMED; TRIED TO RELEASE BUT UNSUCCESSFUL
KDR 750/03 MAKH-28-P-16 440 313.50 348.50 17.00 18.00 35.00 160 113.55 273.50 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 499.50 538.00 21.00 17.50 38.50 180 129.03 303.80 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 96.00 480.00
KABITIRTHA
RIG SETTING AND SITE PREPARATION DONE; 114 MM DIA DRILLING; 12 M
DICD100H/1 MRKB 89/SP-7(C) 820 0.00 23.60 0.00 23.60 23.60 95 167.74 65.00 7/8/2020 -
HW LINER LOWERED; HQ DRILLING; SHALE FM.

KDR 750(02) MRKB 88/SP-5(C) 660 20.00 65.50 23.20 22.30 45.50 121 167.74 179.10 7/7/2020 - HQ DRILLING IN PROGRESS; SHALE FM.

LY 44/01 MRKB 86/SP-3(C) 660 463.10 484.60 12.50 9.00 21.50 103 129.03 142.00 6/9/2020 - CONTROL VALVE CHANGED AND HYD. OIL LEAKAGE REPAIRED; NQ DRILLING;
SHALE TO HARD SHALE FM.
Sub Total - 90.60 319.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 681.4 712.9 16.50 15.00 31.50 172 103.23 214.50 3/2/2020 - NQ DRILLING IN PROGRESS;SAND AND SANDSTONE FM.
HQ INNER TUBE RELEASED; NQ ROD LOWERED & LANDING RING STABILIZER
RIG 4 DI-17/01 MABD-89 /P-80 450 343 347 0.00 4.00 4.00 84 51.61 6.00 6/16/2020 - CUTTING; BH WASHED; NQ ROD P/O; NQ ROD LOWERED; DRILLING;
SHEARZONE AND COAL FM.

Rig 1 LY-44/01 MABD-92 /P-81 400 50.8 65.3 8.00 6.50 14.50 103 81.67 65.30 7/6/2020 - HQ DRILLING IN PROGRESS; FRACTURED SHALE TO HARD SHALE FM.

Rig 2 LY-44/02 MABD-90/P-90 400 356.5 356.5 0.00 0.00 0.00 116.13 139.00 6/17/2020 - TARGET DEPTH ACHIEVED; DRILLING STOPPED BY GEOLOGIST

Rig 5 LY-44/03 MABD-91 /P-55 400 176.5 206 15.00 14.50 29.50 105 129.03 184.50 6/30/2020 - NQ DRILLING IN PROGRESS; SHALE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 158 38.71 17.00 3/16/2020 Redrill NON CORING HQ REDILLING; SHALE FM.
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 136 70.00 0.00 4/25/2019 Redrill NON CORING HQ REDRILLING; SAND FM.
Sub Total - 79.50 622.00
HAMIRPUR
DRILLING IN PROGRESS; HEAVY RAINFALL HINDERED PROGRESS; MUD PUMP
LY-44 GLT-7 6.50 10.50 4.00 0.00 4.00 25 36.00 10.5 7/6/2020
UNDER REPAIR

DY50CR/04 0.00 0.00 0.00 0.00 33.33 0 DISCUSSION WITH PVT. LAND OWNER FOR NEW BH POINT UNSUCCESSFUL

DY50CR/05 0.00 0.00 0.00 0.00 0.00 33.33 0 DISCUSSION WITH PVT. LAND OWNER FOR NEW BH POINT SUCCESSFUL; RIG
BEING SHIFTED FROM FARSI TO GALOTE SITE
Sub Total - 4.00 25.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0
BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 08-07-20 08-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 2.00 8.00 6.00 0.00 6.00 8 7/7/2020 - DRILLING IN PROGRESS

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 12.90 0 - - MATERIALS UNDER SHIFTING

Rig 6 - Dyna -
KIOM/66/44 33.30 33.30 0.00 0.00 0.00 10 25.81 61.8 7/4/2020 7/8/2020 BH MEASURED AND CLOSED
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 6.00 10.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - AGREE TO GIVE THEIR LAND FOR DRILLING
SHIFTING OF RIG AND MATERIALS IN PROGRESS; NEGOTIATION FOR BH NPP-
Dy50CR/10 NPP-25 0.00 0.00 0.00 0.00 0.00 129.03 123.50 - - 25 DONE
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - AGREE TO GIVE THEIR LAND FOR DRILLING
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - AGREE TO GIVE THEIR LAND FOR DRILLING
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
KMA03 / 270° /
UCD 60-1 125 2.75 34.85 12.00 12.55 7.55 32.10 174.19 133.25 7/7/2020 - 17 RUNS DRILLED; 1 HR POWERCUT; H/L AS CORE LEFT IN BARREL; HARD FM.
-24°
RIG SHIFTED TO POINT; MUCKING IN DRIVE; 2 SHIFTS OFF DUE TO JOB
UCD 60-2 0.00 0.00 0.00 0.00 0.00 0.00 0 - -
TRAINING
Sub Total - 32.10 0.00
AGUCHA UG
Location - North
TOWING HOOK MODIFIED AND TRIED AT SURFACE; PLAN RECEIVED AND
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 51.61 3.5 7/2/2020 -
COMPRESSOR SHIFTED TO UG CV-105
56
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- 30 M CEMENT CUTTING; 100% W/RETURN; HQ DRILLING STARTED BUT
DIMP-175 96 mm
109.00 119.00 10.00 0.00 10.00 0 129.03 59 6/22/2020 -
AGAIN 100% W/LOSS AT 118.50 M DEPTH; BOTTOM 10 M CEMENTED
Sub Total - 10.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N 13.80 M DRILLING DONE; R/I OS BARREL, FRACTURED GROUND SO SHORT
KDR-1200/02 20 324.30 338.10 8.30 5.50 13.8 400 83.1 6/19/2020 -
Q) RUNS TAKEN; CORING
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 08-07-20 08-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
Sub Total - 13.80 400.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 08-07-20 08-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
TSL DHANBAD
MANPOWER ENGAGED IN SHIFTING DRILLING ACCESSORIES FROM
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0
BHELATAND OLD SITE TO BHELATAND NEW SITE

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA
COMPLETE HQ STRING P/O; AS CORE SLIPPED IN BARREL, MAXIMUM
PORTION OF LAST CORE WAS GROUND AND INNER BODY OF BIT ALSO
DYNA 350 KBH-10-R 1500 962.60 967.10 0.00 4.50 4.50 285 129.03 112.5 1/22/2020 -
GROUND; BARREL CLEANED; R/I HQ STRING WITH BARREL UPTO BOTTOM;
BH WASHED; HQ DRILLING RESUMED
Sub Total - 4.50 285.00
DATE: 07-07-20

Starting Closing Target Progress Date of


Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO Depth Depth HSD Commence SITE UPDATES REMARKS
(m) (m) (m) I II III total 07-07-20 07-07-20 ment Closure
(m) (m)
PATRATU

NQ STRINGS LOWERED AND BH WASHED; NQ DRILLING RECOMMENCED


Dy(175/3) BH - 05 1000 863.00 870.00 0.00 7.00 7.00 220 45.16 118 5/22/2020 -
THROUGH FRACTURED FM. WITH FREQUENT BLOCKAGE

Sub Total - 7.00 220.00


KHARKHAREE
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 33.87 109.65 6/12/2020 7/4/2020 ALL RODS AND CASING DISMANTLED AND SHIFTED TO MAIN CAMP
LY-44 MAKH-29-P-18 300 163.00 184.50 11.50 10.00 21.50 80 56.45 159.00 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 50 0.00 0.60 6/5/2020 7/1/2020 FISHING CONTINUES

KDR 750/03 MAKH-28-P-16 440 276.50 313.50 18.00 19.00 37.00 155 99.35 238.50 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 454.00 499.50 24.50 21.00 45.50 190 112.90 265.30 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 104.00 475.00
KABITIRTHA

DICD100H/1 MRKB 89/SP-7(C) 820 0.00 0.00 0.00 0.00 0.00 32 146.77 41.40 - - RIG AND MATERIALS SHIOFTED TO NEW BH SP-07 WITH GREAT DIFFICULTY

RIG AND MATERIALS SHIFTED TO NEW POINT; SITE PREPARATION


KDR 750(02) MRKB 88/SP-5(C) 660 0.00 20.00 0.00 20.00 20.00 64 146.77 133.60 7/7/2020 - COMPLETE; 15 M HW LINER LOWERED IN HOLE; HQ DRILLING STARTED;
SHALE FM.
CONTROL VALVE CHANGED AND HYD. OIL LEAKAGE REPAIRED; NQ DRILLING;
LY 44/01 MRKB 86/SP-3(C) 660 450.10 463.10 4.50 8.50 13.00 59 112.90 120.50 6/9/2020 -
SHALE TO HARD SHALE FM.
Sub Total - 33.00 155.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 648.9 681.4 16.90 15.60 32.50 182 90.32 183.00 3/2/2020 - NQ DRILLING IN PROGRESS;SAND AND SHALE FM.
332 M NQ ROD LOWERED AND BH WASHED; NQ P/O; HQ ROD LOWERED
RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 30 45.16 2.00 6/16/2020 - AND CONNECTED; RELEASER TOOLS LOWERED ND CONNECTED BUT SLIPPED
2 TIMES; SHEAR ZONE FM.
HQ DRILLING IN PROGRESS; SANDY SHALE TO HARD SHALE FM.; PROGRESS
Rig 1 LY-44/01 MABD-92 /P-81 400 32.4 50.8 9.40 9.00 105 70.00 50.80 7/6/2020 -
LOW DUE TO RAIN
NQ DRILLING IN PROGRESS; SANDY SHALE TO COAL, SHALE FM.; PROGRESS
Rig 2 LY-44/02 MABD-90/P-90 400 335.5 356.5 9.50 11.50 21.00 100 101.61 139.00 6/17/2020 -
LOW DUE TO HEAVY RAIN

Rig 5 LY-44/03 MABD-91 /P-55 400 148.5 176.5 17.00 11.00 28.00 105 112.90 155.00 6/30/2020 - NQ DRILLING IN PROGRESS; SAND,SHALE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 152 33.87 17.00 3/16/2020 Redrill NON CORING HQ REDILLING; SHALE FM.
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 0.00 68 60.00 0.00 4/25/2019 Redrill NON CORING HQ REDRILLING; SAND TO SANDY SHALE FM.
Sub Total - 81.50 674.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 07-07-20 07-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
HAMIRPUR

3 M PX CASING INSERTED; HQ ARRANGED AND DRILLING DONE; RIG B/D


LY-44 3.00 6.50 3.50 0.00 3.50 20 24.00 6.5 7/6/2020 AND REPAIRED; DRILLING;MUD PUMP UNDER REPAIRING; HEAVY RAINFALL.

DY50CR/04 0.00 0.00 0.00 0.00 16.67 0 DISCUSSION WITH PVT. LAND OWNER FOR NEW BH POINT UNSUCCESSFUL

DY50CR/05 0.00 0.00 0.00 0.00 0.00 16.67 0 DISCUSSION WITH PVT. LAND OWNER FOR NEW BH POINT UNSUCCESSFUL
Sub Total - 3.50 20.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE BH POINTS; NO FURTHER
DY 35/01 0 0 0 0 0.00 0 BH POINTS PROVIDED BY GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/67/39 0.00 2.00 2.00 0.00 2.00 2 7/7/2020 - RIG SET; DRILLING IN PROGRESS

SHIFTING FROM ONE HILL TO ANOTHER; SHIFTING HAMPERED DUE TO


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 11.29 0 - -
HEAVY RAIN
Rig 6 - Dyna -
KIOM/66/44 19.30 33.30 14.00 0.00 14.00 50 22.58 61.8 7/4/2020 - DRILLING IN PROGRESS
50H

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 16.00 60.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
AGREE TO GIVE THEIR LAND FOR DRILLING
RIG AND MATERIALS SHIFTED FROM BH TO ROADSIDE; ALL CORE BOXES
Dy50CR/10 SP-07 300 349.00 349.00 0.00 0.00 0.00 112.90 123.50 6/25/2020 7/6/2020 SHIFTED TO MECL OFFICE; 2 NEW BH POINTS SHOWN; NEGOTIATION FOR
LAND IN PROCESS
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - AGREE TO GIVE THEIR LAND FOR DRILLING
RIG IDLE AT CAMP AS CULTIVATION STARTED AND LANDOWNERS DID NOT
Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - -
AGREE TO GIVE THEIR LAND FOR DRILLING
Sub Total - 0.00 0.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT SHIFT Day upto upto Date of
BH NO (m) Depth Depth I II III total HSD 07-07-20 07-07-20 Commence Closure SITE UPDATES REMARKS
(m) (m) ment
(m) (m)
HZL KAYAD
UCD 40
KMA02 / 270° /
UCD 60-1 125 122.15 125.25 0.00 3.10 3.10 0 154.84 101.15 6/29/2020 7/7/2020 DRILLING; 1 RUN;BH CLOSED; ALL RODS HOISTED
-42°
KMA03 / 270° /
UCD 60-1 125 0.00 2.75 0.00 0.00 2.75 7/7/2020 - RIG ALLIGNMENT SET; SUPPORTING DONE; DRILLING; 1 RUN; HARD FM.
-24°

PERMISSION GIVEN FOR ENTRY INTO MINE PREMISES; RIG AND MATERIALS
SHIFTED TO MINE PREMISES; MATERIALS LOADED IN LHD AND
UCD 60-2 0.00 0.00 0.00 0.00 0.00 0 - -
TRANSFERRED TO N400 POCKET AND STACKED PROPERLY; MUCKING 2
BUCKETS IN DRILLING POCKET, BUT STILL NOT CLEARED
Sub Total - 3.10 0.00 154.84
AGUCHA UG
Location - North
COMPRESSOR NOT BEING ABLE TO BE TOWED BY VOLVO; NEED TO MODIFY
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 45.16 3.5 7/2/2020 - TOWING HOOK ACCORDING TO VOLVO
56
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- HQ LOWERED UPTO BOTTOM BUT FOUND COMPLETE CEMENT LOSS; 1 M
DIMP-175 96 mm
108.00 109.00 1.00 0.00 1.00 0 112.90 49 6/22/2020 -
HQ DRILLING THEN AGAIN CEMENTING
Sub Total - 1.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE HOLE JOBS HAVE BEEN
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE
Sub Total - 0.00 0.00
TDMA ZAWAR
DD20ZWE272(N 6.30 M DRILLING DONE; MDD; P/O MOTOR;R/I FLEXI; REAMING AND
KDR-1200/02 20 318.00 324.30 6.00 0.30 6.3 400 69.3 6/19/2020 -
Q) SURVEY DONE; P/O FLEXI
Sub Total - 6.30 400.00
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN BASTACOLLA

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA
RIG MUD PUMP AND SUPPLY PUMP REPAIRED; SUPPLY PUMP SHIFTED DUE
DYNA 350 KBH-10-R 1500 940.10 962.60 7.50 15.00 22.50 270 112.90 108 1/22/2020 - TO HEAVY RAIN; HQ DRILLING; BUT IN LAST RUN CORE SLIPPED IN BARREL,
SO NEEDED TO BE P/O
Sub Total - 22.50 270.00
DATE: 06-07-20
Target Progress
Starting Closing Date of
Rig Type BH NO T.D. SHIFT SHIFT Day total upto upto
Depth Depth SHIFT I HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 06-07-20 06-07-20
(m) (m) ment
(m) (m)
PATRATU

NQ DRILLING IN PROGRESS; DRILLING CONTINUES


Dy(175/3) BH - 05 1000 852.00 863.00 10.00 1.00 11.00 210 38.71 111 5/22/2020 - THROUGH LOOSE AND FRACTURE FM. WITH
FREQUENT BLOCKAGES; P/O FOR BIT CHECKING

Sub Total - 11.00 210.00


KHARKHAREE
ALL HQ CASING AND HW LINER RELEASED; RIG
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 90 29.03 109.65 6/12/2020 7/4/2020
SHIFTED TO MAHUDA PETROL PUMP
DRILLING IN PROGRESS; HQ CASING EXTENDED TO
LY-44 MAKH-29-P-18 300 145.50 163.00 9.00 8.50 17.50 80 48.39 137.50 6/30/2020 -
154.50 M.

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 40 0.00 0.60 6/5/2020 7/1/2020 FISHING CONTINUES

KDR 750/03 MAKH-28-P-16 440 247.50 276.50 15.50 13.50 29.00 150 85.16 201.50 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 409.50 454.00 24.00 20.50 44.50 185 96.77 219.80 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 91.00 545.00
KABITIRTHA
740 M NQ DRILL ROD, 220 M HQ DRILL ROD, 12 M
DICD100H/1 MRKB 85/SP-6(C) 730 740.00 740.00 0.00 0.00 0.00 60 125.81 41.40 6/1/2020 7/5/2020
HW LINER DISMANTLED;
ALL DRILL MATERIALS AND RIG SHIFTED TO BASE
KDR 750(02) MRKB 88/SP-5(C) 660 0.00 0.00 0.00 0.00 0.00 20 125.81 113.60 - -
CAMP

LY 44/01 MRKB 86/SP-3(C) 660 431.10 450.10 9.00 10.00 19.00 77 96.77 107.50 6/9/2020 - MAIN WINCH PULLEY FITTED; NQ DRILLING IN
PROGRESS; SHALE TO HARD SHALE FM.
Sub Total - 19.00 157.00
BADAM

RIG 3 100H/03 MABD-77/P-76 900 617.6 648.9 16.30 15.00 31.30 162 77.42 150.50 3/2/2020 - NQ DRILLING IN PROGRESS;SAND AND SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 52 38.71 2.00 6/16/2020 - DUE TO FISHING, 6 M HQ ROD UNSCREWED

HQ DRILLING IN PROGRESS; SAND TO SANDY


Rig 1 LY-44/01 MABD-92 /P-81 400 11 32.4 11.40 10.00 110 58.33 32.40 - -
SHALE FM.
NQ DRILLING IN PROGRESS; SANDY SHALE TO
Rig 2 LY-44/02 MABD-90/P-90 400 313.5 335.5 13.50 8.50 22.00 90 87.10 118.00 6/17/2020 -
SHALE FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 129.5 148.5 10.50 8.50 19.00 90 96.77 127.00 6/30/2020 - NQ DRILLING IN PROGRESS; SHALE FM.

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 152 29.03 17.00 3/16/2020 Redrill NON CORING HQ REDILLING; COAL AND SHALE FM.

Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 0.00 50.00 0.00 4/25/2019 Redrill UNDER NEGOTIATION WITH LAND OWNER
Sub Total - 72.30 656.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 06-07-20 06-07-20
(m) (m) ment
(m) (m)
HAMIRPUR
GALOTE SITE: RIG SET AND WATER
LY-44 0.00 3.00 3.00 0.00 3.00 10 12.5 3 7/6/2020 ARRANGEMENTS DONE; DRILLING STARTED AFTER
6 PM
DISCUSSION WITH PVT. LAND OWNER FOR NEW
BH POINT UNSUCCESSFUL
FARSI SITE: DISCUSSION WITH PVT. LAND OWNER
0.00
FOR NEW BH POINT UNSUCCESSFUL
Sub Total - 3.00 10.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING HAMPERED DUE TO HEAVY RAIN

SHIFTING FROM ONE HILL TO ANOTHER; SHIFTING


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 9.68 0 - -
HAMPERED DUE TO HEAVY RAIN

Rig 6 - Dyna - 50H KIOM/66/44 8.20 19.30 11.10 0.00 11.10 40 19.35 47.8 7/4/2020 - DRILLING IN PROGRESS

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 11.10 40.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

AS PER INSTRUCTION BH CLOSED; ALL NQ RODS,


Dy50CR/10 SP-07 300 349.00 349.00 0.00 0.00 0.00 19 96.77 123.50 6/25/2020 7/6/2020 HQ CASING, HW LINER P/O; WAITING FOR MECL
DECISION

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 0.00 19.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 06-07-20 06-07-20
(m) (m) ment
(m) (m)
HZL KAYAD
UCD 40

UCD 60-1 KMA02 / 270° / 125 98.10 122.15 0.00 9.05 15.00 24.05 0 116.13 95.3 6/29/2020 - DRILLING; 10 RUNS; HARD FM.; 1 TIME H/L FOR
-42° BIT CHANGE
Sub Total - 24.05 0.00 116.13
AGUCHA UG
Location - North
COMPRESSOR SHIFTED TO MINE PREMISES;
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 38.71 3.5 7/2/2020 -
WAITING FOR UG SHIFTING PLAN
56
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180- 7 M HQ DRILLING PROGRESS; 100% W/LOSS AT
DIMP-175 96 mm
101.00 108.00 7.00 0.00 7.00 0 96.77 48 6/22/2020 -
108 M DEPTH; BOTTOM 10 M CEMENTED
Sub Total - 7.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE

Sub Total - 0.00 0.00


TDMA ZAWAR
3 M DRILLING DONE; R/I FLEXI, REAMING AND
DD20ZWE272(N
KDR-1200/02 20 315.00 318.00 0.00 3.00 3 200 63 6/19/2020 - SURVEY, P/O FLEXI, R/I MOTOR; MOTORIZED
Q)
DIRECTIONAL DRILLING
Sub Total - 3.00 200.00
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN BASTACOLLA

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA

HQ DRILLING DONE, BUT PUMP BLOCKAGE


OBSERVED; TRIED TO RELEASE INNER TUBE BUT
DYNA 350 KBH-10-R 1500 925.10 940.10 9.00 6.00 15.00 300 96.77 85.5 1/22/2020 - FAILED; WIRELINE ROPE GOT BROKEN; P/O 420 M;
WIRELINE ROPE REJOINED; INNER TUBE RELEASED;
R/I; RESUMED DRILLING

Sub Total - 15.00 300.00


DATE: 05-07-20
Target Progress
Starting Closing Date of
Rig Type BH NO T.D. SHIFT SHIFT Day total upto upto
Depth Depth SHIFT I HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 05-07-20 05-07-20
(m) (m) ment
(m) (m)
PATRATU
Dy(175/3) BH - 05 1000 840.00 852.00 6.00 6.00 12.00 160 32.26 100 5/22/2020 - NQ DRILLING IN PROGRESS
Sub Total - 12.00 160.00
KHARKHAREE

HQ CASING JAMMED; TRIED TO RELEASE BY


FISHING BUT UNSUCCESFUL; 50 L DIESEL FLUSHED
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 110 24.19 109.65 6/12/2020 7/4/2020 IN BH AND ALLOWED TO REST; COAL CORE
EXCISION AND ALL CORE BOXES SHIFTED TO
BASTACOLLA CAMP

DRILLING IN PROGRESS; PROGRESS POOR DUE TO


LY-44 MAKH-29-P-18 300 139.50 145.50 3.00 3.00 6.00 60 40.32 120.00 6/30/2020 -
HIGHLY BROKEN FM.
BQ ROD PAIRED AND P/D UPTO 340 M AND
KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 50 0.00 0.60 6/5/2020 7/1/2020
CUTTING NQ ROD; ALL BQ P/O.
KDR 750/03 MAKH-28-P-16 440 223.50 247.50 13.50 10.50 24.00 105 70.97 172.50 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 385.50 409.50 12.00 12.00 24.00 120 80.65 175.30 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 54.00 445.00
KABITIRTHA
AFTER REMNANT DRILLING, BH CLOSED; COAL
DICD100H/1 MRKB 85/SP-6(C) 730 715.80 740.00 13.40 10.80 24.20 156 104.84 41.40 6/1/2020 7/5/2020
AND SANDSTONE FM.; 100% W/LOSS IN BH

KDR 750(02) MRKB 87/SP-2(C) 660 593.00 593.00 0.00 0.00 0.00 16 104.84 113.60 6/18/2020 7/4/2020 CORE BOXES AND NQ RODS, AFTER DISMANTLING,
SHIFTED TEO CAMP WITH VERY DIFFICULTY

NQ DRILLING; HARD SHALE FM.,RIG B/D ( MAIN


LY 44/01 MRKB 86/SP-3(C) 660 426.60 431.10 4.50 0.00 4.50 19 80.65 88.50 6/9/2020 - WINCH PULLEY DAMAGED); WORKERS ENGAGED
IN KDR SITE FOR ROD AND LINER DISMATLING

Sub Total - 28.70 191.00


BADAM
RIG 3 100H/03 MABD-77/P-76 900 605.1 605.1 0.00 0.00 0.00 64.52 106.70 3/2/2020 - WEEKLY OFF

RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 32.26 2.00 6/16/2020 - WEEKLY OFF

Rig 1 LY-44/01 MABD-92 /P-81 400 0 0 0.00 0.00 46.67 0.00 - - WEEKLY OFF

Rig 2 LY-44/02 MABD-90/P-90 400 292.5 292.5 0.00 0.00 0.00 72.58 75.00 6/17/2020 - WEEKLY OFF

Rig 5 LY-44/03 MABD-91 /P-55 400 107 107 0.00 0.00 0.00 80.65 85.50 6/30/2020 - WEEKLY OFF

Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 24.19 17.00 3/16/2020 Redrill WEEKLY OFF
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 40.00 0.00 4/25/2019 Redrill WEEKLY OFF
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 05-07-20 05-07-20
(m) (m) ment
(m) (m)
HAMIRPUR
SHIFTING AND FOUNDATION JAM COMPLETE;
LY:44 0.00 LOCAL ISSUES; STILL NEGOTIATING WITH PVT.
LANOWNER BUT UNSUCCESSFUL

0.00
Sub Total - 0.00 0.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING NOT POSSIBLE DUE TO HEAVY RAIN

SHIFTING FROM ONE HILL TO ANOTHER; SHIFTING


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 8.06 0 - -
HAMPERED DUE TO HEAVY RAIN

Rig 6 - Dyna - 50H KIOM/66/44 3.00 8.20 5.20 0.00 5.20 30 16.13 36.7 7/4/2020 - MACHINE UNDER SHIFTING

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 5.20 40.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
3 M DRILLED THEN WAITING FOR DECISION OF
Dy50CR/10 SP-07 300 346.00 349.00 3.00 0.00 3.00 12 80.65 123.50 6/25/2020 -
MECL FOR HOLE CLOSURE
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 32.26 67.50 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 3.00 12.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 05-07-20 05-07-20
(m) (m) ment
(m) (m)
HZL KAYAD
UCD 40

UCD 60-1 KMA02 / 270° / 125 98.10 98.10 0.00 0.00 0.00 0.00 0 96.77 71.25 6/29/2020 - WEEKLY OFF
-42°
Sub Total - 0.00 0.00 96.77
AGUCHA UG
Location - North COMPRESSOR SHIFTED FROM UG TO SURFACE;
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 32.26 3.5 7/2/2020 - NEW COMPRESSOR READY TO BE SHIFTED TO
56 MINE PREMISES
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm
101.00 101.00 0.00 0.00 0.00 0 80.65 41 6/22/2020 - WEEKLY OFF

Sub Total - 0.00 0.00


SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE

Sub Total - 0.00 0.00


TDMA ZAWAR
DD20ZWE272(N 8.80 M DRILLING DONE; MOTORIZED DIRECTIONAL
KDR-1200/02 20 306.20 315.00 5.80 3.00 8.8 200 60 6/19/2020 -
Q) DRILLING; MOTOR P/O
Sub Total - 8.80 200.00
TSL DHANBAD
MANPOWER ENGAGED IN SHIFTING LY: 38
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0
MACHINE

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA

HQ DRILLING DONE, BUT SUDDEN TORQUE AND


DYNA 350 KBH-10-R 1500 911.60 925.10 9.00 4.50 13.50 300 80.65 70.5 1/22/2020 - PUMP BLOCKAGE OBSERVED; TRIED TO RELEASE
INNER TUBE BUT FAILED; P/O 77 PAIRS TO
SURFACE AND R/I; RESUMED DRILLING

Sub Total - 13.50 300.00


DATE: 04-07-20
Target Progress
Starting Closing Date of
Rig Type BH NO T.D. SHIFT SHIFT Day total upto upto
Depth Depth SHIFT I HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 04-07-20 04-07-20
(m) (m) ment
(m) (m)
PATRATU
NQ DRILLING; BH WASHED; NQ DRILLING
Dy(175/3) BH - 05 1000 820.00 840.00 14.00 6.00 20.00 210 5/22/2020 - CONTINUED THROUGH FRACTURED FM. AND CLAY
ZONE
Sub Total - 20.00 210.00
KHARKHAREE
BH CLOSED BY GEOLOGIST; BH WASHED,
CDR-1000 MAKH 25-P-28 700 686.90 686.90 0.00 0.00 0.00 60 6/12/2020 7/4/2020 COMPLETE NQ RODS WITH BARREL P/O; GPL
DONE UPTO 686.90 M
LY-44 MAKH-29-P-18 300 110.00 139.50 14.50 15.00 29.50 75 6/30/2020 - DRILLING IN PROGRESS
COAL CORE EXCISION AND ALL CORE BOXES
KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 6/5/2020 7/1/2020
SHIFTED TO BASTACOLA CAMP
KDR 750/03 MAKH-28-P-16 440 188.50 223.50 20.00 15.00 35.00 155 6/29/2020 - DRILLING IN PROGRESS
Di - 8 MAKH-27-P-27 690 351.00 385.50 16.50 18.00 34.50 185 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 99.00 475.00
KABITIRTHA

44 NOS. NQ RODS SHIFTED TO LY:44 SITE; PUMP


DICD100H/1 MRKB 85/SP-6(C) 730 700.80 715.80 0.00 15.00 15.00 132 6/1/2020 - MOTOR AND CARTRIDGE FITTED AND TESTED; NQ
DRILLING; COAL FM.; 100% W/LOSS IN BH

REMNANT DRILLING DONE AND BH


KDR 750(02) MRKB 87/SP-2(C) 660 575.20 593.00 17.80 0.00 17.80 133 6/18/2020 7/4/2020 CLOSEDCOMPLETE NQ RODS, 215 M HQ RODS
AND 12 M HW LINER P/O
NQ DRILLING; HARD SHALE TO SHALE AND
LY 44/01 MRKB 86/SP-3(C) 660 402.40 426.60 13.00 11.20 24.20 94 6/9/2020 -
SANDSTONE FM.
Sub Total - 57.00 359.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 579.4 605.1 12.30 13.40 25.70 184 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 36 6/16/2020 - DUE TO FISHING, HQ ROD UNSCREWED FROM 285
M TO 320 M; SHEAR ZONE FM.

Rig 1 LY-44/01 MABD-92 /P-81 400 0 0 0.00 0.00 10 - - FOUNDATION BOLT JAM AND MACHINE SETTING
DONE

Rig 2 LY-44/02 MABD-90/P-90 400 275 292.5 9.00 8.50 17.50 90 6/17/2020 - NQ DRILLING;SAND, SANDY SHALE TO SHALE FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 65 107 22.00 20.00 42.00 125 6/30/2020 - NQ DRILLING IN PROGRESS; SAND FM.

RIG & MATERIALS SHIFTED TO SUSPENDED BH P-


Rig 6 50 - CR/08 MABD-79/P-83 600 471 471 0.00 0.00 0.00 34 3/16/2020 Redrill 83; MACHINE SETTING AND SUMP PIT CLEANING
DONE
LAND OWNER STOPPED WORK; UNDER
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 0.00 4/25/2019 Redrill
NEGOTIATION
Sub Total - 85.20 479.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 04-07-20 04-07-20
(m) (m) ment
(m) (m)
HAMIRPUR
SITE PREP. COMPLETE; RIG AND ALL MATERIALS
UNDER SHIFTING; LOCAL ISSUES; DISCUSSION
LY:44 0.00
WITH PRIVATE LAND OWNER OF NEW HOLE POINT
UNSUCCESSFUL

0.00
Sub Total - 0.00 0.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 - - SHIFTING FROM ONE HILL TO ANOTHER

SHIFTING; 1000 M TO BE SHIFTED FROM ONE HILL


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 - -
TO ANOTHER

Rig 6 - Dyna - 50H KIOM/66/44 0.00 3.00 3.00 0.00 3.00 30 7/4/2020 - MACHINE UNDER SHIFTING

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 - - OFF


Sub Total - 3.00 40.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

DRILLING IN PROGRESS; PROGRESS GREATLY


Dy50CR/10 SP-07 300 311.00 346.00 23.00 12.00 35.00 98 6/25/2020 - HAMPERED DUE TO INTERMITTENT HEAVY
RAINFALL

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 35.00 98.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 04-07-20 04-07-20
(m) (m) ment
(m) (m)
HZL KAYAD
UCD 40

UCD 60-1 KMA02 / 270° / 125 73.70 98.10 0.00 13.75 10.65 24.40 0 6/29/2020 - 10 MINS POWERCUT; 14 RUNS; 2 TIMES H/L FOR
-42° CHANGING BIT; HARD FM.
Sub Total - 24.40 0.00
AGUCHA UG
Location - North SURFACE COMPRESSOR SHIFTED FROM
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 7/2/2020 - WORKSHOP TO CAMP; HYD. OIL AND FILTER
56 CHANGED
Sub Total - 0.00 0.00
AGUCHA SUR PF
Surface to -180-
DIMP-175 96 mm
87.00 101.00 14.00 0.00 14.00 0 6/22/2020 - HQ DRILLING; HARD FM.; 20% W/LOSS IN BH

Sub Total - 14.00 0.00


SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 NO WORK DONE

Sub Total - 0.00 0.00


TDMA ZAWAR
DD20ZWE272(N
KDR-1200/02 20 300.00 306.20 3.20 3.00 6.2 200 6/19/2020 - 6.20 M DRILLING DONE
Q)
Sub Total - 6.20 200.00
TSL DHANBAD
MANPOWER ENGAGED IN SHIFTING LY: 38
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00
MACHINE

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA
AFTER REACHING BOTTOM, HQ DRILLING
DYNA 350 KBH-10-R 1500 871.10 911.60 18.00 22.50 40.50 352 1/22/2020 -
RESUMED AND DRILLED UPTO 911.60 M
Sub Total - 40.50 352.00
DATE: 03-07-20
Target Progress
Starting Closing Date of
Rig Type BH NO T.D. SHIFT SHIFT Day total upto upto
Depth Depth SHIFT I HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 03-07-20 03-07-20
(m) (m) ment
(m) (m)
PATRATU
NQ STRINGS LOWERED UPTO 802 M; NQ DRILLING
Dy(175/3) BH - 05 1000 802.00 820.00 5.00 13.00 18.00 190 19.35 68 5/22/2020 - TARGET 10TH JULY
IN PROGRESS
Sub Total - 18.00 190.00
KHARKHAREE
DRILLING IN PROGRESS; POOR PROGRESS DUE TO
CDR-1000 MAKH 25-P-28 700 657.25 686.90 18.00 11.65 29.65 255 14.52 109.65 6/12/2020 - BH CLOSED, GPL TODAY
HARD FM.
LY-44 MAKH-29-P-18 300 83.50 110.00 14.00 12.50 26.50 70 24.19 84.50 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 0.00 0.60 6/5/2020 7/1/2020 WAITING FOR FISHING TOOL CUTTER WILL REACH TODAY

KDR 750/03 MAKH-28-P-16 440 149.50 188.50 22.50 16.50 39.00 150 42.58 113.50 6/29/2020 - DRILLING IN PROGRESS

DRILLING IN PROGRESS; IN 2ND SHIFT ALL HQ ROD


Di - 8 MAKH-27-P-27 690 330.80 351.00 20.20 0.00 20.20 135 48.39 116.80 6/25/2020 - WITH BARREL P/O; HQ CASING DONE UPTO 351
M; SUMP PIT CLEANED AND NQ PAIR MADE; NQ
ROD WITH BARREL P/D TO BOTTOM

Sub Total - 115.35 610.00


KABITIRTHA

HYD. FOOT CLAMP JAWS AND CYLINDER CHANGED


AND 60 NOS DRILL ROD PAIR MADE; R/I 700.8 M
NQ DRILL ROD AND BH WASHED; TRIED TO
DICD100H/1 MRKB 85/SP-6(C) 730 700.80 700.80 0.00 0.00 0.00 48 62.90 2.20 6/1/2020 - EXTEND BH BUT WATER PUMP PRESSURE NOT NEW MOTOR SENT TODAY
DEVELOPED AND AUTOMATICALLY STOPPED; NO
WORK DONE AS MECHANIC NOT AVAILABLE ON
SITE; 100% W/LOSS IN BH

KDR 750(02) MRKB 87/SP-2(C) 660 541.00 575.20 14.80 19.40 34.20 149 62.90 95.80 6/18/2020 - NQ DRILLING IN PROGRESS; SHALE AND COAL FM. MUST CLOSE TODAY; SHIFT TO NEXT BH IN 2 DAYS

NQ DRILLING; HARD SHALE TO SHALE AND


LY 44/01 MRKB 86/SP-3(C) 660 380.90 402.40 10.00 11.50 21.50 80 48.39 59.80 6/9/2020 -
SANDSTONE FM.
Sub Total - 55.70 277.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 552 579.4 13.20 14.20 27.40 184 38.71 81.00 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.
HQ ROD UNSCREWED FROM 269 M TO 285 M;
RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 36 19.35 2.00 6/16/2020 - HOLE SHOULD BE ABANDONED, IN TALKS
SHEAR ZONE FM.
RIG, MATERIALS AND DERRICK SHIFTED TO NEW
Rig 1 LY-44/01 MABD-92 /P-81 400 0 0 0.00 0.00 10 23.33 0.00 - -
POINT P81

Rig 2 LY-44/02 MABD-90/P-90 400 255 275 11.00 9.00 20.00 100 43.55 57.50 6/17/2020 - NQ DRILLING; COAL AND SHALE FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 51 65 8.00 6.00 14.00 80 48.39 43.50 6/30/2020 - HQ DRILLING IN PROGRESS; HARD SHALE FM.

Rig 6 50 - CR/08 MABD-88 /P-82 750 606.25 606.25 0.00 0.00 0.00 50 14.52 17.00 6/10/2020 7/2/2020 HQ AND HW LINER P/O; TRACTOR TROLLEY
LOADED; MACHINE UNDER SHIFTING
REDRILLING SUSPENDED HOLE;HQ NON CORING
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 34 20.00 0.00 4/25/2019 Redrill REDRILLING; NO WORK DONE IN 2ND SHIFT DUE NON CORING STRING SHOULD BE USED
TO MANPOWER SHORTAGE
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 03-07-20 03-07-20
(m) (m) ment
(m) (m)
Sub Total - 61.40 460.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 03-07-20 03-07-20
(m) (m) ment
(m) (m)
HAMIRPUR LY:44 EXPECTED TO START BY MONDAY/TUESDAY
0.00

0.00
Sub Total - 0.00 0.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING FROM ONE HILL TO ANOTHER

SHIFTING; 1000 M TO BE SHIFTED FROM ONE HILL


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 4.84 0 - - WILL START TOMORROW
TO ANOTHER
DRILLED 1.5 M, BH CLOSED; CASING P/O AND
Rig 6 - Dyna - 50H KIOM/65/34 49.10 50.60 1.50 0.00 1.50 15 9.68 28.5 6/29/2020 7/3/2020 WILL START TODAY
SHIFTING

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 1.50 15.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

DUE TO BAD GROUND CONDITION OWING TO


RAIN, WATER SUPPLY STOPPED; REPAIRED
PIPELINE OF A LOCAL FARMER AND ARRANGED
Dy50CR/10 SP-07 300 293.00 311.00 9.00 9.00 18.00 78 48.39 85.50 6/25/2020 -
WATER; DRILLING IN PROGRESS; PROGRESS
GREATLY HAMPERED DUE TO INTERMITTENT
HEAVY RAINFALL

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 32.26 67.50 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 18.00 78.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 03-07-20 03-07-20
(m) (m) ment
(m) (m)
HZL KAYAD
UCD 40

UCD 60-1 KMA02 / 270° / 125 55.35 73.70 0.00 8.15 10.20 18.35 0 58.06 46.85 6/29/2020 - 40 MINS POWERCUT; 6 RUNS; HARD FM.
-42°
Sub Total - 18.35 0.00 58.06
AGUCHA UG
Location - North
COMPRESSOR RADIATOR DAMAGED; 2ND
UDD-330 105 CV SBH No. 3.50 3.50 0.00 0.00 0.00 0 19.35 3.5 7/2/2020 -
COMPRESSOR BEING ARRANGED FROM SURFACE
56
Sub Total - 0.00 0.00
AGUCHA SUR PF
CEMENT CUTTING; WATER RETURNED FROM HOLE
Surface to -180-
DIMP-175 96 mm
72.50 87.00 14.50 0.00 14.50 0 48.39 27 6/22/2020 - THEN HQ DRILLING STARTED; HARD FM.; 20%
W/LOSS IN BH
Sub Total - 14.50 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE

Sub Total - 0.00 0.00


TDMA ZAWAR
DD20ZWE272(N P/O BARREL, R/I MOTOR; MOTOR P/O AS NOT
KDR-1200/02 20 300.00 300.00 0.00 0.00 0 200 45 6/19/2020 -
Q) CUTTING; R/I MOTOR
Sub Total - 0.00 200.00
TSL DHANBAD

WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 MANPOWER ENGAGED IN SHIFTING LY: 38
MACHINE

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA
MAIN WINCH SEAL ARRANGED AND BROUGHT
FROM KOLHAPUR THEN INSTALLED AND FOUND
DYNA 350 KBH-10-R 1500 871.10 871.10 0.00 0.00 0.00 90 48.39 16.5 1/22/2020 -
OK; 128 PAIRS HQ STRINGS LOWERED; LOWERING
CONTINUES
Sub Total - 0.00 90.00
DATE: 02-07-20
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 02-07-20 02-07-20
(m) (m) ment
(m) (m)
PATRATU
NQ DRILLING IN PROGRESS; NQ STRINGS P/O AS
Dy(175/3) BH - 05 1000 781.00 802.00 16.00 5.00 21.00 250 12.90 50 5/22/2020 -
BIT DAMAGED
Sub Total - 21.00 250.00
KHARKHAREE
DRILLING IN PROGRESS; PROGRESS HAMPERED IN
CDR-1000 MAKH 25-P-28 700 625.75 657.25 13.50 18.00 31.50 245 9.68 80.00 6/12/2020 - 1ST SHIFT AS DRILLING WAS STOPPED DUE TO
SHORTAGE OF WATER
LY-44 MAKH-29-P-18 300 55.00 83.50 14.50 14.00 28.50 70 16.13 58.00 6/30/2020 - DRILLING IN PROGRESS

KDR 750/01 MAKH-24-P-11 470 367.50 367.50 0.00 0.00 0.00 0.00 0.60 6/5/2020 7/1/2020 WAITING FOR FISHING TOOL

HQ DRILLING; ALL HQ RODS WITH BARREL P/O; HQ


KDR 750/03 MAKH-28-P-16 440 116.50 149.50 18.00 15.00 33.00 155 28.39 74.50 6/29/2020 - CASING DONE UPTO 134.50 M; NQ DRILLING IN
PROGRESS
Di - 8 MAKH-27-P-27 690 283.70 330.80 23.40 23.70 47.10 185 32.26 96.60 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 140.10 655.00
KABITIRTHA

FUEL PUMP REPAIRED; AMC PUMP NOT WORKING


PROPERLY & BH JAMMED; TRIED TO RELEASE BUT
ROD SLIPPED AT 217.4 M DEPTH; RH TAPE
INSERTED, TRIED TO RELEASE BUT UNSUCCESFUL;
DICD100H/1 MRKB 85/SP-6(C) 730 699.80 700.80 1.00 0.00 1.00 80 41.94 2.20 6/1/2020 - ROD AGAIN SLIPPED AT 21 M FROM GL; POLYMER,
CAUSTIC SODA MIXED WITH HIGH VISCOSITY AND
RELEASED BOTH RH TAPE UPTO 217.4 M; TRIED TO
RELEASE INNER TUBE BUT UNSUCCESFUL; P/O
ANOTHER 482.6 M DRILL ROD. HYD. FOOT CLAMP
NOT WORKING PROPERLY; 100% W/LOSS IN BH

SUMP PIT CLEANED,NEW MUD MIXED; NQ


KDR 750(02) MRKB 87/SP-2(C) 660 515.50 541.00 7.20 18.30 25.50 122 41.94 61.60 6/18/2020 -
DRILLING IN PROGRESS; SHALE FM.
RD WATER SUPPLY PUMP REPAIRED; NQ DRILLING
LY 44/01 MRKB 86/SP-3(C) 660 362.10 380.90 9.50 9.30 18.80 98 32.26 38.30 6/9/2020 -
IN PROGRESS; HARD SHALE FM.
Sub Total - 45.30 300.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 526.2 552 12.60 13.20 25.80 172 25.81 53.60 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.

RIG 4 DI-17/01 MABD-89 /P-80 450 343 343 0.00 0.00 0.00 76 12.90 2.00 6/16/2020 - 26 M HQ ROD SLIPPED; HQ ROD UNSCREWED
FROM 26 M TO 269 M; SHEAR ZONE FM.

Rig 1 LY-44/01 MABD-92 /P-81 400 0 0 0.00 0.00 0.00 - - MACHINE REPAIRED AND MATERIALS UNDER
SHIFTING, MACHINE STANDBY AT CAMP

Rig 2 LY-44/02 MABD-90/P-90 400 234.5 255 9.50 11.00 20.50 90 29.03 37.50 6/17/2020 - NQ DRILLING; COAL AND SHALE FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 30.5 51 11.00 9.50 20.50 90 32.26 29.50 6/30/2020 - HQ DRILLING IN PROGRESS; SANDY SHALE FM.

BH CLOSED BY CMPDI GEOLOGIST; BH WASHED


Rig 6 50 - CR/08 MABD-88 /P-82 750 606.25 606.25 0.00 0.00 0.00 30 9.68 17.00 6/10/2020 7/2/2020
AND FOOT CLAMP REPAIRED
REDRILLING SUSPENDED HOLE; MACHINE SET AND
Rig 7 Dy-120/02 MABD-44/P-72 850 526.9 526.9 0.00 0.00 34 0.00 4/25/2019 Redrill WATER ARRANGEMENTS DONE; REDRILLING
NONCORING PX CASING DONE
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 02-07-20 02-07-20
(m) (m) ment
(m) (m)
Sub Total - 66.80 458.00
HAMIRPUR
0.00

0.00
Sub Total - 0.00 0.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING FROM ONE HILL TO ANOTHER

Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 3.23 0 - - SHIFTING; 1000 M TO BE SHIFTED FROM ONE HILL
TO ANOTHER

Rig 6 - Dyna - 50H KIOM/65/34 34.10 49.10 15.00 0.00 15.00 50 6.45 27 6/29/2020 - DRILLING IN PROGRESS

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 15.00 60.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Dy50CR/10 SP-07 300 249.50 293.00 24.00 19.50 43.50 110 0.00 6/25/2020 - DRILLING IN PROGRESS
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 32.26 67.50 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 43.50 110.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
UCD 40

POWER CUT BY SOILTECH; HARD FM.; H/L FOR BIT


UCD 60-1 KMA02 / 270° / 125 34.50 55.35 0.00 10.70 10.15 20.85 0 38.71 28.5 6/29/2020 - CHOPPING; DUE TO MACHINE SHIFTING OF
-42°
SOILTECH, FUMES IN DRIVE SO CREW LEFT EARLY

Sub Total - 20.85 0.00 38.71


AGUCHA UG
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 02-07-20 02-07-20
(m) (m) ment
(m) (m)

Location - North COMPRESSOR AND MACHINE ENGINE SERVICED;


UDD-330 105 CV SBH No. 0.00 3.50 0.00 3.50 3.50 0 12.90 3.5 7/2/2020 - SHIFT UNABLE TO ENTER MINE PREMISES DUE TO
56 UNION STRIKE
Sub Total - 3.50 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 02-07-20 02-07-20
(m) (m) ment
(m) (m)
AGUCHA SUR PF

CREW CAME LATE DUE TO UNION STRIKE; RODS


LOWERED AND CEMENT CUTTING BUT AGAIN
Surface to -180-
DIMP-175 96 mm
68.00 72.50 4.50 0.00 4.50 0 32.26 12.5 6/22/2020 - WATER LOSS AT 69.50 M DEPTH; ALL RODS AND
BARREL REMOVED AND LOWERED; BH CEMENTED
BOTTOM 6 M

Sub Total - 4.50 0.00


SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA

KDR-1200 RAE-025 L1 797.40 797.40 0.00 0.00 0.00 0 12.4 NO WORK DONE

Sub Total - 0.00 0.00


TDMA ZAWAR
DD20ZWE272(H
KDR-1200/02 20 278.80 300.00 11.00 10.20 21.2 200 45 6/19/2020 - 21.20 M DRILLING DONE; CORING
Q)
Sub Total - 21.20 200.00
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 FLANGE WELDING IN 9 SEAM

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA
P/O COMPLETED; CORE REMOVED FROM 868.10
M TO 871.10 M; OBSERVED LEAKAGE IN MAIN
DYNA 350 KBH-10-R 1500 868.10 871.10 3.00 0.00 3.00 82 32.26 16.5 1/22/2020 -
WINCH SEAL; MAST DOWN AND REMOVED
DAMAGED SEAL; RIG B/D
Sub Total - 3.00 82.00
DATE: 01-07-20
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 01-07-20 01-07-20
(m) (m) ment
(m) (m)
PATRATU
ALTERNATOR REPAIRED; NQ DRILLING IN
Dy(175/3) BH - 05 1000 752.00 781.00 15.00 14.00 29.00 250 6.45 29 5/22/2020 -
PROGRESS
Sub Total - 29.00 250.00
KHARKHAREE
CDR-1000 MAKH 25-P-28 700 577.25 625.75 27.00 21.50 48.50 270 4.84 48.50 6/12/2020 - DRILLING IN PROGRESS
LY-44 MAKH-29-P-18 300 25.50 55.00 15.00 14.50 29.50 65 8.06 29.50 6/30/2020 - DRILLING IN PROGRESS
BH CLOSED BY GEOLOGIST; ALL BQ RODS WITH
KDR 750/01 MAKH-24-P-11 470 366.90 367.50 0.60 0.00 0.60 80 0.00 0.60 6/5/2020 7/1/2020 BARREL P/O; NQ RODS JAMMED SO TRIED TO
RELEASE BY FISHING
DRILLING IN PROGRESS; HW LINER CASING
KDR 750/03 MAKH-28-P-16 440 75.00 116.50 27.00 14.50 41.50 140 14.19 41.50 6/29/2020 -
EXTENDED

ALL HQ ROD WITH BARREL P/O AS BIT DAMAGED


Di - 8 MAKH-27-P-27 690 234.20 283.70 23.20 26.30 49.50 160 16.13 49.50 6/25/2020 -
THEN R/I AND DRILLING IN PROGRESS

Sub Total - 169.60 715.00


KABITIRTHA

RIG UNDER REPAIR; DRILLING COULD NOT BE


EXTENDED; HYD. FOOT CLAMP REPAIRED; P/O
698.60 M ROD, CORE CLEANED FROM CORE
DICD100H/1 MRKB 85/SP-6(C) 730 698.60 699.80 0.00 1.20 1.20 127 20.97 1.20 6/1/2020 -
BARREL, BH WASHED AND R/I; HYD. FOOT CLAMP
NOT WORKING PROPERLY; DRILLING; FRACTURED
COAL FM.; 100% W/LOSS IN BH.

KDR 750(02) MRKB 87/SP-2(C) 660 479.40 515.50 19.50 16.60 36.10 145 20.97 36.10 6/18/2020 - NQ DRILLING; SHALE AND SANDSTONE FM.

LY 44/01 MRKB 86/SP-3(C) 660 342.60 362.10 9.50 10.00 19.50 68 16.13 19.50 6/9/2020 - NQ DRILLING; HARD SHALE FM.
Sub Total - 56.80 340.00
BADAM
RIG 3 100H/03 MABD-77/P-76 900 498.4 526.2 15.60 12.20 27.80 184 12.90 27.80 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.
H/L FOR CHANGING BIT; WHILE HQ DRILLING ROD
RIG 4 DI-17/01 MABD-89 /P-80 450 341 343 2.00 0.00 2.00 72 6.45 2.00 6/16/2020 - BROKE BUT WAS NOT RELEASED; TRYING TO FISH
OUT ; SHEAR ZONE FM.

Rig 2 LY-44/02 MABD-90/P-90 400 217.5 234.5 8.00 9.00 17.00 90 14.52 17.00 6/17/2020 - NQ DRILLING; COAL AND SHALE FM.

Rig 5 LY-44/03 MABD-91 /P-55 400 21.5 30.5 5.00 4.00 9.00 65 16.13 9.00 6/30/2020 - HQ DRILLING IN PROGRESS; HARD SHALE FM.

NQ DRILLING; 50% W/LOSS IN BH; COAL AND


Rig 6 50 - CR/08 MABD-88 /P-82 750 589.25 606.25 17.00 0.00 17.00 90 4.84 17.00 6/10/2020 - SHALE FM.; TARGET DEPTH ACHIEVED DRILLING
STOPPED BY GEOLOGIST
Sub Total - 72.80 501.00
HAMIRPUR
0.00

0.00
Sub Total - 0.00 0.00
GMRDS
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED BY
GMRDS
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 01-07-20 01-07-20
(m) (m) ment
(m) (m)
LY 38/01 0 0 0 0 0.00 0
LY 38/02 0 0 0 0 0.00 0
RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
KURMITAR

Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING FROM ONE HILL TO ANOTHER

SHIFTING; 1000 M TO BE SHIFTED FROM ONE HILL


Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 1.61 0 - -
TO ANOTHER

Rig 6 - Dyna - 50H KIOM/65/20 22.10 34.10 12.00 0.00 12.00 40 3.23 12 6/29/2020 - DRILLING IN PROGRESS

Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF


Sub Total - 12.00 50.00
SOMAVARAM
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

Dy50CR/10 SP-07 300 225.50 249.50 9.00 15.00 24.00 100 0.00 6/25/2020 - DRILLING IN PROGRESS; POOR PROGRESS DUE TO
HEAVY RAIN
RIG IDLE AT CAMP AS CULTIVATION STARTED AND
Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 16.13 24.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0.00 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 24.00 100.00
GSI MAHUDA

0.00

Sub Total - 0.00 0.00


HZL KAYAD
UCD 40
CORE BOXES SHIFTED FROM UG TO SURFACE;
UCD 60-1 KMA02 / 270° / 125 26.85 34.50 0.00 0.00 7.65 7.65 0 19.35 7.65 6/29/2020 - WATER AVAILABLE AFTER 7:30 PM; H/L FOR BIT
-42°
CHOPPING; HARD FM.
Sub Total - 7.65 0.00 19.35
AGUCHA UG
Location - North COMPRESSOR AND MACHINE ENGINE SERVICED;
UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 6.45 0 - - SHIFT UNABLE TO ENTER MINE PREMISES DUE TO
56 UNION STRIKE
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto
BH NO Depth Depth SHIFT I Day total HSD Commence Date of Closure SITE UPDATES REMARKS
(m) II III 01-07-20 01-07-20
(m) (m) ment
(m) (m)
AGUCHA SUR PF
CEMENT CUTTING; THEN HQ DRILLING STARTED
Surface to -180-
DIMP-175 96 mm
60.00 68.00 8.00 0.00 8.00 0 16.13 8 6/22/2020 - BUT AGAIN 80% TO 100% W/LOSS IN BH SO AGAIN
BOTTOM 8 M CEMENTED
Sub Total - 8.00 0.00
SKM

SKM PASTE
AS PER INSTRUCTIONS OF HZL, PASTE FILL SERVICE
DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0
HOLE JOBS HAVE BEEN STOPPED FOR COVID 19
HOLE NO-03 ]

Sub Total - 0.00 0.00


TDMA AGUCHA
NQ DRILLING IN PROGRESS; 2ND SHIFT OFF DUE
KDR-1200 RAE-025 L1 785.00 797.40 12.40 0.00 12.40 200 12.4
TO UNION STRIKE
Sub Total - 12.40 200.00
TDMA ZAWAR
DD20ZWE272(H
KDR-1200/02 20 255.00 278.80 12.00 11.80 23.8 200 23.8 6/19/2020 - 23.80 M DRILLING DONE; CORING
Q)
Sub Total - 23.80 200.00
TSL DHANBAD
WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 WAITING FOR UG FLANGE WELDING

BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA

TRIED TO SOLVE FOOT CLAMP PROBLEM BUT TO


NO AVAIL; HQ DRILLING CONTINUED BUT DURING
DYNA 350 KBH-10-R 1500 854.60 868.10 0.00 13.50 13.50 255 16.13 13.5 1/22/2020 - INNER TUBE RETRIEVAL WIRELINE ROPE BROKE;
P/O 53 PAIRS, WIRELINE ROPE JOINED BUT INNER
TUBE STUCK IN BARREL SO COMPLETE P/O
DECIDED

Sub Total - 13.50 255.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 30-06-20 30-06-20 Closure
(m) (m) ment
(m) (m)

NTPC BH CLOSED BY NTPC OFFICER; COAL& SHALE


6/30/2020 LY - 44/01 PMPT-02 110 83.50 110.00 15.00 11.50 26.50 95 150 6/26/2020 6/30/2020
KERANDARI FM.
26.50 95.00
NQ DRILLING; P/O DUE TO CORE DROP; NQ
PATRATU 6/30/2020 Dy(175/3) BH - 05 1000 747.00 752.00 2.00 3.00 5.00 210 800.00 577 5/22/2020 - STRINGS LOWERED AND DRILLING
RECOMMENCED
Sub Total - 5.00 210.00
KHARKHARI 6/30/2020 CDR-1000 MAKH 25-P-28 700 525.85 577.25 27.00 24.40 51.40 255 300.00 774.95 6/12/2020 - DRILLING IN PROGRESS
6 M HW LINER CASING DONE THEN HQ
KHARKHARI 6/30/2020 LY-44 MAKH-29-P-18 300 0.00 25.50 8.50 17.00 25.50 60 300.00 357.50 5/27/2020 -
DRILLING IN PROGRESS
BQ RODS SHIFTED AT BH POINT FROM MAIN
KHARKHARI 6/30/2020 KDR 750/01 MAKH-24-P-11 470 366.90 366.90 0.00 0.00 0.00 0 400.00 366.90 6/5/2020 - CAMP AND CHECKING THROUGH REAMER
SHELL AND BIT
KHARKHARI 6/30/2020 KDR 750/03 MAKH-28-P-16 440 29.50 75.00 26.00 19.50 45.50 140 500.00 575.50 6/15/2020 - DRILLING IN PROGRESS
ALL HQ ROD WITH BARREL P/O AS BIT
KHARKHARI 6/30/2020 Di - 8 MAKH-27-P-27 690 204.50 234.20 12.50 17.20 29.70 135 500.00 590.70 6/25/2020 - DAMAGED THEN R/I AND DRILLING IN
PROGRESS
Sub Total - 152.10 590.00

NQ DRILLING; WAITING FOR DECISION;


FAULT ZONE SO DRILLING WITH DIFFICULTY
KABITIRTHA 6/30/2020 DICD100H/1 MRKB 85/SP-6(C) 730 680.05 698.60 13.15 5.40 18.55 148 650.00 698.60 6/1/2020 -
AND JAMMING TENDENCY; 100% W/LOSS
IN BH; FRACTURED SHALE AND COAL FM.

KABITIRTHA 6/30/2020 KDR 750(02) MRKB 87/SP-2(C) 660 443.80 479.40 15.90 19.70 35.60 128 600.00 1003.30 6/18/2020 - R/I 443.8 M NQ ROD AND BH WASHED;
DRILLING; SHALE AND SANDSTONE FM.

P/O ANOTHER 177.1 M NQ ROD; SUMP PIT


CLEANED AND FRESH MUD MIXED; R/I 327.1
KABITIRTHA 6/30/2020 LY 44/01 MRKB 86/SP-3(C) 660 327.10 342.60 4.00 11.50 15.50 70 366.74 342.60 6/9/2020 -
M ROD AFTER CHANGING BIT; DRILLING;
HARD SHALE FM.
Sub Total - 69.65 346.00
BADAM 6/30/2020 RIG 3 100H/03 MABD-77/P-76 900 452.5 498.4 25.00 20.90 45.90 206 600.00 546.35 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.
HQ DRILLING IN PROGRESS; FRACTURED
BADAM 6/30/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 295.6 341 22.00 23.40 45.40 213 750.00 388.75 6/16/2020 -
SHALE, SHALE AND SANDSTONE FM.
NQ DRILLING; SAND AND SHALE FM.; SHEAR
BADAM 6/30/2020 Rig 2 LY-44/02 MABD-90/P-90 400 195 217.5 13.50 9.00 22.50 128 300.00 340.00 6/17/2020 -
ZONE ENCOUNTERED
5 M PX CASING AND 21.50 M HW LINER
BADAM 6/30/2020 Rig 5 LY-44/03 MABD-91 /P-55 400 0 21.5 10.50 11.00 21.50 85 347.50 - -
PLACED; HQ DRILLING IN PROGRESS
NQ DRILLING IN PROGRESS; SHALE, COAL
BADAM 6/30/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 573.4 589.25 8.85 7.00 15.85 158 400.00 723.65 6/10/2020 - FM.; SHEAR ZONE ENCOUNTERED; 70%
W/LOSS IN BH
Sub Total - 151.15 790.00
HAMIRPUR 6/30/2020 0.00
SIKAR 6/30/2020 0.00
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/30/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/30/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/30/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/30/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 30-06-20 30-06-20 Closure
(m) (m) ment
(m) (m)

KURMITAR 6/30/2020 Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 47.3 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/30/2020 Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 120 110.75 6/23/2020 6/27/2020 SHIFTING

Rig 6 - Dyna -
KURMITAR 6/30/2020 KIOM/65/20 11.10 22.10 11.00 0.00 11.00 50 22.1 - - DRILLING IN PROGRESS
50H

KURMITAR 6/30/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 120 77.25 6/23/2020 6/27/2020 OFF
Sub Total - 11.00 50.00
BABJA 6/30/2020 DY:50CR/11 0.00 MACHINE ARRIVED AT HO
MACHINE SHIFTED TO AMD HAMIRPUR
BABJA 6/30/2020 LY:44 0.00
PROJECT
Sub Total - 0.00 0.00

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/30/2020 DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 1000.00 548.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

SOMAVARAM 6/30/2020 Dy50CR/10 SP-07 300 180.50 225.50 30.00 15.00 45.00 115 800.00 557.50 6/25/2020 - DRILLING IN PROGRESS

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/30/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 800.00 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/30/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 800.00 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 45.00 115.00

GSI MAHUDA 6/30/2020 0.00

Sub Total - 0.00 0.00


UCD 40
HZL KAYAD KMA02 / 270° /
6/30/2020 UCD 60-1 125 8.25 26.85 0.00 9.15 9.45 18.60 0 6/11/2020 - H/L FOR BIT CHOPPING; HARD FM.
-42°
Sub Total - 18.60 0.00 0.00
COMPRESSOR SHIFTED TO 105cv; AIR HOSE
Location - North
AND WATER HOSE CONNECTED AND
AGUCHA UG 6/30/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 - -
HANGED; HAMMER OPENED AND BIT
56
CHANGED
Sub Total - 0.00 0.00
Surface to -180- 100% W/LOSS IN BH; CEMENTING DONE
AGUCHA SUR PF 6/30/2020 DIMP-175 96 mm
60.00 60.00 0.00 0.00 0.00 0 6/22/2020 -
UPTO 48 M; WOC
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/30/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 30-06-20 30-06-20 Closure
(m) (m) ment
(m) (m)

BAND CUTTING SUCCESFUL; NQ DRILLING IN


TDMA AGUCHA 6/30/2020 KDR-1200 0.00 15.00 8.00 7.00 15.00 400
PROGRESS
Sub Total - 15.00 400.00
DD20ZWE272(H
TDMA ZAWAR 6/30/2020 KDR-1200/02 20 231.00 255.00 12.00 12.00 24 400 6/19/2020 - 24 M DRILLING DONE; CORING
Q)
Sub Total - 24.00 400.00
TSL DHANBAD 6/30/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 WAITING FOR UG FLANGE WELDING

TSL DHANBAD 6/30/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00


NGRI KOYNA 6/30/2020 DYNA 350 KBH-10-R 1500 812.60 854.60 20.60 21.40 42.00 383 1/22/2020 - HQ DRILLING CONTINUED
Sub Total - 42.00 383.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 29-06-20 29-06-20 Closure
(m) (m) ment
(m) (m)

NTPC HQ DRILLING IN PROGRESS; SHALE AND


6/29/2020 LY - 44/01 PMPT-02 110 53.50 83.50 15.00 15.00 30.00 100 123.5 6/26/2020 -
KERANDARI COAL FM.
30.00 100.00
BATTERY DISCHARGED; BATTERY AND
ELECTRICIAN ARRANGED FROM BADAM SITE
PATRATU 6/29/2020 Dy(175/3) BH - 05 1000 731.00 747.00 5.00 11.00 16.00 180 773.33 572 5/22/2020 -
AND PATRATU MARKET; NQ DRILLING IN
PROGRESS.
Sub Total - 16.00 180.00
KHARKHARI 6/29/2020 CDR-1000 MAKH 25-P-28 700 479.95 525.85 24.60 21.30 45.90 255.00 290.00 723.55 6/12/2020 - DRILLING IN PROGRESS
FOUNDATION BOLT JAMMED AND DERRICK
KHARKHARI 6/29/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 290.00 332.00 5/27/2020 6/19/2020 FITTED AND PUMP SETTING DONETO
STARTD MACHINE IN P-18
BQ INNER TUBE STUCK IN BH; FISHING
KHARKHARI 6/29/2020 KDR 750/01 MAKH-24-P-11 470 366.90 366.90 0.00 0.00 0.00 40.00 386.67 366.90 6/5/2020 -
CONTINUES

RIG AND ALL MATERIALS SHIFTED TO P-16;


RIG SETTING DONE; HW LINER CASING
KHARKHARI 6/29/2020 KDR 750/03 MAKH-28-P-16 440 0.00 29.50 6.00 23.50 29.50 130.00 483.33 530.00 6/15/2020 6/27/2020
DONE UPTO 6 M; HQ DRILLING IN
PROGRESS
KHARKHARI 6/29/2020 Di - 8 MAKH-27-P-27 690 162.50 204.50 21.00 21.00 42.00 165.00 483.33 561.00 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 117.40 590.00

P/O ANOTHER 332.20 M AND R/I 662.20 M


AFTER BIT CHANGE AND BH WASHING; NQ
KABITIRTHA 6/29/2020 DICD100H/1 MRKB 85/SP-6(C) 730 662.20 680.05 2.70 15.15 17.85 144 628.33 680.05 6/1/2020 -
DRILLING; FRACTURED SHALE, COAL AND
SANDSTONE FM; 100% W/LOSS IN BH

72 M ROD R/I IN HOLE; BH WASHED; NQ


KABITIRTHA 6/29/2020 KDR 750(02) MRKB 87/SP-2(C) 660 413.80 443.80 18.00 12.00 30.00 140 580.00 967.70 6/18/2020 - DRILLING; SHALE TO FRACTURED SHALE
FM.; 443.8 M P/O AS CORE DROPPED IN
CORE BARREL

60 M DRILL ROD R/I AND BH WASHED; NQ


KABITIRTHA 6/29/2020 LY 44/01 MRKB 86/SP-3(C) 660 318.10 327.10 7.00 2.00 9.00 66 350.07 327.10 6/9/2020 - DRILLING IN PROGRESS; HARD SHALE FM.;
P/O 150 M DRILL ROD AS BIT DAMAGED;
WORK STOPPED DUE TO RAIN
Sub Total - 56.85 350.00
BADAM 6/29/2020 RIG 3 100H/03 MABD-77/P-76 900 418.5 452.5 18.50 15.50 34.00 253 580.00 500.45 3/2/2020 - NQ DRILLING IN PROGRESS; SHALE FM.
HQ DRILLING IN PROGRESS; COAL AND
BADAM 6/29/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 259.5 295.6 20.40 15.70 36.10 155 725.00 343.35 6/16/2020 -
SANDSTONE FM.
DRILLING IN PROGRESS; SAND AND SHALE
BADAM 6/29/2020 Rig 2 LY-44/02 MABD-90/P-90 400 153.5 195 25.00 16.50 41.50 150 290.00 317.50 6/17/2020 -
FM.
MACHINE AND MATERIALS SHIFTED;
BADAM 6/29/2020 Rig 5 LY-44/03 MABD-91 /P-55 400 0 0 0.00 0.00 0.00 20 326.00 - - GROUTING AND MACHINE SETTING DONE;
DRILLING TO START
NQ DRILLING IN PROGRESS; HARD SHALE
BADAM 6/29/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 552.8 573.4 11.60 9.00 20.60 154 386.67 707.80 6/10/2020 -
FM. 70% W/LOSS IN BH
Sub Total - 132.20 732.00
HAMIRPUR 6/29/2020 0.00
SIKAR 6/29/2020 0.00
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 29-06-20 29-06-20 Closure
(m) (m) ment
(m) (m)

RIG IDLE DUE TO UNAVAILABILITY OF ANY


GMRDS 6/29/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/29/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/29/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/29/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/29/2020 Rig 4 - VOL-180 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 47.3 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/29/2020 Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 116 110.75 6/23/2020 6/27/2020 SHIFTING

Rig 6 - Dyna -
KURMITAR 6/29/2020 KIOM/65/20 0.00 11.10 11.10 0.00 11.10 50 11.1 - - DRILLING IN PROGRESS
50H

KURMITAR 6/29/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 116 77.25 6/23/2020 6/27/2020 SHIFTING
Sub Total - 11.10 60.00
BABJA 6/29/2020 DY:50CR/11 0.00 MACHINE ARRIVED AT HO
MACHINE TO REACH HAMIRPUR SITE ON
BABJA 6/29/2020 LY:44 0.00
30.06.2020
Sub Total - 0.00 0.00

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/29/2020 DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 966.67 548.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

SOMAVARAM 6/29/2020 Dy50CR/10 SP-07 300 132.50 180.50 24.00 24.00 48.00 115 773.33 512.50 6/25/2020 - DRILLING IN PROGRESS

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/29/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 773.33 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/29/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 773.33 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 48.00 115.00

GSI MAHUDA 6/29/2020 0.00

Sub Total - 0.00 0.00


UCD 40 63.5

RIG SHIFTED TO NEW POINT; MACHINE SET,


HZL KAYAD KMA02 / 270° / ELECTRICAL AND WATER CONNECTIONS
6/29/2020 UCD 60-1 125 0.00 8.25 0.00 0.00 8.25 8.25 0 60.7 6/11/2020 -
-42° DONE; NAGLE SET, MAST SUPPORT DONE;
DRILLING; HARD FM.

Sub Total - 8.25 0.00 0.00 124.20


Location - North SHIFTING PLAN RECEIVED BUT VOLVO NOT
AGUCHA UG 6/29/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 203 - - COMING FOR SHIFTING; POINT MARKING
56 DONE
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 29-06-20 29-06-20 Closure
(m) (m) ment
(m) (m)

ENGINE RPM DROPPED AUTOMATICALLY IN


LOAD; FEED PUMP CHANGED AND HQ
Surface to -180-
AGUCHA SUR PF 6/29/2020 DIMP-175 96 mm
55.00 60.00 5.00 0.00 5.00 0 65.4 6/22/2020 - DRILLING DONE; 100% W/LOSS AT 60 M
DEPTH; TRIED TO FILL CRACKS BY AUS PLUG
BUT NOT SUCCEEDED

Sub Total - 5.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/29/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00


WOC; NQ LOWERED UPTO 750 M; BAND
TDMA AGUCHA 6/29/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 130 0
CUTTING IN PROGRESS
Sub Total - 0.00 130.00
DD20ZWE272(H
TDMA ZAWAR 6/29/2020 KDR-1200/02 20 207.00 231.00 12.00 12.00 24 200 231 6/19/2020 - 24 M DRILLING DONE; CORING
Q)
Sub Total - 24.00 200.00

TSL DHANBAD 6/29/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 0 RIG MAST DOWN AND SMALL ACCESSORIES
SHIFTED TO BASTACOLLA

TSL DHANBAD 6/29/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 0.00

HYD. ELBOW OF MAIN PUMP REPAIRED;


22.5 PAIR HW LOWERED TO BPTTOM, MUD
PUMPED BUT TUBE BLOCKED DUE TO RUST
NGRI KOYNA 6/29/2020 DYNA 350 KBH-10-R 1500 809.00 812.60 0.00 3.60 3.60 315 148.6 1/22/2020 - INSIDE PIPE, FAILED TO RELEASE, 79.5 PAIRS
HQ FILLED WITH MUD P/O; REMOVED
INNER TUBE AND CLEANED PROPERLY; R/I
UPTO BOTTOM; DRILLING RECOMMENCED;

Sub Total - 3.60 315.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 28-06-20 28-06-20 Closure
(m) (m) ment
(m) (m)

HW LINER REAMING AD 11 M LOWERED HQ


NTPC
6/28/2020 LY - 44/01 PMPT-02 110 35.50 53.50 6.00 12.00 18.00 82 93.5 6/26/2020 - DRILLING IN PROGRESS; VERY HARD SHALE
KERANDARI
FM.
18.00 82.00

NQ LOWERED AND BH WASHED; NQ


DRILLING; RIG OFF AFTER 2 AM AS LIGHTS
WERE OFF FOR DISCHARGED BATTERY;
PATRATU 6/28/2020 Dy(175/3) BH - 05 1000 714.00 731.00 9.00 8.00 17.00 210 746.67 556 5/22/2020 -
ALREADY INFORMED SHANTIMOY
MUKHERJEE TO SEND BATTERY AND
ELECTRICIAN

Sub Total - 17.00 210.00


KHARKHARI 6/28/2020 CDR-1000 MAKH 25-P-28 700 453.55 479.95 12.90 13.50 26.40 185.00 280.00 677.65 6/12/2020 - DRILLING IN PROGRESS
FOUNDATION MAKING FOR SETTING RIG IN
KHARKHARI 6/28/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 280.00 332.00 5/27/2020 6/19/2020
P-18
BQ INNER TUBE STUCK IN BH SO TRIED TO
KHARKHARI 6/28/2020 KDR 750/01 MAKH-24-P-11 470 366.90 366.90 0.00 0.00 0.00 30.00 373.33 366.90 6/5/2020 -
RELEASE BY FISHING

COAL CORE EXCISION AND SHIFTING CORE


BOXES TO BASTACOLA CAMP; ALL RODS
KHARKHARI 6/28/2020 KDR 750/03 MAKH-26-P-15 300 323.00 323.00 0.00 0.00 0.00 466.67 500.50 6/15/2020 6/27/2020
AND CASING DISMANTLED AND READY TO
SHIFT
KHARKHARI 6/28/2020 Di - 8 MAKH-27-P-27 690 136.00 162.50 14.50 12.00 26.50 105.00 466.67 519.00 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 52.90 320.00
NQ DRILLING; SHALE, FRACTURED SHALE,
KABITIRTHA 6/28/2020 DICD100H/1 MRKB 85/SP-6(C) 730 647.70 662.20 9.00 5.50 14.50 168 606.67 662.20 6/1/2020 - SANDSTONE FM.; POOR PROG. DUE TO
100%W/ LOSS IN BH
NQ DRILLING; SHALE FM.; 72 M DRILL ROD
KABITIRTHA 6/28/2020 KDR 750(02) MRKB 87/SP-2(C) 660 388.40 413.80 13.40 12.00 25.40 105 560.00 937.70 6/18/2020 -
P/O DUE TO JAMMING TENDENCY

NQ DRILLING; SHALE TO HARD SHALE FM.;


KABITIRTHA 6/28/2020 LY 44/01 MRKB 86/SP-3(C) 660 307.60 318.10 5.50 5.00 10.50 58 333.40 318.10 6/9/2020 - P/O 60 M ROD DUE TO JAMMING
TENDENCY
Sub Total - 50.40 331.00
BADAM 6/28/2020 RIG 3 100H/03 MABD-77/P-76 900 418.5 418.5 0.00 0.00 0.00 0 560.00 466.45 3/2/2020 - SUNDAY OFF

BADAM 6/28/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 259.5 259.5 0.00 0.00 0.00 0 700.00 307.25 6/16/2020 - SUNDAY OFF

BADAM 6/28/2020 Rig 2 LY-44/02 MABD-90/P-90 400 153.5 153.5 0.00 0.00 0.00 0 280.00 276.00 6/17/2020 - SUNDAY OFF

BADAM 6/28/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 326.00 6/1/2020 6/23/2020 SUNDAY OFF

BADAM 6/28/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 552.8 552.8 0.00 0.00 0.00 0 373.33 687.20 6/10/2020 - SUNDAY OFF
Sub Total - 0.00 0.00
HAMIRPUR 6/28/2020 0.00
SIKAR 6/28/2020 0.00
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/28/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/28/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/28/2020 LY 38/02 0 0 0 0 0.00 0
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 28-06-20 28-06-20 Closure
(m) (m) ment
(m) (m)
GMRDS 6/28/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/28/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 47.3 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/28/2020 Rig 5 - LY-38/02 KIOM/54/61 27.75 27.75 0.00 0.00 0.00 10 112 110.75 6/23/2020 6/27/2020 SHIFTING

Rig 6 - Dyna - RIG OFF FOR MANPOWER SHORTAGE; 15 L


KURMITAR 6/28/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - -
50H MOBIL TOPPED UP

KURMITAR 6/28/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 112 77.25 6/23/2020 6/27/2020 SHIFTING
Sub Total - 0.00 20.00
BABJA 6/28/2020 DY:50CR/11 0.00 MACHINE ARRIVED AT HO
MACHINE TO BE SHIFTED TO AMD
BABJA 6/28/2020 LY:44 0.00
HAMIRPUR SITE
Sub Total - 0.00 0.00

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/28/2020 DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 933.33 548.00 6/3/2020 6/21/2020 STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

AMC PUMP HEAD CHANGED; 1.60 M HW


LINER ADDED, HOLE WASHED, RESLIPPAGE
OF HW LINER; 31 M HW LINER ADDED,
SOMAVARAM 6/28/2020 Dy50CR/10 SP-07 300 125.00 132.50 4.00 3.50 7.50 47 746.67 464.50 6/25/2020 -
TOTAL CASING 47.60 M; ALL HQ STRINGS
P/O TO SURFACE; R/I HQ CASING UPTO
132.50 M WITH WASH DOWN

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/28/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 746.67 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/28/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 746.67 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 7.50 47.00

GSI MAHUDA 6/28/2020 0.00

Sub Total - 0.00 0.00


UCD 40 63.5
HZL KAYAD KMA01 / 270° /
6/28/2020 UCD 60-1 130 115.95 115.95 0.00 0.00 0.00 0.00 0 52.45 6/11/2020 - SUNDAY OFF
+25°
Sub Total - 0.00 0.00 0.00 115.95
Location - North SHIFTING PLAN RECEIVED BUT VOLVO NOT
AGUCHA UG 6/28/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 203 - - COMING FOR SHIFTING; POINT MARKING
56 DONE
Sub Total - 0.00 0.00
Surface to -180-
AGUCHA SUR PF 6/28/2020 DIMP-175 96 mm
38.00 55.00 0.00 17.00 17.00 0 26.4 6/22/2020 - HQ DRILLING IN PROGRESS
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 28-06-20 28-06-20 Closure
(m) (m) ment
(m) (m)
Sub Total - 17.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/28/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00

NQ Rods lowered upto 750 mtr for


cementing, 7 bag cement mixing in mixer
TDMA AGUCHA 6/28/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 130 0
machine. Borehole cementing upto 750 mtr
and all rods P/out. Wait for cement seting.

Sub Total - 0.00 130.00

DD20ZWE272(H 21 M DRILLING DONE; CORING; FRACTURED


TDMA ZAWAR 6/28/2020 KDR-1200/02 20 186.00 207.00 9.60 11.40 21 200 167.6 6/19/2020 -
Q) GROUND; SHORT RUNS TAKEN

Sub Total - 21.00 200.00


HOUSE KEEPING AND ELECTRICAL
TSL DHANBAD 6/28/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 0
CONNECTION DONE IN INCLINED

TSL DHANBAD 6/28/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 15.00

P/O 690 M, INNER TUBE RELEASED WITH


CORE; DURING RELEASING INNER TUBE
WIRELINE ROPE BROKE AND WAS REJOINED
NGRI KOYNA 6/28/2020 DYNA 350 KBH-10-R 1500 809.00 809.00 0.00 0.00 0.00 233 141.2 1/22/2020 - AND RELEASED CATCHER BY RELEASER; P/O
REMAINING STRING TO CHECK BIT
CONDITION; R/I UPTO 666 M BUT FOUND
HYD HOSE CRACKED, REPAIRED

Sub Total - 0.00 233.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 27-06-20 27-06-20 Closure
(m) (m) ment
(m) (m)

NTPC HQ DRILLING IN PROGRESS; VERY HARD


6/27/2020 LY - 44/01 PMPT-02 110 16.50 35.50 9.50 9.50 19.00 104 6/26/2020 -
KERANDARI SHALE FM.
19.00 104.00

NQ DRILLING;ALTERNATOR REPAIRED; NQ
PATRATU 6/27/2020 Dy(175/3) BH - 05 1000 709.00 714.00 5.00 0.00 5.00 160 5/22/2020 - STRINGS P/O DUE TO BIT DAMAGE; 348 M
LOWERED AFTER BIT CHANGE; SHALE FM.

Sub Total - 5.00 160.00


KHARKHARI 6/27/2020 CDR-1000 MAKH 25-P-28 700 406.40 453.55 22.50 24.65 47.15 255.00 6/12/2020 - DRILLING IN PROGRESS

KHARKHARI 6/27/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 15.00 5/27/2020 6/19/2020 RIG AND ALL MATERIALS SHIFTED TO P-18
FISHING DONE; BQ DRILLING STARTED AT
KHARKHARI 6/27/2020 KDR 750/01 MAKH-24-P-11 470 364.50 366.90 0.00 2.40 2.40 85.00 6/5/2020 - 364.50 M BUT BQ INNER TUBE STUCK IN BH;
TRIED TO RELEASE BUT NOT SUCCEEDED
KHARKHARI 6/27/2020 DY-120/02 0.00 0.00 0.00 0.00 0.00 20 - - RIG SHIFTED TO BADAM SITE BY TRAILER

BH CLOSED BY GEOLOGIST; COMPLETE NQ


ROD WITH BARREL P/O; COMPLETE HQ
KHARKHARI 6/27/2020 KDR 750/03 MAKH-26-P-15 300 318.50 323.00 4.50 0.00 4.50 90.00 6/15/2020 6/27/2020
CASING P/O; HW CASING RELEASED AND
P/O
KHARKHARI 6/27/2020 Di - 8 MAKH-27-P-27 690 88.50 136.00 24.00 23.50 47.50 160.00 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 101.55 625.00
NQ DRILLING; SHALE, FRACTURED SHALE,
KABITIRTHA 6/27/2020 DICD100H/1 MRKB 85/SP-6(C) 730 622.60 647.70 15.10 10.00 25.10 159 6/1/2020 - SANDSTONE FM.; POOR PROG. DUE TO
100%W/ LOSS IN BH

KABITIRTHA 6/27/2020 KDR 750(02) MRKB 87/SP-2(C) 660 343.10 388.40 21.90 23.40 45.30 163 6/18/2020 - NQ DRILLING; SHALE FM.

KABITIRTHA 6/27/2020 LY 44/01 MRKB 86/SP-3(C) 660 287.30 307.60 11.50 8.80 20.30 91 6/9/2020 - NQ DRILLING; SHALE TO HARD SHALE FM.

Sub Total - 90.70 413.00


BADAM 6/27/2020 RIG 3 100H/03 MABD-77/P-76 900 382.7 418.5 20.70 15.10 35.80 195 3/2/2020 - NQ DRILLING; SHALE FM.
HQ DRILLING; FRACTURED SHALE TO
BADAM 6/27/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 232.6 259.5 11.40 15.50 26.90 146 6/16/2020 -
SANDSTONE FM.

BADAM 6/27/2020 Rig 2 LY-44/02 MABD-90/P-90 400 136 153.5 8.50 9.00 17.50 95 6/17/2020 - NQ DRILLING; SHALE TO HARD SHALE FM.

BADAM 6/27/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 6/1/2020 6/23/2020 MATERIALS UNDER SHIFTING

BADAM 6/27/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 531.6 552.8 12.80 8.40 21.20 122 6/10/2020 - NQ DRILLING; HARD SHALE FM.
Sub Total - 101.40 558.00
HAMIRPUR 6/27/2020 0.00
SIKAR 6/27/2020 0.00

Sub Total - 0.00 0.00

SIKAR 6/27/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - PROJECT COMPLETE; RIG SHIFTING TO AMD


HAMIRPUR SITE
PROJECT COMPLETE; RIG SHIFTING TO AMD
SIKAR 6/27/2020 Dy 50CR/05 0 0 0 0 0.00 0 - -
HAMIRPUR SITE
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 27-06-20 27-06-20 Closure
(m) (m) ment
(m) (m)

RIG IDLE DUE TO UNAVAILABILITY OF ANY


GMRDS 6/27/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/27/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/27/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/27/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/27/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/27/2020 Rig 5 - LY-38/02 KIOM/54/61 27.00 27.75 0.75 0.00 0.75 10 6/23/2020 6/27/2020 BH CLOSED; ALL CASING P/O AND SHIFTING

Rig 6 - Dyna -
KURMITAR 6/27/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 - - RIG OFF FOR MANPOWER SHORTAGE
50H

KURMITAR 6/27/2020 Rig 7 - LY-38/01 KIOM/64/59 32.20 34.00 1.80 0.00 1.80 10 6/23/2020 6/27/2020 BH CLOSED; ALL CASING P/O AND SHIFTING
Sub Total - 2.55 20.00
BABJA 6/27/2020 DY:50CR/11 0.00 MACHINE TO COME TO HO ASANSOL
MACHINE TO BE SHIFTED TO AMD
BABJA 6/27/2020 LY:44 0.00
HAMIRPUR SITE
Sub Total - 0.00 0.00

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/27/2020 DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 6/3/2020 6/21/2020 STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

AMC PUMP REPAIRED; CASING AND HW


LINER ADDED; DRILLING; HW LINER SLIPPED
SOMAVARAM 6/27/2020 Dy50CR/10 SP-07 300 78.00 125.00 24.00 23.00 47.00 130 6/25/2020 -
INTO HOLE; ARRANGEMENTS FOR CASING
DONE

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/27/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/27/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 47.00 130.00

GSI MAHUDA 6/27/2020 0.00

Sub Total - 0.00 0.00


RODS WITH BARREL JAMMED IN HOLE;
KMA01 / 270° /
HZL KAYAD 6/27/2020 UCD 60-1 130 112.20 115.95 0.00 3.05 0.70 3.75 0 6/11/2020 - RELEASED BUT BIT AND REAMER SHELL LEFT
+25°
IN HOLE
Sub Total - 3.75 0.00
Location - North SHIFTING PLAN RECEIVED BUT VOLVO NOT
AGUCHA UG 6/27/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 - - COMING FOR SHIFTING; POINT MARKING
56 DONE
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 27-06-20 27-06-20 Closure
(m) (m) ment
(m) (m)

Surface to -180-
AGUCHA SUR PF 6/27/2020 DIMP-175 96 mm
21.00 38.00 0.00 17.00 17.00 0 6/22/2020 - HQ DRILLING IN PROGRESS
Sub Total - 17.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/27/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00

TDMA 6/27/2020 0 0 0 0 0.00 0 RIG SENT TO AGUCHA & DRILL EQUIPMENTS


BAMANIYA SENT TO DARIBA ON 17.06.20

Sub Total - 0.00 0.00

BW LH Rods lowering for unscrew. Pullout


running in progress.P/out all, unscrewed 53
TDMA AGUCHA 6/27/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 100 mtr from barrel. BW & NW remove from
stand and NQ shifted at stand for cement
grouting (Band cutting)

Sub Total - 0.00 100.00


18.40 M DRILLING DONE; HQ CASING UPTO
DD20ZWE272(H
TDMA ZAWAR 6/27/2020 KDR-1200/02 20 167.60 186.00 6.20 12.20 18.4 200 6/19/2020 - 167.60 M,R/I NQ, CORING; 100% W/LOSS IN
Q)
BH
Sub Total - 18.40 200.00

TSL DHANBAD 6/27/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 HOUSE KEEPING AND ELECTRICAL
CONNECTION DONE IN INCLINED

6/27/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 15.00

WOC; RIH HQ DRILL PIPE UPTO BOTTOM,


NO CEMENT TAG FOUND; DRILLED UPTO
NGRI KOYNA 6/27/2020 DYNA 350 KBH-10-R 1500 805.20 809.00 0.00 3.80 3.80 240 1/22/2020 - 809 M AND OBSERVED BIT BLOCKED BADLY;
INNER TUBE STUCK IN BARREL AND STRING
FULL OF WATER; HQ P/O STARTED

Sub Total - 3.80 240.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 26-06-20 26-06-20 Closure
(m) (m) ment
(m) (m)

NTPC HQ DRILLING IN PROGRESS; LATE START


6/26/2020 LY - 44/01 PMPT-02 110 0.00 16.50 6.00 10.50 16.50 55 56.5 6/26/2020 -
KERANDARI DUE TO HEAVY RAIN
16.50 55.00
NQ DRILLING; MACHINE IDLE FROM 11 PM
AS ALTERNATOR FAN BROKE DUE TO
PATRATU 6/26/2020 Dy(175/3) BH - 05 1000 688.00 709.00 15.00 6.00 21.00 180 693.33 534 5/22/2020 -
SLIPPAGE OF ALTERNATOR MOUNTING
BOLT
Sub Total - 21.00 180.00

KHARKHARI 6/26/2020 CDR-1000 MAKH 25-P-28 700 394.00 406.40 0.00 12.40 12.40 220.00 260.00 604.10 6/12/2020 - HQ CASING DONE UPTO 365.30 M; BH
WASHED, THEN DRILLING IN PROGRESS

KHARKHARI 6/26/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 260.00 332.00 5/27/2020 6/19/2020

FISHING CONTINUES; FISHING STARTED ON


KHARKHARI 6/26/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 90.00 346.67 364.50 6/5/2020 -
21-06-20

KHARKHARI 6/26/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 260.00 118.75 2/9/2020 6/18/2020

DRILLING IN PROGRESS; POOR PROGRESS


KHARKHARI 6/26/2020 KDR 750/03 MAKH-26-P-15 300 310.00 318.50 1.00 7.50 8.50 120.00 433.33 496.00 6/15/2020 -
DUE TO VERY HARD FM.
KHARKHARI 6/26/2020 Di - 8 MAKH-27-P-27 690 16.50 88.50 48.00 24.00 72.00 170.00 433.33 445.00 6/25/2020 - DRILLING IN PROGRESS
Sub Total - 92.90 600.00
NQ DRILLING; SHALE, FRACTURED SHALE,
KABITIRTHA 6/26/2020 DICD100H/1 MRKB 85/SP-6(C) 730 591.60 622.60 17.00 14.00 31.00 204 563.33 622.60 6/1/2020 - SANDSTONE FM.; POOR PROG. DUE TO
100%W/ LOSS IN BH

KABITIRTHA 6/26/2020 KDR 750(02) MRKB 87/SP-2(C) 660 287.90 343.10 29.20 26.00 55.20 177 520.00 867.00 6/18/2020 - NQ DRILLING; SHALE FM.

KABITIRTHA 6/26/2020 LY 44/01 MRKB 86/SP-3(C) 660 266.20 287.30 10.10 11.00 21.10 82 300.06 287.30 6/9/2020 - NQ DRILLING; SHALE TO HARD SHALE FM.

Sub Total - 107.30 463.00


BADAM 6/26/2020 RIG 3 100H/03 MABD-77/P-76 900 342.7 382.7 20.00 20.00 40.00 184 520.00 430.65 3/2/2020 - NQ DRILLING; SHALE FM.
HQ DRILLING; FRACTURED SHALE TO SHALE
BADAM 6/26/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 206.6 232.6 14.30 11.70 26.00 132 650.00 280.35 6/16/2020 -
FM.
NQ DRILLING; SHALE TO VERY HARD SHALE
BADAM 6/26/2020 Rig 2 LY-44/02 MABD-90/P-90 400 121 136 8.50 6.50 15.00 85 260.00 258.50 6/17/2020 -
FM.

BADAM 6/26/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 326.00 6/1/2020 6/23/2020 MATERIALS UNDER SHIFTING

BADAM 6/26/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 493.3 531.6 20.30 18.00 38.30 173 346.67 666.00 6/10/2020 - NQ DRILLING; SANDY SHALE FM.
Sub Total - 119.30 574.00
HAMIRPUR 6/25/2020 0.00
SIKAR 6/25/2020 0.00

Sub Total - 0.00 0.00


SIKAR 6/25/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
SIKAR 6/25/2020 Dy 50CR/05 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/25/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 26-06-20 26-06-20 Closure
(m) (m) ment
(m) (m)
GMRDS 6/25/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/25/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/25/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/26/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 47.3 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/26/2020 Rig 5 - LY-38/02 KIOM/54/61 17.50 27.00 9.50 0.00 9.50 20 104 110 6/23/2020 - DRILLING IN PROGRESS

Rig 6 - Dyna -
KURMITAR 6/26/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - RIG OFF FOR MANPOWER SHORTAGE
50H

KURMITAR 6/26/2020 Rig 7 - LY-38/01 KIOM/64/59 18.60 32.20 13.60 0.00 13.60 20 104 75.45 6/23/2020 - DRILLING IN PROGRESS
Sub Total - 23.10 40.00
BABJA 6/25/2020 DY:50CR/11 0.00 MACHINE TO COME TO HO ASANSOL
MACHINE TO BE SHIFTED TO AMD
BABJA 6/25/2020 LY:44 0.00
HAMIRPUR SITE
Sub Total - 0.00 0.00

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/26/2020 DY-100H/02 NPP- 0.00 0.00 0.00 0.00 0.00 866.67 548.00 6/3/2020 6/21/2020 STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

DRILLING;BUT NOW AMC PUMP B/D, SO


SOMAVARAM 6/26/2020 Dy50CR/10 SP-07 300 48.00 78.00 24.00 6.00 30.00 100 693.33 410.00 6/25/2020 -
DRILLING STOPPED

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/26/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 693.33 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/26/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 693.33 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 30.00 100.00

GSI MAHUDA 6/25/2020 0.00

Sub Total - 0.00 0.00


KMA01 / 270° / H/L FOR BIT CHOPPING; HARD FM. POOR
HZL KAYAD 6/26/2020 UCD 40 130 98.30 112.20 0.00 6.80 7.10 13.90 0 112.2 6/11/2020 -
+25° VENTILATION; 13.90 M DRILLED
Sub Total - 13.90 0.00
Location - North SHIFTING PLAN RECEIVED BUT VOLVO NOT
AGUCHA UG 6/26/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 203 - - COMING FOR SHIFTING; POINT MARKING
56 DONE
Sub Total - 0.00 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 26-06-20 26-06-20 Closure
(m) (m) ment
(m) (m)

HW P/O, BIT REMOVED ANDLOWERED AS A


GUIDE THEN PW REAMING STATED AND
Surface to -180- REAMED UPTO 4.5 M THEN ALL P/O; 4.5 M
AGUCHA SUR PF 6/26/2020 DIMP-175 117 mm
18.00 21.00 0.00 3.00 3.00 0 26.4 6/22/2020 -
PW , 9.65 M HW CASING LANDED, THEN HQ
STARTED AND REAMED UPTO 18 M THEND
DRILLING STARTED

Sub Total - 3.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/25/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00

TDMA RIG SENT TO AGUCHA & DRILL EQUIPMENTS


6/25/2020 0 0 0 0 0.00 0
BAMANIYA SENT TO DARIBA ON 17.06.20

Sub Total - 0.00 0.00

BW and NW rods lowered for unscrewing.


TDMA AGUCHA 6/26/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 121 0 Unscrewed and P/out recovered 78 mtr

Sub Total - 0.00 121.00


20.60 M DRILLING DONEP/O FOR HQ
TDMA ZAWAR 6/26/2020 KDR-1200/02 DD20ZWE272(H 20 147.00 167.60 12.00 8.60 20.6 200 167.6 6/19/2020 - CASING AT 167.60 M, B/D DUE TO HYD.
Q)
HOSE DAMAGED
Sub Total - 20.60 200.00
HOUSE KEEPING AND ELECTRICAL
TSL DHANBAD 6/26/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 0
CONNECTION DONE IN INCLINED

6/25/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 15.00


CEMENTATION JOB DONE WITH
NGRI KOYNA 6/26/2020 DYNA 350 KBH-10-R 1500 805.20 805.20 0.00 0.00 0.00 30 141.2 1/22/2020 - DISPLACEMENT; P/O COMPLETE NQ STRING
AND WOC
Sub Total - 0.00 30.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 25-06-20 25-06-20 Closure
(m) (m) ment
(m) (m)

MACHINE AND DERRICK SHIFTED TO NEW


NTPC
6/25/2020 LY - 44/01 PMPT-00 0.00 0.00 0.00 0.00 0.00 5 0 40 - - BH POINT PMPT 02; MACHINE FOUNDATION
KERANDARI
JAM DONE
0.00 5.00

NQ DRILLING THROUGH SHALE FM.; SLOW


PATRATU 6/25/2020 Dy(175/3) BH - 05 1000 665.00 688.00 10.00 13.00 23.00 250 666.67 513 5/22/2020 - PROGRESS DUE TO FREQUENT BLOCKAGE
FOR FRACTURED FM AND HEAVY RAINFALL

Sub Total - 23.00 250.00

WORK STARTED AT 3 PM AFTER


NEGOTIATIONS WITH LOCALS; HQ CASING
KHARKHARI 6/25/2020 CDR-1000 MAKH 25-P-28 700 394.00 394.00 0.00 0.00 0.00 120.00 250.00 591.70 6/12/2020 -
EXTENDED UPTO 350.80 M BY REAMING;
WORK HINDERED DUE TO HEAVY RAINFALL

KHARKHARI 6/25/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 0.00 250.00 332.00 5/27/2020 6/19/2020

FISHING CONTINUES; WORK STOPPED IN


KHARKHARI 6/25/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 70.00 333.33 364.50 6/5/2020 -
2ND SHIFT DUE TO HEAVY RAINFALL

KHARKHARI 6/25/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 0.00 250.00 118.75 2/9/2020 6/18/2020

KHARKHARI 6/25/2020 KDR 750/03 MAKH-26-P-15 300 302.50 310.00 7.50 0.00 7.50 70.00 416.67 487.50 6/15/2020 - CONFUSION REGARDING CLOSURE OF BH

HW LINER CASING DONE UPTO 9 M; HQ


KHARKHARI 6/25/2020 Di - 8 MAKH-27-P-27 690 0.00 16.50 7.00 9.50 16.50 90.00 416.67 373.00 6/25/2020 - DRILLING IN PROGRESS; RAIN STOPPED
WORK
Sub Total - 24.00 350.00
NQ DRILLING; FRACTURED SHALE,
KABITIRTHA 6/25/2020 DICD100H/1 MRKB 85/SP-6(C) 730 571.50 591.60 8.90 11.20 20.10 168 541.67 591.60 6/1/2020 - SANDSTONE, COAL FM.; POOR PROG. DUE
TO 100%W/ LOSS IN BH

KABITIRTHA 6/25/2020 KDR 750(02) MRKB 87/SP-2(C) 660 235.70 287.90 26.10 26.10 52.20 135 500.00 811.80 6/18/2020 - NQ DRILLING; SHALE FM.

KABITIRTHA 6/25/2020 LY 44/01 MRKB 86/SP-3(C) 660 245.40 266.20 11.40 9.40 20.80 93 283.39 266.20 6/9/2020 - NQ DRILLING; SHALE TO VERY HARD SHALE
FM.

Sub Total - 93.10 396.00

BADAM 6/25/2020 RIG 3 100H/03 MABD-77/P-76 900 304.7 342.7 20.00 18.00 38.00 173 500.00 390.65 3/2/2020 - NQ DRILLING; SANDY SHALE TO SHALE FM.

BADAM 6/25/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 183.1 206.6 13.50 10.00 23.50 131 625.00 254.35 6/16/2020 - HQ REAMING COMPLETE; HQ DRILLING;
FRACTURED SHALE FM.

BADAM 6/25/2020 Rig 2 LY-44/02 MABD-90/P-90 400 97.5 121 10.50 13.00 23.50 125 250.00 243.50 6/17/2020 - NQ DRILLING; SHALE TO SAND FM.

MATERIALS SHIFTED TO SUKULKHAPIA


BADAM 6/25/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 0 0.00 326.00 6/1/2020 6/23/2020 CAMP, BUT DUE TO HEAVY RAIN RIG
SHIFTING WAS NOT POSSIBLE
NQ DRILLING; SAND TO SANDY SHALE
BADAM 6/25/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 451.9 493.3 21.00 20.40 41.40 144 333.33 627.70 6/10/2020 -
FM.FM.
Sub Total - 126.40 573.00
HAMIRPUR 6/25/2020 0.00
SIKAR 6/25/2020 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 25-06-20 25-06-20 Closure
(m) (m) ment
(m) (m)

Sub Total - 0.00 0.00


SIKAR 6/25/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
SIKAR 6/25/2020 Dy 50CR/05 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/25/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/25/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/25/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/25/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/25/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 0 0 47.3 6/12/2020 6/24/2020 SHIFTING

KURMITAR 6/25/2020 Rig 5 - LY-38/02 KIOM/54/61 12.00 17.50 5.50 0.00 5.50 15 100 100.5 6/23/2020 - DRILLING IN PROGRESS

Rig 6 - Dyna -
KURMITAR 6/25/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 0 0 - - RIG OFF FOR MANPOWER SHORTAGE
50H

KURMITAR 6/25/2020 Rig 7 - LY-38/01 KIOM/64/59 12.00 18.60 6.60 0.00 6.60 15 100 61.85 6/23/2020 - DRILLING IN PROGRESS
Sub Total - 12.10 30.00
BABJA 6/25/2020 DY:50CR/11 0.00 MACHINE TO COME TO HO ASANSOL
MACHINE TO BE SHIFTED TO AMD
BABJA 6/25/2020 LY:44 0.00
HAMIRPUR SITE
Sub Total - 0.00 0.00
RIG AND ALL ACCESSORIES SHIFTED TO
SOMAVARAM 6/25/2020 DY-100H/02 NPP-19 530 548.00 548.00 0.00 0.00 0.00 35 833.33 548.00 6/3/2020 6/21/2020
CAMP
RIG & SITE SET UP DONE; DRILLING IN
SOMAVARAM 6/25/2020 Dy50CR/10 SP-07 300 0.00 48.00 24.00 24.00 48.00 95 666.67 380.00 6/25/2020 -
PROGRESS; 16 M HW LINER INSTALLED

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/25/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 666.67 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/25/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 666.67 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 48.00 130.00

GSI MAHUDA 6/25/2020 0.00

Sub Total - 0.00 0.00


H/L FOR BIT CHANGE AND BIT CHOPPING;
KMA01 / 270° /
HZL KAYAD 6/25/2020 UCD 40 130 81.30 98.30 0.00 6.80 10.20 17.00 0 0 98.3 6/11/2020 - HARD FM. POOR VENTILATION; 17 M
+25°
DRILLED
Sub Total - 17.00 0.00
Location - North WAITING FOR VOLVO COMPRESSOR
AGUCHA UG 6/25/2020 UDD-330 105 CV SBH No. 0.00 0.00 0.00 0.00 0.00 0 0 203 - - SHIFTING, VOLVO B/D; DAMAGED RODS
56 AND GUIDES SHIFTED TO SURFACE
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 25-06-20 25-06-20 Closure
(m) (m) ment
(m) (m)
Sub Total - 0.00 0.00
18 M HQ RODS LANDED AS GUIDE AND
Surface to -180-
AGUCHA SUR PF 6/25/2020 DIMP-175 117 mm
18.00 18.00 0.00 0.00 0.00 0 0 23.4 6/22/2020 - THEN HW CASING AND REAMING UPTO 9 M
DEPTH
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/25/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00

TDMA RIG SENT TO AGUCHA & DRILL EQUIPMENTS


6/25/2020 0 0 0 0 0.00 0
BAMANIYA SENT TO DARIBA ON 17.06.20

Sub Total - 0.00 0.00


Rods unscrew and rods shifted from camp
TDMA AGUCHA 6/25/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 146
to site
Sub Total - 0.00 146.00
DD20ZWE272(H
TDMA ZAWAR 6/25/2020 KDR-1200/02 20 123.00 147.00 12.00 12.00 24 200 0 147 6/19/2020 - 24 M DRILLING DONE
Q)
Sub Total - 24.00 200.00
TSL DHANBAD 6/25/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 ENCASING JOB COMPLETED

6/25/2020 BH 01 0.00 SITE PREP. WORK CONTINUES

Sub Total - 0.00 15.00

COMPLETE HQ PIPES WITH BARREL P/O TO


FIND BIT MOUTH BLOCKED BY FRACTURED
NGRI KOYNA 6/25/2020 DYNA 350 KBH-10-R 1500 805.20 805.20 0.00 0.00 0.00 180 0 141.2 1/22/2020 - ROCK;NQ RODS LOWERED TILL BOTTOM
FOR CEMENTATION; WORK SLOW DUE TO
HEAVY RAIN FAST WINDS.

Sub Total - 0.00 180.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)

TARGET DEPTH ACHIEVED SO BH CLOSED BY


NTPC
6/24/2020 LY - 44/01 35.10 40.00 4.90 0.00 4.90 20 0 40 6/20/2020 6/24/2020 NTPC OFFICER; BH PLUGGING COMPLETE;
KERANDARI
ALL MATERIALS SHIFTED TO NEW BH [POINT

4.90 20.00
1.1/4" HOSE PIPE DAMAGED, REPAIRED
THEN MACHINE STARTED; NQ DRILLING;
PATRATU 6/24/2020 Dy(175/3) BH - 05 1000 646.00 665.00 5.00 14.00 19.00 190 640.00 490 5/22/2020 -
POOR PROGRESS DUE TO DOWN HOLE
PROBLEM
Sub Total - 19.00 190.00
KHARKHARI 6/24/2020 CDR-1000 MAKH 25-P-28 700 394.00 394.00 0.00 0.00 0.00 0.00 240.00 591.70 6/12/2020 - DRILLING STOPPED BY LOCALS

KHARKHARI 6/24/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 0.00 240.00 332.00 5/27/2020 6/19/2020 DRILLING STOPPED BY LOCALS

KHARKHARI 6/24/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 0.00 320.00 364.50 6/5/2020 - DRILLING STOPPED BY LOCALS

KHARKHARI 6/24/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 0.00 240.00 118.75 2/9/2020 6/18/2020 DRILLING STOPPED BY LOCALS

KHARKHARI 6/24/2020 KDR 750/03 MAKH-26-P-15 300 302.50 302.50 0.00 0.00 0.00 0.00 400.00 480.00 6/15/2020 - DRILLING STOPPED BY LOCALS

KHARKHARI 6/24/2020 Di - 8 MAKH-27-P-27 690 0.00 0.00 0.00 0.00 0.00 0.00 400.00 356.50 5/19/2020 6/21/2020 DRILLING STOPPED BY LOCALS
Sub Total - 0.00 0.00
NQ DRILLING; FRACTURED SHALE FM AND
KABITIRTHA 6/24/2020 DICD100H/1 MRKB 85/SP-6(C) 730 559.00 571.50 6.10 6.40 12.50 168 520.00 571.50 6/1/2020 - FAULT ZONE, COAL FM. L PLATE SETTING OF
ROTATION MOTOR; POOR PROG. DUE TO
100%W/ LOSS IN BH

RIG DISMANTLED AND REPAIRING DONE,


TESTED AND SHIFTED TO BH POINT AND
KABITIRTHA 6/24/2020 KDR 750(02) MRKB 87/SP-2(C) 660 222.70 235.70 0.00 13.00 13.00 98 480.00 759.60 6/18/2020 -
LEVELLING DONE; ALTERNATOR CHARGING;
NQ DRILLING; SHALE FM.

WATER SUPPLY PUMP REPAIRED; NQ


KABITIRTHA 6/24/2020 LY 44/01 MRKB 86/SP-3(C) 660 230.60 245.40 7.70 7.10 14.80 50 266.72 245.40 6/9/2020 -
DRILLING; SHALE TO FRACTURED SHALE FM.

Sub Total - 40.30 316.00


NQ DRILLING; SANDY SHALE, SAND AND
BADAM 6/24/2020 RIG 3 100H/03 MABD-77/P-76 900 268.3 304.7 20.40 16.00 36.40 127 480.00 352.65 3/2/2020 -
COAL FM.
HQ REAMING FROM 106 M TO 181 M;
BADAM 6/24/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 183.1 183.1 0.00 0.00 0.00 109 600.00 230.85 6/16/2020 -
SAHLE TO SAND FM.

BADAM 6/24/2020 Rig 2 LY-44/02 MABD-90/P-90 400 73.5 97.5 10.00 14.00 24.00 125 240.00 220.00 6/17/2020 - NQ DRILLING; SHALE TO SAND FM.

HW LINER P/O AND PVC CASING LOWERED;


BADAM 6/24/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 30 326.00 6/1/2020 6/23/2020
3 M HW LINER MADE

BADAM 6/24/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 409.8 451.9 21.00 21.10 42.10 158 320.00 586.30 6/10/2020 - NQ DRILLING;COAL, SANDSTONE FM.
Sub Total - 102.50 549.00
HAMIRPUR 6/24/2020 0.00
SIKAR 6/24/2020 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)
Sub Total - 0.00 0.00
SIKAR 6/24/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
SIKAR 6/24/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0.00 0 5/29/2020 6/19/2020 RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/24/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/24/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/24/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/24/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/24/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 0 0 47.3 6/12/2020 6/24/2020 BH CLOSED AND CASING P/O

KURMITAR 6/24/2020 Rig 5 - LY-38/02 KIOM/54/61 5.70 12.00 6.30 0.00 6.30 10 96 95 6/23/2020 - DRILLING IN PROGRESS

Rig 6 - Dyna -
KURMITAR 6/24/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 0 0 - - RIG OFF FOR MANPOWER SHORTAGE
50H

KURMITAR 6/24/2020 Rig 7 - LY-38/01 KIOM/64/59 5.50 12.00 6.50 0.00 6.50 10 96 55.25 6/23/2020 - DRILLING IN PROGRESS
Sub Total - 12.80 20.00
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/24/2020 DY:50CR/11 0.00
POINT
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/24/2020 LY:44 0.00
POINT
Sub Total - 0.00 0.00

BH CLOSED;P/O ALL NW RODS AND HQ


CASING 20.50 M; R/I NW L/H WITH TAPE
UPTO 270.50 M, FOUND HELD UP AS BH
WALL COLLAPSED, REHOISTED STRINGS TO
SOMAVARAM 6/24/2020 DY-100H/02 NPP-19 530 548.00 548.00 0.00 0.00 0.00 40 800.00 548.00 6/3/2020 6/21/2020
SURFACE; TOTAL CASING RETRIEVED 344.50
M, LIH 54.80 M; HW LINER RECIPROCATED,
MADE FREE FROM JAM; 32.30 M HW LINER
RELEASED

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/24/2020 Dy50CR/10 SP-07 0.00 0.00 0.00 0.00 0.00 10 640.00 332.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/24/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 640.00 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/24/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 640.00 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 0.00 50.00

GSI MAHUDA 6/24/2020 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)
Sub Total - 0.00 0.00
BIT CHANGED; HARD FM. POOR
HZL KAYAD 6/24/2020 UCD 40 KMA01 / 270° / 130 63.50 81.30 0.00 8.30 9.50 17.80 0 0 81.3 6/11/2020 - VENTILATION; DRILLING FROM 6.15 PM TO
+25°
10.40 PM
Sub Total - 17.80 0.00
Location - North
RIG AND OTHER EQUIPMENTS SHIFTED TO
AGUCHA UG 6/24/2020 UDD-330 255 CV SBH No. 61.50 61.50 0.00 0.00 0.00 0 0 203 6/19/2020 6/23/2020
105 CV
55
Sub Total - 0.00 0.00
6 M HQ DRILLING DONE THEN RODS P/O
Surface to -180-
AGUCHA SUR PF 6/24/2020 DIMP-175 96 mm
12.00 18.00 6.00 0.00 6.00 0 0 23.4 6/22/2020 - FOR REAMING HW CASING; WORK
HAMPERED DUE TO HEAVY RAIN
Sub Total - 6.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/24/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00

TDMA RIG SENT TO AGUCHA & DRILL EQUIPMENTS


6/24/2020 0 0 0 0 0.00 0
BAMANIYA SENT TO DARIBA ON 17.06.20

Sub Total - 0.00 0.00


BW rods lowered and NQ unscrewed, P/out
TDMA AGUCHA 6/24/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 141
in progres
Sub Total - 0.00 141.00
DD20ZWE272(H
TDMA ZAWAR 6/24/2020 KDR-1200/02 20 99.00 123.00 12.00 12.00 24 200 0 123 6/19/2020 - 24 M DRILLING DONE
Q)
Sub Total - 24.00 200.00

TSL DHANBAD 6/24/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 18 M 6" CASING DONE;V - CUTTING AND
WELDING WORK CONTINUING

6/24/2020 BH 01 0.00 Site Preparation Work Continue

Sub Total - 0.00 15.00

FOOT CLAMP AND SUPPLY PUMP NOT


WORKING PROPERLY; FOOT CLAMP
REPLACED, SUPPLY PUMP REPAIRED; HQ
NGRI KOYNA 6/24/2020 DYNA 350 KBH-10-R 1500 796.00 805.20 0.00 9.20 9.20 288 0 141.2 1/22/2020 - DRILLING RESUMED BUT EXTRA TORQUE
AND BLOCKING AND JAMMING TENDENCY
OBSERVED; P/O STRINGS FOR CEMENTING
JOB

Sub Total - 9.20 288.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)

NTPC
6/23/2020 LY - 44/01 PMPT - 01 40 1.00 35.10 19.10 15.00 34.10 85 0 35.1 6/20/2020 - DRILLING IN PROGRESS
KERANDARI
34.10 85.00
NQ DRILLING; POOR PROG. DUE TO DOWN
PATRATU 6/23/2020 Dy(175/3) BH - 05 1000 617.00 646.00 14.00 15.00 29.00 270 613.33 471 5/22/2020 -
HOLE PROBLEM
Sub Total - 29.00 270.00
DRILLING IN PROGRESS; COMPLETE ROD
WITH BARREL JAMMED SO TRIED TO
KHARKHARI 6/23/2020 CDR-1000 MAKH 25-P-28 700 375.00 394.00 15.00 4.00 19.00 265.00 230.00 591.70 6/12/2020 -
RELEASEBY FISHING AND SUCCESSFUL;
COMPLETE ROD WITH BARREL P/O

KHARKHARI 6/23/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 230.00 332.00 5/27/2020 6/19/2020

KHARKHARI 6/23/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 65.00 306.67 364.50 6/5/2020 - FISHING CONTINUES

KHARKHARI 6/23/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 230.00 118.75 2/9/2020 6/18/2020

KHARKHARI 6/23/2020 KDR 750/03 MAKH-26-P-15 300 275.50 302.50 15.00 12.00 27.00 160.00 383.33 480.00 6/15/2020 - DRILLING IN PROGRESS

KHARKHARI 6/23/2020 Di - 8 MAKH-21-P-22 730 735.00 735.00 0.00 0.00 0.00 40.00 383.33 356.50 5/19/2020 21.06.2020 RIG AND MATERIALS SHIFTED TO P -27
Sub Total - 46.00 530.00

NQ DRILLING; FRACTURED SHALE FM AND


KABITIRTHA 6/23/2020 DICD100H/1 MRKB 85/SP-6(C) 730 536.50 559.00 9.30 13.20 22.50 144 498.33 559.00 6/1/2020 - FAULT ZONE; POOR PROG. DUE TO 100%W/
LOSS IN BH AND HEAVY RAINFALL

HQ DRILLING; HQ P/O UPTO 222.7 M AND


KABITIRTHA 6/23/2020 KDR 750(02) MRKB 87/SP-2(C) 660 208.20 222.70 14.50 0.00 14.50 101 460.00 746.60 6/18/2020 - R/I; NQ ROD PAIR MAKING DONE AND R/I
UPTO 222.7 M; RAIN HAMPERED PROGRESS

DERRICK PULLEY CHANGED; NQ DRILLING;


KABITIRTHA 6/23/2020 LY 44/01 MRKB 86/SP-3(C) 660 218.10 230.60 2.00 10.50 12.50 55 250.05 230.60 6/9/2020 - W/ LOSS IN HOLE; PROG. HAMPERED DUE
TO RAIN
Sub Total - 49.50 300.00

BH WASHED; HQ LOWERED AND TAPE


CONNECTED AND HQ P/O; HQ ROD
BADAM 6/23/2020 RIG 3 100H/03 MABD-77/P-76 900 259.3 268.3 4.00 5.00 9.00 127 460.00 316.25 3/2/2020 -
LOWERED AND BH WASHED; DRILLING;
SANDY SHALE TO FRACTURED SHALE FM.

NQ DRILLING; FRACTURED SHALE; ROD JAM


DUE TO SHEAR ZONE; NQ JAM RELEASED
BADAM 6/23/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 173.3 183.1 8.80 1.00 9.80 109 575.00 230.85 6/16/2020 -
AND ROD P/O; HQ ROD P/O FOR HQ
EXTENSION

BADAM 6/23/2020 Rig 2 LY-44/02 MABD-90/P-90 400 47.5 73.5 15.50 10.50 26.00 125 230.00 196.00 6/17/2020 - HQ DRILLING; SANDY SHALE TO SHALE FM.

BADAM 6/23/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 30 0.00 326.00 6/1/2020 6/23/2020 BH CLOSED BY CMPDI GEOLOGIST

BADAM 6/23/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 373 409.8 16.80 20.00 36.80 158 306.67 544.20 6/10/2020 - NQ DRILLING; SHALE FM.
Sub Total - 81.60 549.00
HAMIRPUR 6/23/2020 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)
SIKAR 6/23/2020 0.00

Sub Total - 0.00 0.00


SIKAR 6/23/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
SIKAR 6/23/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0.00 0 5/29/2020 6/19/2020 RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/23/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/23/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/23/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/23/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/23/2020 Rig 4 - VOL-180 KIOM/52/57 26.70 26.70 0.00 0.00 0.00 0 0 47.3 6/12/2020 - RIG OFF

KURMITAR 6/23/2020 Rig 5 - LY-38/02 KIOM/54/61 0.00 5.70 5.70 0.00 5.70 10 92 88.7 6/23/2020 - DRILLING IN PROGRESS

Rig 6 - Dyna -
KURMITAR 6/23/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 0 0 - - RIG OFF FOR MANPOWER SHORTAGE
50H

KURMITAR 6/23/2020 Rig 7 - LY-38/01 KIOM/64/59 0.00 5.50 5.50 0.00 5.50 10 92 48.75 6/23/2020 - DRILLING IN PROGRESS
Sub Total - 11.20 20.00
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/23/2020 DY:50CR/11 0.00
POINT
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/23/2020 LY:44 0.00
POINT
Sub Total - 0.00 0.00
BH CLOSED;P/O ALL RODS AND HQ CASING
SOMAVARAM 6/23/2020 DY-100H/02 NPP-19 530 548.00 548.00 0.00 0.00 0.00 105 766.67 548.00 6/3/2020 6/21/2020 37.70 M; TOTAL RELEASED 309.20 M; LIH
90.10 M

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/23/2020 Dy50CR/10 NPP- 0.00 0.00 0.00 0.00 0.00 0 613.33 332.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/23/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 613.33 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/23/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 613.33 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 0.00 105.00

GSI MAHUDA 6/23/2020 0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 23-06-20 23-06-20 Closure
(m) (m) ment
(m) (m)

CABLE HANGING DONE MANUALLY;


ELECTRIC CONNECTION DONE; POOR
KMA01 / 270° /
HZL KAYAD 6/23/2020 UCD 40 130 54.05 63.50 0.00 0.00 9.45 9.45 0 0 63.5 6/11/2020 - VENTILATION; WATER PUMP
+25°
MAINTENANCE; DRILLING FROM 7.30 PM
TO 11 PM

Sub Total - 9.45 0.00

ALL RODS LOWERED WITH GUIDE; HAMMER


CHOKED, ALL RODS P/O FOUND THAT TOP
Location - North
VALVE DAMAGED, REPLACED AND
AGUCHA UG 6/23/2020 UDD-330 255 CV SBH No. 47.00 61.50 5.00 9.50 14.50 0 0 203 6/19/2020 -
LOWERED; DRILLING DONE; ALL RODS
55
HOISTED FOR SURVEY; TARGET DEPTH
ACHIEVED

Sub Total - 14.50 0.00


Surface to -180-
AGUCHA SUR PF 6/23/2020 DIMP-175 96 mm
3.00 12.00 9.00 0.00 9.00 0 0 17.4 6/22/2020 - HQ DRILLING

Sub Total - 9.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/23/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00


TDMA Rig send to Agucha site & drill equipments
6/23/2020 0 0 0 0 0.00 0
BAMANIYA send at Dariba site on dated 17.06.20
Sub Total - 0.00 0.00

TDMA AGUCHA 6/23/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 123

Sub Total - 0.00 123.00


DD20ZWE272(H
TDMA ZAWAR 6/23/2020 KDR-1200/02 20 75.00 99.00 12.00 12.00 24 200 0 99 6/19/2020 - 24 M DRILLING DONE
Q)
Sub Total - 24.00 200.00

TSL DHANBAD 6/23/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15 18 M 6" CASING DONE;V - CUTTING AND
WELDING WORK CONTINUING

6/23/2020 BH 01 0.00 Site Preparation Work Continue

Sub Total - 0.00 15.00

SYNCHRONISING COUPLING FITTED FROM


NGRI KOYNA 6/23/2020 DYNA 350 KBH-10-R 1500 793.00 796.00 0.00 3.00 3.00 288 0 132 1/22/2020 -
KOLHAPUR; HQ DRILLING RESUMED

Sub Total - 3.00 288.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 22-06-20 22-06-20 Closure
(m) (m) ment
(m) (m)

LAND OWNER UNDER NEGOTIATION WITH


NTPC
6/22/2020 LY - 44/01 1.00 1.00 0.00 0.00 0.00 0.00 0 0 1 6/20/2020 - LOCALS; NO DRILLING DONE; DRILLING
KERANDARI
COMMENCED ON 23 RD MORNING

0.00 0.00
HW LINER EXTENDED 18 M; NQ LOWERED
580 M; BH WASHED AND NQ DRILLING
PATRATU 6/22/2020 Dy(175/3) BH - 05 1000 603.00 617.00 0.00 14.00 14.00 160 586.67 442 5/22/2020 -
STARTED; PROGRESS HAMPERED DUE TO
RAIN
Sub Total - 14.00 160.00

KHARKHARI 6/22/2020 CDR-1000 MAKH 25-P-28 700 339.00 375.00 13.50 22.50 36.00 270.00 220.00 572.70 6/12/2020 - NQ P/D UPTO 339 M ; DRILLING IN
PROGRESS

KHARKHARI 6/22/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 0.00 220.00 332.00 5/27/2020 6/19/2020

KHARKHARI 6/22/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 50.00 293.33 364.50 6/5/2020 - FISHING CONTINUES

RIG AND MATERIALS SHIFTED TO MAIN


KHARKHARI 6/22/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 50.00 220.00 118.75 2/9/2020 6/18/2020
CAMP

KHARKHARI 6/22/2020 KDR 750/03 MAKH-26-P-15 300 241.00 275.50 16.50 18.00 34.50 160.00 366.67 453.00 6/15/2020 - DRILLING IN PROGRESS

ALL HQ CASING AND HW LINER CASING P/O;


KHARKHARI 6/22/2020 Di - 8 MAKH-21-P-22 730 735.00 735.00 0.00 0.00 0.00 50.00 366.67 356.50 5/19/2020 21.06.2020
ALL RODS AND CASING DISMANTLED
Sub Total - 70.50 580.00

NQ DRILLING; FRACTURED SHALE FM; 100%


KABITIRTHA 6/22/2020 DICD100H/1 MRKB 85/SP-6(C) 730 507.50 536.50 13.50 15.50 29.00 190 476.67 536.50 6/1/2020 -
W/LOSS IN BH

KABITIRTHA 6/22/2020 KDR 750(02) MRKB 87/SP-2(C) 660 162.20 208.20 23.20 22.80 46.00 142 440.00 732.10 6/18/2020 - HQ DRILLING; SHALE FM

POOR PROGRESS AS DERRICK PULLEY


KABITIRTHA 6/22/2020 LY 44/01 MRKB 86/SP-3(C) 660 208.90 218.10 9.20 0.00 9.20 47 233.38 218.10 6/9/2020 -
BROKEN DOWN

Sub Total - 84.20 379.00


DRILLING; 166M HQ ROD SLIPPED; HQ ROD
BADAM 6/22/2020 RIG 3 100H/03 MABD-77/P-76 900 234 259.3 13.50 11.80 25.30 201 440.00 307.25 3/2/2020 -
AND BARREL RELEASED
NQ DRILLING; INTERSPERSED SAND AND
BADAM 6/22/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 117.4 173.3 25.00 30.90 55.90 246 550.00 221.05 6/16/2020 -
SHALE FM.

HQ DRILLING; FRACTURED SHALE TO SHALE


BADAM 6/22/2020 Rig 2 LY-44/02 MABD-90/P-90 400 29.5 47.5 9.00 9.00 18.00 80 220.00 170.00 6/17/2020 -
FM;

WAITING FOR DECISION OF CMPDI


BADAM 6/22/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 0.00 0.00 326.00 6/1/2020 -
GEOLOGIST

BADAM 6/22/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 347.3 373 12.00 13.70 25.70 172 293.33 507.40 6/10/2020 - HQ DRILLING; FRACTURED SHALE TO SHALE
FM.
Sub Total - 124.90 699.00
HAMIRPUR 6/22/2020 0.00
Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 22-06-20 22-06-20 Closure
(m) (m) ment
(m) (m)
SIKAR 6/22/2020 0.00

Sub Total - 0.00 0.00


SIKAR 6/22/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION
SIKAR 6/22/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0.00 0 5/29/2020 6/19/2020 RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS 6/22/2020 DY 35/01 0 0 0 0 0.00 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS 6/22/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/22/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/22/2020 RD/60 (REPL) 0 0 0 0 0.00 20
Sub Total - 0.00 20.00

KURMITAR 6/22/2020 Rig 4 - VOL-180 KIOM/52/57 25.60 26.70 1.10 1.10 0 0 47.3 6/12/2020 - DRILLING

KURMITAR 6/22/2020 Rig 5 - LY-38/02 KIOM/00/00 0.00 0.00 0.00 0.00 10 88 83 - - SHIFTING COMPLETED

Rig 6 - Dyna -
KURMITAR 6/22/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/22/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 10 88 43.25 - - SHIFTING COMPLETED
Sub Total - 1.10 20.00
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/22/2020 DY:50CR/11 0.00
POINT
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA 6/22/2020 LY:44 0.00
POINT
Sub Total - 0.00 0.00

SOMAVARAM 6/22/2020 DY-100H/02 NPP-19 530 548.00 548.00 0.00 0.00 0.00 90 733.33 548.00 6/3/2020 6/21/2020 P/O ALL RODS TO SURFACE WITH 20.30 M
HQ CASING; LIH 133.60 M

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/22/2020 Dy50CR/10 NPP- 0.00 0.00 0.00 0.00 0.00 0 586.67 332.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/22/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 586.67 0.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION


SOMAVARAM 6/22/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 586.67 355.00 - - STARTED AND LANDOWNERS DID NOT
AGREE TO GIVE THEIR LAND FOR DRILLING

Sub Total - 0.00 90.00

GSI MAHUDA 6/22/2020 0.00

Sub Total - 0.00 0.00


Target Progress
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT upto upto Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III 22-06-20 22-06-20 Closure
(m) (m) ment
(m) (m)

FOOT CLAMP SEAL CUT; MAS SUPPORT


RELEASED, ALL RODS HOISTED, ALL
CONNECTIONS DISMANTLED FOR RIG
KMA01 / 270° / CHANGE FROM UCD 40 TO UCD 60; UCD 60
HZL KAYAD 6/22/2020 UCD 40 130 51.25 54.05 0.00 2.80 0.00 2.80 0 6/11/2020 -
+25° PLACED IN POCKET, ANGLE SET, WATER
CONNECTION DONE, ELECTRIC CABLE
CONNECTION NOT DONE DUE TO ABSENSE
OF SCISSORLIFT

Sub Total - 2.80 0.00


Location - North I M DRILLED AFTER RECEIVING DIESEL;
AGUCHA UG 6/22/2020 UDD-330 255 CV SBH No. 46.00 47.00 1.00 0.00 1.00 0 6/19/2020 - HAMMER CHOKED, RODS P/O AND FOUND
55 THAT ROD GUIDE CRACKED
Sub Total - 1.00 0.00
SITE PREPARATION DONE THEN 3 M
AGUCHA SUR PF 6/22/2020 DIMP-175 Surface to -180 0.00 3.00 3.00 0.00 3.00 0 6/22/2020 -
DRILLING DONE
Sub Total - 3.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/22/2020 DW-35 FILL-02 BORE 0.00 0.00 0.00 0.00 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 ] FOR COVID 19

Sub Total - 0.00 0.00


TDMA Rig send to Agucha site & drill equipments
6/22/2020 0 0 0 0 0.00 0
BAMANIYA send at Dariba site on dated 17.06.20
Sub Total - 0.00 0.00
BW Left hand rods received from Dariba and
TDMA AGUCHA 6/22/2020 KDR-1200 RAE-025 L1 0.00 0.00 0.00 0.00 0.00 75 shifted in mines premises, Then try to rods
unscrew by BW Rods
Sub Total - 0.00 75.00
DD20ZWE272(H
TDMA ZAWAR 6/22/2020 KDR-1200/02 20 45.00 75.00 18.00 12.00 30 200 6/19/2020 - 30 M DRILLING DONE
Q)
Sub Total - 30.00 200.00
Day Total - 18m(Encasing)
TSL DHANBAD 6/22/2020 WO Rig BH No.04 0.00 0.00 0.00 0.00 0.00 15
Month Total - 210m

6/22/2020 BH 01 0.00 Site Preparation Work Continue

Sub Total - 0.00 15.00

NGRI KOYNA 6/22/2020 DYNA 350 KBH-10-R 1500 793.00 793.00 0.00 0.00 0.00 0 1/22/2020 - RIG B/D

Sub Total - 0.00 0.00


Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III Closure
(m) (m) ment

MOBIL AND DIESEL FILTER CHANGED ANAD


MOBIL TOPPED UP 21 L AND MUD PUMP FITTED;
PATRATU 6/21/2020 Dy(175/3) BH - 05 1000 600.00 603.00 3.00 0.00 3.00 100 5/22/2020 - NQ DRILLING; HW LINER CASING SLIPPED SO NQ
ROD HOISTING 603 M; HOISTING SLOW DUE TO
HEAVY RAIN AND FOOT CLAMP WEAK

Sub Total - 3.00 100.00


DRILLING NOT EXTENDED DUE TO JAMMING AND
KHARKHARI 6/21/2020 CDR-1000 MAKH 25-P-28 700 339.00 339.00 0.00 0.00 0.00 130.00 6/12/2020 - BLOCKING TENDENCY; ALL HQ ROD WITH BARREL
P/O; HQ CASING DONE UPTO 339 M

KHARKHARI 6/21/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 5/27/2020 6/19/2020 ALL ROD AND CASING SHIFTED TO MAIN CAMP

KHARKHARI 6/21/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 50.00 6/5/2020 - RIG REPAIRED; FISHING CONTINUES

ALL HQ CASING AND HW LINER P/O; ALL CASING


KHARKHARI 6/21/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 50.00 2/9/2020 6/18/2020
AND RODS DISMANTLED

KHARKHARI 6/21/2020 KDR 750/03 MAKH-26-P-15 300 218.00 241.00 12.00 11.00 23.00 100.00 6/15/2020 - DRILLING IN PROGRESS
DRILLING IN PROG. 59 PAIR NQ ROD P/O; GPL
KHARKHARI 6/21/2020 Di - 8 MAKH-21-P-22 730 733.00 735.00 2.00 0.00 2.00 80.00 5/19/2020 21.06.2020 DONE UPTO 735 M; COMPLETE RODS WITH
BARREL P/O
Sub Total - 25.00 410.00

NQ DRILLING; SHALE FM. PROGRESS HAMPERED


KABITIRTHA 6/21/2020 DICD100H/1 MRKB 85/SP-6(C) 730 489.50 507.50 8.50 9.50 18.00 86 6/1/2020 -
DUE TO RAIN AND 100% W/LOSS IN BH

KABITIRTHA 6/21/2020 KDR 750(02) MRKB 87/SP-2(C) 660 133.10 162.20 14.60 14.50 29.10 102 6/18/2020 - HQ DRILLING; SHALE FM; PROGRESS HAMPERED
DUE TO RAIN

KABITIRTHA 6/21/2020 LY 44/01 MRKB 86/SP-3(C) 660 202.70 208.90 2.00 4.20 6.20 42 6/9/2020 - RIG REPAIRED; NQ DRILLING, HARD SHALE FM.
PROGRESS HAMPERED DUE TO RAIN

Sub Total - 53.30 230.00


BADAM 6/21/2020 RIG 3 100H/03 MABD-77/P-76 900 234 234 0.00 0.00 0.00 0 3/2/2020 - SUNDAY WEEKLY OFF

BADAM 6/21/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 117.4 117.4 0.00 0.00 0.00 0 6/16/2020 - SUNDAY WEEKLY OFF

BADAM 6/21/2020 Rig 2 LY-44/02 MABD-90/P-90 400 29.5 29.5 0.00 0.00 0.00 0 6/17/2020 - SUNDAY WEEKLY OFF

BADAM 6/21/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 326 326 0.00 0.00 0.00 0.00 0 6/1/2020 - SUNDAY WEEKLY OFF

BADAM 6/21/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 347.3 347.3 0.00 0.00 0.00 0 6/10/2020 - SUNDAY WEEKLY OFF
Sub Total - 0.00 0.00
HAMIRPUR 6/21/2020 0.00
SIKAR 6/21/2020 0.00

Sub Total - 0.00 0.00


Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III Closure
(m) (m) ment

SIKAR 6/21/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - RIG IDLE WAITING FOR HO DECISION


SIKAR 6/21/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0.00 0 5/29/2020 6/19/2020 RIG IDLE WAITING FOR HO DECISION
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS 6/21/2020 DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS 6/21/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/21/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/21/2020 RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00

KURMITAR 6/21/2020 Rig 4 - VOL-180 KIOM/52/57 21.00 25.60 4.60 0.00 4.60 0 6/12/2020 - DRILLING IN PROGRESS

KURMITAR 6/21/2020 Rig 5 - LY-38/02 KIOM/53/60 32.00 32.00 0.00 0.00 0.00 10 6/15/2020 6/20/2020 SHIFTING

Rig 6 - Dyna -
KURMITAR 6/21/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/21/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 10 - - SHIFTING
Sub Total - 4.60 20.00
WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA 6/21/2020 DY50CR/07 0.00
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA 6/21/2020 DY:50CR/11 0.00 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA 6/21/2020 LY:44 0.00 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

Sub Total - 0.00 0.00

BH CLOSED; BH IS IN CIRCULATION AND


ROTATION; 548 M NQ STRINGS WITH CORE
SOMAVARAM 6/21/2020 DY-100H/02 NPP-19 530 545.00 548.00 3.00 0.00 3.00 70 6/3/2020 - BARREL P/O TO SURFACE; TRIED TO RETRIEVE HQ
CASING BY PULLING BUT SNAPPED AT 100 M, P/O
TO SURFACE; 20 PAIR NQ ROD BREAKUP

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


SOMAVARAM 6/21/2020 Dy50CR/10 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


SOMAVARAM 6/21/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED AND


SOMAVARAM 6/21/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - LANDOWNERS DID NOT AGREE TO GIVE THEIR
LAND FOR DRILLING
Sub Total - 3.00 70.00

GSI MAHUDA 6/21/2020 0.00

Sub Total - 0.00 0.00


Location - North 8" DRILLING TO 46 M ; ALL RODS P/O FOR
AGUCHA UG 6/21/2020 UDD-330 255 CV SBH No. 34.00 46.00 12.00 0.00 12.00 0 6/19/2020 - SURVEY; ALL RODS LOWERED; NO DRILLING DONE
55 DUE TO DIESEL BROWSER B/D
Sub Total - 12.00 0.00
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I Day total HSD Commence SITE UPDATES REMARKS
(m) II III Closure
(m) (m) ment

RIG SETUP AT BH POINT AND CHECKED BY


AGUCHA SUR PF 6/21/2020 DIMP-175 Surface to -180 72 72 0 0 0.00 0 3/14/2020 -
SURVEYOR TEAM, SITE PREPARATION
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/21/2020 DW-35 FILL-02 BORE 0 0 0 0 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
6/21/2020 Dyna50H DD20BKE 0 0 0 0 0.00 0

Sub Total - 0.00 0.00

TDMA AGUCHA 6/21/2020 KDR-1200 RAE-025 L1 810 810 0 0 0.00 0 Hydco machine setup done , try to release jam
Sub Total - 0.00 0.00
DD20ZWE272(H CEMENT CUTTING; ROD GUIDE PLATE REPAIRED;
TDMA ZAWAR 6/21/2020 KDR-1200/02 20 24.00 45.00 6.00 15.00 21 0 6/19/2020 -
Q) 100 % W/ LOSS IN BH
Sub Total - 21.00 0.00

TSL DHANBAD 6/21/2020 WORKOVER RIG BH 04 248 248 0 0 0.00 NO REPORT

6/21/2020 BH 01 0.00 NO REPORT


Sub Total - 0.00 0.00

NGRI KOYNA 6/21/2020 DYNA 350 KBH-10-R 1500 793.00 793.00 0.00 0.00 0.00 0 1/22/2020 - RIG B/D

Sub Total - 0.00 0.00


NTPC LAND OWNER UNDER NEGOTIATION WITH
6/21/2020 LY - 44/01 1.00 1.00 0.00 0.00 0.00 0.00 0 6/20/2020 -
KERANDARI LOCALS; NO DRILLING DONE
0.00 0.00

KMA01 / 270° /
HZL KAYAD 6/21/2020 UCD 40 160 51.25 51.25 0.00 0.00 0.00 0.00 0 6/11/2020 - NO REPORT
+25°

Sub Total - 0.00 0.00

ZAWAR 6/21/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR 6/21/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR 6/21/2020 UCD 60-3 BI- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
430/134/80°/15°

ZAWAR 6/21/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
70°/0°
Sub Total - 0.00 0.00
Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II III total Closure
(m) (m) ment

DRILLING IN PROGRESS; NQ DRILLING; PROG.


PATRATU 6/20/2020 Dy(175/3) BH - 05 1000 575.00 600.00 15.00 10.00 25.00 270 5/22/2020 -
POOR DUE TO DOWN HOLE PROBLEM
Sub Total - 25.00 270.00

DRILLING IN PROGRESS; POOR PROG. DUE TO W/


KHARKHARI 6/20/2020 CDR-1000 MAKH 25-P-28 700 309.50 339.00 22.50 7.00 29.50 245.00 6/12/2020 -
LOSS AND GAS ENCONTERED

COAL CORE EXCISION AND ALL NQ ROD


KHARKHARI 6/20/2020 LY-44 MAKH-23-P-17 430 404.00 404.00 0.00 0.00 0.00 5/27/2020 6/19/2020
DISMANTLED
KHARKHARI 6/20/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.50 0.00 0.00 0.00 6/5/2020 - RIG B/D
GPL UNDER PROCESS; NQ ROD P/D UP TO 759 M
KHARKHARI 6/20/2020 DY-120/02 MAKH010-P-21 770 759.00 759.00 0.00 0.00 0.00 130.00 2/9/2020 6/18/2020 AS ELECTRIC TOOL HELD UP TA 739 M; BH
WASHED; GPL DONE UPTO 759 M

KHARKHARI 6/20/2020 KDR 750/03 MAKH-26-P-15 300 189.00 218.00 21.50 7.50 29.00 155.00 6/15/2020 - RIG STOPPED DUE TO ELECTRICAL SHORT CIRCUIT

DRILLING IN PROGRESS; PROGRESS POOR DUE TO


KHARKHARI 6/20/2020 Di - 8 MAKH-21-P-22 730 716.00 733.00 10.50 6.50 17.00 200.00 5/19/2020 -
VERY HARD FM.
Sub Total - 75.50 730.00

NQ DRILLING; SHALE FM. PROGRESS HAMPERED


KABITIRTHA 6/20/2020 DICD100H/1 MRKB 85/SP-6(C) 730 456.50 489.50 15.00 18.00 33.00 184 6/1/2020 -
DUE TO RAIN AND 100% W/LOSS IN BH

HQ DRILLING; SHALE FM; PROGRESS HAMPERED


KABITIRTHA 6/20/2020 KDR 750(02) MRKB 87/SP-2(C) 660 86.70 133.10 23.20 23.20 46.40 140 6/18/2020 -
DUE TO RAIN

CLUTCH REPAIRED; NQ DRILLING; SHALE FM. ;


KABITIRTHA 6/20/2020 LY 44/01 MRKB 86/SP-3(C) 660 194.20 202.70 3.00 5.50 8.50 47 6/9/2020 - RIG B/D AS HYD. SYSTEM NOT WORKING
PROPERLY; PROGRESS SUFFERED DUE TO RAIN
Sub Total - 87.90 371.00
BADAM 6/20/2020 RIG 3 100H/03 MABD-77/P-76 900 193.5 234 22.50 18.00 40.50 160 3/2/2020 - HQ DRILLING ;SAND STONE FM.

BADAM 6/20/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 94.9 117.4 11.10 11.40 22.50 130 6/16/2020 - HQ DRILLING; HQ, NQ LOWERED; NQ DRILLING

BADAM 6/20/2020 Rig 2 LY-44/02 MABD-90/P-90 400 12 29.5 8.00 9.50 17.50 80 6/17/2020 - ROCK DRILL PUMP B/D

TARGET DEPTH ACHIEVED. MACHINE STOPPED


BADAM 6/20/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 323.5 326 2.50 0.00 0.00 2.50 15 6/1/2020 -
BY GEOLOGIST; METAMORPHIC FM.

BADAM 6/20/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 309.2 347.3 20.10 18.00 38.10 162 6/10/2020 - HQ DRILLING; FRACTURED SHALE TO SHALE FM.

Sub Total - 121.10 547.00


HAMIRPUR 6/20/2020 0.00
SIKAR 6/20/2020 0.00
0.00
Sub Total - 0.00 0.00
SIKAR 6/20/2020 Dy 50CR/04 0 0 0 0 0.00 0 - - IDLE WAITING FOR HO DECISION

RIG AND MATERIALS SHIFTED TO MAIN CAMP;


SIKAR 6/20/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0.00 0 5/29/2020 6/19/2020
RIG CLEANING AND SHIFTING TO LOADING POINT

Sub Total - 0.00 0.00


Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II III total Closure
(m) (m) ment

RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE


GMRDS 6/20/2020 DY 35/01 0 0 0 0 0.00 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS 6/20/2020 LY 38/01 0 0 0 0 0.00 0
GMRDS 6/20/2020 LY 38/02 0 0 0 0 0.00 0
GMRDS 6/20/2020 RD/60 (REPL) 0 0 0 0 0.00 0
Sub Total - 0.00 0.00

KURMITAR 6/20/2020 Rig 4 - VOL-180 KIOM/52/57 21.00 21.00 0.00 0.00 0.00 0 6/12/2020 - DRILLING STOPPED DUE TO HEAVY RAIN

KURMITAR 6/20/2020 Rig 5 - LY-38/02 KIOM/53/60 32.00 32.00 0.00 0.00 0.00 0 6/15/2020 6/20/2020 DRILLING STOPPED DUE TO HEAVY RAIN

Rig 6 - Dyna -
KURMITAR 6/20/2020 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/20/2020 Rig 7 - LY-38/01 KIOM/00/00 0.00 0.00 0.00 0.00 0.00 0 - - SHIFTING STOPPED DUE TO HEAVY RAIN
Sub Total - 0.00 0.00
WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA 6/20/2020 DY50CR/07 0.00
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA 6/20/2020 DY:50CR/11 0.00 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA 6/20/2020 LY:44 0.00 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
SUMP PIT CLEANED; R/I NQ ROD FROM 158 M TO
SOMAVARAM 6/20/2020 DY-100H/02 NPP-19 530 511.00 545.00 14.50 19.50 34.00 140 6/3/2020 - 442 M BUT FOUND HELD UP; WASHED DOWN
AND REACHED BOTTOM; DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/20/2020 Dy50CR/10 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/20/2020 Dy50H/04 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/20/2020 Dy-50CR/01 NPP- 0.00 0.00 0.00 0.00 0.00 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 34.00 140.00

GSI MAHUDA 6/20/2020 0.00

Sub Total - 0.00 0.00


Location - North
8" DRILLING TO 22 M THE RODS P/O; RODS
AGUCHA UG 6/20/2020 UDD-330 255 CV SBH No. 1.00 34.00 21.00 12.00 33.00 0 6/19/2020 -
LOWERED AND DRILLED TO 34 M
55
Sub Total - 33.00 0.00
RIG SETUP AT BH POINTAND CHECKED BY
AGUCHA SUR PF 6/20/2020 DIMP-175 Surface to -180 72 72 0 0 0.00 0 3/14/2020 -
SURVEYOR TEAM, SITE PREPARATION
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/20/2020 DW-35 FILL-02 BORE 0 0 0 0 0.00 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


Starting Closing Date of
Rig Type T.D. SHIFT SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II III total Closure
(m) (m) ment

TDMA
BAMANIYA
6/20/2020 Dyna50H DD20BKE 0 0 0 0 0.00 0
Sub Total - 0.00 0.00

TDMA AGUCHA 6/20/2020 KDR-1200 RAE-025 L1 810 810 0 0 0.00 0 Hydco machine setup done , try to release jam

Sub Total - 0.00 0.00

DD20ZWE272(H DRILLING; 100% W/ LOSS; BARREL P/O; COMPLET


TDMA ZAWAR 6/20/2020 KDR-1200/02 20 12.00 24.00 12.00 0.00 12.00 0 6/19/2020 -
Q) HOLE CEMENTED; WOC; CEMENT CUTTING.

Sub Total - 12.00 0.00


24 M 6" CASING DONE;V - CUTTING AND
TSL DHANBAD 6/20/2020 WORKOVER RIG BH 04 248 248 0 0 0.00 20
WELDING WORK CONTINUING
6/20/2020 BH 01 SITE PREPARATION WORK CONTINUES
Sub Total - 0.00 20.00

NGRI KOYNA 6/20/2020 DYNA 350 KBH-10-R 1500 793.00 793.00 0.00 0.00 0.00 0 1/22/2020 - RIG B/D

Sub Total - 0.00 0.00


DRILLING STARTED AT 3.05 PM BUT LOCALS
NTPC CAME AND STOPPED DRILLING ACTIVITIES; LAND
6/20/2020 LY - 44/01 0.00 1.00 0.00 1.00 0.00 1.00 5 6/20/2020 -
KERANDARI OWNER UNDER DISCUSSION WITH LOCALS BUT
NO COMPROMISE REACHED.
1.00 5.00

FEED NOT WORKING; MACHINE STARTED LATE


KMA01 / 270° /
HZL KAYAD 6/20/2020 UCD 40 160 41.40 51.25 0.00 7.20 2.65 9.85 0 6/11/2020 - DUE TO LATE BLAST; HARD FM. POOR
+25°
VENTILATION; RIG B/D( FOOT CLAMP SEAL CUT).

Sub Total - 9.85 0.00

ZAWAR 6/20/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR 6/20/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR 6/20/2020 UCD 60-3 BI- 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
430/134/80°/15°

ZAWAR 6/20/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0.00 0 MACHINE SENT TO TDMA FATEHNAGAR
70°/0°
Sub Total - 0.00 0.00
Starting Closing Date of
Rig Type T.D. SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

DRILLING IN PROGRESS; NQ DRILLING; PROG.


PATRATU 6/19/2020 Dy(175/3) BH - 05 1000 536 575 22 17 39 250 5/22/2020 -
POOR DUE TO DOWN HOLE PROBLEM
Sub Total - 39.00 250.00

KHARKHARI 6/19/2020 CDR-1000 MAKH 25-P-28 700 260.20 309.5 29 20.3 49.30 280.00 6/12/2020 - DRILLING IN PROGRESS

BH CLOSED BY GEOLOGIST; ALL NQ RODS WITH


KHARKHARI 6/19/2020 LY-44 MAKH-23-P-17 430 404.00 404 0 0 0.00 20.00 5/27/2020 6/19/2020 BARREL P/O; ALL HQ CASING P/O AND
DISMANTLED
KHARKHARI 6/19/2020 KDR 750/01 MAKH-24-P-11 470 364.50 364.5 0 0 0.00 60.00 6/5/2020 - RIG B/D
KHARKHARI 6/19/2020 DY-120/01 MAKH012-P-24 760 767.50 767.5 0 0 0.00 40.00 2/19/2020 6/1/2020 RIG DISPATCHED TO HO

WAITING FOR GPL; LOGGER VAN COULD NOT


KHARKHARI 6/19/2020 DY-120/02 MAKH010-P-21 770 759.00 759 0 0 0.00 0.00 2/9/2020 6/18/2020
REACH SITE DUE TO BAD ROAD CONDITION;

KHARKHARI 6/19/2020 KDR 750/03 MAKH-26-P-15 300 147.50 189 25.5 16 41.50 165.00 6/15/2020 - DRILLING IN PROGRESS
KHARKHARI 6/19/2020 Di - 8 MAKH-21-P-22 730 691.50 716 12.5 12 24.50 200.00 5/19/2020 - DRILLING IN PROGRESS
Sub Total - 115.30 765.00

NQ DRILLING; SHALE FM. PROGRESS HAMPERED


KABITIRTHA 6/19/2020 DICD100H/1 MRKB 85/SP-6(C) 730 423.5 456.5 14.5 18.5 33 180 6/1/2020 -
DUE TO RAIN AND 100% W/LOSS IN BH

KABITIRTHA 6/19/2020 KDR 750(02) MRKB 87/SP-2(C) 660 46 86.7 23.3 17.4 40.7 116 6/18/2020 - HQ DRILLING; SHALE FM; PROGRESS HAMPERED
DUE TO RAIN

HQ DRILLING; HQ RODS P/O 194.2 M NA D THEN


R/I, 180 M NQ ROD PAIR MAKING; NO WORK
KABITIRTHA 6/19/2020 LY 44/01 MRKB 86/SP-3(C) 660 189.2 194.2 5 0 5 32 6/9/2020 - DONE IN 2ND SHIFT DUE TO CONTINUOUS
RAINFALL WHICH HAS LEFT 2 WORKERS SICK AS
NO RAIN COVER WAS AVAILABLE
Sub Total - 78.70 328.00
HQ CORING DRILLING COMMENCED IN 2ND
BADAM 6/19/2020 RIG 3 100H/03 MABD-77/P-76 900 177.55 193.5 0 15.95 15.95 150 3/2/2020 -
SHIFT; SHALE FM.

BADAM 6/19/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 60.80 94.9 17 17.1 34.10 144 6/16/2020 - DRILLING IN PROGRESS; SHALE FM.

BADAM 6/19/2020 Rig 2 LY-44/02 MABD-90/P-90 400 12.00 12 0 0 0.00 0 6/17/2020 - ROCK DRILL PUMP B/D

TARGET DEPTH ACHIEVED. MACHINE STOPPED


BADAM 6/19/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 309.00 323.5 14.5 0 14.50 50 6/1/2020 -
BY GEOLOGIST

BADAM 6/19/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 281.00 309.2 16.2 12 28.20 169 6/10/2020 - HQ DRILLING; SANDY SHALE TO SHALE FM.
Sub Total - 92.75 513.00
HAMIRPUR 6/18/2020
SIKAR 6/18/2020

Sub Total - 0.00 0.00


SIKAR 6/18/2020 Dy 50CR/04 0 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
SIKAR 6/18/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0 0 5/29/2020 6/19/2020 GPL COMPLETE; SITE WINDUP
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS 6/18/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS 6/18/2020 LY 38/01 0 0 0 0 0 0
GMRDS 6/18/2020 LY 38/02 0 0 0 0 0 0

GMRDS 6/18/2020 RD/60 (REPL) 0 0 0 0 0 0

Sub Total - 0.00 0.00


Rig 4 - VOL-
KURMITAR 6/19/2020 KIOM/52/57 13 21 8 0 8 0 6/12/2020 - DRILLING IN PROGRESS
180
Rig 5 - LY-
KURMITAR 6/19/2020 KIOM/53/60 24.5 32 7.5 0 7.5 10 6/15/2020 - DRILLING IN PROGRESS
38/02
Rig 6 - Dyna -
KURMITAR 6/19/2020 KIOM/00/00 0 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/19/2020 Rig 7 - LY-38/01KIOM/50/62 43.25 43.25 0 0 0 10 6/4/2020 6/18/2020 SHIFTING
Sub Total - 15.50 20.00
WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA 6/18/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA 6/18/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA 6/18/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT


Sub Total - 0.00 0.00
DRILLING IN PROGRESS; NQ RODS P/O TO
SURFACE AS INNER TUBE JAMMED; CORE BARREL
SOMAVARAM 6/19/2020 DY-100H/02 NPP-19 530 472 511 25.5 13.5 39 165 6/3/2020 -
CLEANED AND R/I 158 M NQ RODS WITH CORE
BARREL

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/19/2020 Dy50CR/10 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/19/2020 Dy50H/04 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/19/2020 Dy-50CR/01 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 39.00 165.00

GSI MAHUDA 6/18/2020

Sub Total - 0.00 0.00


Location - North GUIDE CRACKED; MACHINE SETUP AT NEW
AGUCHA UG 6/19/2020 UDD-330 255 CV SBH No. 0 1 0 1 1 0 6/19/2020 - POINT; NEW GUIDE SHIFTED TO UG AND
55 DRILLING STARTED
Sub Total - 1.00 0.00

AGUCHA SUR PF 6/19/2020 DIMP-175 Surface to -180 72 72 0 0 0 0 3/14/2020 - SITE PREPARATION IN PROGRESS
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/19/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
6/19/2020 Dyna50H DD20BKE 0 0 0 0 0 0

Sub Total - 0.00 0.00

TDMA AGUCHA 6/19/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 Hydco machine setup done , try to release jam
Sub Total - 0.00 0.00
DD20ZWE272(H
TDMA ZAWAR 6/19/2020 KDR-1200/02 20 0.00 12.00 2.50 9.50 12 0 6/19/2020 -
Q)
Sub Total - 12.00 0.00
WORKOVER 24 M 6" CASING DONE;V - CUTTING AND
TSL DHANBAD 6/19/2020 BH 04 248 248 0 0 0 20
RIG WELDING WORK CONTINUING
6/19/2020 BH 01 SITE PREPARATION WORK CONTINUES
Sub Total - 0.00 20.00
RIG B/D; WIRELINE WINCH NOT WORKING;
WHEN WIWRELINE MOTOR DISMANTLED SEEN
NGRI KOYNA 6/19/2020 DYNA 350 KBH-10-R 793 793.00 0 0 0 0 1/22/2020 - THAT SYNCHRONISING COUPLING DAMAGED;
PART GIVEN TO KOLHAPUR WORKSHOP FOR IT
TO BE MADE
Sub Total - 0.00 0.00

Starting Closing Date of


Rig Type T.D. SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I SHIFT III Day total Commence SITE UPDATES REMARKS
(m) II Closure
(m) (m) ment

LOCAL PEOPLE ARE POSING AS HINDRANCE TO


START DRILLING ACTIVITY; DISCUSSION OF LAND
NTPC
6/18/2020 LY - 44/01 0 0 0 0 0 0 - - OWNER AND NTPC OFFICIALS WITH LOCALS BUT
KERANDARI
NO COMPROMISATION REACHED; DISCUSSION
CONTINUES

0.00

MICRO FEED CARTRIDGE NOT WORKING; 4 TIMES


KMA01 / 270° / H/L FOR BIT CHOPPING; MACHINE STARTED LATE
HZL KAYAD 6/19/2020 UCD 40 110 30.35 41.5 0 3.85 7.2 11.15 6/11/2020 -
+25° DUE TO LATE BLAST; VERY HARD AND
FRACTURED FM. POOR VENTILATION.

Sub Total - 11.15

ZAWAR 6/18/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR 6/18/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR 6/18/2020 UCD 60-3 BI- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


430/134/80°/15°

ZAWAR 6/18/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


70°/0°
Sub Total - 0.00
Starting Closing Date of
Rig Type T.D. SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

1" HOSE PIPE DAMAGED, CHANGED AND


PATRATU 6/18/2020 Dy(175/3) BH - 05 1000 519 536 5 12 17 190 5/22/2020 - DRILLING STARTED; PROGRESS POOR DUE TO
HARD FM.
Sub Total - 17.00 190.00

KHARKHARI 6/18/2020 CDR-1000 MAKH 25-P-28 700 210.90 260.2 27 22.3 49.30 265.00 6/12/2020 - DRILLING IN PROGRESS

KHARKHARI 6/18/2020 LY-44 MAKH-23-P-17 430 388.00 404 7 9 16.00 80.00 5/27/2020 - DRILLING IN PROGRESS

KHARKHARI 6/18/2020 KDR 750/01 MAKH-24-P-11 470 354.00 364.5 10.5 0 10.50 140.00 6/5/2020 - DRILLING IN PROGRESS; NQ ROD STUCK IN HOLE
SO FISHING OPERATION IS UNDERWAY

KHARKHARI 6/18/2020 DY-120/01 MAKH012-P-24 760 767.50 767.5 0 0 0.00 0.00 2/19/2020 6/1/2020 RIG SHIFTING NOT POSSIBLE DUE TO LAND
OWNER'S OBJECTION

BH CLOSED AD WAITING FOR GPL; BH WASHED


KHARKHARI 6/18/2020 DY-120/02 MAKH010-P-21 770 756.90 759 2.1 0 2.10 160.00 2/9/2020 6/18/2020
AND COMPLETE RODS WITH BARREL P/O

DRILLING IN PROGRESS; PROG. POOR IN 2ND


KHARKHARI 6/18/2020 KDR 750/03 MAKH-26-P-15 300 119.00 147.5 22.5 6 28.50 120.00 6/15/2020 - SHIFT AS WORK WAS STOPPED BY LOCAL
VILLAGERS
KHARKHARI 6/18/2020 Di - 8 MAKH-21-P-22 730 669.50 691.5 9 13 22.00 190.00 5/19/2020 - DRILLING IN PROGRESS
Sub Total - 128.40 955.00

NQ DRILLING; NQ P/O 120 M; 100% W/ LOSS IN


KABITIRTHA 6/18/2020 DICD100H/1 MRKB 85/SP-6(C) 730 399.5 423.5 17 7 24 151 6/1/2020 - BH; BIT CHANGED ND 416.5 M ROD R/I; BH
WASHED; FRACTURED SHLE AND SANDSTONE
FM. PROGRESS HAMPERED DUE TO RAIN

114 M DIA NC DRILLING; 12 MHW LINER


KABITIRTHA 6/18/2020 KDR 750(02) MRKB 87/SP-2(C) 660 0 46 22.8 23.2 46 129 - - LOWERED HQ DRILLING; SHALE FM.; PROGRESS
HAMPERED DUE TO RAIN

CLUTCH REPAIRED; HQ DRILLING; SHALE FM;


KABITIRTHA 6/18/2020 LY 44/01 MRKB 86/SP-3(C) 660 167.8 189.2 10.9 10.5 21.4 64 6/9/2020 -
PROGRESS HAMPERED DUE TO RAIN

Sub Total - 91.40 344.00


REDRILLING BH SUSPENDED AT 177.55 M; 58.10
BADAM 6/18/2020 RIG 3 100H/03 MABD-77/P-76 900 177.55 177.55 0 0 0.00 150 3/2/2020 Re-drilling
M N/C HQ DRILLING TO 147 M
DRILLING IN PROGRESS; SANDY SHALE TO SHALE
BADAM 6/18/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 26.40 60.8 17.4 17 34.40 137 6/16/2020 -
FM.

BADAM 6/18/2020 Rig 2 LY-44/02 MABD-90/P-90 400 12.00 12 0 0 0.00 6/17/2020 - DRILLING IN PROGRESS; COAL AND SHALE FM.

BADAM 6/18/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 278.50 309 17 13.5 30.50 100 6/1/2020 - NQ DRILLING IN PROGRESS; SHALE AND SANDY
SHALE FM.

BADAM 6/18/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 245.70 281 18.3 17 35.30 169 6/10/2020 - HQ DRILLING; SANDY SHALE TO SHALE FM.
Sub Total - 100.20 556.00
HAMIRPUR 6/18/2020
SIKAR 6/18/2020

Sub Total - 0.00 0.00


SIKAR 6/18/2020 Dy 50CR/04 0 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
SIKAR 6/18/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0 0 5/29/2020 - WAITING FOR GPL
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS 6/18/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS 6/18/2020 LY 38/01 0 0 0 0 0 0
GMRDS 6/18/2020 LY 38/02 0 0 0 0 0 0

GMRDS 6/18/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00
Rig 4 - VOL-
KURMITAR 6/18/2020 KIOM/52/57 6 13 7 0 7 0 6/12/2020 - DRILLING IN PROGRESS
180
Rig 5 - LY-
KURMITAR 6/18/2020 KIOM/53/60 17.8 24.5 6.7 0 6.7 10 6/15/2020 - DRILLING IN PROGRESS
38/02
Rig 6 - Dyna -
KURMITAR 6/18/2020 KIOM/00/00 0 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/18/2020 Rig 7 - LY-38/01KIOM/50/62 42 43.25 1.25 0 1.25 10 6/4/2020 6/18/2020 BH CLOSED
Sub Total - 14.95 20.00

CHOTIA 6/18/2020 DY50CR/07 WORK TERMINATED; RIG SHIFTED TO CAMP FOR


CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA 6/18/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA 6/18/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

Sub Total - 0.00 0.00


SOMAVARAM 6/18/2020 DY-100H/02 NPP-19 530 425.5 472 23.5 23 46.5 150 6/3/2020 - DRILLING IN PROGRESS
RIG IDLE AT CAMP AS CULTIVATION STARTED
SOMAVARAM 6/18/2020 Dy50CR/10 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/18/2020 Dy50H/04 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING

RIG IDLE AT CAMP AS CULTIVATION STARTED


SOMAVARAM 6/18/2020 Dy-50CR/01 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 46.50 150.00

GSI MAHUDA 6/18/2020

Sub Total - 0.00 0.00


COMPRESSOR SEPARATOR, HYD, FILTER AND
Location - North
HYD. OIL CHANGED; NRB FITTED AND 8" DILLING
AGUCHA UG 6/18/2020 UDD-330 255 CV SBH No. 58 61.5 3.5 0 3.5 0 6/13/2020 6/18/2020
DONE UPTO 61.50 M; NO WORK DONE IN 2ND
54
SHIFT
Sub Total - 3.50 0.00

AGUCHA SUR PF 6/18/2020 DIMP-175 Surface to -180 72 72 0 0 3/14/2020 - POI RELEASED, POINT LOCATED

Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/18/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
6/18/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA 6/18/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR 6/18/2020 KDR-1200/02 417 417 0 0 0 0 3/1/2020 - WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00

TSL DHANBAD 6/18/2020 WORKOVER BH 04 248 248 0 0 0 20 30 M 6" CASING DONE;V - CUTTING AND
RIG WELDING WORK CONTINUING
SHIFTING OF LY 38 MACHINE FROM BASTACOLLA
6/18/2020 BH 01
TO SIJUA COLLIERY
Sub Total - 0.00 20.00

RIG B/D; WIRELINE WINCH NOT WORKING;


NGRI KOYNA 6/18/2020 DYNA 350 KBH-10-R 785.1 793.00 7.9 0 7.9 190 1/22/2020 - WHEN WIWRELINE MOTOR DISMANTLED SEEN
THAT SYNCHRONISING COUPLING DAMAGED

Sub Total - 7.90 190.00

Starting Closing Date of


Rig Type T.D. SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I SHIFT III Day total Commence SITE UPDATES REMARKS
(m) II Closure
(m) (m) ment

LOCAL PEOPLE ARE POSING AS HINDRANCE TO


START DRILLING ACTIVITY; DISCUSSION OF LAND
NTPC 6/18/2020 LY - 44/01 0 0 0 0 0 0 - - OWNER WITH LOCALS BUT NO
KERANDARI
COMPROMISATION REACHED; DISCUSSION
CONTINUES

0.00

MICRO FEED CARTRIDGE NOT WORKING; ROD


KMA01 / 270° / BROKEN IN HOLE, FISHING; MACHINE STARTED
HZL KAYAD 6/18/2020 UCD 40 110 26.3 30.35 0 3.2 0.85 4.05 6/11/2020 -
+25° LATE DUE TO LATE BLAST; VERY HARD AND
FRACTURED FM. POOR VENTILATION.

Sub Total - 4.05

ZAWAR 6/18/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR 6/18/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR 6/18/2020 UCD 60-3 BI- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


430/134/80°/15°

ZAWAR 6/18/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


70°/0°
Sub Total - 0.00
Starting Closing Date of
Rig Type T.D. SHIFT Day Date of
SITE DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

KHARKHARI 6/17/2020 CDR-1000 MAKH 25-P-28 700 163.20 210.9 27 20.7 47.70 270.00 6/12/2020 - DRILLING IN PROGRESS

KHARKHARI 6/17/2020 LY-44 MAKH-23-P-17 430 369.50 388 10.5 8 18.50 80.00 5/27/2020 - DRILLING IN PROGRESS

DRILLING PROG. POOR DUE TO JAMMING AND


Video Call through Shyamacharan regarding RPM,
BLOCKING TENDENCY ALL NQ ROD WITH BARREL
KHARKHARI 6/17/2020 KDR 750/01 MAKH-24-P-11 470 346.20 354 6 1.8 7.80 140.00 6/5/2020 - water return, viscosity. Current Solution and action to
P/O AFTER BARREL CHANGE P/D; POOR PROG
be taken
DUE TO DOWN HOLE PROBLEM

KHARKHARI 6/17/2020 DY-120/01 MAKH012-P-24 760 767.50 767.5 0 0 0.00 0.00 2/19/2020 6/1/2020 RIG SHIFTING NOT POSSIBLE DUE TO LAND
OWNER'S OBJECTION Rig is to be shifted to Maindhemo asap
KHARKHARI 6/17/2020 DY-120/02 MAKH010-P-21 770 747.50 756.9 5 4.4 9.40 220.00 2/9/2020 - POOR PROG. DUE TO 100% W/LOSS AND
BLOCKING AND JAMMING TENDENCY

DRILLING IN PROGRESS; PROG. POOR IN 2ND


SHIFT AS HQ RODS WITH BARREL P/O; HQ
KHARKHARI 6/17/2020 KDR 750/03 MAKH-26-P-15 300 85.00 119 29 5 34.00 150.00 6/15/2020 -
CASING DONE UPTO 114 M, NQ ROD WITH
BARREL P/D THEN R/I
KHARKHARI 6/17/2020 Di - 8 MAKH-21-P-22 730 647.50 669.5 13.5 8.5 22.00 200.00 5/19/2020 - DRILLING IN PROGRESS
Sub Total - 139.40 1060.00 Rod Grease is to be sent

REDRILLING BH SUSPENDED AT 177.55 M; 36 M


BADAM 6/17/2020 RIG 3 100H/03 MABD-77/P-76 900 177.55 177.55 0 0 0.00 81 3/2/2020 Re-drilling N/C HQ DRILLING TO 88.90 M; OPERATOR
SHORTAGE SO NO WORK DONE IN 2ND SHIFT

WATER ARRANGEMENTS DONE; HW LINER


REAMING FOR 18.70 M; HQ DRILLING; NO WORK
BADAM 6/17/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 21.40 26.4 5 0 5.00 57 6/16/2020 -
DONE IN 2ND SHIFT DUE TO SHORTAGE OF
OPERATOR

WATER ARRANGEMENT DONE; PX DRILLING 4 M;


BADAM 6/17/2020 Rig 2 LY-44/02 MABD-90/P-90 400 0.00 12 4 8 12.00 40 6/17/2020 -
HW LINER LOWERED UPTO 12 M; SAND FM.

NQ DRILLING IN PROGRESS; SHALE AND SANDY


BADAM 6/17/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 238.00 278.5 22.5 18 40.50 125 6/1/2020 -
SHALE FM.

BADAM 6/17/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 202.50 245.7 22.5 20.7 43.20 180 6/10/2020 - HQ DRILLING; SHALE FM.

Sub Total - 100.70 483.00


RIG MAINTENANCE DONE AND VIBRATION PLATE
FITTED; NQ ROD WITH CORE BARREL R/I UPTO
SOMAVARAM 6/17/2020 DY-100H/02 NPP-19 530 397.5 425.5 14 14 28 100 6/3/2020 -
BOTTOM; 1.80 M HQ CASING ADDED; PROGRESS
HINDERED BY RAIN

GPL DONE; ALL TYPE OF ROD, CASING PAIR


SOMAVARAM 6/17/2020 Dy50CR/10 NPP-73 349 349 0 0 0 5 5/31/2020 6/15/2020 BREAKUP; RIG AND PARTIALLY MATERIALS
SHIFTED TO CAMP
SOMAVARAM 6/17/2020 Dy50H/04 NPP- 0 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
RIG IDLE AT CAMP AS CULTIVATION STARTED
SOMAVARAM 6/17/2020 Dy-50CR/01 NPP- 0 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 28.00 105.00
Rig 4 - VOL-
KURMITAR 6/17/2020 KIOM/52/57 3 6 3 0 3 0 6/12/2020 - DRILLING IN PROGRESS
180
Rig 5 - LY-
KURMITAR 6/17/2020 KIOM/53/60 12.1 17.8 5.7 0 5.7 10 6/15/2020 - DRILLING IN PROGRESS
38/02
Rig 6 - Dyna -
KURMITAR 6/17/2020 KIOM/00/00 0 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR 6/17/2020 Rig 7 - LY-38/01KIOM/50/62 40.5 42 1.5 0 1.5 10 6/4/2020 - DRILLING IN PROGRESS
Sub Total - 10.20 20.00

RIG REPAIRED; HQ ROD HOISTED 519 M; HQ


CASING CONNECTED TILL 519 M; NQ ROD PAIRED
PATRATU 6/17/2020 Dy(175/3) BH - 05 1000 519 519 0 0 0 160 5/22/2020 -
AND LOWERED TILL 450 M; FOOT CLAMP
DAMAGED SO HOISTING AND LOWERING SLOW

Sub Total - 0.00 160.00


HAMIRPUR 6/17/2020
SIKAR 6/17/2020

Sub Total - 0.00 0.00


SIKAR 6/17/2020 Dy 50CR/04 0 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
SIKAR 6/17/2020 Dy 50CR/05 GKDC-27 500 500 0 0 0 0 5/29/2020 - WAITING FOR GPL
Sub Total - 0.00 0.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS 6/17/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS 6/17/2020 LY 38/01 0 0 0 0 0 0
GMRDS 6/17/2020 LY 38/02 0 0 0 0 0 0

GMRDS 6/17/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00

OLD NQ BIT CUT AND BH CLEANED; NQ CORE


KABITIRTHA 6/17/2020 DICD100H/1 MRKB 85/SP-6(C) 730 377.5 399.5 4.5 17.5 22 141 6/1/2020 - DRILLING IN PROGRESS; 100 % W/ LOSS IN BH;
HARD SHALE FM.

RIG WITH ALL DRILL MATERIALS SHIFTED TO NEW


KABITIRTHA 6/17/2020 KDR 750(02) MRKB 87/SP-2(C) 660 0 0 0 0 0 14 - - POINT; RIG SETTING AND SITE PREPARATION; NO
WORK DONE IN 2ND SHIFT AS ALL WORKERS
WERE ENGAGED IN RIG SHIFTING DUTY
HQ DRILLING; RIG B/D( HYDRAULIC PUMP CHAIN
SPROCKET DAMAGED)ARRANGED FROM HO AND
KABITIRTHA 6/17/2020 LY 44/01 MRKB 86/SP-3(C) 660 162.6 167.8 2 3.2 5.2 23 6/9/2020 -
FITTED; CLUTCH NOT WORKING PROPERLY SO NO
WORK DONE
Sub Total - 27.20 178.00
8" DRILLING DONE FROM 55 M TO 58
Location - North
M;COMPRESSOR B/D, SEPARATOR FILTER
AGUCHA UG 6/17/2020 UDD-330 255 CV SBH No. 55 58 0 3 3 0 6/13/2020 -
CHOKED, NON RETURN VALVE LEAKAGE;
54
REPAIRING
Sub Total - 3.00 0.00

AGUCHA SUR PF 6/17/2020 DIMP-175 Surface to -180 72 72 0 0 3/14/2020 - POI RELEASED, POINT LOCATED
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM 6/17/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
6/17/2020 Dyna50H DD20BKE 0 0 0 0 0 0

Sub Total - 0.00 0.00


TDMA AGUCHA 6/17/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR 6/17/2020 KDR-1200/02 417 417 0 0 0 0 3/1/2020 - WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00

TSL DHANBAD 6/17/2020 WORKOVER BH 04 248 248 0 0 0 20 30 M 6" CASING DONE;V - CUTTING AND
RIG WELDING WORK CONTINUING
6/17/2020 BH 01 SITE PREP WORK CONTINUING
Sub Total - 0.00 20.00

RIG B/D; WIRELINE PULLEY PROBLEM; MAST


DOWN, ALL PULLEY CHECKED AND FOUND
NGRI KOYNA 6/17/2020 DYNA 350 KBH-10-R 785.1 785.10 0 0 0 0 1/22/2020 - THATBEARING DAMAGED; BEARING NOT
AVAILABLE IN LOCAL MARKET, ORDERED AND
WILL GET BEARING ON 18.06.20

Sub Total - 0.00 0.00


WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA 6/17/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA 6/17/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA 6/17/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

Sub Total - 0.00 0.00

Starting Closing Date of


Rig Type T.D. SHIFT Date of
SITE DATE BH NO Depth Depth SHIFT I SHIFT III Day total Commence SITE UPDATES REMARKS
(m) II Closure
(m) (m) ment

MACHINE SHIFTED TO BH POINT; MACHINE


SETTING AND GROUTING; MATERIALS SHIFTED
NTPC KERANDARI 6/17/2020 LY - 44/01 0 0 0 0 0 0 - -
TO BH POINT. DRILLING COULD NOT BE STARTED
DUE TO RAIN
0.00
CREW LATE DUE TO LATE BLAST. GMC LOOSE
KMA01 / 270° / DRESSING; POWERCUT;H/L EACH RUN FOR BIT
HZL KAYAD 6/17/2020 UCD 40 110 19.5 26.3 2.05 4.75 0 6.8 6/11/2020 -
+25° CHOPPING; POOR VENTILATION; VERY HARD
FRACTURED FM.
Sub Total - 6.80

ZAWAR 6/17/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR 6/17/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR 6/17/2020 UCD 60-3 BI- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


430/134/80°/15°

ZAWAR 6/17/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR


70°/0°
Sub Total - 0.00
Starting Closing Date of
Rig Type T.D. SHIFT Day Date of
SITE MONTH DATE BH NO Depth Depth SHIFT I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

KHARKHARI June,20 6/16/2020 CDR-1000 MAKH 25-P-28 700 109.40 163.2 31.5 22.3 53.80 270.00 6/12/2020 - DRILLING IN PROGRESS

KHARKHARI June,20 6/16/2020 LY-44 MAKH-23-P-17 430 347.50 369.5 12 10 22.00 80.00 5/27/2020 - DRILLING IN PROGRESS
DRILLING PROG. POOR DUE TO JAMMING AND
KHARKHARI June,20 6/16/2020 KDR 750/01 MAKH-24-P-11 470 343.20 346.2 0 3 3.00 110.00 6/5/2020 - BLOCKING TENDENCY ALL NQ ROD WITH BARREL Viscosity is fine now 46 as per the video.
P/O AND P/D; POOR PROG DUE TO DOWN HOLE
PROBLEM

RIG SHIFTING NOT POSSIBLE DUE TO LAND


KHARKHARI June,20 6/16/2020 DY-120/01 MAKH012-P-24 760 767.50 767.5 0 0 0.00 2/19/2020 6/1/2020
OWNER'S OBJECTION
POOR PROG. DUE TO 100% W/LOSS AND
KHARKHARI June,20 6/16/2020 DY-120/02 MAKH010-P-21 770 739.00 747.5 4 4.5 8.50 220.00 2/9/2020 -
BLOCKING AND JAMMING TENDENCY
KHARKHARI June,20 6/16/2020 KDR 750/03 MAKH-26-P-15 300 24.00 85 32 29 61.00 160.00 6/15/2020 - DRILLING IN PROGRESS

KHARKHARI June,20 6/16/2020 Di - 8 MAKH-21-P-22 730 632.50 647.5 4 11 15.00 160.00 5/19/2020 - BIT CHANGED AND ALL NT ROD WITH BARREL
PULLED DOWN; DRILLING IN PROGRESS

Sub Total - 163.30 1000.00


REDRILLING BH SUSPENDED AT 177.55 M;
BADAM June,20 6/16/2020 RIG 3 100H/03 MABD-77/P-76 900 177.55 177.55 0 0 0.00 58 3/2/2020 Re-drilling Where is the operator?
22.90M N/C HQ DRILLING TO 52.90 M
MACHINE SETTING AND SITE PREPARATION; HQ
BADAM June,20 6/16/2020 RIG 4 DI-17/01 MABD-89 /P-80 450 0.00 21.4 0 21.4 21.40 87 6/16/2020 -
DRILLING; SAND FM.
MACHINE SETTING AND CEMENT GROUTING AT
BADAM June,20 6/16/2020 Rig 2 LY-44/02 MABD-90/P-90 400 0.00 0 0 0 0.00 10 - -
NEW POINT P-90
NQ DRILLING IN PROGRESS; FRACTURED SHALE
BADAM June,20 6/16/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 211.50 238 12 14.5 26.50 100 6/1/2020 -
AND SANDY SHALE FM.

BADAM June,20 6/16/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 168.90 202.5 16 17.6 33.60 180 6/10/2020 - HQ DRILLING; SANDY SHALE FM.
Sub Total - 81.50 435.00

HQ CASING REAMING FROM 275 M TO 397.50 M.


BH WASHED; 20 PAIR HQ RODS P/O; P/O 281.50
M TO SURFACE; HQ CASING R/I UPTO 361.50 M
SOMAVARAM June,20 6/16/2020 DY-100H/02 NPP-19 530 397.5 397.5 0 0 0 90 6/3/2020 - BUT FOUND HELD UP , FURTHER 36 M REACHED
BY CIRCULATION AND ROTATION; R/I NQ ROD
WITH CORE BARREL UPTO 121.50 M; RAINS
HINDERED WORK

SOMAVARAM June,20 6/16/2020 Dy50CR/10 NPP-73 349 349 0 0 0 40 5/31/2020 6/15/2020 BH CLOSED;UNDER GPL; UNSCREWED 211 M HQ
CASING; 6 M LIH; HW LINER RETRIEVED
SOMAVARAM June,20 6/16/2020 Dy50H/04 NPP- 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
RIG IDLE AT CAMP AS CULTIVATION STARTED
SOMAVARAM June,20 6/16/2020 Dy-50CR/01 NPP- 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 0.00 130.00

KURMITAR June,20 6/16/2020 Rig 4 - VOL- KIOM/52/57 2 3 1 0 1 6/12/2020 - DRILLING IN PROGRESS


180
Rig 5 - LY-
KURMITAR June,20 6/16/2020 KIOM/53/60 5.6 12.1 6.5 0 6.5 10 6/15/2020 - DRILLING IN PROGRESS
38/02
Rig 6 - Dyna -
KURMITAR June,20 6/16/2020 KIOM/00/00 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR June,20 6/16/2020 Rig 7 - LY-38/01KIOM/50/62 35.5 40.5 5 0 5 10 6/4/2020 - DRILLING IN PROGRESS
Sub Total - 12.50 20.00
1/4 " HYDRAULIC PIPE DAMAGED, CHANGED BUT
PATRATU June,20 6/16/2020 Dy(175/3) BH - 05 1000 497 519 14 8 22 190 5/22/2020 - Viscosity measurement video should be sent
DAMAGED AGAIN; PROGRESS POOR
Sub Total - 22.00 190.00
Shall try asap to send to Hamirpur alongwith one
SIKAR June,20 6/16/2020 Dy 50CR/04 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
operator so that work can start.

TARGET DEPTH ACHIEVED; AFTER DECISION BH Currently quarantine going on for the five workers
SIKAR June,20 6/16/2020 Dy 50CR/05 GKDC-27 487 500 8 5 13 85 5/29/2020 -
EXTENDED 10 M; 100% W/LOSS AND HARD FM. reached to Hamirpur.

Sub Total - 13.00 85.00


RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS June,20 6/16/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/16/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/16/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/16/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00
FISHING OPERATION; 377.50 M NQ DRILL ROD
AFTER NQ IMP ORE BIT CHIPPING; BIT CUTTING;
180 M DRILL ROD P/O DUE TO HIGH
TORQUE;197.50 M MORE DRILL ROD P/O AS IMP
KABITIRTHA June,20 6/16/2020 DICD100H/1 MRKB 85/SP-6(C) 730 377.5 377.5 0 0 0 84 6/1/2020 - Drilling should start from 2nd shift today
BIT DMAGED; R/I 377.50 M ROD WITH AX ST
CORE BARREL WITH IMP CORE BIT; AX BIT
DAMAGED SO P/O 377.50 M ROD; 100% W/LOSS
IN BH.
BH CLOSED BY CMPDI; 620 M NQ ROD P/O AND
KABITIRTHA June,20 6/16/2020 KDR 750(02) MRKB 84/SP-1(C) 610 620.5 625 4.5 0 4.5 102 5/29/2020 6/16/2020 DISMANTLED, 215 M HQ ROD P/O AND Drilling should start from tomorrow
DISMANTLED, 12 M HW LINER P/O AND
DISMANTLED

KABITIRTHA June,20 6/16/2020 LY 44/01 MRKB 86/SP-3(C) 660 145.3 162.6 7.8 9.5 17.3 81 6/9/2020 - HQ DRILLING; PROGRESS LOW DUE TO HARD FM.

Sub Total - 21.80 267.00


Location - North
8" DRILLING DONE FROM 37 M TO 55 M; H/L AT
AGUCHA UG June,20 6/16/2020 UDD-330 255 CV SBH No. 37 55 0 18 18 0 6/13/2020 -
46 M DEPTH FOR BH SURVEY
54
Sub Total - 18.00 0.00

AGUCHA SUR PF June,20 6/16/2020 DIMP-175 Surface to -180 72 72 0 0 3/14/2020 - WAITING FOR POI

Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June,20 6/16/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June,20 6/16/2020 Dyna50H DD20BKE 0 0 0 0 0 0

Sub Total - 0.00 0.00


TDMA AGUCHA June,20 6/16/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June,20 6/16/2020 KDR-1200/02 417 417 0 0 0 0 3/1/2020 - WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00
WORKOVER 24 M 6" CASING DONE;V - CUTTING AND
TSL DHANBAD June,20 6/16/2020 BH 04 248 248 0 0 0 15
RIG WELDING WORK CONTINUING
June,20 6/16/2020 BH 01 SITE PREP WORK CONTINUING
Sub Total - 0.00 15.00
HQ LOWERED UPTO BOTTOM BUT INTERRUPTED
BY RAIN; HQ DRILLING FROM 766.90 M TO
NGRI KOYNA June,20 6/16/2020 DYNA 350 KBH-10-R 766.9 785.10 4 14.2 18.2 290 1/22/2020 - 785.10 M; WHILE RETREIVING INNER TUBE
WIRELINE ROPE BROKE, 15 PAIRS HQ RODS
HOISTED AND ROPE MANUALLY ENGAGED

Sub Total - 18.20 290.00


WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA June,20 6/16/2020 DY50CR/07 Rig should be shifted asap to Dhanbad Tata
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA June,20 6/16/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

Today truck is reaching site to be shifted to Hamirpur


BABJA June,20 6/16/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
alongwith manpower.
Sub Total - 0.00 0.00

Starting Closing Date of


Rig Type T.D. SHIFT Date of
SITE MONTH DATE BH NO Depth Depth SHIFT I SHIFT III Day total Commence SITE UPDATES REMARKS
(m) II Closure
(m) (m) ment

CREW LATE DUE TO LATE BLAST. GMC LOOSE


KMA01 / 270° /
HZL KAYAD June,20 6/16/2020 UCD 40 110 9.65 19.5 0 9.85 0 9.85 6/11/2020 - DRESSING; BIT CHANGED; POOR VENTILATION
+25°
HARD FRACTURED FM.
Sub Total - 111.50

ZAWAR June,20 6/16/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR June,20 6/16/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR June,20 6/16/2020 UCD 60-3 BI- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
430/134/80°/15°

ZAWAR June,20 6/16/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
70°/0°
Sub Total - 0.00
MAHUDA Send Supervisor to area to setup camp asap
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

KHARKHARI June,20 6/15/2020 CDR-1000 MAKH 25-P-28 700 65.90 109.4 22.5 21 43.50 220.00 6/12/2020 - DRILLING IN PROGRESS

KHARKHARI June,20 6/15/2020 LY-44 MAKH-23-P-17 430 328.00 347.5 8.5 11 19.50 80.00 5/27/2020 - DRILLING IN PROGRESS
DRILLING PROG. POOR DUE TO JAMMING AND Shear Zone & Highly Fractured. Machine not
KHARKHARI June,20 6/15/2020 KDR 750/01 MAKH-24-P-11 470 336.50 343.2 4.3 2.4 6.70 100.00 6/5/2020 - BLOCKING TENDENCY AND ALSO HINDERED DUE progressing further. Video recording of mud viscosity
TO HIGHLY BROKEN FM. required.
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/15/2020 DY-120/01 MAKH012-P-24 760 767.50 767.5 0 0 0.00 2/19/2020 6/1/2020
OWNER'S OBJECTION
POOR PROG. DUE TO 100% W/LOSS AND
KHARKHARI June,20 6/15/2020 DY-120/02 MAKH010-P-21 770 730.00 739 2.6 6.4 9.00 200.00 2/9/2020 -
BLOCKING AND JAMMING TENDENCY
RIG SHIFTED AND SET TO NEW POINT P-15; HQ
KHARKHARI June,20 6/15/2020 KDR 750/03 MAKH-26-P-15 300 0.00 24 9 15 24.00 130.00 6/15/2020 -
DRILLING IN PROGRESS
DRILLING IN PROGRESS; POOR PROG. AS ALL
KHARKHARI June,20 6/15/2020 Di - 8 MAKH-21-P-22 730 616.50 632.5 13 3 16.00 160.00 5/19/2020 -
RODS WERE P/O AS BIT GOT DAMAGED
Sub Total - 118.70 890.00
REDRILLING BH SUSPENDED AT 177.55 M; 30 M
BADAM June,20 6/15/2020 RIG 3 100H/03 MABD-77/P-76 900 177.55 177.55 0 0 0.00 58 3/2/2020 Re-drilling
N/C HQ DRILLING
RIG 4 DI- MACHINE AND MATERIALS SHIFTED TO NEW
BADAM June,20 6/15/2020 MABD-89 /P-80 450 0.00 0 0 0 0.00 50 - - Operator Required. Single Shift running
17/01 POINT P 80

BADAM June,20 6/15/2020 Rig 1 LY-44/01 MABD-/P- 0 0.00 0.00 0 0 0.00 0 - - SHIFTED TO NTPC KERADARI PROJECT

MACHINE AND MATERIALS SHIFTED TO NEW


BADAM June,20 6/15/2020 Rig 2 LY-44/02 MABD-90/P-90 400 0.00 0 0 0 0.00 25 - -
POINT P 90

BADAM June,20 6/15/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 173.20 211.5 15 23.3 38.30 140 6/1/2020 - DRILLING IN PROGRESS; SANDY SHALE FM.

HQ DRILLING; SANDY SHALE AND FRACTURED


BADAM June,20 6/15/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 134.50 168.9 18 16.4 34.40 206 6/10/2020 -
SHALE FM.
Sub Total - Where are the operators? Are other machines
72.70 371.00 required?
INNER TUBE JAMMED IN BARREL, COMPLETE
SOMAVARAM June,20 6/15/2020 DY-100H/02 NPP-19 530 393 397.5 4.5 0 4.5 140 6/3/2020 - ROD WITH BARREL P/O TO SURFACE; BH WASHE;
HQ REAMING FROM 101M TO 275 M

BH CLOSED; UNDER CIRCULATION FOR GPL; GPL


SOMAVARAM June,20 6/15/2020 Dy50CR/10 NPP-73 349 349 0 0 0 50 5/31/2020 6/15/2020 NOT COMPLETED; R/I NQ ROD UPTO 217 M
WASHED DOWN UPTO BOTTOM
SOMAVARAM June,20 6/15/2020 Dy50H/04 NPP- 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
RIG IDLE AT CAMP AS CULTIVATION STARTED
SOMAVARAM June,20 6/15/2020 Dy-50CR/01 NPP- 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 4.50 190.00
Rig 4 - VOL-
KURMITAR June,20 6/15/2020 180 KIOM/52/57 2 2 0 0 0 6/12/2020 - RIG OFF

KURMITAR June,20 6/15/2020 Rig 5 - LY- KIOM/53/60 0 5.6 5.6 0 5.6 10 6/15/2020 - DRILLING IN PROGRESS
38/02
Rig 6 - Dyna -
KURMITAR June,20 6/15/2020 KIOM/00/00 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR June,20 6/15/2020 Rig 7 - LY-38/01KIOM/50/62 33 35.5 2.5 0 2.5 10 6/4/2020 - DRILLING IN PROGRESS
Sub Total - 8.10 20.00

DRILLING IN PROGRESS; PROGRESS POOR DUE TO Video of Viscosity Measurement Required. Check RPM
PATRATU June,20 6/15/2020 Dy(175/3) BH - 05 1000 464 497 15 18 33 250 5/22/2020 - DOWN HOLE PROBLEMS AND HARD FORMATION of spindle. Progress could improve

Sub Total - 33.00 250.00


SIKAR June,20 6/15/2020 Dy 50CR/04 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
POOR PROG. DUE TO 100% W/LOSS AND VERY
SIKAR June,20 6/15/2020 Dy 50CR/05 GKDC-27 470.5 487 10.5 6 16.5 135 5/29/2020 - About to close. We should plan its shifting to HP asap.
HARD FM.
Sub Total - 16.50 135.00
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE


GMRDS June,20 6/15/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/15/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/15/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/15/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00

WATER SUPPLY ARRANGEMENTS DONE; RAIN


HINDERED PROGRESS; P/O 377 M ROD AS BIT Action should be taken on the operator for the
KABITIRTHA June,20 6/15/2020 DICD100H/1 MRKB 85/SP-6(C) 730 369.5 377.5 8 0 8 96 6/1/2020 - BROKEN AND LEFT IN BH; NO PROPER
negligence.
ARRANGEMENTS FOR FISHING OPERATION
PRESENT; 100 % W/ LOSS IN BH.

NQ DRILLING; COAL AND SHALE FM.; SITE


KABITIRTHA June,20 6/15/2020 KDR 750(02) MRKB 84/SP-1(C) 610 596.5 620.5 14.9 9.1 24 106 5/29/2020 - GEOLOGIST STOPPED BH; PROGRESS HAMPERED
DUE TO RAIN

HQ DRILLING; HARD SHALE FM; 100% W/LOSS IN


KABITIRTHA June,20 6/15/2020 LY 44/01 MRKB 86/SP-3(C) 660 125.1 145.3 9.7 10.5 20.2 74 6/9/2020 - BH; PROGRESS HAMPERED DUE TO RAIN AND
HARD SHALE FM.
Sub Total - 52.20 276.00
KMA01 / 270° / CREW LATE DUE TO LATE BLAST. HARD
HZL KAYAD June,20 6/15/2020 UCD 40 110 6.35 9.65 0.75 2.55 3.3 0 6/15/2020 -
+25° FRACTURED FM.
Sub Total - 75.70 350.00

ZAWAR June,20 6/15/2020 UCD 40 mrl -59 ,BH -ZI/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
59/11/-10°
ZAWAR June,20 6/15/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
35°/225°

ZAWAR June,20 6/15/2020 UCD 60-3 BI- 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
430/134/80°/15°
ZAWAR June,20 6/15/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 MACHINE SENT TO TDMA FATEHNAGAR
70°/0°
Sub Total - 0.00 0.00
Location - North
AGUCHA UG June,20 6/15/2020 UDD-330 255 CV SBH No. 22 37 0 15 15 0 6/13/2020 - 8" DRILLING DONE FROM 22 M TO 37 M
54
Sub Total - 15.00 0.00

AGUCHA SUR PF June,20 6/15/2020 DIMP-175 Surface to -180 72 72 0 0 3/14/2020 - WAITING FOR POI
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June,20 6/15/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA June,20 6/15/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June,20 6/15/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June,20 6/15/2020 KDR-1200/02 417 417 0 0 0 0 3/1/2020 - WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00

WORKOVER 18 M 6" CASING DONE; 3 NOS. CASING


TSL DHANBAD June,20 6/15/2020 BH 04 248 248 0 0 0 0 TRANSPORTED FROM SIJUA 2 PIT COLLIERY TO 2
RIG
PIT SITE LOCATION
June,20 6/15/2020 BH 01 SITE PREP WORK CONTINUING
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

Sub Total - 0.00 0.00

HQ LOWERED UPTO 650 M; 12 BAGS BENTONITE


MUD PREPARED AND FLUSHED IN HOLE AS PER
INSTRUCTION FROM HO; RODS P/O AND HOLE What was the purpose of bentonite flushing? Now what
KEPT IDLE FOR SETTING UP OF BENTONITE; HQ is the further planning? Rakesh should go to site as
NGRI KOYNA June,20 6/15/2020 DYNA 350 KBH-10-R 758.9 766.90 0 8 8 280
RODS LOWERED WITH ROTATION AND soon as possible and take charge. Should we use
CIRCULATION; HQ DRILLING FROM 758.90 M TO bentonite in place of polymer?
766.90 M; HQ RODS HOISTING COMPLETED; 3 M
CORE LEFT IN BARREL.

Sub Total - 8.00 280.00


WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA June,20 6/15/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA June,20 6/15/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA June,20 6/15/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

POOR PROG. DUE TO 100 % W/ LOSS AND HEAVY


KHARKHARI June,20 6/14/2020 CDR-1000 MAKH 25-P-28 700 54.30 65.9 4.5 7.1 11.60 130.00 6/12/2020 -
RAIN

PROGRESS HINDERED DUE TO 100% W/ LOSS


KHARKHARI June,20 6/14/2020 LY-44 MAKH-23-P-17 430 325.00 328 3 0 3.00 20.00 5/27/2020 - AND HEAVY RAIN. DRILLING STOPPED DUE TO
SHORTAGE OF WATER

DRILLING PROG. POOR DUE TO JAMMING AND


KHARKHARI June,20 6/14/2020 KDR 750/01 MAKH-24-P-11 470 332.00 336.5 0 4.5 4.50 90.00 6/5/2020 - BLOCKING TENDENCY AND ALSO HINDERED DUE
TO HEAVY RAIN
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/14/2020 DY-120 MAKH012-P-24 760 767.50 767.5 0 0 0.00 2/19/2020 6/1/2020
OWNER'S OBJECTION
KHARKHARI June,20 6/14/2020 DY-120/2 MAKH010-P-21 770 724.00 730 3 3 6.00 145.00 2/9/2020 - POOR PROG. DUE TO 100% W/LOSS
RIG SHIFTING HINDERED DUE TO HEAVY
KHARKHARI June,20 6/14/2020 KDR 750/03 MAKH-22-P-10 460 472.70 472.7 0 0 0.00 5/22/2020 6/8/2020 RAINFALL
DRILLING IN PROGRESS; PROGRESS POOR DUE TO
KHARKHARI June,20 6/14/2020 Di - 8 MAKH-21-P-22 730 598.00 616.5 9.5 9 18.50 120.00 5/19/2020 - HEAVY RAINFALL
Sub Total - 43.60 505.00

BADAM June,20 6/14/2020 RIG 3 100H/03 MABD-86/P-92 657.5 657.50 657.5 0 0 0.00 0 5/18/2020 6/8/2020 WEEKLY OFF. NO PROGRESS

RIG 4 DI-
BADAM June,20 6/14/2020 17/01 MABD-80 /P-84 640 509.15 509.15 0 0 0.00 0 3/17/2020 6/12/2020 WEEKLY OFF. NO PROGRESS

BADAM June,20 6/14/2020 Rig 1 LY-44/01 MABD-/P- 0 0.00 0.00 0 0 0.00 0 - - WEEKLY OFF. NO PROGRESS

BADAM June,20 6/14/2020 Rig 2 LY-44/02 MABD-84/P-87 400 375.00 375 0 0 0.00 0 5/13/2020 6/12/2020 WEEKLY OFF. NO PROGRESS

BADAM June,20 6/14/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 173.20 173.2 0 0 0.00 0 6/1/2020 - WEEKLY OFF. NO PROGRESS

BADAM June,20 6/14/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 134.50 134.5 0 0 0.00 0 6/10/2020 - WEEKLY OFF. NO PROGRESS
Sub Total - 0.00 0.00
INNER TUBE JAMMED IN BARREL, P/O, RELEASED
SOMAVARAM June,20 6/14/2020 DY-100H/02 NPP-19 530 369 393 18 6 24 80 6/3/2020 - AND CLEANED THEN R/I
RIG RAN IN 12 HR SHIFT DUE TI BAD BH
SOMAVARAM June,20 6/14/2020 Dy50CR/10 NPP-73 325.5 349 11 12.5 23.5 120 5/31/2020 - CONDITION
SOMAVARAM June,20 6/14/2020 Dy50H/04 NPP- 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
RIG IDLE AT CAMP AS CULTIVATION STARTED
SOMAVARAM June,20 6/14/2020 Dy-50CR/01 NPP- 0 0 0 0 0 - - AND LANDOWNERS DID NOT AGREE TO GIVE
THEIR LAND FOR DRILLING
Sub Total - 47.50 200.00
Rig 4 - VOL-
KURMITAR June,20 6/14/2020 180 KIOM/52/57 2 2 0 0 0 0 - - RIG OFF DUE TO LOCAL FESTIVAL

Rig 5 - LY-
KURMITAR June,20 6/14/2020 38/02 KIOM/00/00 0 0 0 0 0 0 - - RIG OFF DUE TO LOCAL FESTIVAL

KURMITAR June,20 6/14/2020 Rig 6 - Dyna - KIOM/00/00 0 0 0 0 0 0 - - OFF FOR MANPOWER SHORTAGE
50H
KURMITAR June,20 6/14/2020 Rig 7 - LY-38/01KIOM/50/62 33 33 0 0 0 0 6/4/2020 - RIG OFF DUE TO LOCAL FESTIVAL
Sub Total - 0.00 0.00
HYDRAULIC HOSE PIPE GOT DAMAGED AND WAS
PATRATU June,20 6/14/2020 Dy(175/3) BH - 05 1000 448 464 8 8 16 260 5/22/2020 - RPAIRED; POOR PROG. DUE TO DOWN HOLE
PROBLEM AND VERY HARD FM.
Sub Total - 16.00 260.00
SIKAR June,20 6/14/2020 Dy 50CR/04 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
POOR PROG. DUE TO 70% W/LOSS AND VERY
SIKAR June,20 6/14/2020 Dy 50CR/05 GKDC-27 447 470.5 9 14.5 23.5 143 5/29/2020 -
HARD FM.
Sub Total - 23.50 143.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS June,20 6/14/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/14/2020 LY 38/01 0 0 0 0 0 0
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

GMRDS June,20 6/14/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/14/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00

WATER SUPPLY TANKER OVERTURNED DUE TO


KABITIRTHA June,20 6/14/2020 DICD100H/1 MRKB 85/SP-6(C) 730 363.5 369.5 0 6 6 26 6/1/2020 - POOR ROAD CONDITIONS AND 100% W/LOSS IN
BH SO PROGRESS HINDERED.

NQ DRILLING; COAL AND SHALE FM.; 72 M RODS


KABITIRTHA June,20 6/14/2020 KDR 750(02) MRKB 84/SP-1(C) 610 570 596.5 13.2 13.3 26.5 98 5/29/2020 - P/O AFTER BH WASHING; 100% W/LOSS IN BH;
PROGRESS HAMPERED DUE TO HEAVY RAIN

HQ DRILLING; HARD SHALE FM; PROGRESS


KABITIRTHA June,20 6/14/2020 LY 44/01 MRKB 86/SP-3(C) 660 113.5 125.1 5.8 5.8 11.6 41 6/9/2020 - HAMPERED DUE TO HEAVY RAIN AND HARD AND
FRACTURED FM.
Sub Total - 44.10 165.00
mrl -59 ,BH -ZI/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/14/2020 UCD 40 0 0 0 0 0 0
59/11/-10° 19
ZI/418/13/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/14/2020 UCD 60-2 0 0 0 0 0 0
35°/225° 19

DRILLING COMPLETELY STOPPED DUE TO COVID


ZAWAR June,20 6/14/2020 UCD 60-3 BI- 0 0 0 0 0 0
19
430/134/80°/15°
ZAWAR June,20 6/14/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 DRILLING COMPLETELY STOPPED DUE TO COVID
70°/0° 19
Sub Total - 0.00 0.00
Location - North
AGUCHA UG June,20 6/14/2020 UDD-330 255 CV SBH No. 7 22 0 15 15 0 6/13/2020 - 8" DRILLING DONE FROM 7 M TO 22 M
53
Sub Total - 15.00 0.00
SURFACE TO
AGUCHA SUR PF June,20 6/14/2020 DIMP-175 -180
0 0 0 0 0 0 WAITING FOR POI
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June,20 6/14/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June,20 6/14/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June,20 6/14/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June,20 6/14/2020 KDR-1200/02 417 417 0 0 0 0 WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00
WORKOVER 3 NOS. CASING TRANSPORTED FROM SIJUA 2 PIT
TSL DHANBAD June,20 6/14/2020 BH 04 248 248 0 0 0 0
RIG COLLIERY TO 2 PIT SITE LOCATION
June,20 6/14/2020 BH 01
Sub Total - 0.00 0.00

ANGLE DEVIATION MEASURED AT 751 M FOUND


89.9°; DRILLI9NG FROM 755.90 M TO 758.90,
CORE SLIPPED INTO BARREL, 40 PAIRS HQ RODS
NGRI KOYNA June,20 6/14/2020 DYNA 350 KBH-10-R 749.9 758.90 9 0 9 280
HOISTED; 3 M CORE FOUND IN BARREL; HQ
LOWERING COMPLETE;WORK HINDERED DUE TO
HEAVY RAIN.

Sub Total - 9.00 280.00


Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

WORK TERMINATED; RIG SHIFTED TO CAMP FOR


CHOTIA June,20 6/14/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 18.00 0.00

BABJA June,20 6/14/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA June,20 6/14/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

DRILLING; PROGRESS HINDERED DUE TO HEAVY


KHARKHARI June,20 6/13/2020 CDR-1000 MAKH 25-P-28 700 30.00 54.3 12.7 11.6 24.30 160.00 6/12/2020 -
RAINFALL

DRILLING; PROGRESS HINDERED DUE TO HEAVY


KHARKHARI June,20 6/13/2020 LY-44 MAKH-23-P-17 430 309.50 325 6 9.5 15.50 70.00 5/27/2020 - RAINFALL
ALL NQ ROD WITH BARREL P/O; PROGRESS
KHARKHARI June,20 6/13/2020 KDR 750/01 MAKH-24-P-11 470 315.00 332 8.7 8.3 17.00 135.00 6/5/2020 - HINDERED DUE TO HAVY RAINFALL AND 100%
W/ LOSS
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/13/2020 DY-120 MAKH012-P-24 760 767.50 767.5 0 0 0.00 2/19/2020 6/1/2020 OWNER'S OBJECTION
KHARKHARI June,20 6/13/2020 DY-120/2 MAKH010-P-21 770 724.00 724 0 0 0.00 2/9/2020 - RIG B/D
RIG SHIFTING NOT POSSIBLE DUE TO HEAVY
KHARKHARI June,20 6/13/2020 KDR 750/03 MAKH-22-P-10 460 472.70 472.7 0 0 0.00 5/22/2020 6/8/2020
RAINFALL
DRILLING IN PROGRESS; PROGRESS HINDERED
KHARKHARI June,20 6/13/2020 Di - 8 MAKH-21-P-22 730 571.00 598 12 15 27.00 160.00 5/19/2020 -
DUE TO HEAVY RAINFALL
Sub Total - 83.80 525.00
MACHINE AND MATERIALS SHIFTED TO
BADAM June,20 6/13/2020 RIG 3 100H/03 MABD-86/P-92 657.5 657.50 657.5 0 0 0.00 58 5/18/2020 6/8/2020
PREVIOUSLY SUSPENDED BH MABD 77/P-76

RIG 4 DI- HW CASING P/O; PVC CASING LOWERED, HQ, NQ


BADAM June,20 6/13/2020 17/01 MABD-80 /P-84 640 509.15 509.15 0 0 0.00 32 3/17/2020 6/12/2020 RODS SHIFTED TO SUKULKHAPIA CAMP

MACHINE STANDING IN CAMP, MACHINE


BADAM June,20 6/13/2020 Rig 1 LY-44/01 MABD-/P- 0 0.00 0.00 0 0 0.00 - - LOADING IN TRACTOR

BADAM June,20 6/13/2020 Rig 2 LY-44/02 MABD-84/P-87 400 375.00 375 0 0 0.00 35 5/13/2020 6/12/2020 HW CASING P/O; PVC CASING LOWERED

DRILLING, PROG. POOR AS DRILLING THROUGH


BADAM June,20 6/13/2020 Rig 5 LY-44/03 MABD-87 /P-89 400 158.50 173.2 14.7 0 14.70 55 6/1/2020 - FRACTURED COAL, SHALE FM
HQ DRILLING, SANDY SHALE AND FRACTURED
BADAM June,20 6/13/2020 Rig 6 50 - CR/08 MABD-88 /P-82 750 98.50 134.5 18 18 36.00 208 6/10/2020 - COAL FM.
Sub Total - 50.70 388.00
SOMAVARAM June,20 6/13/2020 DY-100H/02 NPP-19 530 309 369 33 27 60 160 6/3/2020 - DRILLING IN PROGRESS
ALL NQ STRINGS WITH CORE BARREL P/O TO
SURFACE, WATER CONTROL VALVE CHANGED,
SOMAVARAM June,20 6/13/2020 Dy50CR/10 NPP-73 315 325.5 0 10.5 10.5 130 5/31/2020 - BIT CHANGED, BH WASHED DOWN AND
REACHED BOTTOM, DRILLING.
SOMAVARAM June,20 6/13/2020 Dy50H/04 NPP- 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
AS CULTIVATION HAS STARTED, NO LAND
SOMAVARAM June,20 6/13/2020 Dy-50CR/01 NPP- 0 0 0 0 0 - - OWNER HAS PERMITTED DRILLING ACTIVITIES ,
RIG IDLE AT CAMP
Sub Total - 70.50 290.00
Rig 4 - VOL-
KURMITAR June,20 6/13/2020 KIOM/52/57 2 2 0 0 0 - - RIG BREAKDOWN
180
Rig 5 - LY-
KURMITAR June,20 6/13/2020 KIOM/00/00 0 0 0 0 0 10 - - SHIFTING
38/02
Rig 6 - Dyna -
KURMITAR June,20 6/13/2020 KIOM/00/00 0 0 0 0 0 - - RIG IDLE DUE TO MANPOWER SHORTAGE
50H
KURMITAR June,20 6/13/2020 Rig 7 - LY-38/01KIOM/50/62 27.5 33 5.5 0 5.5 10 6/4/2020 - DRILLING
Sub Total - 5.50 20.00
PATRATU June,20 6/13/2020 Dy(175/3) BH - 05 1000 410 448 18 20 38 250 22.05.20 - HQ DRILLING IN PROGRESS
Sub Total - 38.00 250.00
SIKAR June,20 6/13/2020 Dy 50CR/04 0 0 0 0 0 - - IDLE WAITING FOR HO DECISION
POOR PROG. DUE TO 90% W/LOSS AND VERY
SIKAR June,20 6/13/2020 Dy 50CR/05 GKDC-27 421.5 447 15 10.5 25.5 195 5/29/2020 - HARD FM.
Sub Total - 25.50 195.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS June,20 6/13/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/13/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/13/2020 LY 38/02 0 0 0 0 0 0
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

GMRDS June,20 6/13/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00

STEPS TAKEN TO COUNTER 100% W/ LOSS IN BH;


WATER TANKER DID NOT REACH SITE DUE TO
KABITIRTHA June,20 6/13/2020 DICD100H/1 MRKB 85/SP-6(C) 730 363.5 363.5 0 0 0 75 6/1/2020 - BAD ROAD CONDITIONS; SUPPLY PUMP SHIFTED
TO NEW POND AND TRIED TO REACH MACHINE
BY FLAT PIPE; BH JAM, BH WASHED.

NQ DRILLING; COAL AND SHALE FM.; 100%


KABITIRTHA June,20 6/13/2020 KDR 750(02) MRKB 84/SP-1(C) 610 532.1 570 21.9 16 37.9 150 5/29/2020 - W/LOSS IN BH

HQ DRILLING; HARD AND FRACTURED FM, SO


KABITIRTHA June,20 6/13/2020 LY 44/01 MRKB 86/SP-3(C) 660 88.5 113.5 13.3 11.7 25 65 6/9/2020 -
PROG. POOR

Sub Total - 62.90 290.00

ZAWAR June,20 6/13/2020 UCD 40 mrl -59 ,BH -ZI/- 176.05 176.05 0 0 0 0 DRILLING COMPLETELY STOPPED DUE TO COVID
59/11/-10° 19
ZI/418/13/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/13/2020 UCD 60-2 234.35 234.35 0 0 0 0
35°/225° 19

DRILLING COMPLETELY STOPPED DUE TO COVID


ZAWAR June,20 6/13/2020 UCD 60-3 BI- 24.5 24.5 0 0 0 0 19
430/134/80°/15°
HMBH/390/13/2 DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/13/2020 UCD 60-1 128 128 0 0 0 0
70°/0° 19
Sub Total - 0.00 0.00
Location - North
AGUCHA UG June,20 6/13/2020 UDD-330 255 CV SBH No. 0 7 0 7 7 0 6/13/2020 - 8" DRILLING DONE UPTO 7 M
53
Sub Total - 7.00 0.00

PLANNING TEAM DECIDED TO GIVE NEW POINT


AGUCHA SUR PF June,20 6/13/2020 DIMP-175 Surface to -180 72 72 0 0 AND POI TO BE RELEASED ON 15.06.20

Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June,20 6/13/2020 DW-35 FILL-02 BORE 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 ] COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June,20 6/13/2020 Dyna50H DD20BKE 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June,20 6/13/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June,20 6/13/2020 KDR-1200/02 417 417 0 0 0 0 WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00

TSL DHANBAD June,20 6/13/2020 Workover Rig Sijua 2 pit 248 248 0 10
Sub Total - 0.00 10.00
HQ LOWERED UPTO 729.40 M, HQ DRILLING TO
NGRI KOYNA June,20 6/13/2020 DYNA 350 KBH-10-R 729.4 749.90 4 16.5 20.5 300 749.90 M; HIGHLY FRACTURED ZONE
Sub Total - 20.50 300.00
WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA June,20 6/13/2020 DY50CR/07 0 0
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA June,20 6/13/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

BABJA June,20 6/13/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

RIG SHIFTED TO NEW POINT AND SET; HQ


KHARKHARI June,20 6/12/2020 CDR:1000 MAKH 25/P-28 700 0.00 30 8.7 21.3 30.00 190.00 12.06.20
DRILLING

KHARKHARI June,20 6/12/2020 LY:44 MAKH 23/P-17 430 287.00 309.5 11 11.5 22.50 80.00 27.05.20 DRILLING IN PROGRESS
POOR PROGRESS IN 2ND SHIFT DUE TO CORE
KHARKHARI June,20 6/12/2020 KDR:750/01 MAKH 24/P-11 470 264.40 315 40 10.6 50.60 165.00 05.06.20
DROP
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/12/2020 DY:120/01 MAKH 12/P-24 760 767.50 767.5 0 0 0.00 0.00 19.02.20 01.06.20
OWNER'S OBJECTION
KHARKHARI June,20 6/12/2020 DY:120/02 MAKH 10/P-21 770 724.00 724 0 0 0.00 0.00 10.02.20 RIG B/D
ALL NQ ROD DISMANTLED; READY TO BE SHIFTED
KHARKHARI June,20 6/12/2020 KDR:750/03 MAKH 22/P-10 460 472.70 472.7 0 0 0.00 0.00 22.05.20 10.06.20
TO NEW POINT
KHARKHARI June,20 6/12/2020 DY: DI-8 MAKH 21/P-22 730 538.00 571 18 15 33.00 180.00 19.05.20 DRILLING IN PROGRESS
Sub Total - 136.10 615.00

162 M NW L/H ROD LOWERED; HQ ROD TAPE


CONNECTED; MAIN WINCH WIRE ROPE BROKEN
BADAM June,20 6/12/2020 DY: 100H/03 MABD 86/P-92 657.5 657.50 657.5 0 0 0.00 46 18.05.20 08.06.20 WHILE HOISTING 4 PAIRS OF NW L/H ROD;
REPAIRED AND NW L/H ROD HOISTED 162 M
AND 10 M HQ ROD RECOVERED

BADAM June,20 6/12/2020 DY:DI-17 MABD80/P-84 640 509.15 509.15 0 0 0.00 86 BH CLOSED ; NQ ROD P/O; 261 M HQ ROD P/O

MACHINE STANDING IN CAMP, MACHINE


BADAM June,20 6/12/2020 LY:44/01 MABD /P- 0 0.00 0.00 0 0 0.00 0.00 LOADING IN TRACTOR
BH CLOSED BY CMPDI GEOLOGIST AND CORE
BADAM June,20 6/12/2020 LY: 44/02 MABD 84/P-87 400 375.00 375 0 0 0.00 25 13.05.20 12.06.20 BOXES SHIFTED TO SUKULKHAPIA CAMP; NQ ROD
P/O
5 HRS LOST AS PRESSURE PLATE DAMAGED SO
BADAM June,20 6/12/2020 LY: 44/03 MABD87/P-89 400 152.50 158.5 6 0 6.00 25 01.06.20
PROGRESS LOW; SHALE FM
HQ DRILLING, SANDY SHALE AND VERY HARD
BADAM June,20 6/12/2020 DY: 50 CR/08 MABD 88/P-92 750 66.00 98.5 18 14.5 32.50 184 10.06.20
SHALE FM.
Sub Total - 38.50 234.00
NPP 19/ MGSE FOOT CLAMP REPAIRED AND LIGHTING PROBLEM
SOMAVARAM June,20 6/12/2020 DY: 100H/02 530 202 254.5 25.5 27 52.5 187 03.06.20
137 SORTED OUT.

SUMP PIT FILLED WITH CUTTINGS SO CLEANED;


AMC PUMP REPAIRED;BH WASHED 48 M AND
REACHED BOTTOM; TRIED DRILLING 3 TIMES BUT
SOMAVARAM June,20 6/12/2020 DY: 50CR/10 P-73/MGSE 135 294 312 15 3 18 123 31.05.20
W/ BLOCKAGE, HIGH TORQUE AND STRINGS JAM
SEEN; 14 PAIR STRINGS P/O BY TOP DRIVE AND
FREED

SOMAVARAM June,20 6/12/2020 DY: 50H/04 0 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE

SOMAVARAM June,20 6/12/2020 DY: 50CR/01 P-74/MGSE 136 367 367 0 0 0 0 31.05.20 10.06.20 RIG AND OTHER MATERIALS SHIFTED TO CAMP
Sub Total - 70.50 310.00

KURMITAR June,20 6/12/2020 Vol 180 (SPS) KIOM/52/20/57 0 2 2 0 2 0 SHIFTING , SETTING AND DRILLING

KURMITAR June,20 6/12/2020 LY 38/02 KIOM/48/56 44.1 51 6.9 6.9 10 01.06.20 12.06.20 BH MEASURED AND CLOSED
KURMITAR June,20 6/12/2020 DY 50H KIOM/00/00 0 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE
KURMITAR June,20 6/12/2020 LY 38/01 KIOM/50/20/62 24.5 27.5 3 3 10 04.06.20 DRILLING
Sub Total - 11.90 20.00
PATRATU June,20 6/12/2020 DY:175/03 5 1000 373 410 19 18 37 230 22.05.20 HQ DRILLING IN PROGRESS
Sub Total - 37.00 230.00
SIKAR June,20 6/12/2020 DY: 50CR/04 GKDC-26 420 420 420 0 0 0 0 18.03.20 06.06.20 IDLE WAITING FOR HO DECISION
POOR PROG. DUE TO 90% W/LOSS AND VERY
SIKAR June,20 6/12/2020 DY:50CR/05 GKDC-27 393.5 421.5 13 15 28 195 29.05.20 HARD FM.
Sub Total - 28.00 195.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS June,20 6/12/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/12/2020 LY 38/01 0 0 0 0 0 0
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

GMRDS June,20 6/12/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/12/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00

PIPELINE MADE AS IT WAS NOT POSSIBLE FOR


TRACTOR TO REACH SITE DUE TO MUDDY ROAD
KABITIRTHA June,20 6/12/2020 DY: 100H/01 MRKB 85/SP-6 730 342 363.5 12 9.5 21.5 152 CONDITIONS; 358.5 M ROD P/O AND R/I DUE TO
CORE DROP IN BARREL; RAIN HAMPERED
PROGRESS ALSO 100% W/LOSS I BH

NQ DRILLING; COAL AND SHALE FM.; 100%


KABITIRTHA June,20 6/12/2020 KDR 750/02 MRKB 84/SP-1 610 447.8 489.9 22.1 20 42.1 165 W/LOSS IN BH; PROGRESS HAMPERED DUE TO
HEAVY RAIN

HQ DRILLING; HARD SHALE FM; PROGRESS


KABITIRTHA June,20 6/12/2020 LY: 44/01 MRKB 86/SP-3 660 33 60 12 15 27 70 09.06.2020 HAMPERED DUE TO HEAVY RAIN

Sub Total - 90.60 387.00


mrl -59 ,BH -ZI/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/12/2020 UCD 40 0 0 0 0 0 0
59/11/-10° 19
ZI/418/13/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June,20 6/12/2020 UCD 60-2 0 0 0 0 0 0
35°/225° 19

DRILLING COMPLETELY STOPPED DUE TO COVID


ZAWAR June,20 6/12/2020 UCD 60-3 BI- 0 0 0 0 0 0
19
430/134/80°/15°
ZAWAR June,20 6/12/2020 UCD 60-1 HMBH/390/13/2 0 0 0 0 0 0 DRILLING COMPLETELY STOPPED DUE TO COVID
70°/0° 19
Sub Total - 0.00 0.00
Location - North
AIR COMPRESSOR SILENCER FITTED; WAITING
AGUCHA UG June,20 6/12/2020 UDD-330 255 CV SBH No. 0 0 0 0 0 0 FOR POWER CONNECTION
53
Sub Total - 0.00 0.00
SURFACE TO
AGUCHA SUR PF June,20 6/12/2020 DIMP-175 -180
0 0 0 0 0 0 WAITING FOR NEW BH POINT
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June,20 6/12/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVICE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June,20 6/12/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June,20 6/12/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June,20 6/12/2020 KDR-1200/02 417 417 0 0 0 0 WORK STOPPED DUE TO COVID 19
(HQ)
Sub Total - 0.00 0.00
WORKOVER
TSL DHANBAD June,20 6/12/2020 BH 04 0 0 0 0 0 0 SITE PREPARATION AND 6" ENCASING 18 M
RIG
Sub Total - 0.00 0.00

HQ LOWERED UPTO 670 M , CEMENT TAG


FOUND, WORK INTERRUPTED DUE TO HEAVY
RAIN; AFTER DRILLING CEMENT WHEN HQ
NGRI KOYNA June,20 6/12/2020 DYNA 350 KBH-10-R 729.4 729.40 0 0 0 230 DRILLING STARTED, HIGH TORQUE WAS FOUND
SO ROD P/O; BIT DAMAGED, CHANGED AND 27
PAIR ROD LOWERED

Sub Total - 0.00 230.00


Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

WORK TERMINATED; RIG SHIFTED TO CAMP FOR


CHOTIA June,20 6/12/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA June,20 6/12/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA June,20 6/12/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

50 L DIELSEL FLUSHED IN HOLE AND RESTED; 326 MACHINE BEING SHIFTED TO NEXT POINT; EXPECTED
KHARKHARI June,20 6/11/2020 CDR:1000 MAKH 06/P-29 715 706.45 706.45 0 0 0.00 150.00 09.06.20 M HQ CASING RELEASED; 30.70 M CASING AND
TO START WITHIN A DAY OR TWO
12 M HW LINER LIH DUE TO HEAVY JAM

DM 10 ENGINE GOT B/D; ENGINE SENT FROM


KHARKHARI June,20 6/11/2020 LY:44 MAKH 23/P-17 430 282.50 287 2 2.5 4.50 40.00 27.05.20 HO; ENGINE REPLACED AND DRILLING
RECOMMENCED
KHARKHARI June,20 6/11/2020 KDR:750/01 MAKH 24/P-11 470 226.40 264.4 20.8 17.2 38.00 150.00 05.06.20 DRILLING IN PROGRESS
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/11/2020 DY:120/01 MAKH 12/P-24 760 767.50 767.5 0 0 0.00 0.00 19.02.20 01.06.20
OWNER'S OBJECTION
KHARKHARI June,20 6/11/2020 DY:120/02 MAKH 10/P-21 770 724.00 724 0 0 0.00 0.00 10.02.20 RIG B/D
COAL CORE EXCISION; HQ CASING AND HW LINER NEXT POINT IS READY; WILL SHIFT WITHIN A DAY OR
KHARKHARI June,20 6/11/2020 KDR:750/03 MAKH 22/P-10 460 472.70 472.7 0 0 0.00 60.00 22.05.20 10.06.20 P/O AND DISMANTLED TWO
KHARKHARI June,20 6/11/2020 DY: DI-8 MAKH 21/P-22 730 508.00 538 14 16 30.00 180.00 19.05.20 DRILLING IN PROGRESS
Sub Total - 72.50 580.00
UNSCREW WILL BE COMPLETED TODAY; SHIFTING
BADAM June,20 6/11/2020 DY: 100H/03 MABD 86/P-92 657.5 657.50 657.5 0 0 0.00 69 18.05.20 08.06.20 162 M HQ RODS UNSCREWED
TOMORROW AND WILL START ON SUNDAY

BADAM June,20 6/11/2020 DY:DI-17 MABD80/P-84 640 509.15 509.15 0 0 0.00 0 TARGET DEPTH ACHIEVED, WAITING FOR CMPDI WILL START ON SUNDAY

MACHINE STANDING IN CAMP, MACHINE


BADAM June,20 6/11/2020 LY:44/01 MABD /P- 0 0.00 0.00 0 0 0.00 TO GO TO NTPC PROJECT WITHIN 2- 3 DAYS
LOADING IN TRACTOR

BADAM June,20 6/11/2020 LY: 44/02 MABD 84/P-87 400 375.00 375 0 0 0.00 0 13.05.20 TARGET DEPTH ACHIEVED, WAITING FOR CMPDI WILL START ON MONDAY

BADAM June,20 6/11/2020 LY: 44/03 MABD87/P-89 400 137.50 152.5 15 0 15.00 60 01.06.20 HQ DRILLING, SANDY SHALE FM.
BADAM June,20 6/11/2020 DY: 50 CR/08 MABD 88/P-92 750 30.00 66 18 18 36.00 190 10.06.20 HQ DRILLING, SHALE FM.
Sub Total - 51.00 250.00
NPP 19/ MGSE NQ P/O TO SURFACE AS TUBE JAMMED IN
SOMAVARAM June,20 6/11/2020 DY: 100H/02 530 202 254.5 25.5 27 52.5 187 03.06.20
137 BARREL THEN R/I

BH IS IN SOFT AND DUST COAL FM. BH IS IN VERY


CRITICAL POSITION TO EXTEND WITH CORE
SOMAVARAM June,20 6/11/2020 DY: 50CR/10 P-73/MGSE 135 294 312 15 3 18 123 31.05.20 RECOVERY; 6 PAIR ROD P/O AND BH WASHED; WILL CLOSE IN 2 -3 DAYS; NO MORE POINTS AVAILABLE
OPERATION STOPPED AND SUMP PIT CLEANING

SOMAVARAM June,20 6/11/2020 DY: 50H/04 0 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE

DUE TO RAIN TRACTOR DID NOT REACH SITE SO WILL CLOSE IN 2 -3 DAYS; NO MORE POINTS
SOMAVARAM June,20 6/11/2020 DY: 50CR/01 P-74/MGSE 136 367 367 0 0 0 0 31.05.20 10.06.20 CORE BOXES MANUALLY MOVED TO CAMP AVAILABLE; IS BEING SHIFTED FROM PREVIOUS POINT

Sub Total - 70.50 310.00

KURMITAR June,20 6/11/2020 Vol 180 (SPS) KIOM/00/00 0 0 0 0 0 0 SHIFTING

KURMITAR June,20 6/11/2020 LY 38/02 KIOM/48/56 38.5 44.1 5.6 5.6 10 01.06.20 DRILLING
KURMITAR June,20 6/11/2020 DY 50H KIOM/00/00 0 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE
KURMITAR June,20 6/11/2020 LY 38/01 KIOM/50/20/62 19 24.5 5.5 5.5 10 04.06.20 DRILLING
Sub Total - 11.10 20.00
PATRATU June,20 6/11/2020 DY:175/03 5 1100 335 373 19 19 38 230 22.05.20 HQ DRILLING IN PROGRESS
Sub Total - 38.00 230.00
SIKAR June,20 6/11/2020 DY: 50CR/04 GKDC-26 420 420 420 0 0 0 0 18.03.20 06.06.20 IDLE WAITING FOR HO DECISION

SIKAR June,20 6/11/2020 DY:50CR/05 GKDC-27 373 393.5 11 9.5 20.5 180 29.05.20 POOR PROG. DUE TO 100% W/LOSS AND VERY
HARD FM.
Sub Total - 20.50 180.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY MORE
GMRDS June,20 6/11/2020 DY 35/01 0 0 0 0 0 0 BH POINTS; NO FURTHER BH POINTS PROVIDED
BY GMRDS
GMRDS June,20 6/11/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/11/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/11/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00
NQ DRILLING, SHALE FM. PROGRESS HAMPERED
KABITIRTHA June,20 6/11/2020 DY: 100H/01 MRKB 85/SP-6 730 308 342 17 17 34 152
DUE TO HEAVY RAIN; 100% W/LOSS AT 339 M
Rig Type T.D. Starting Closing SHIFT Day Date of Date of
SITE MONTH DATE BH NO Depth Depth Shift I HSD Commence SITE UPDATES REMARKS
(m) II total Closure
(m) (m) ment

NQ DRILLING; SANDSTONE AND SHALE FM.; 100%


KABITIRTHA June,20 6/11/2020 KDR 750/02 MRKB 84/SP-1 610 447.8 489.9 22.1 20 42.1 165 W/LOSS IN BH; PROGRESS HAMPERED DUE TO
HEAVY RAIN

HQ DRILLING; HARD SHALE FM; DRILL BIT


KABITIRTHA June,20 6/11/2020 LY: 44/01 MRKB 86/SP-3 660 33 60 12 15 27 70 09.06.2020 CHANGED; PROGRESS HAMPERED DUE TO HEAVY
RAIN
Sub Total - 103.10 387.00
mrl -59 ,BH -ZI/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June'20 6/11/2020 UCD 40 0 0 0 0 0 0
59/11/-10° 19
ZI/418/13/- DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June'20 6/11/2020 UCD 60-2 0 0 0 0 0 0 19
35°/225°

DRILLING COMPLETELY STOPPED DUE TO COVID


ZAWAR June'20 6/11/2020 UCD 60-3 BI- 0 0 0 0 0 0
19
430/134/80°/15°
HMBH/390/13/2 DRILLING COMPLETELY STOPPED DUE TO COVID
ZAWAR June'20 6/11/2020 UCD 60-1 0 0 0 0 0 0
70°/0° 19
Sub Total - 0.00 0.00

MACHINE SETUP AT POINT BUT COMPRESSOR


SILENCER PIPE DAMAGED; BROUGHT TO
Location - North SURFACE AND REPAIRED; NO SUPPORT TO UPPER
AGUCHA UG June'20 6/11/2020 UDD-330 255 CV SBH No. 0 0 0 0 0 0 MAST JACK CYLINDER WITH ROOF AND WITHOUT
53
SUPPORT HIGH RISK OF HOLE DEVIATION
PREVALENT

Sub Total - 0.00 0.00


SURFACE TO
AGUCHA SUR PF June'20 6/11/2020 DIMP-175 -180 0 0 0 0 0 0 WAITING FOR NEW BH POINT
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June'20 6/11/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVIOCE HOLE JOBS HAVE BEEN STOPPED FOR
HOLE NO-03 COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June'20 6/11/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June'20 6/11/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June'20 6/11/2020 KDR-1200/02 (HQ) 417 417 0 0 0 0 WORK STOPPED DUE TO COVID 19
Sub Total - 0.00 0.00
WORKOVER
TSL DHANBAD June'20 6/11/2020 RIG BH 04 0 0 0 0 0 0 SITE PREPARATION AND 6" ENCASING 18 M
Sub Total - 0.00 0.00

HQ ROD P/O COMPLETED AFTER HO DECISION OF


CEMENTING; NQ RODS SHIFTED AND 50 PAIR NQ
NGRI KOYNA June'20 6/11/2020 DYNA 350 KBH-10-R 718.4 729.40 11 0 11 180
ROD LOWERED; RAIN HINDERED EXECUTION OF
WORK IN BOTH SHIFTS

Sub Total - 11.00 180.00


WORK TERMINATED; RIG SHIFTED TO CAMP FOR
CHOTIA June'20 6/11/2020 DY50CR/07
CLEANING AND REPAIRING
Sub Total - 0.00 0.00

BABJA June'20 6/11/2020 DY:50CR/11 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT

BABJA June'20 6/11/2020 LY:44 RIG IDLE DUE TO UNAVILABILITY OF NEXT POINT
Sub Total - 0.00 0.00
Date of
Rig Type T.D. Starting Closing Date of
SITE MONTH DATE BH NO Shift I SHIFT II Day total HSD Commencem SITE UPDATES REMARKS
(m) Depth (m) Depth (m) ent Closure

BH CLOSED, GPL DONE;HQ CASING JAMMED


KHARKHARI June,20 6/10/2020 CDR:1000 MAKH 06/P-29 715 706.45 706.45 0 0 0.00 150.00 09.06.20 356.70M FROM BOTTOM SO FISHING UNDER
PROCESS
KHARKHARI June,20 6/10/2020 LY:44 MAKH 23/P-17 430 261.50 282 9.5 11 20.50 75.00 27.05.20 DRILLING IN PROGRESS
DRILLING IN PROGRESS; WORK STOPPED BY
KHARKHARI June,20 6/10/2020 KDR:750/01 MAKH 24/P-11 470 197.70 226.4 25.9 2.8 28.70 100.00 05.06.20
LOCALS IN 2ND SHIFT
RIG SHIFTING NOT POSSIBLE DUE TO LAND
KHARKHARI June,20 6/10/2020 DY:120/01 MAKH 12/P-24 760 767.50 767.5 0 0 0.00 0.00 19.02.20 01.06.20
OWNER'S OBJECTION
KHARKHARI June,20 6/10/2020 DY:120/02 MAKH 10/P-21 770 724.00 724 0 0 0.00 0.00 10.02.20 RIG B/D
KHARKHARI June,20 6/10/2020 KDR:750/03 MAKH 22/P-10 460 472.70 472.7 0 0 0.00 60.00 22.05.20 10.06.20 BH CLOSED. GPL COMPLETED
KHARKHARI June,20 6/10/2020 DY: DI-8 MAKH 21/P-22 730 478.00 508 15 15 30.00 160.00 19.05.20 DRILLING IN PROGRESS
Sub Total - 79.20 545.00

NQ ROD P/O 241 M; L/H ROD COMING FROM


BADAM June,20 6/10/2020 DY: 100H/03 MABD 86/P-92 657.5 657.50 657.5 0 0 0.00 34 18.05.20 08.06.20
PATRATU SITE AND L/H ROD 42 PAIRS MADE

TARGET DEPTH ACHIEVED SO MACHINE


BADAM June,20 6/10/2020 DY:DI-17 MABD80/P-84 640 506.10 509.15 3.05 0 3.05 29
STOPPED BY GEOLOGIST
MACHINE STANDING IN CAMP, MACHINE
BADAM June,20 6/10/2020 LY:44/01 MABD /P- 0 0.00 0.00 0 0 0.00
LOADING IN TRACTOR
NQ DRILLING, FRACTURED SHALE, VERY HARD
BADAM June,20 6/10/2020 LY: 44/02 MABD 84/P-87 400 355.00 375 10 10 20.00 110 13.05.20
SHALE FM.
BADAM June,20 6/10/2020 LY: 44/03 MABD87/P-89 400 123.50 137.5 14 0 14.00 60 01.06.20 DRILLING, SANDY SHALE FM.
BADAM June,20 6/10/2020 DY: 50 CR/08 MABD 88/P-92 750 0.00 30 12 18 30.00 137 10.06.20 NEW POINT STARTED; HQ DRILLING
Sub Total - 64.00 307.00
NPP 19/ MGSE GEARBOX REPAIRED; DRILLING STARTED BUT
SOMAVARAM June,20 6/10/2020 DY: 100H/02 530 169 202 9 24 33 113 03.06.20
137 GOT HINDERED DUE TO HEAVY RAIN
DRILLING; BH LEFT IN CIRCULATION AND
SOMAVARAM June,20 6/10/2020 DY: 50CR/10 P-73/MGSE 135 273 294 15 6 21 155 31.05.20 ROTATION DUE TO HEAVY RAIN SO PROGRESS
POOR
SOMAVARAM June,20 6/10/2020 DY: 50H/04 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE

GPL CONTINUATION INCOMPLETE AS GPL VAN


DID NOT REACH SITE DUE TO HEAVY RAIN, SO
SOMAVARAM June,20 6/10/2020 DY: 50CR/01 P-74/MGSE 136 367 367 0 0 0 20 31.05.20 10.06.20 BH CLOSED; CONTINUOUS HINDRANCE OF
RAIN NQ P/O AND HW LINERS RETRIEVED
FROM HOLE

Sub Total - 54.00 288.00

KURMITAR June,20 6/10/2020 Vol 180 (SPS) KIOM/00/00 0 0 0 0 0 0 SHIFTING

KURMITAR June,20 6/10/2020 LY 38/02 KIOM/48/56 32 38.5 6.5 6.5 20 01.06.20 DRILLING
KURMITAR June,20 6/10/2020 DY 50H KIOM/00/00 0 0 0 RIG IDLE DUE TO MANPOWER SHORTAGE
KURMITAR June,20 6/10/2020 LY 38/01 KIOM/50/20/62 16 19 3 3 10 04.06.20 DRILLING
Sub Total - 9.50 30.00
DRILLING; POOR PROGRESS AS WHEN RPM IS
PATRATU June,20 6/10/2020 DY:175/03 5 1100 312 335 10 13 23 300 22.05.20 INCREASED TORQUE IS INCREASING SO
DRILLING AT LOW RPM.
Sub Total - 23.00 300.00
SIKAR June,20 6/10/2020 DY: 50CR/04 GKDC-26 420 420 420 0 0 0 0 18.03.20 06.06.20 IDLE WAITING FOR HO DECISION

SIKAR June,20 6/10/2020 DY:50CR/05 GKDC-27 327.5 349.5 13 9 22 130 29.05.20 POOR PROG. DUE TO 100% W/LOSS AND VERY
HARD FM.
Sub Total - 22.00 130.00
RIG IDLE DUE TO UNAVAILABILITY OF ANY
GMRDS June,20 6/10/2020 DY 35/01 0 0 0 0 0 0 MORE BH POINTS; NO FURTHER BH POINTS
PROVIDED BY GMRDS
GMRDS June,20 6/10/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/10/2020 LY 38/02 0 0 0 0 0 0

GMRDS June,20 6/10/2020 RD/60 (REPL) 0 0 0 0 0 0


Sub Total - 0.00 0.00
KABITIRTHA June,20 6/10/2020 DY: 100H/01 MRKB 85/SP-6 730 266 308 21 21 42 176 NQ DRILLING, SHALE FM.
Date of
Rig Type T.D. Starting Closing Date of
SITE MONTH DATE BH NO Shift I SHIFT II Day total HSD Commencem SITE UPDATES REMARKS
(m) Depth (m) Depth (m) ent Closure

NQ DRILLING; SANDSTONE AND SHALE FM.;


KABITIRTHA June,20 6/10/2020 KDR 750/02 MRKB 84/SP-1 610 407.1 447.8 20.3 20.4 40.7 104
100% W/LOSS IN BH

KABITIRTHA June,20 6/10/2020 LY: 44/01 MRKB 86/SP-3 6 33 15 12 27 60 09.06.2020 HQ DRILLING; HARD SHALE FM.
Sub Total - 109.70 340.00
mrl -59 ,BH -ZI/- DRILLING COMPLETELY STOPPED DUE TO
ZAWAR June'20 6/10/2020 UCD 40 0 0 0 0 0 0 COVID 19
59/11/-10°
ZAWAR June'20 6/10/2020 UCD 60-2 ZI/418/13/- 0 0 0 0 0 0 DRILLING COMPLETELY STOPPED DUE TO
35°/225° COVID 19

DRILLING COMPLETELY STOPPED DUE TO


ZAWAR June'20 6/10/2020 UCD 60-3 BI- 0 0 0 0 0 0 COVID 19
430/134/80°/15°
HMBH/390/13/2 DRILLING COMPLETELY STOPPED DUE TO
ZAWAR June'20 6/10/2020 UCD 60-1 0 0 0 0 0 0
70°/0° COVID 19
Sub Total - 0.00 0.00

Location - North AS CONCRETE PLATFORM WAS NOT SET SO


AGUCHA UG June'20 6/10/2020 UDD-330 255 CV SBH No. 0 0 0 0 0 0
MACHINE SETTING WAS NOT DONE
53
Sub Total - 0.00 0.00
SURFACE TO
AGUCHA SUR PF June'20 6/10/2020 DIMP-175 -180 0 0 0 0 0 0 WAITING FOR NEW BH POINT
Sub Total - 0.00 0.00

SKM PASTE AS PER INSTRUCTIONS OF HZL, PASTE FILL


SKM June'20 6/10/2020 DW-35 FILL-02 BORE 0 0 0 0 0 0 SERVIOCE HOLE JOBS HAVE BEEN STOPPED
HOLE NO-03 FOR COVID 19

Sub Total - 0.00 0.00


TDMA
BAMANIYA
June'20 6/10/2020 Dyna50H DD20BKE 0 0 0 0 0 0
Sub Total - 0.00 0.00
TDMA AGUCHA June'20 6/10/2020 KDR-1200 RAE-025 L1 810 810 0 0 0 0 WAITING FOR HYDCO MACHINE
Sub Total - 0.00 0.00
DD20ZWE264
TDMA ZAWAR June'20 6/10/2020 KDR-1200/02 (HQ) 417 417 0 0 0 0 WORK STOPPED DUE TO COVID 19
Sub Total - 0.00 0.00
WORKOVER
TSL DHANBAD June'20 6/10/2020 SIJUA 2 PIT 0 0 0 0 0 0 SITE PREPARATION
RIG
Sub Total - 0.00 0.00

20 BAGS CEMENT MIXED WITH DR. FIXIT ,


NGRI KOYNA June'20 6/10/2020 DYNA 350 KBH-10-R 729.4 729.40 0 0 0 90 SODA ASH AND COCO HUSK FLUSHED INTO
THE HOLE; NQ P/O COMPLETED; WOC

Sub Total - 0.00 90.00


WORK TERMINATED; RIG SHIFTED TO CAMP
CHOTIA June'20 6/10/2020 DY50CR/07
FOR CLEANING AND REPAIRING
Sub Total - 0.00 180.00
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA June'20 6/10/2020 DY:50CR/11
POINT
RIG IDLE DUE TO UNAVILABILITY OF NEXT
BABJA June'20 6/10/2020 LY:44 POINT
Sub Total - 0.00 180.00
Date of
SITE MONTH DATE Rig Type BH NO Projected Starting Closing Shift I SHIFT II Day total HSD Commencem Date of SITE UPDATES REMARKS
Depth (m) Depth (m) Depth Closure
ent

WAITNG BH CLOSED AND GPL DONE UPTO


KHARKHARI June,20 6/9/2020 CDR:1000 MAKH 06/P-29 715 706.45 706.45 GPL DONE 0.00 0.00
FOR GPL 706.45 M

KHARKHARI June,20 6/9/2020 LY:44 MAKH 23/P-17 400 239.00 262 11 12 23.00 80.00 27.05.20 DRILLING IN PROGRESS
KHARKHARI June,20 6/9/2020 KDR:750/01 MAKH 24/P-11 580 148.30 197.7 29.8 19.6 49.40 150.00 05.06.20 DRILLING IN PROGRESS

RIG SHIFTING NOT POSSIBLE DUE


KHARKHARI June,20 6/9/2020 DY:120/01 MAKH 12/P-24 760 767.50 767.5 0 0 0.00 0.00 19.02.20 01.06.20 TO LAND OWNER'SOBJECTION

POOR PROG. DUE TO 100% W/LOSS


KHARKHARI June,20 6/9/2020 DY:120/02 21 770 718.00 724 5 1 6.00 190.00 10.02.20 AND INTERMITTENT JAMMING
TENDENCY; GEARBOX B/D IN 2ND
SHIFT

BH CLOSED. GPL NOT COMPLETED


AS ELECTRICAL TOOL HELD UP AT
KHARKHARI June,20 6/9/2020 KDR:750/03 MAKH 22/P-10 460 472.70 472.7 0 0 0.00 60.00 22.05.20 08.06.20 201 M. NQ ROD PULL DOWN UPTO
472.70 M; BH WASHED

KHARKHARI June,20 6/9/2020 Di-8 22 730 451.00 478 15 12 27.00 160.00 19.05.20 DRILLING IN PROGRESS
Sub Total - 105.40 640.00

BADAM June,20 6/9/2020 DY: 100H/03 MABD 86/P-92 655.00 657.50 657.5 0 0 0.00 34 18.05.2020 08.06.20 SHIFTING; HQ ROD NOT RELEASED

BADAM June,20 6/9/2020 DY: 17 MABD80/P-84 640.00 473.80 506.1 17.5 14.8 32.30 144 DRILLING, SAND-SHALE FM.
BADAM June,20 6/9/2020 LY:44/01 MABD 35/P-77 98 98.20 98.20 0 0 0.00
NQ DRILLING, FRACTURED SHALE,
BADAM June,20 6/9/2020 LY: 44/02 MABD 84/P-87 400 328.50 355 14.5 12 26.50 100 13.05.2020 SANDY SHALE AND METAMORPHIC
FM.
BADAM June,20 6/9/2020 LY: 44/03 MABD87/P-89 400.00 109.70 123.5 13.8 0 13.80 45 01.06.2020 DRILLING, SHALE FM.
MACHINE AND MATERIALS SHIFTED
BADAM June,20 6/9/2020 DY: 50 CR/08 MABD 85/P-91 630.00 584.00 584 0 0 0.00 32 16.05.2020 08.06.20
TO CAMP
Sub Total - 40.30 177.00
RIG B/D, RH GEAR BOX MAIN SHAFT
SOMAVARAM June,20 6/9/2020 DY: 100H/02 NPP 19/ MGSE 137 530 169 169 0 0 0 0 03.06.20 REPAIRED & TAKEN FROM LOCAL
WORKSHOP

W/ BLOCKAGE AT BOTTOM SO 4
SOMAVARAM June,20 6/9/2020 DY: 50CR/10 P-73/MGSE 135 249 273 15 9 24 173 31.05.20 PAIR RODS P/O, WASHED AND
REACHED BOTTOM
RIG IDLE DUE TO MANPOWER
SOMAVARAM June,20 6/9/2020 DY: 50H/04 0 0
SHORTAGE

GPL NOT COMPLETED NQ STRINGS


SOMAVARAM June,20 6/9/2020 DY: 50CR/01 P-74/MGSE 136 367 367 0 0 0 37 31.05.20 WITH SHOE BIT R/I UPTO 186M; BH
WASHED TILL BOTTOM

Sub Total - 24.00 210.00


KURMITAR June,20 6/9/2020 Vol 180 (SPS) KIOM/00/00 0 0 0 0 0 0 SHIFTING
DRILLING; TANKER B/D BUT
KURMITAR June,20 6/9/2020 LY 38/02 KIOM/48/56 29.6 32 2.4 2.4 15 01.06.20
REPAIRED SO PROG. POOR
RIG IDLE DUE TO MANPOWER
KURMITAR June,20 6/9/2020 DY 50H KIOM/00/00 0 0 0 SHORTAGE
DRILLING; TANKER B/D BUT
KURMITAR June,20 6/9/2020 LY 38/01 KIOM/50/20/62 15 16 1 1 10 04.06.20
REPAIRED SO PROG. POOR
Sub Total - 3.40 25.00
Date of
SITE MONTH DATE Rig Type BH NO Projected Starting Closing Shift I SHIFT II Day total HSD Commencem Date of SITE UPDATES REMARKS
Depth (m) Depth (m) Depth Closure
ent

NQ ROD LOWERED FOLOWED BY


HQ BARREL WITH BIT, ONE CUT HQ
ROD RELEASED, HQ ROD LOWERED
PATRATU June,20 6/9/2020 DY:175/03 5 1100 312 312 0 0 0 130 22.05.20 AND BH WASHED; TRIED HQ
DRILLING BUT UNSUCCESSFUL;
DRILLING STARTED ON 10.6.20
MORNING

Sub Total - 0.00 130.00


SIKAR June,20 6/9/2020 DY: 50CR/04 GKDC-26 420 420 420 0 0 0 0 18.03.20 28.05.20 SHIFTING TO LOADING POINT
POOR PROG. DUE TO 100% W/LOSS
SIKAR June,20 6/9/2020 DY:50CR/05 GKDC-27 327.5 349.5 13 9 22 130 29.05.20 AND VERY HARD FM.
Sub Total - 22.00 130.00
RIG IDLE DUE TO UNAVAILABILITY
OF ANY MORE BH POINTS; NO
GMRDS June,20 6/9/2020 DY 35/01 0 0 0 0 0 0 FURTHER BH POINTS PROVIDED BY
GMRDS
GMRDS June,20 6/9/2020 LY 38/01 0 0 0 0 0 0
GMRDS June,20 6/9/2020 LY 38/02 0 0 0 0 0 0
GMRDS June,20 6/9/2020 RD/60 (REPL) 0 0 0 0 0 0
Sub Total - 0.00 0.00

KABITIRTHA June,20 6/9/2020 DICD 100H/01 MRKB 85/SP-6 730 239 266 14 13 27 184 NQ DRILLING, VERY HARD SHALE
FM.

NQ DRILLING;INVERTOR NOT
WORKING;MACHINE STARTING
KABITIRTHA June,20 6/9/2020 KDR 750/02 MRKB 84/SP-1 610 383.3 407.1 16.3 7.5 23.8 104
PROBLEM; 100% W/LOSS IN BH, SO
POOR PROG. IN 2ND SHIFT

MACHINE REPAIRING (CLUTCH


AND BRAKE); SITE SETTING &
KABITIRTHA June,20 6/9/2020 LY: 44/01 MRKB 86/SP-3 0 6 6 0 6 10 TESTING (PUMP & LIGHT); ALL
WORKERS ENGAGED IN 1ST SHIFT
SO NO PROG. IN 2ND SHIFT

Sub Total - 56.80 298.00