XXX 新建工程

LEED認證施工相片記錄
階段 編碼 SSP1 營建工作場所污染防治管理 選項 收件狀態
Stage coding Construction workplace pollution prevention management
S101 工區周邊安全圍籬設置 (下方設置有防溢座)
Safety fence around the work area (with anti-overflow seat below)
必要 ○

工區車輛出入口設置洗車台及高壓沖洗設備
S102 Set up car wash station and high pressure washing equipment at 必要 ○
the vehicle entrance and exit of the work area
1.假設工程
Assumption 工區車輛出入口設置截排水溝
S103 必要 ○
engineering Vehicle access at the work area

工區內設置逕流廢水控制系統(導水溝、截水溝、排水口保護等措施)
S104 Set up runoff wastewater control system in the work area (conduit, 必要 ○
intercepting ditch, drain protection, etc)

設置臨時性或永久性沉砂池/集水坑(井)措施
S105 Temporary or permanent grit chamber/collection pit (well) 必要 ○
measures

開挖土方堆置區覆蓋防塵布或防塵網等措施
S201 Measures such as excavating earthwork stacking area to cover 選用 ○
2.物料堆置 dust cloth or dustproof net
Material
stacking 進場材料暫存區,依規定底部墊高、採行覆蓋防塵布或防塵網等措施
S202 Entry material temporary storage area, according to the 必要 ○
provisions of the bottom of the height, the adoption of dust-
proof cloth or dust-proof net measures

基地內開挖後土方運送、裝載過程(需鋪蓋防塵網)
S301 Earthwork transportation and loading process after excavation in the base 必要 ○
(need to cover dust-proof net)

工區內車行路面鋪設鋼板、打設混擬土、鋪設級配等防塵措施
S302 Dust-preventing measures such as paving steel plates, laying 必要 ○
mixed soil, laying grading, etc

3.車行路徑/
裸露地表 S303 工區內外車行路面、及裸露地面灑水防塵 必要 ○
Road surface and exposed ground sprinkler dustproof
Car route /
Bare surface 車輛離開工區前清洗輪胎、覆蓋防塵網
S304 Cleaning the tires and covering the air filter before leaving 必要 ○
the work area
工區內行政區域、周邊圍籬植生綠化
S305 Planting greening in the administrative area and surrounding 選用 ○
fences in the work area

S306 工區內外道路定期清掃 選用 ○
Regular cleaning of roads inside and outside the work area

結構體施工階段,鷹架外緣加裝防塵罩網
4.結構體 S401 During the construction phase of the structure, the outer edge 必要 ○
Structure of the scaffold is equipped with a dust cover net

階段 編碼 MRC2 營建廢棄物回收管理 選項 收件狀態


Stage coding Construction waste recycling management
營建廢棄物暫存區設置有頂蓋並標示分類項目
M101 The temporary storage area of the construction waste is 選用 ○
1.設置暫存區 provided with a top cover and marked with classification items
Set the staging
area 營建廢棄物暫存區指派人員清潔整理
M102 Construction waste temporary storage area designated personnel 選用 ○
cleaning
裝載、運送、進回收廠過程
M201 必要 ○
Loading, transportation, and recycling process
2.回收流程
廢棄物磅單、簽收單等證明文件
Recycling M202
Proof of waste bills, receipts, etc
必要 ○
process

M203 施工人員生活廢棄物暫存區 選用 ○
Construction personnel living waste temporary storage area

階段 編碼 EQC3.1 室內空氣品質管理 選項 收件狀態


Stage coding Indoor Air Quality Management

空調設備安裝前臨時堆置區(確實架高與地面隔離、並保持密封狀態)
E101 Temporary storage area before installation of air-conditioning equipment 必要 ○
(actually the height is isolated from the ground and kept sealed)

1.建材進場 具甲醇等溢散性氣味建材集中存放,並保持存放空間通風(控制污染源)
Building E102 Concentrated odor building materials such as methanol are stored centrally 必要 ○
materials and keep the storage space ventilated (control pollution source)
entering

裝修建材進場後堆置區(確實架高與地面隔離、並保持原始包裝)
E103 After the decoration of the building materials enters the yard, the storage
area (the height is isolated from the ground and kept in the original
必要 ○
packaging)

室內塗料以低汙染手法粉刷(噴漆改以刷漆等手法)
E201 Indoor paints are painted with low-pollution techniques (painting is 選用 ○
changed to paint, etc)

木工施作區,加強粉塵隔離措施(使用塑膠膜阻斷傳播路徑)
E202 Woodworking area, strengthening dust isolation measures (using plastic film 必要 ○
to block the propagation path)

2.粉塵控制 粉塵作業區清掃,降低汙染源(灑水、集塵、排氣等手法)
Dust control E203 Dust cleaning area to reduce pollution sources (sprinkling, dust 必要 ○
collection, exhaust, etc)
粉塵作業區施工人員確實配戴個人防護具
E204 Dust work area construction personnel do wear personal 必要 ○
protective equipment
作業環境加裝通風排氣設備
E205 Ventilation and exhaust equipment installed in the working 必要 ○
environment
工區內禁止施工車輛空轉警語標誌
E301 Construction vehicle idling warning signs are prohibited in the 必要 ○
work area
工區內禁止施工人員抽菸警語標誌
E302 Construction workers are prohibited from smoking warning signs 必要 ○
in the work area
室內施工過程,保持開放式自然通風
E303 Indoor construction process, maintaining open natural 必要 ○
ventilation
3.施工過程
construction 空調設備安裝過程,風口及開口部位防塵保護
process E304 Air conditioning equipment installation process, dustproof 必要 ○
protection at the tuyere and opening

E305 建材安裝後之保護措施 必要 ○
Protective measures after installation of building materials

黏著劑、環保塗料三階段施工照片(進場、施作過程、完工後)
E306 Three-phase construction photos of adhesives and 必要 ○
environmentally friendly coatings (entry, implementation,
completion)

※註 ○ = 尚缺件 ● = 已備查