NO PROJCET ITEM LIFTING DATE SHIFTING DATE
81 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 24 July, 2020 24 July, 2020
(1/4 nos of LQ modules) (LQ1A)
82 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 25 July, 2020 25 July, 2020
(2/4 nos of LQ modules) (LQ1B)
83 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 26 July, 2020 26 July, 2020
(3/4 nos of LQ modules) (LQ1C)
63 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE (EX-8110A) 27 July, 2020 27 July, 2020
64 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE (EX-8110B) 7 August, 2020 7 August, 2020
65 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE (EX-8110C) 8 August, 2020 8 August, 2020
84 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 27 July, 2020 27 July, 2020
(4/4 nos of LQ modules) (LQ1D)
89 PEGAGA CPP LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ MODULE 31 July, 2020 31 July, 2020
(1/4nos of LQ modules)
118 PEGAGA CPP LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ MODULE 1//8/2020 1//8/2020
(2/4nos of LQ modules)
119 PEGAGA CPP LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ MODULE 2 August, 2020 2 August, 2020
(3/4nos of LQ modules)
120 PEGAGA CPP LIFT & INTEGRATE LEVEL 2 MODULE ONTO LEVEL 1 LQ MODULE 3 August, 2020 3 August, 2020
(4/4nos of LQ modules)
77 PEGAGA CPP LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ MODULE 7 August, 2020 7 August, 2020
(1/4nos of LQ modules)
78 PEGAGA CPP LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ MODULE 8 August, 2020 8 August, 2020
(2/4nos of LQ modules)
79 PEGAGA CPP LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ MODULE 9 August, 2020 9 August, 2020
(3/4nos of LQ modules)
80 PEGAGA CPP LIFT & INTEGRATE LEVEL 3 MODULE ONTO LEVEL 2 LQ MODULE 10 August, 2020 10 August, 2020
LIFTING & SHIFTING SCHEDULE 2020 rev.0
NO PROJCET ITEM LIFTING WEIGHT CRANE TRANSPORTER LIFTING DATE SHIFTING DATE REMARKS
61 PEGAGA CPP ERECTION OF LQ BASE FRAME 92.27 250T x 2, 280 x 1 nos 48 axles + 2 PPU 9-Jul-20 7/8/2020 400mt x 3 nos
Postpone
81 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 69.1 Option 1: 400t x 2 18 axle + 1 PPU 7/24/2020 7/24/2020
(1/4 nos of LQ modules) Option 2: CC8800 single lift
LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME Option 1: 400t x 2
82 PEGAGA CPP (2/4 nos of LQ modules) 62.58 Option 2: CC8800 single lift 18 axle + 1 PPU 7/25/2020 7/25/2020
83 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 56.91 Option 1: 400t x 2 18 axle + 1 PPU 7/26/2020 7/26/2020
(3/4 nos of LQ modules) Option 2: CC8800 single lift
64 PEGAGA CPP INSTALLATION OF GAS TURBINE GENERATOR PACKAGE Maxer 400MT TRANSPORTER 7-Aug-20 8/7/2020
(EX-8110B) TBC by Engineering
84 PEGAGA CPP LIFT & INTEGRATE LEVEL 1 MODULE ONTO BASE FRAME 59.33 Option 1: 400t x 2 18 axle + 1 PPU 9-Aug-20 8/9/2020
(4/4 nos of LQ modules) Option 2: CC8800 single lift
68 PEGAGA CPP INSTALLATION OF COOLER DECK Maxer (400MT) x 2 nos. 36 axles + 2 PPU 7-Sep-20 9/7/2020
PROJCET ITEM
PEGAGA CPP Diesel Storage Tank Row 6
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 1&2 (A&B)
ONGC 98/2 JACKET SKIRT PILE SLEEVES - ROW 6&7 (A&B)
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(1/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(2/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(3/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 1 MODULE ONTO
PEGAGA CPP BASE FRAME
(4/4 nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 2 MODULE ONTO
PEGAGA CPP LEVEL 1 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 3 MODULE ONTO
PEGAGA CPP LEVEL 2 LQ MODULE
(4/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(1/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(2/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(3/4nos of LQ modules)
LIFT & INTEGRATE LEVEL 4 MODULE ONTO
PEGAGA CPP LEVEL 3 LQ MODULE
(4/4nos of LQ modules)
ONGC 98/2
U PEGAGA
TOTAL
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
18 axle + 1 PPU
0
16
16
24-Jul-20
25-Jul-20
26-Jul-20
27-Jul-20
31-Jul-20
1-Aug-20
2-Aug-20
3-Aug-20
7-Aug-20
8-Aug-20
9-Aug-20
10-Aug-20
14-Aug-20
15-Aug-20
16-Aug-20
17-Aug-20
24 axles + 2 PPU
PROJCET ITEM
ONGC 98/2 CPP SUB CELLAR ROW (PORTION 1)
ONGC 98/2 CPP SUB CELLAR ROW 6-7 (PORTION 2)
ONGC 98/2 JACKET TOWER A (LEG 1A & 2A)
ONGC 98/2 JACKET TOWER 1B
ONGC 98/2 LQ INSTALLATION OF LEVEL 4 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 5 FRAMING
ONGC 98/2 JACKET BUOYANCY TANK ROW 1
ONGC 98/2 JACKET BUOYANCY TANK CENTER
ONGC 98/2 JACKET BUOYANCY TANK ROW 7
ONGC 98/2 JACKET X-PANEL ROW 1
ONGC 98/2 JACKET X-PANEL ROW 7
ONGC 98/2 JACKET X-PANEL ROW 2
ONGC 98/2 JACKET X-PANEL ROW 6
PEGAGA CPP UPENDING & ERECTION OF HELIDECK
FRAME C/W PANCAKE ONTO LQ
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
PEGAGA CPP INSTALLATION OF COOLER DECK
ONGC 98/2
U PEGAGA
TOTAL
PROJCET ITEM
ONGC 98/2 CPP CELLAR DECK PORTION 1
ONGC 98/2 CPP CELLAR DECK PORTION 2
ONGC 98/2 CPP CELLAR DECK PORTION 3
ONGC 98/2 CPP MAIN DECK 3ND PORTION
ONGC 98/2 CPP MAIN DECK 1ND PORTION
ONGC 98/2 CPP MAIN DECK 2ND PORTION
ONGC 98/2 LQ INSTALLATION OF LEVEL 1 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 2 FRAMING
ONGC 98/2 LQ INSTALLATION OF LEVEL 3 FRAMING
PEGAGA CPP ERECTION OF LQ BASE FRAME
PEGAGA CPP INSTALLATION OF SERVICE DECK
ONGC 98/2
U PEGAGA
TOTAL