LIFTING PLAN

LIFT TITLE / Kerja mengangkat: GROSS LOAD # / Berat kasar DATE / Tarikh:
#:
LIFTING Service Water Filter Package Max 4 MT
Activity / Aktiviti: Permit No. / No. Permit:
LIFTING Service Water Filter Package
Lift location / Lokasi mengangkat: Project / Projek:
PEGAGA CPP TOPSIDE PEGAGA DEVELOPMENT PROJECT
Supervisor’s Name / Nama Penyelia: Lifting Category / Kategori Kerja Mengangkat:
SHAFIQ / Non-Routine (Simple) lift
Non-Routine (Complex / Critical / Heavy) Lift

Value / Nilai
No. Description / Perincian Unit
Crane 1 (400MT)
1 Weight of the lifted load (Load) Tonnes
Berat beban yang akan diangkat tan 4
(beban)
2 Lifting Beam tonnes
Berat Lifting Beam tan 1
3 Hook blocks weight tonnes
Berat Hook Block tan 5.3
4 Lifting Shackles & slings tonnes
Berat Lifting Shackles & slings tan 0.5
* Total weight Tonnes
* Jumlah Berat tan
10.8

Value / Nilai
No. Description / Perincian Unit
Crane 1 (400MT)
1 Total weight as per above * Tonnes
Jumlah berat seperti di atas * 10.8
tan
2 Main boom length
m 66
Panjang Boom Utama
3 Counter weight tonnes
Berat Counter weight tan 205
4 Radius / Angle
M/* 18m
Radius / Sudut
5 Safe Lift Capacity of crane (Chart)
tonnes
Kapasiti kren mengangkat dengan
tan
105.5MT
selamat (carta)
6 % of chart capacity used **
Peratusan (%) carta kapasiti % 10.23%
mengangkat yang digunakan **
** % of chart capacity used = determine routine or non routine lift (Less than 50%: Routine Lift; More than 50% : Non Routine Lift)
** Peratusan (%) carta kapasiti mengangkat = menentukan jenis kerja mengangkat (Kurang dari 50% : Rutin, Lebih dari 50% : Bukan Rutin)

Rigging Foreman / Supervisor / Engineering Dept. (complex, critical, heavy lift) Construction / Project Manager
Engineer Rigging Superintendent (non-routine simple lift)

Signature: Signature: Signature:


Name: Name: Name:

For HSE / Management Use:

HSE-CL-136 Rev 1 (July 2016) Page 1 of 5


LIFTING PLAN
LIFT TITLE / Kerja mengangkat: GROSS LOAD # / Berat kasar DATE / Tarikh:
#:
LIFTING Service Water Filter Package Max 4 MT
Complete all information. Use as many sheets as necessary.
Lengkapkan semua maklumat. Gunakan helaian tambahan sekiranya perlu.

CRANE
Certificate Operating Boom
Capacity /
Description / / Sijil SWL Radius / Angle / Remark /
Operator Keupayaan
Perincian (MT) Radius Sudut Catatan
Yes No kren (MT)
operasi (m) Boom
Manitowoc / 400 105.5 18 80

WIRE ROPE SLING


Certificate Capacity / Good Condition /
SWL Remark /
Description / Perincian / Sijil Keupayaan Keadaan selamat
(MT) Catatan
Yes No sling (MT) Yes / Ya No / Tidak
2 LEGGED WIRE ROPE
SLING:
/ 35 35 / BY VENDOR
LENGTH 1: 4527MM
LENGTH 2: 4578MM
25MT X 4M X 4NOS / 25 25 / BY VENDOR

SHACKLE
Certificate Capacity / Good Condition /
SWL Remark /
Description / Perincian / Sijil Keupayaan Keadaan selamat
(MT) Catatan
Yes No shackle (MT) Yes / Ya No / Tidak
35MT SHACKLE / 35 35 /

HSE-CL-136 Rev 1 (July 2016) Page 2 of 5


LIFTING PLAN
LIFT TITLE / Kerja mengangkat: GROSS LOAD # / Berat kasar DATE / Tarikh:
#:
LIFTING Service Water Filter Package Max 4 MT

KEY PERSONNEL INVOLVED IN THE OPERATION


Designation / A B Communication Mode Acknowledgment /
Name / Nama
Jawatan Yes No Yes No / Cara Komunikasi Perakuan

Note / A - Do Crane Operator Aware of load to be lifted / Adakah Operator Kren mengetahui
Nota: dan faham keadaan beban yang akan diangkat
B - Briefing of the operation / Taklimat berkaitan kerja mengangkat

PRECAUTION / Kawalan
Description / Perincian Yes No Remarks / Catatan
Are rigging and slinging arrangements
correct /
Adakah aturan rigging & slinging betul?
Is weather condition good
/
Adakah cuaca dalam keadaan baik?
Are all obstruction cleared / crane path
marked / barricaded
/
Adakah semua halangan dibersihkan serta
laluan kren ditanda / dikepung
Are procedure / documentation approved
Adakah prosedur / dokumen telah /
disahkan?
Job Hazard Analysis (JHA) recommendation
completed /
Cadangan dari JHA telah dilaksanakan
Are there any special precautions?
Adakah terdapat sebarang langkah /
berjaga-jaga?

HSE-CL-136 Rev 1 (July 2016) Page 3 of 5


LIFTING PLAN
LIFT TITLE / Kerja mengangkat: GROSS LOAD # / Berat kasar DATE / Tarikh:
#:
LIFTING Service Water Filter Package Max 4 MT
On the rigging sketch (Figure 1) identify the following / Lakarkan perincian dibawah pada Rajah 1:
1. Lift points / titik mengangkat
2. Shackles/swivel eyes
3. Slings, sling angles, and sling loads / wayar sling, sudut sling dan keupayaan sling
4. Accessories / peralatan rigging
5. Capacities / kapasiti
6. Center of Gravity (COG) / titik graviti

Figure 1: Rigging Sketch (Rajah 1: Lakaran Rigging)

HSE-CL-136 Rev 1 (July 2016) Page 4 of 5


LIFTING PLAN
LIFT TITLE / Kerja mengangkat: GROSS LOAD # / Berat kasar DATE / Tarikh:
#:
LIFTING Service Water Filter Package Max 4 MT
On the Load path Sketch (Figure 2), sketch the load path including all relevant aspects such as load
height, obstructions, crane speeds etc.
Lakarkan laluan beban yang akan diangkat termasuk semua aspekyang berkaitan seperti ketinggian
beban, halangan, kelajuan kren dan lain-lain pada Rajah 2

Manitowoc M16000S3
Boom length: 66m
Working Radius: 18m

Load: 10.8MT
Crane Capacity: 105.5MT
% utilization: 10.23%

66m

18m max radius

Figure 2: Load path Sketch (Rajah 2: Lakaran laluan mengangkat)

HSE-CL-136 Rev 1 (July 2016) Page 5 of 5