HOMEWORK 2

Situation 1
Question: Find the Labour cost for the Layout
Given : 30m length and 12m width
2 labourers at 20sqm per day
labor cost = Php 300/day

Solution unit
Area 360 sqm
Labourers 2 person working for 20sqm

Total Day 18 x 2
Total Day 36
Labor Cost 36 x 300
Total Labor Cost Php 10800.00

Situation 2
Question: Find the Total Volume of the Concrete structure
Given : Total volume of the rectangular and total volume of the triangular prism
Solution Volume Unit/s
Volume of Rectangular 2.622 cum
Volume of Triangular Prism 1.461055552 cum
Volume of the Concrete Structure 1.161 cum

Question: Calculate the Total Cost of all materials


Given Unit/s
Volume : 1.161 cubic meter
Class A Waste
Unit Cost Total Cost Unit
(1:2:4) Ratio Equivalent Factor Quantity Equivalent
Cement 9 0.03 11 225 2475.00 bag
Sand 0.44 0.15 0.59 800 472.00 cum
Gravel 0.88 0.05 1.07 1200 1284.00 cum

Cement Sand Gravel Total


Material Cost Php. 4,231.00
2,475.00 472.00 1,284.00 Cost

Question : Find the labour cost for concreting water through


Given : 2workers at 0.4cum / day
Php 500.00 /day
Solution Unit/s
Total Volume 1.161 cum
2 Labour/day 0.4 cum
Total Days 3 days
Total labour Cost 3000 PhP

Question : What is the total mass of concrete?


Given : 2400 kilograms/cum
Solution Unit/s
Mass Density 2400 kg/cum
Total Volume 1.161 cum
Total Mass of
2786.4 kg
Concrete